This document is a Solicitation (Standard Form 1442) for a construction services project issued by the Department of Veterans Affairs Network Contracting Office 9 in Murfreesboro, TN. The solicitation is for repair and restoration work at the Robley Rex VAMC in Louisville, Kentucky, specifically addressing storm and snow damage. The project, numbered 603-26-103, involves comprehensive repair services including culvert replacement, parking lot curb repairs, fence restoration, tree and limb removal, stump grinding, installing concrete parking stops, drainage system repairs, and underground drain installation.
The solicitation is 100% set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) with a project magnitude between $25,000 and $100,000. Key dates include a site visit on December 12, 2025, a deadline for Request for Information (RFI) submissions on December 26, 2025, and the official bid opening on January 6, 2026 at 2:00 PM EDT via Microsoft Teams. Bidders must have an active System for Award Management (SAM) registration and be listed in the SBA Dynamic Small Business Search (DSBS), with electronic bid submissions required via email. The project aims to improve safety and functionality of the medical center's facilities and grounds by addressing infrastructure damage.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24926B0001 0002.docx | DOCX document | |
| Attachment 2 RFI Responses - 603-26-103 - Storm and Snow Damage Repair.pdf | ||
| Attachment 1 Sign In Sheet Site Visit 603-26-103 Repair Storm and Snow Damage.pdf | ||
| 36C24926B0001 0001.docx | DOCX document | |
| Attachment 7 Request For Information Form.docx | DOCX document | |
| Attachment 5 General Conditions Breakout.xlsx | XLSX spreadsheet | |
| Attachment 1 Drawings - S-1 Rev 1.pdf | ||
| Attachment 6 Contractor EMR Certification Form.docx | DOCX document | |
| Attachment 2 - 17A Drain Issue Image.png | PNG image | |
| Attachment 8 Wage Dermination Number KY20240093 - Modification 9 - 8-22-2025.pdf | ||
| Attachment 4 Calculation of Self Performed Work.xlsx | XLSX spreadsheet | |
| Attachment 3 Pricing Schedule.xlsx | XLSX spreadsheet |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C24926B0001
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE
DOCUMENTS (
Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24926B0001 X 12-05-2025 603-26-1-2311-0003 603-26-103 90C Department of Veterans Affairs Network Contracting Office 9 (90C)
NCO 9
1639 Medical Center Parkway, Suite 204 Murfreesboro TN 37129 Robert Glenn robert.glenn2@va.gov
Robert Glenn Jr 615-225-3413 This project is for construction services to Repair Storm and Snow Damage at the Robely Rex VAMC, Louisville
, KY.
The Contractor shall complete all work required per the construction documents for Project #603-26-103: Repair Storm and Snow Damage. Work includes general construction, alterations and removing hazardous conditions such as fallen trees and damaged infrastructure.
See: Important Bidders Information NAICS Code: 238990 Building and Property Specialty Trade Services Size Standard: $19M Project Magnitude is between $25,000 and $100,000
Set-Aside: 100% Service-Disabled Veteran Owned Small Business (SDVOSB) (See VAAR Clause 852.219-10).
In order to be eligible to receive an award under this solicitation, the SDVOSB contractor must be listed and viewable in the SBA Dynamic Small Business Search (DSBS) https://dsbs.sba.gov/search/dsp_dsbs.cfm at the time bids are due and at the time the time of award. Consequently, bidders in reverification status will not be eligible to submit bids for this project.
Please include a copy of SBA Dynamic Small Business Search (DSBS) certification verification. In accordance with FAR 52.204-7, System for Award Management (SAM), all prospective bidders must have an active SAM registration at the time of bids due and award.
Site Visit: December 12, at 2:00 PM, EDT at Robely Rex VAMC, Engineering B-018. SEE FAR 52.237-1 for additional information. In accordance with FAR 52.204-7, all prospective bidders must have an active SAM registration at time of bids due and award.
