P01 - Specifications - 515-21-103.pdf
PDF 4 MB Posted
- Attached to
- Z1DA--Replace Elevators Building 2, 7, 13, 39 & 82 515-21-103 Federal contract opportunity
- Solicitation number
- 36C25022B0037
About this file
This pre-solicitation announcement provides advance notice of an upcoming Invitation for Bid to replace elevators at the Veterans Administration Medical Center in Battle Creek, Michigan. The project scope includes furnishing all labor, materials, equipment, and supervision to replace elevators in Buildings 2, 7, 13, 39 and 82. The performance period is 730 calendar days from notice to proceed. The estimated cost range is $1-5 million. The NAICS code is 238990 and small business size standard is $16.5 million. The government intends to award a firm fixed price contract within 120 days of bid opening. This acquisition is a 100% set-aside for qualified Service-Disabled Veteran Owned Small Businesses. Offers will only be accepted from verified SDVOSBs registered in the Vendor Information Pages database. The solicitation is expected to be issued on June 3, 2022 and will be available for download at SAM.gov. Questions should be directed to the named contracting specialist by email only. Offerors must complete SAM registration, representations and certifications, and VETS-4212 reporting (if applicable) prior to submission.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| S04 - Pre-Bid Site Visit Attendance Log - 515-21-103.pdf | ||
| 36C25022B0037 0002.docx | DOCX document | |
| 36C25022B0037 0001.docx | DOCX document | |
| P01 - Attachment 3 Sarix IMP Brand Name Only Justification signed - 515-21-103.pdf | ||
| P09 - SOW Final - 515-21-103.pdf | ||
| P01 - Attachment 3 PACS Brand Name Only Justification signed - 515-21-103.pdf | ||
| Drawings - 515-21-103.pdf | ||
| S02 - Wage Determination MI20220157 June 3 - 515-21-103.pdf | ||
| S02 - Contractor EMR Certification Form - 515-21-103.pdf | ||
| P01 - Attachment 3 KABA Brand Name Only Justification signed - 515-21-103.pdf | ||
| 36C25022B0037_1.pdf | ||
| S02 - RFI Form - 515-21-103.pdf | ||
| 36C25022B0037.docx | DOCX document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Manual 100% Bid Documents -
FOR CONSTRUCTION
Replace Elevators Buildings 2, 7, 13, 39, 82 VA Battle Creek Medical Center VA Project No. 515-21-103
December 13, 2021
638 S. Grand Avenue 211 E. Water St. Suite 213L Fowlerville, MI 48836 Kalamazoo, MI 49007
12/13/2021
12/13/2021
12/13/2021
Revision: 12-20 Replace Elevators 100% Bid Documents Buildings 2, 7, 13, 39, 82
Battle Creek, Michigan VA Project No. 515-21-103
00 01 10 - 1/3
TABLE OF CONTENTS
SECTION 00 01 10 - TABLE OF CONTENTS
DEPARTMENT OF VETERANS AFFAIRS VHA MASTER SPECIFICATIONS
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 03-20 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 03-20 01 33 23 Shop Drawings, Product Data, and Samples 06-21
01 33 23 MAXIMO - ASSET / PMI SCHEDULER
01 35 26 Safety Requirements 07-20 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 00 Quality Control Report Form 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 01-21 01 81 13 Sustainable Construction Requirements 10-17
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17 02 82 11 Traditional Asbestos Abatement 01-21 02 82 13.19 Asbestos Floor Tile and Mastic Abatement 01-21
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 10-17
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 04-20 09 65 19 Resilient Tile Flooring 05-18 09 91 00 Painting 01-21
Battle Creek, Michigan VA Project No. 515-21-103
00 01 10 - 2/3
TABLE OF CONTENTS
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 10 – SPECIALTIES
10 26 00 Wall and Door Protection 01-21
DIVISION 14 – CONVEYING EQUIPEMENT
14 21 10 Modernization of Traction Elevator 12-20 14 24 10 Modernization of Hydraulic Elevator 12-20
