Amendment #05 to Request for Lease Proposals (RLP) #36C24W26R0077 for Santa Cruz, California, issued November 16, 2026, by the General Services Administration (GSA) modifies five key areas of the solicitation. The amendment clarifies parking requirements to mandate no fewer than on-site parking spaces required by local code (or approximately 5 spaces per 1,000 ABOA SF if no local minimum applies), with the Government reserving no more than 55 parking spaces that must be secured, lit, and included in rental costs. The occupancy requirement is revised to require space readiness within 12 months of Lease Award Date for existing space or 18 months for new construction, with an absolute maximum completion date of 30 months; the offeror's proposed schedule will be evaluated under Factor 2 (Qualifications and Past Performance). Exhibit 18 (FAR 52.204-24) is deleted from the RLP document list, as this representation has been consolidated into FAR 52.240-90, which offerors complete through the System for Award Management (SAM).

The amendment also requires submission of GSA Form 527 (Contractor's Qualifications and Financial Information) for the proposed General Contractor only, not the offeror itself, with the offeror's financial capability evaluated separately based on Volume II information. All page limits previously imposed on technical proposals are removed, including limits on case studies (Factor 2) and Operations and Maintenance Plan narratives (Factor 3), with flexibility for architectural renderings, site characteristic submissions, and documentation requirements. The page limit removal applies retroactively to all offers, including those received on November 9, 2026, and proposals will not be found unacceptable or rated lower for exceeding former page limits. Offerors must acknowledge receipt of this amendment by signature and return it with their proposal to the Lease Contracting Officer (LCO) and VA broker, with failure to acknowledge potentially resulting in offer rejection.

View the file

Other files

File Type Posted
Santa Cruz - RLP Amendment No 4.pdf PDF
AreaTable1.1_Rev1_093026.pdf PDF
Santa Cruz - RLP Amendment No 3.pdf PDF
ConceptualFloorPlanWithEPowerLocations_0930_26.pdf PDF
Santa Cruz - RFI Responses_100126.pdf PDF
Santa Cruz - Pre-bid Conference Transcript.pdf PDF
Santa Cruz - RLP Amendment No 2.pdf PDF
Santa Cruz - Pre-bid Presentation.pdf PDF
PRE-BID Conference Information.pdf PDF
AMENDMENT No. 1 RLP 36C24W26R0077- signed.pdf PDF
04.A Lease Appendix - Broker Project MAY 2026.pdf PDF
08. GSA Form 1364 - Attachment No. 1.xlsx XLSX spreadsheet
21. VA Handbook 6500.6 - Contract Security_MAR 2010.pdf PDF
19. Representation Regarding Certain Telecomm - FAR 52.204-24.pdf PDF
17. Cert and Commitment of Energy Performance_FEB 2026.pdf PDF
14. GSA Form 527 - Contractors Qualifications.pdf PDF
13. GSA Standard Form 330 - Architect Engineer Qualifications.pdf PDF
04.C Lease Appendix - New Construction MAY 2026.pdf PDF
01. GSA Template 3516 - Solicitation Provisions DEC 2025.pdf PDF
04.B Lease Appendix - CA Tax MAY 2026.pdf PDF
22. DOL County Wage Determination CA20260018.pdf PDF
06. Security Requirements FSL Secutity Level II.pdf PDF
05. Agency Specific Requirements.pdf PDF
03. Offeror Compliance Matrix FEB 2026.xlsx XLSX spreadsheet
36C24W26R0077.docx DOCX document
11. Past Performance List of References_FEB 2026.docx DOCX document
04.D Lease Appendix - Net of Utilities MAY 2026.pdf PDF
23. RLP Exhibit - Broker Project MAY 2026.pdf PDF
26. Seismic Offer Forms.pdf PDF
09. GSA Form 1364 - Proposal to Lease Space.pdf PDF
25. RLP Exhibit - Net of Utilities MAY 2026.pdf PDF
24. RLP Exhibit - New Construction MAY 2026.pdf PDF
20. GSA Template 3517B - General Clauses_April 2026.pdf PDF
0 - Santa Cruz - RLP - 36C24W26R0077 003.pdf PDF
16. Operations and Maintenance Plan Acknowledgement_FEB 2026.pdf PDF
12. Past Performance Questionnaire - PPQ_FEB 2026.docx DOCX document
07. GSA Form 1217 - Lessor's Annual Cost Statement.pdf PDF
10. VA Form 10091 - FSC Vendor File Request.pdf PDF
18. Offering Entity Acknowledgement Form.pdf PDF
00. No Proposal_Market Response Form_MAR 2026.pdf PDF
04. Santa Cruz - Draft Lease.pdf PDF
02. Pre-bid Registration Form - FEB 2026.pdf PDF
15. GSA Form 12000 - Prelease FPLS Evaluation - Part A or Part B.docx DOCX document
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lessor _______ Gov’t. ________ Page 1 of 4 Page _____ of _____

November 16, 2026

AMENDMENT # 05

RLP # 36C24W26R0077

Santa Cruz, CA

Purpose

This amendment makes the following changes to the Request for Lease Proposals (RLP):

1. Clarifies the parking requirement in Paragraph 1.02 C.

2. Revises the occupancy requirement in Paragraph 1.02 G.

3. Deletes Exhibit 18 (FAR 52.204-24) from the List of RLP Documents in Paragraph 1.06.

4. Requires GSA Form 527 for the General Contractor only (Paragraph 3.01 X).

5. Removes page limits from the technical proposal (Paragraph 3.02 D and Paragraph 4.03 C, Factors

1, 2 and 3).