To obtain clarifications and/or additional information concerning the contract requirement, Scope of Work and/or drawings, submit a written request for information (RFI) via email to Robert.glenn2@va.gov. RFIs must be specific in identifying section, paragraph, and page number and mustbe in question format. All RFIs submitted shall include the project number and title, contractor name, city, state, phone number, date submitted and RFI questions. Questions received after 2:00 PM EDT, December 26, 2025, will not be answered unless determined to be in the best interest of the government. Telephone requests will NOT be accepted. Technical questions will not be answered at the site visit as questions MUST BE in writing and submitted as an RFI.
The official bid opening will be January 6, 2026, at 2:00PM EDT and will occur via Microsoft Teams meeting. Please call 1-205-235-3524 Conf. No. 122 874 961# five minutes before the bid opening to be present for the bid opening.
Submit electronic copy of bids with bid bond(s) via email to robert.glenn2@va.gov and matthew.whisman@va.gov. All bid documents must be received on or before the due date/time stated in Block 13.
X 52.211-10 X
2PM
EST
01-06-2026 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER
THAN
FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
Bid Item:
603-3660162-2311-854200-3223 23NRNR001
90C Network Contracting Office 9 Department of Veterans Affairs Network Contracting Office (90C) 1639 Medical Center Parkway Suite 204 Murfreesboro TN 37129 90C FSC e-Invoicing Payment http://www.fsc.va.gov/fsc/einvoice.asp Invoice Setup Information 1-877-489-6135 Invoice must be submitted electronically
Setup 1-877-489-6135 X Matthew R. Whisman Contracting Officer
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| STATEMENT OF WORK | 5 |
| A.3 PRICE/COST SCHEDULE | 8 |
| ITEM INFORMATION | 8 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 9 |
| A.4 IMPORTANT BIDDER INFORMATION | 9 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 17 |
| 2.1 52.216-1 TYPE OF CONTRACT (APR 1984) | 17 |
| 2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 17 |
| 2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 17 |
| 2.4 52.228-1 BID GUARANTEE (SEP 1996) | 18 |
| 2.5 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021) | 19 |
| 2.6 52.240-90 SECURITY PROHIBITIONS AND EXCLUSIONS REPRESENTATIONS AND CERTIFICATIONS (NOV 2025) (DEVIATION) | 19 |
| 2.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 23 |
| 2.8 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 24 |
| REPRESENTATIONS AND CERTIFICATIONS | 24 |
| GENERAL CONDITIONS | 24 |
| 4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 24 |
| 4.2 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JAN 2025) | 24 |
| 4.3 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020) | 28 |
| 4.4 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022) | 28 |
| 4.5 52.240-91 SECURITY PROHIBITIONS AND EXCLUSIONS (NOV 2025) (DEVIATION) | 33 |
| 4.6 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 42 |
| 4.7 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020) | 43 |
| 4.8 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 45 |
| 4.9 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 46 |
| 4.10 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 2019) | 47 |
| 4.11 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 47 |
| 4.12 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) | 47 |
| 4.13 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 48 |
| 4.14 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 49 |
| 4.15 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 49 |
| 4.16 List of Attachments | 52 |
STATEMENT OF WORK
INTRODUCTION.
1.1. Repair and rectify damage sustained from recent storm and snow events, ensuring safety and functionality of the facilities, grounds and surrounding areas at Robley Rex VA Medical Center, Louisville, KY. This project is essential to improve safety for patients, staff, and visitors by removing hazardous conditions such as fallen trees and damaged infrastructure. Moreover, these repairs are critical to restore the full functionality of the medical center grounds, enhancing accessibility, security, and overall operational efficiency.
PART 2 - WORK DESCRIPTION
2.1. Culvert Repair
A. Inspection: Conduct a thorough inspection of all culverts to assess the extent of damage.
B. Replacement:
1. Storm Drain Culverts (Parking Lots/Roadways): Remove and replace three culverts in the parking lots/roadways with recessed flat grates/grilles that shall have a Class D load rating, including removing any hardened asphalt and/or concrete from culvert basin drains.
2. Storm Drain Culvert (Loading Dock): Replace the remaining storm drain culvert in the curb opposite the loading dock to match existing conditions.