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 27 26 Wiring Devices 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 09-19 27 05 26 Grounding and Bonding for Communications Systems 06-15 27 05 33 Raceways and Boxes for Communications Systems 10-18 27 10 00 Control, Communication and Signal Wiring 06-15 27 15 00 Communications Structured Cabling 01-16
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18 28 05 13 Conductors and Cables for Electronic Safety and Security 10-18 28 05 26 Grounding and Bonding for Electronic Safety and Security 09-11 28 05 28.33 Conduits and Backboxes for Electronic Safety and Security 09-11 28 13 00 Physical Access Control System 10-11 28 23 00 Video Surveillance 09-11 28 31 00 Fire Detection and Alarm 10-11 28 52 31 Emergency Call System 06-15
APPENDIX
Asbestos Survey, Rev 07-2019
Battle Creek, Michigan VA Project No. 515-21-103
00 01 10 - 3/3
TABLE OF CONTENTS
END OF TABLE OF CONTENTS 00 01 10
Revision: 05-20 Replace Elevators
Battle Creek, Michigan VA Project No. 515-21-103
00 01 15 - 1/2
LIST OF DRAWING SHEETS
SECTION 00 01 15 - LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
G-001 COVER SHEET
G-002 PHASING PLAN
ARCHITECTURE
A-001 ARCHITECTURAL LEGENDS, SYMBOLS, AND ABBREVIATIONS
A-110 DETAILS, INTERIOR ELEVATIONS, AND SCHEDULES
02_A-002 OVERALL PLANS - AREA OF WORK
02_A-003 ELEVATOR PHOTOS
02_A-101 FLOOR PLANS AND SECTIONS - E1 & E2
02_A-102 FLOOR PLANS AND SECTIONS - E3
07_A-002 OVERALL PLANS - AREA OF WORK
07_A-003 ELEVATOR PHOTOS
07_A-101 FLOOR PLANS AND SECTIONS
13_A-002 OVERALL PLANS - AREA OF WORK
13_A-003 ELEVATOR PHOTOS
13_A-101 FLOOR PLANS AND SECTIONS
39_A-002 OVERALL PLANS - AREA OF WORK
39_A-003 ELEVATOR PHOTOS
39_A-101 FLOOR PLANS AND SECTIONS
82_A-002 OVERALL PLANS - AREA OF WORK
82_A-003 ELEVATOR PHOTOS
82_A-101 FLOOR PLANS AND SECTIONS
MECHANICAL
00_M-000 MECHANICAL GENERAL INFORMATION
02_M-002 OVERALL PLANS - AREA OF WORK
02_M-101 MECHANICAL FLOOR PLANS - E1 & E2
ELECTRICAL
00_E-000 ELECTRICAL GENERAL INFORMATION
02_E-002 OVERALL PLANS - AREA OF WORK
02_ED101 ELECTRICAL DEMOLITION PLANS - E1 & E2
02_ED102 ELECTRICAL DEMOLITION PLANS - E3
02_E-101 ELECTRICAL FLOOR PLANS - E1 & E2
02_E-102 ELECTRICAL FLOOR PLAN - E3
07_E-002 OVERALL PLANS - AREA OF WORK
07_ED101 ELECTRICAL DEMOLITION FLOOR PLANS
07_E-101 ELECTRICAL FLOOR PLANS
13_E-002 OVERALL PLANS - AREA OF WORK
13_ED101 ELECTRICAL DEMOLITION FLOOR PLANS
13_E-101 ELECTRICAL FLOOR PLANS
Revision: 05-20 Replace Elevators
Battle Creek, Michigan VA Project No. 515-21-103
00 01 15 - 2/2
LIST OF DRAWING SHEETS
39_E-002 OVERALL PLANS - AREA OF WORK
39_ED101 ELECTRICAL DEMOLITION FLOOR PLANS
39_E-101 ELECTRICAL FLOOR PLANS
82_E-002 OVERALL PLANS - AREA OF WORK
82_ED101 ELECTRICAL DEMOLITION FLOOR PLANS
82_E-101 ELECTRICAL FLOOR PLANS
END OF SECTION 00 01 15
Revision: 03-20 Replace Elevators
Battle Creek, Michigan VA Project No. 515-21-103 i
SECTION 01 00 00 - GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,
AND IMPROVEMENTS
1.10 RESTORATION
1.11 AS-BUILT DRAWINGS
1.12 TEMPORARY USE OF ELEVATORS
1.13 TEMPORARY TOILETS
1.14 AVAILABILITY AND USE OF UTILITY SERVICES
1.15 TESTS
1.16 INSTRUCTIONS
1.17 RELOCATED EQUIPMENT AND ITEMS
1.18 CONSTRUCTION SIGN
1.19 SAFETY SIGN
1.20 INDUSTRY STANDARDS
1.21 GOVERNING REGULATIONS AND AUTHORITIES
Battle Creek, Michigan VA Project No. 515-21-103
01 00 00 - 1/14
GENERAL REQUIREMENTS
VISN 10 Master Specifications 11-15
PART 1 - GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to Section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall furnish all labor, materials, equipment, management, supervision, tools, and all other necessary resources for Project 515-21-103 Replace Elevators, Buildings 2 ,5, 6, 7, 9, 13, 39, and 82as required by drawings and specifications.