Except as provided below, all other terms and conditions of the RLP remain unchanged.

Changes to the RLP

Change 1. Paragraph 1.02 C, Parking Delete sub-paragraph C in its entirety and replace it with the following:

C. The Property must provide no fewer than the number of on-site parking spaces required by local code for the offered Building and the Government’s intended use (or, if no local minimum applies, no fewer than approximately 5 spaces per 1,000 ABOA SF). Of the parking provided on the Property, the Government requires no more than 55 parking spaces (any combination of structured/inside or surface/outside parking spaces) reserved for the exclusive use of the Government. These reserved spaces must be secured and lit in accordance with the Security Requirements set forth in the Lease. Offeror must include the cost of the reserved parking as part of the rental consideration.

Paragraph 1.05 C (parking must be on site and adjacent to the building) is unchanged.

Change 2. Paragraph 1.02 G, Occupancy Delete sub-paragraph G in its entirety and replace it with the following:

G. The Government requires that the Space be ready for occupancy within 12 months of the Lease Award Date for a lease of existing space and within 18 months of the Lease Award Date for new construction, or by the completion date in the Lessor’s construction schedule approved by the LCO, whichever is later. In no event will the Government accept a completion date later than 30 months after the Lease Award Date. The Offeror’s proposed schedule will be considered in the evaluation of Factor 2, Offeror’s Qualifications and Past Performance.

Change 3. Paragraph 1.06 A, List of RLP Documents In the table of RLP documents, delete the row for Exhibit 18, “Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment – FAR 52.204-24,” and replace it with:

Exhibit 18: INTENTIONALLY DELETED

FAR 52.204-24 has been consolidated into FAR 52.240-90. Offerors complete the FAR 52.240-90 representation as part of their representations and certifications in the System for Award Management (SAM). Paragraph 3.01 SS is unchanged.

Lessor _______ Gov’t. ________ Page 2 of 4 Page _____ of _____

Change 4. Paragraph 3.01 X, GSA Form 527 Delete sub-paragraph X in its entirety and replace it with the following:

X. GSA Form 527 – Contractor’s Qualifications and Financial Information. Offeror must submit a completed GSA Form 527 for the proposed General Contractor (and any other entity proposed to act as the prime construction contractor), with all required sections addressing experience, financial capacity, and outstanding commitments. A GSA Form 527 is not required for the Offeror. The Offeror’s financial capability is evaluated based on the information required in Volume II.

Change 5. Page limits

a. Paragraph 3.02 D. Delete sub-paragraph D in its entirety and replace it with the following:

D. Offers must be organized and provided as set forth in the Offeror Proposal Compliance Matrix and adhere to the documentation requirements specified in the technical evaluation factors. To the extent items are missing or not adequately addressed in a proposal, the LCO may determine the proposal to be unacceptable and therefore excluded from the competition, at the sole discretion of the LCO.

b. Paragraph 4.03 C.1, Factor 1, IV. Factor 1 Documentation Requirements. Delete the text in its entirety and replace it with the following:

Offeror must include all documentation outlined in the submittal requirements above in Volume I.A

– Technical Proposal, labeled “Factor 1 – Technical Quality,” as follows:

• Architectural Concept & Building Design submissions must include narratives, renderings, and a reasonable number of drawings; renderings must not be duplicated in drawing sets.

• Quality of Site Characteristics & Development submissions must include narratives, renderings, and a reasonable number of drawings.

• Narratives should be concise. Marketing materials and duplicative images should not be included.

c. Paragraph 4.03 C.3, Factor 2, IV. Factor 2 Documentation Requirement. Delete the bullet “Case studies (no more than five) must be limited to two (2) pages each” and replace it with:

• Case studies are limited to no more than five.

All other Factor 2 documentation requirements, including the limit of five past performance references and PPQs, are unchanged.

d. Paragraph 4.03 C.5, Factor 3, IV. Factor 3 Documentation Requirements. Delete the bullet “Operations and Maintenance Plan narrative submissions are limited to five (5) pages” and replace it with:

• Operations and Maintenance Plan narratives should be concise.

e. Application. The page limits removed by this Change 5 no longer apply to any offer, including initial offers received on 11/9/2026. The Government will not find an offer unacceptable, or rate it lower, because it exceeded a page limit in effect before this amendment.

Acknowledgment Offerors must acknowledge receipt of this amendment by signing below and returning it to the LCO, with a copy to the VA broker. Failure to acknowledge this amendment may result in rejection of the offer.

Lessor _______ Gov’t. ________ Page 3 of 4 Page _____ of _____

END OF AMENDMENT

November 16, 2026

J.P. Niega Contracting Officer

Lessor _______ Gov’t. ________ Page 4 of 4 Page _____ of _____

Acknowledgement of Receipt

Amendment # 05 – 36C24W24R0070 – Santa Cruz, CA

Company______________________________________________________________________

Name_________________________________________________________________________

Title__________________________________________________________________________

Signature of Offeror____________________________________________Date________________________

Return and initial/sign this amendment with your Proposal.

2026-11-16T10:34:41-0800
JOHN PAUL NIEGA

File details come from the government source that posted it. Updated .