3. Basin across from Lot 17. Refer to Lot 17 Drainage Repair.
4. Remove hardened asphalt and/or concrete from culvert basin drain adjacent to Lot 17.
2.2. Parking Lot Curbs
A. Inspection: Identify and mark all damaged curbs in the parking lot areas as indicated in the attached drawing.
B. Replacement: Replace curbs that are significantly damaged or missing with 8" 5000psi concrete curbs.
C. Repair: Repair identified damages to curbs in the attached drawing to match the existing materials and finish including:
1. Patch/repair curb in front of Bldg. 7 Laundry
2. Patch/Repair curb in front of Bldg. 8 Boiler Plant
2.3. Fence Repair Along Country Club Road
A. Inspection: Assess the entire length of the fence along Country Club Road, consisting of wooden posts with two (2) steel cables running through them, for damage from the storm and snow.
B. Repair:
1. Replace any broken wooden posts.
2. Straighten the fence by resetting any leaning or misaligned posts to their correct positions. This shall include fill rock or concrete at the base to stabilize.
3. Reinforcement: Ensure all repaired sections are secure and stable.
2.4. Tree and Limb Removal
A. Fallen Trees and Limbs: Remove all fallen trees and limbs from the property to clear grounds and maintain safety, this excludes the wooded areas.
B. Assessment: Identify all areas where trees and limbs have fallen.
C. Removal: Remove leaning tree at west side of Lot 6 on fence line with apartments Safely cut and remove all debris.
D. Disposal: Dispose of all tree and limb debris in an environmentally responsible manner.
E. Standing Tree Stump Grinding
1. Identification: Locate the standing tree stump that needs to be ground down following the damaged tree felling by others.
2. Stump Grinding: Remove stump at west side of Lot 6 and remove stump along Country Club road at wooden fence & road line. Grind down the stump to prevent obstacle hazards and potential regrowth.
3. Clean-Up: Ensure the area is clear of all debris and is safe post-removal.
2.5. Concrete Parking Stops
A. Provision and Installation: Provide and install 50 concrete parking stops to replace broken and damaged stops, as directed by the COR. Installation shall be conducted on a weekend.
B. Removal and Disposal: Remove and dispose of old, damaged parking stops in an environmentally responsible manner.
2.6. Lot 17 Drainage Repair
A. Inspection: Identify the drain basin emptied from Lot 17 24” drain and subsequent 8” flow restricting and backing up storm runoff.
B. Replacement: Remove existing underground basin and culvert drain. Reinstall new basin replacing 8” Lot 17 drainage restriction with 24” inlet. Reinstall existing drainage to Lot 22, any remaining existing inlets/outlets and add new 24” overflow outlet to adjacent ditch. New 24” outlet shall be at the same elevation or no more than 12” lower that the Lot 17 drain inlet. New 24” overflow shall be routed to adjacent ditch and provided a 24” daylight outlet solution to prevent overflow. New 24” outlet shall have a grate at the end to prevent pest infiltration and if horizontal at ditch elevation shall be periscoped to prevent debris clogging the outlet. Contractor shall make all necessary excavation of the adjacent ditch so that overflow is below Lot17 drain and is downhill in accordance with original flow design.
2.7. Add Underground Drain
A. Inspection: Identify the AHU drain against BLDG 1 as shown in the attached Photo.
B. Install: Run a drain underground on either side and potentially a rock run off trench on the right side of the sidewalk to prevent water and/or freezing on or along sidewalk & surfaces.
2.8. Repair Bldg. 4 Storm Line
A. Inspection: Identify and mark 12” terracotta collapsed and/or blocked storm drain line in front of Bldg. 4 as shown in drawings.
B. Replacement: Replace and repair drain line as necessary. Restore any landscaping, sidewalks, and/or parking lots damaged by replacement.
PART 3 - SAFETY AND COMPLIANCE
3.1. Safety Protocols: Implement all necessary safety measures to protect workers, VA Medical Center staff, and visitors during the repair and removal processes.
3.2. Regulatory Compliance: All work must comply with relevant local, state, and federal regulations, as well as VA policies and procedures.
3.3. Environmental Considerations: Ensure that all materials removed, especially trees and debris, are disposed of in an environmentally responsible manner.