B. Visits to the site by offerors shall be as specified in solicitation provision 52.236-27 Site Visit (Construction).
C. Offices of Monument Engineering Group Associates, Inc., (MEGA) as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer.
D. Prior to commencing work, general contractor shall provide proof that a OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) shall maintain a presence at the work site at any time work is being performed.
E. Training:
1. All on-site workers of the prime and sub-contractors shall have completed and received a certificate of completion of the 10-hour OSHA certified Construction Safety course or other equivalent competency training. The Construction Superintendent shall have completed and received certification of completing the 30-hour OSHA Construction Safety course.
2. Submit OSHA certifications for all on-site workers to the VA COR prior to any worker beginning on-site work.
1.3 STATEMENT OF BID ITEM(S)
A. The Statement of Bid Item(s) is located within the solicitation Information and Instructions to Bidder section.
B. ALL PRICING IS TO BE ENTERED IN BLOCK 17 OF THE SF1442 SOLICITATION
OFFER PAGE (BLOCK 17) OR THE BID SCHEDULE IF SO INCLUDED WITH THE
SOLICITATION.
Battle Creek, Michigan VA Project No. 515-21-103
01 00 00 - 2/14
GENERAL REQUIREMENTS
VISN 10 Master Specifications 11-15
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security:
1. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They shall also be subject to inspection of their personal effects when entering or leaving the project site.
2. No photography of VA premises is allowed without permission of the VA COR.
3. VA reserves the right to close down or shut down the project site and order General
Contractor’s employees off the premises in the event of a national emergency.
The General Contractor may return to the site only with the written approval of the Contracting Officer.
4. For working outside the “regular hours” as defined in the contract, the contractor shall give 5 working days prior notice to the VA COR so that security and any necessary escort arrangements can be provided for the workers. This notice is separate from any notices required for utility shutdown described later in this section.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the
Contracting officers representative (VA COR) for any locked storage area, office or storage trailer, and any other locks installed by permission of the VA COR at the project site.
2. The General Contractor shall turn over all permanent lock cylinders to the VA COR for permanent installation.
1.6 OPERATIONS AND STORAGE AREAS
A. Working space and space available for storing materials shall be as shown on the drawings or as determined by the VA COR.
B. Workmen are subject to the rules of the Medical Center applicable to their conduct.
C. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
Battle Creek, Michigan VA Project No. 515-21-103
01 00 00 - 3/14
GENERAL REQUIREMENTS
VISN 10 Master Specifications 11-15
D. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by VA COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment shall be permitted subject to fire and safety requirements.
E. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by VA COR. All such actions shall be coordinated with the VA COR.
F. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by VA COR.
G. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with BC VAMC Fire Service.
Battle Creek, Michigan VA Project No. 515-21-103
01 00 00 - 4/14
GENERAL REQUIREMENTS
VISN 10 Master Specifications 11-15
H. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by VA
COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of VA COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the VA COR’s prior knowledge and written approval of the Contracting Officer. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and 27 05 11 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS for additional requirements.
2. Contractor shall submit a request to interrupt any such services to VA COR, in writing, 7 calendar days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the
VA COR.
5. In case of a contract construction emergency, service will be interrupted on approval of VA COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
Battle Creek, Michigan VA Project No. 515-21-103
01 00 00 - 5/14
GENERAL REQUIREMENTS
VISN 10 Master Specifications 11-15
J. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks, and entrances must be approved by the VA COR.