3.4. Contractor shall provide all road and parking lot barriers & signage necessary to accomplish repair work. Includes erecting barriers early to prevent parking spaces from being used as necessary. Contractor shall provide all flaggers, and traffic control, etc as necessary when conducting work or impeding traffic in roadways.
PART 4 - SCHEDULING AND COMPLETION
4.1. Hours of Operation
A. RRVAMC’s normal hours of operation are 8:00 am - 4:30 pm. All work associated with this contract not impacting hospital operations will be conducted during those hours unless the contractor has received prior approval from the COR. Any work that does impact hospital operations shall be conducted after-hours and coordinated with the COR.
4.2. Coordination
A. All coordination shall be with the on-site Contracting Officer Representative (COR).
B. The Contractor is responsible to coordinate and pay for all underground utility locates required.
4.3. Deliverables:
A. Complete replacement of the four storm drain culverts identified in the attached drawing, including recessed flat grates with a load class of D and additional load class D grates installed 12" into the parking lot from two culverts.
B. Fully repaired or replaced parking lot curbs identified in the attached drawing, with replacements using 8" 5000psi concrete curbs and repairs matching existing curbs.
C. Repaired and secure perimeter fences along Country Club Road with correctly reset fence posts.
D. Removal of all fallen trees and limbs.
E. Grinding down of standing tree stump.
F. Provision, installation, and disposal of concrete parking stops.
4.4. Timeline.
A. Provide a detailed project schedule outlining key milestones and expected completion dates, aiming for project completion within 90 days from the start date, weather permitting.
END SCOPE OF WORK
A.3 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| __________________ |
| __________________ |
603-26-103 REPAIR STORM AND SNOW DAMAGE REPAIR SCOPE OF WORK: Contractor will repair and rectify the damages sustained from recent storm and snow events, ensuring safety and functionality of the facilities, grounds and surrounding areas at Robley Rex VA Medical Center To include: Culvert replacement, Parking lot curbs, Fence repair along Country Club Road, Bollard replacement (Zorn and Country Club), Tree and Limb Removal, Standing tree stump grinding, Concrete parking stops, Parking Lot 17 Drainage Repair, adding underground drain, repair Building 4 Storm Line
| GRAND TOTAL |
| __________________ |
36C24926B0001
Page 1 of Page 1 of
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
A.4 IMPORTANT BIDDER INFORMATION
IMPORTANT BIDDER INFORMATION
BIDDING MATERIALS: All bidding materials consisting of drawings, specifications, contract forms, Amendments, and other documents will be posted to the Contract Opportunities Government website located at https://sam.gov/. This is the only official location where these documents can be obtained and where updates are posted. No ‘hard copy’ bidding materials are available.
BID SUBMISSION: The following documents must be included in the bid submission in the formats as stated:
| - | One (1) electronic original, fully completed and signed and dated SF 1442 Offer page, acknowledgment of all amendments issued by either completing block 19 of the SF1442 or completing blocks 15a, b, and c of the Amendment(s) and providing them with the SF 1442 Offer page; bid prices on all line items listed on the Price/Cost Schedule; completed Representations and Certifications section (FAR 52.204-8, 52.209-5 (Deviation), and 52.209-7); and fully completed Contractor Experience Modification Rate (EMR) Certification documents. |
| - | One (1) electronic original, completed and signed, SF 24 Bid Bond or other allowable Bid Security. Document shall be emailed to the Contract Specialist/Contracting Officer responsible for solicitation in accordance with FAR 28.101 and FAR 28.102. Any missing elements of the bid submission could render the offeror ineligible and their bid will not be considered. |
Contracting Officer – Matthew R. Whisman – Matthew.Whisman@va.gov Bidders are responsible for ensuring and verifying their offer and all required bid documents are received at the office and point of contact designated in block 8 of the SF 1442 and by the date and time specified in block 13A of the SF 1442 (subject to amendment).