K. Coordinate the work for this contract with other construction operations as directed by VA COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the VA COR, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and VA COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of VA COR to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Prior to the furnishing of any new items and any related work thereof, a mutual agreement between the Contractor and Contracting Officer on the total cost shall first be negotiated and a contract modification executed incorporating the changed work. Contractor is cautioned only the Contracting Officer has the authority to make changes to the contract related to this section. Any changed work performed or new items provided prior to Contracting Officer authorization shall result in no adjustment to the contract price.
Battle Creek, Michigan VA Project No. 515-21-103
01 00 00 - 6/14
GENERAL REQUIREMENTS
VISN 10 Master Specifications 11-15
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and VA COR together shall make a thorough re-survey of the areas of buildings involved.
They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government shall be identified by attached tags or noted on drawings or in specifications as items to be stored.
Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by VA
COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government.
When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
Battle Creek, Michigan VA Project No. 515-21-103
01 00 00 - 7/14
GENERAL REQUIREMENTS
VISN 10 Master Specifications 11-15
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
A. Protection of Land Resources: Prior to construction, identify all land resources to be preserved within the work area. Do not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, topsoil, and landforms without permission from the COR. Do not fasten or attach ropes, cables, or guys to trees for anchorage unless specifically authorized, or where special emergency use is permitted.
Use of heavy equipment on facility grounds shall utilize protection mats as required to protect the grounds from excessive damage.
B. Restoration of Damaged Property: If any direct or indirect damage is done to public or private property resulting from any act, omission, neglect, or misconduct, the Contractor shall restore the damaged property to a condition equal to that existing before the damage at no additional cost to the Government. Repair, rebuild, or restore property as directed or make good such damage in an acceptable manner.
C. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the VA COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the VA COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
Battle Creek, Michigan VA Project No. 515-21-103
01 00 00 - 8/14
GENERAL REQUIREMENTS
VISN 10 Master Specifications 11-15
1.11 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which shall be kept current during construction of the project, to include all contract changes, modifications and clarifications, along with an on-site as-built ‘red line’ set of drawings and specifications. These drawings and specifications shall contain up to date addendums, approved changes & modifications, approved Request for Information responses, and Architect’s Supplemental Instructions (ASI) for the project. The VA COR shall have ready access to inspect the as-built drawings and specifications, as well as field copies in use, to ensure current drawings and specifications are being deployed for use on project.
B. All variations shall be shown in the same general detail as used in the contract drawings.
To insure compliance, as-built drawings shall be made available for the VA COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the VA COR within 15 calendar days after each completed phase and after the acceptance of the project by the Contracting Officer.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.12 TEMPORARY USE OF ELEVATORS
A. Use of existing elevators for handling building materials and Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the VA COR for use of elevators. The VA
COR will ascertain that elevators are in proper condition. Contractor may use elevators for daily use and for special nonrecurring time intervals when permission is granted. Personnel for operating elevators will not be provided by the Department of Veterans Affairs.
2. Contractor covers and provides maximum protection of following elevator components:
a. Entrance jambs, heads soffits and threshold plates
b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
c. Finish flooring.
3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation. However, if these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during temporary use, they shall be removed and replaced by new hoisting ropes at the contractor’s expense.
4. If brake lining of elevators are excessively worn or damaged during temporary use, they shall be removed and replaced by new brake lining at the contractor’s expense.
Battle Creek, Michigan VA Project No. 515-21-103
01 00 00 - 9/14
GENERAL REQUIREMENTS
VISN 10 Master Specifications 11-15
5. All parts of main controller, starter, relay panel, selector, etc., worn or damaged during temporary use shall be removed and replaced with new parts at the contractor’s expense, if recommended by elevator inspector after elevator is released by Contractor.
6. Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of Contractor as approved by Contracting Officer.
1.13 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workmen) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by VA COR, provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.14 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The Contractor will carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted.
Maintain minimum temperatures as specified for various materials.
1. Obtain heat by connecting to Medical Center heating distribution system.
D. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system.