The official bid opening will be January 6, 2026 at 2:00PM ET and will occur via Microsoft Teams call-in at the following number/code: +1 205-235-3524, Phone Conference ID: 122 874 961#
PROJECT INFORMATION
PROJECT TITLE AND NUMBER: 603-26-103 Repair Storm and Snow Damage PROJECT LOCATION: Robely Rex VAMC, Louisville, KY NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM CODE: (NAICS): 238990 – Building and Property Specialty Trade Services SMALL BUSINESS SIZE STANDARD: $19 Million TYPE OF SET-ASIDE: This solicitation is a 100% set-aside for SERVICE-DISABLED VETERAN OWNED SMALL BUSINESS (SDVOSB).
Federal Holidays. Federal law (5 U.S.C. 6103) establishes the following public holidays for Federal employees: New Year’s Day, Birthday of Martin Luther King, Jr., Washington’s Birthday, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day. Please note that most Federal employees work on a Monday through Friday schedule. For these employees, when a holiday falls on a non-workday -- Saturday or Sunday -- the holiday usually is observed on Monday (if the holiday falls on Sunday) or Friday (if the holiday falls on Saturday).
All contractors are required to complete the VA Privacy Training for Personnel without Access to VA Computer Systems or Direct Access or Use to VA Sensitive Information. A copy of the signed training must be submitted to the COR and uploaded into VA Talent Management System (TMS).
Contractor employees shall not be considered government employees for any purpose under this contract.
Changes to any resultant contract may only be made by a written modification which is formally executed by the contractor and the Contracting Officer.
DATABASE REGISTRATION INFORMATION
SYSTEM FOR AWARD MANAGEMENT (SAM) REGISTRATION: The System for Award Management (SAM) website located at https://sam.gov is the Official U.S. Government system that consolidated the capabilities of the Central Contractor Registration (CCR including FedReg), Online Representations and Certifications Application (ORCA), and the Excluded Parties List System (EPLS). Federal Acquisition Regulations require that federal contractors wishing to do business with the Government and bid on work shall have an active registration in SAM. If the Offeror does not have an active registration in the SAM database at the time of bid submission and are the apparently successful low offeror, the Contracting Officer shall prescribe a time within which the offeror shall have an active registration in SAM; otherwise the Contracting Officer shall deem the offeror’s bid non-responsive to the solicitation requirements and proceed to award to the next lowest offer.
THE EXCLUDED PARTIES LIST SYSTEM (EPLS): To ensure that the individuals or businesses providing services under the contract have not engaged in fraud or abuse regarding Sections 1128 and 1128A of the Social Security Act regarding federal health care programs, the contractor is required to check the Excluded Parties List System (EPLS) located at https://sam.gov for each person or business providing services under this contract. During the performance of this contract the Contractor is prohibited from using any individual or business listed on the List of Excluded Individuals/Entities.
VETS-4212 REPORTING REQUIREMENT: Contractors are required to submit a required annual Form VETS-4212, Federal Contractor Veterans' Employment Report in all cases where the contractor or subcontractor has received an award of $150,000 or more in any fiscal year. Contracting Officers are prohibited from awarding a contract to a contractor that has not submitted a required VETS-4212 Report with respect to the preceding fiscal year if the contractor was subject to the reporting requirement of 38 U.S.C. 4212(d). Submit this report as soon as possible, if not already submitted, to avoid delays in the contract award process. For more information on this requirement and/or for completing the web-based reporting form, visit the following website https://www.dol.gov/agencies/vets/programs/vets4212. See FAR provision 52.222-38, Compliance with Veterans' Employment Reporting Requirements (FEB 2016) under the Representations, Certifications and Other Statements of Offerors, and FAR clause 52.222-37, Employment Reports on Veterans (FEB 2016) under the General Conditions.
BONDING INFORMATION
BID GUARANTEE: A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, shall require rejection of the bid in all cases except those listed in Federal Acquisition Regulation (FAR) 28.101-4. Bid Bonds must be provided using Standard Form 24 (see FAR 28.106-1) and the form must be provided in email and contain the proper solicitation number, bid opening date, and be from a corporate surety listed in Department of Treasury Circular 570. Individual sureties shall be determined acceptable to the Contracting Officer (see FAR 28.203) and be accompanied by Standard Form 28 Affidavit of Individual Surety. Other forms of bid security may be acceptable as denoted in FAR Part 28.203-2.