The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
Battle Creek, Michigan VA Project No. 515-21-103
01 00 00 - 10/14
GENERAL REQUIREMENTS
VISN 10 Master Specifications 11-15
E. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system.
Provide reduced pressure backflow preventer at each connection as per code.
Water is available at no cost to the Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at VA COR discretion) of use of water from Medical Center's system.
1.15 TESTS
A. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
B. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
C. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc. Another example of a system which involves several components of different disciplines is a boiler installation. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, combustion air, controls, steam, feed-water, condensate and other related components.
D. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.
E. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.16 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
Battle Creek, Michigan VA Project No. 515-21-103
01 00 00 - 11/14
GENERAL REQUIREMENTS
VISN 10 Master Specifications 11-15
B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the VA COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. All training shall be videotaped by contractor on HD medium and copy shall be furnished on DVD with each O&M manual. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the VA COR and shall be considered concluded only when the VA COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the VA COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Contracting Officer reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the Contracting Officer, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.17 RELOCATED EQUIPMENT AND ITEMS
A. Contractor shall disconnect, dismantle as necessary, remove and reinstall in new location, all existing equipment and items indicated by symbol "R" or otherwise shown to be relocated by the Contractor.
Battle Creek, Michigan VA Project No. 515-21-103
01 00 00 - 12/14
GENERAL REQUIREMENTS
VISN 10 Master Specifications 11-15
B. Perform relocation of such equipment or items at such times and in such a manner as directed by the VA COR.
C. Suitably cap existing service lines, such as steam, condensate return, water, drain, gas, air, vacuum and/or electrical, at the main whenever such lines are disconnected from equipment to be relocated. Remove abandoned lines in finished areas and cap as specified herein before under paragraph "Abandoned Lines".
D. Provide all mechanical and electrical service connections, fittings, fastenings and any other materials necessary for assembly and installation of relocated equipment; and leave such equipment in proper operating condition.
E. All service lines such as noted above for relocated equipment shall be in place at point of relocation ready for use before any existing equipment is disconnected. Make relocated existing equipment ready for operation or use immediately after reinstallation.
1.18 CONSTRUCTION SIGN
A. Provide a Construction Sign where directed by the VA COR. All wood members shall be of framing lumber. Cover sign frame with 0.7 mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Provide three 100 by 100 mm (4 inch by 4 inch) posts (or equivalent round posts) set 1200 mm (four feet) into ground. Set bottom of sign level at 900 mm (three feet) above ground and secure to posts with through bolts.
Make posts full height of sign. Brace posts with 50 x 100 mm (two by four inch) material as directed.
B. Paint all surfaces of sign and posts two coats of white gloss paint. Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.
C. Maintain sign and remove it when directed by the VA COR.
D. Detail drawing of construction sign showing required legend and other characteristics of sign is shown on the drawings.
1.19 SAFETY SIGN
A. Provide a Safety Sign where directed by VA COR. Face of sign shall be 19 mm (3/4 inch) thick exterior grade plywood. Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm (three feet) into ground. Set bottom of sign level at 1200 mm (four feet) above ground.
B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and design shall be painted with gloss paint of colors noted.
C. Maintain sign and remove it when directed by VA COR.
Battle Creek, Michigan VA Project No. 515-21-103
01 00 00 - 13/14
GENERAL REQUIREMENTS
VISN 10 Master Specifications 11-15
D. Detail drawing of construction sign showing required legend and other characteristics of sign is shown on the drawings.
E. Post the number of accident free days on a daily basis.
1.20 INDUSTRY STANDARDS
A. Applicability of Standards: Except where the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference.
B. Publication Dates: Comply with the standards in effect as of the date of the Contract Documents unless a specific date is indicated in the Contract Documents or the governing regulations cited herein.
C. Conflicting Requirements: Where compliance with two (2) or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent and highest quality requirement. In the event of conflicting requirements within the Contract Documents, comply with the most stringent and highest quality requirement. Request a decision from the VA COR before proceeding on requirements that are different but apparently equal, and where it is uncertain which requirement is the most stringent.
D. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum acceptable. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of the requirements. Request a clarification from the VA COR regarding uncertainties before proceeding.
E. Copies of Standards: Each entity engaged in construction on the Project is required to be familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents. Where copies of standards are needed to perform a required construction activity, the Contractor shall obtain copies directly from the publication source.
F. Abbreviations and Names: Trade association names and titles of general standards are frequently abbreviated. Where such acronyms or abbreviations are used in the Specifications or other Contract Documents, they mean the recognized name of the trade association, standards-generating organization, authorities having jurisdiction, or other entity applicable to the context of the text provision. Refer to Thompson Gale's "Encyclopedia of Associations," available in most libraries.
Battle Creek, Michigan VA Project No. 515-21-103
01 00 00 - 14/14
GENERAL REQUIREMENTS
VISN 10 Master Specifications 11-15
1.21 GOVERNING REGULATIONS AND AUTHORITIES
A. Copies of Regulations: Obtain copies of the following regulations and retain at the Project Site to be available for reference by parties who have a reasonable need during submittals, planning, and progress of the work, until final completion.
1. International Building Code– 2018 edition.
2. International Existing Building Code– 2018 edition.
3. International Mechanical Code– 2018 edition.
4. International Plumbing Code– 2018 edition.
5. International Energy Conservation Code– 2018 edition.
6. International Fire Code– 2018 edition.
7. National Electric Code (NEC) / NFPA 70– 2020 edition.
8. Architectural Barriers Act Accessibility Standards (ABAAS) including VA supplement, Barrier Free Design Guide (PG-18-13)
9. NFPA 101 Life Safety Code – 2018 edition.
10. OSHA 29 CFR Part 1910 Occupational Safety and Health Regulations/2010.
11. OSHA 29 CFR Part 1926 Occupational Safety and Health Regulations for
Construction/2010.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 00 00
Battle Creek, Michigan VA Project No. 515-21-103
01 32 16.15 - 1/8
PROJECT SCHEDULES (SMALL PROJECTS – DESIGN/BID/BUILD)
SECTION 01 32 16.15 - PROJECT SCHEDULES (SMALL PROJECTS – DESIGN/BID/BUILD)
PART 1 - GENERAL
1.1 DESCRIPTION
A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment of the contract requirements (Project Schedule), and shall keep the Project Schedule up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers).
Conventional Critical Path Method (CPM) technique shall be utilized to satisfy both time and cost applications.
1.2 CONTRACTOR'S REPRESENTATIVE
A. The Contractor shall designate an authorized representative responsible for the Project Schedule including preparation, review and progress reporting with and to the Contracting Officer's Representative (VA COR).
B. The Contractor's representative shall have direct project control and complete authority to act on behalf of the Contractor in fulfilling the requirements of this specification section.
C. The Contractor’s representative shall have the option of developing the project schedule within their organization or to engage the services of an outside consultant. If an outside scheduling consultant is utilized, Section 1.3 of this specification shall apply.
1.3 CONTRACTOR'S CONSULTANT
A. The Contractor shall submit a qualification proposal to the VA COR, within 10 days of bid acceptance. The qualification proposal shall include:
1. The name and address of the proposed consultant.
2. Information to show that the proposed consultant has the qualifications to meet the requirements specified in the preceding paragraph.
3. A representative sample of prior construction projects, which the proposed consultant has performed complete project scheduling services. These representative samples shall be of similar size and scope.
B. The Contracting Officer has the right to approve or disapprove the proposed consultant, and shall notify the Contractor of the VA decision within seven calendar days from receipt of the qualification proposal. In case of disapproval, the Contractor shall resubmit another consultant within 10 calendar days for renewed consideration. The Contractor shall have their scheduling consultant approved prior to submitting any schedule for approval.
Battle Creek, Michigan VA Project No. 515-21-103
01 32 16.15 - 2/8
PROJECT SCHEDULES (SMALL PROJECTS – DESIGN/BID/BUILD)
1.4 COMPUTER PRODUCED SCHEDULES
A. The contractor shall provide monthly, to the Department of Veterans Affairs (VA), all computer-produced time/cost schedules and reports generated from monthly project updates. This monthly computer service shall include: three copies of up to five different reports (inclusive of all pages) available within the user defined reports of the scheduling software approved by the Contracting Officer; a hard copy listing of all project schedule changes, and associated data, made at the update and an electronic file of this data;
and the resulting monthly updated schedule in PDM format. These shall be submitted with and substantively support the contractor’s monthly payment request and the signed look ahead report. The VA COR shall identify the five different report formats that the contractor shall provide.