PERFORMANCE AND PAYMENT BONDS: In accordance with Contract Clause 52.228-15, and FAR 28.102, Contractors are reminded that any amount awarded over $35,000.00 shall require a Payment Bond (SF 25A), and awards exceeding $150,000.00 shall require both Payment and Performance Bonds (SF 25). Payment and Performance bonds are due no later than 10 days after notification of award. Bonds must be provided with original ‘wet ink’ signatures - no white-outs or other corrections are allowable. Electronic submission via email only.
SECURITY
BACKGROUND INVESTIGATIONS: All contractor employees are subject to the same level of investigation as VA employees who have access to VA Sensitive Information. The level of background investigation is commensurate with the level of access needed to perform the statement of work. This requirement is also applicable to all subcontractor personnel requiring the same level of access.
Levels and associated types of Background Investigations:
· If the project requires that workers have only limited physical access to the VA facility for a period of one year or less, a local flash badge with fingerprint check is issued.
· If the project requires that workers require un-supervised, logical and/or physical access for 180 consecutive or aggregate days in a 365-day period, over a 3-year period, a background investigation may be required (Special Agency Check (SAC)) which must be completed prior to being allowed access.
· If the project requires that workers have access to a VA Network (such as the Building Management System) or un-supervised, full-time, logical, and/or restricted physical access for more than 6 months or more than 180 aggregate days in a one-year period, a background investigation is required (Special Agency Check and National Agency Check with Written Inquiries (NACI)) and access is not allowed until a favorable SAC completion.
All costs for SAC and NACI checks are borne by the contractor. The VA may at its discretion make deductions against the contract in order to recoup the investigation costs. The estimated cost for a SAC is $30.00 per employee and the estimated cost for a NACI check is $408.00 per employee (subject to change at any time).
MEDICAL CENTER ACCESS: Anyone participating in the site visit, or for any other reason that involves visiting the medical center related to this solicitation, must have a valid ID on their person and their vehicle must be properly registered and insured. Visitors are prohibited from possessing weapons while on a federal installation (See 18 USC 930 – Possession of Firearms and Dangerous Weapons in Federal Facilities). Handheld cellphone usage or texting while driving is also prohibited. All VA Medical Centers and associated properties are Federal Property.
PRIVACY TRAINING: All workers regardless of project length must take VA Privacy Training which will be coordinated after project award with the Contracting Officer’s Representative.
E-VERIFY SYSTEM: Companies awarded a contract with the federal government shall enroll in E-Verify within 30 days of the contract award date. They shall also begin using the E-Verify system to confirm that all of their new hires and their employees directly working on federal contracts are authorized to legally work in the United States. E-Verify is an Internet-based system that allows an employer, using information reported on an employee's Form I-9, to determine the eligibility of that employee to work in the United States. There is no charge to employers to use E-Verify. (FAR 52.222-54).
PRIME CONTRACTOR INFORMATION- SAFETY OR ENVIRONMENTAL VIOLATIONS AND EXPERIENCE MODIFICATION RATING INFORMATION All Bidders/Offerors shall submit information pertaining to their past Safety and Environmental record (using the attached EMR information/data form). The information must contain a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years. If such certification cannot be made, a Bidder/Offeror shall explain why and submit as much information as possible regarding the circumstances of its past safety and environmental record, including the number of EPA violations and/or the number of serious, repeat, and/or willful OSHA violations, along with a detailed description of those violations.
All Bidders/Offerors shall submit information regarding their current Experience Modification Rate (EMR). This information shall be obtained from the Bidders/Offeror’s insurance carrier and be furnished on the insurance carrier’s letterhead. If a Bidder/Offeror’s EMR is above 1.0, Bidder/Offeror must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the elevated EMR and the anticipated date the EMR may be reduced to 1.0 or below.
Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and Puerto Rico shall obtain their EMR rating from their state-run worker’s compensation insurance rating bureau.
If the NCCI cannot issue an EMR because the Bidder/Offeror lacks insurance history, Bidder/Offeror shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier’s letterhead and include a letter from the NCCI indicating that it has assigned Bidder/Offeror a Unity Rating of 1.0.