B. The contractor shall be responsible for the correctness and timeliness of the computer-produced reports. The Contractor shall also responsible for the accurate and timely submittal of the updated project schedule and all CPM data necessary to produce the computer reports and payment request that is specified.
C. The VA shall report errors in computer-produced reports to the Contractor’s representative within ten calendar days from receipt of reports. The Contractor shall reprocess the computer-produced reports and associated diskette(s), when requested by the Contracting Officer’s representative, to correct errors which affect the payment and schedule for the project.
1.5 THE COMPLETE PROJECT SCHEDULE SUBMITTAL
A. Within 45 calendar days after receipt of Notice to Proceed, the Contractor shall submit for the Contracting Officer's review; three blue line copies of the interim schedule on sheets of paper 765 x 1070 mm (30 x 42 inches) and an electronic file in the previously approved CPM schedule program. The submittal shall also include three copies of a computer-produced activity/event ID schedule showing project duration; phase completion dates; and other data, including event cost. Each activity/event on the computer-produced schedule shall contain as a minimum activity/event ID, activity/event description, duration, budget amount, early start date, early finish date, late start date, late finish date and total float. Work activity/event relationships shall be restricted to finish-to-start or start-to-start without lead or lag constraints. Activity/event date constraints, not required by the contract, shall not be accepted unless submitted to and approved by the Contracting Officer. The contractor shall make a separate written detailed request to the Contracting Officer identifying these date constraints and secure the Contracting Officer’s written approval before incorporating them into the network diagram. The Contracting Officer’s separate approval of the Project Schedule shall not excuse the contractor of this requirement. Logic events (non-work) shall be permitted where necessary to reflect proper logic among work events, but shall have zero duration.
The complete working schedule shall reflect the Contractor's approach to scheduling the complete project. The final Project Schedule in its original form shall contain no contract changes or delays which may have been incurred during the final network diagram development period and shall reflect the entire contract duration as defined in the bid documents. These changes/delays shall be entered at the first
Battle Creek, Michigan VA Project No. 515-21-103
01 32 16.15 - 3/8
PROJECT SCHEDULES (SMALL PROJECTS – DESIGN/BID/BUILD)
update after the final Project Schedule has been approved. The Contractor should provide their requests for time and supporting time extension analysis for contract time as a result of contract changes/delays, after this update, and in accordance with Article, ADJUSTMENT OF CONTRACT COMPLETION.
B. Within 30 calendar days after receipt of the complete project interim Project Schedule and the complete final Project Schedule, the Contracting Officer or his representative, shall do one or both of the following:
1. Notify the Contractor concerning his actions, opinions, and objections.
2. A meeting with the Contractor at or near the job site for joint review, correction or adjustment of the proposed plan shall be scheduled if required. Within 14 calendar days after the joint review, the Contractor shall revise and shall submit three blue line copies of the revised Project Schedule, three copies of the revised computer-produced activity/event ID schedule and a revised electronic file as specified by the Contracting Officer. The revised submission shall be reviewed by the Contracting Officer and, if found to be as previously agreed upon, shall be approved.
C. The approved baseline schedule and the computer-produced schedule(s) generated there from shall constitute the approved baseline schedule until subsequently revised in accordance with the requirements of this section.
1.6 WORK ACTIVITY/EVENT COST DATA
A. The Contractor shall cost load all work activities/events except procurement activities.
The cumulative amount of all cost loaded work activities/events (including alternates) shall equal the total contract price. Prorate overhead, profit and general conditions on all work activities/events for the entire project length. The contractor shall generate from this information cash flow curves indicating graphically the total percentage of work activity/event dollar value scheduled to be in place on early finish, late finish. These cash flow curves shall be used by the Contracting Officer to assist him in determining approval or disapproval of the cost loading. Negative work activity/event cost data shall not be acceptable, except on VA issued contract changes.
B. The Contractor shall cost load work activities/events for guarantee period services, test, balance and adjust various systems.
C. The Contractor shall submit, simultaneously with the cost per work activity/event of the…