The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make an initial Determination of Responsibility.
This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.
CONFORMANCE WITH ENVIRONMENTAL MANAGEMENT SYSTEMS: The Contractor shall perform work under this contract consistent with the relevant policy and objectives identified in the agency, organizational, or facility Green Environmental Management System (GEMS) applicable for the contract. The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by the agency, organizational, or facility GEMS, and provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In the event an environmental nonconformance or noncompliance associated with the contracted services is identified, the contractor shall take corrective and/or preventative actions. In the case of a noncompliance, the Contractor shall respond and take corrective action immediately. In the case of a nonconformance, the Contractor shall respond and take corrective action based on the time schedule established by the facility GEMS Coordinator. In addition, the Contractor shall ensure that their employees are aware of the roles and responsibilities identified by the environmental management system and how these requirements affect their work performed under this contract.
All on-site contractor personnel shall complete yearly EPA sponsored environmental training specified for the type of work conducted on-site. Upon inclusion in the contract, the Contracting Officer's Representative will verify that all contractor personnel have acquired EMS Awareness Training at their appropriate site or location.
REFERENCES TO VA ENGINEER, RESIDENT ENGINEER, SENIOR RESIDENT ENGINEER, OR PROJECT MANAGER: Any reference contained within contract specifications and/or drawings to the “VA Engineer”, “Resident Engineer”, “Senior Resident Engineer”, “Project Manager”, or their abbreviations are to be replaced with “Contracting Officer’s Representative (COR)”.
PAYMENT FOR MATERIALS STORED OFF-SITE: Payment in advance of installation for materials stored off-site is not authorized under this contract unless otherwise approved by the Contracting Officer.
SCHEDULE OF MATERIAL SUBMITTALS: The submittals contemplated by FAR 52.236-5, Material and Workmanship, are listed on the Schedule of Material Submittals in the Specifications, if provided. The schedule is for reference only – the selected contractor is responsible to provide all submittals required by the contract.
REVIEW REQUIRED REGISTRATION WITH CONTRACTOR PERFORMANCE ASSESSMENT SYSTEM (CPARS) As prescribed in Federal Acquisition Regulation (FAR) Part 42.15, the Department of Veterans Affairs (VA) evaluates contractor past performance on all contracts that exceed $750,000 and shares those evaluations with other Federal Government contract specialists and procurement officials. The FAR requires that the contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement VA uses an online database, CPARS, which is maintained by the Naval Seal Logistics Center in Portsmouth, Virginia. CPARS has connectivity with the Past Performance Information Retrieval System (PPIRS) database, which is available to all Federal agencies. PPIRS is the system used to collect and retrieve performance assessment reports used in source selection determinations and completed CPARS report cards transferred to PPIRS. CPARS also includes access to the federal awardee performance and integrity information system (FAPIIS). FAPIIS is a web-enabled application accessed via CPARS for contractor responsibility determination information.
Each contractor whose contract award is estimated to exceed $750,000 is required to register with CPARS database at the following web address: www.cpars.csd.disa.mil. Help in registering can be obtained by contacting Customer Support Desk at 207-438-1690. Registration should occur no later than thirty days after contract award and must be kept current should there be any change to the contractor's registered representative.
For contracts with a period of one year or less, the contracting officer will perform a single evaluation when the contract is complete. For contracts exceeding one year, the contracting officer will evaluate the contractor's performance annually. Interim reports will be filed each year until the last year of the contract, when the final report will be completed. The report shall be assigned in CPARS to the contractor's designated representative for comment. The contractor representative will have thirty days to submit any comments and re-assign the report to the VA contracting officer.
Failure to have a current registration in the CPARS database, or to re-assign the report to the VA contracting officer within those thirty days, will result in the Government's evaluation being placed on file in the database with a statement that the “contractor failed to respond.”
NATIONAL ARCHIVES AND RECORDS ADMINISTRATION RECORDS POLICIES
1. Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.
2. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.
3. In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.
4. The Government and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of the Government or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity (HCA). Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, the contractor must report it to Government Contracting Officer. The agency must report promptly to NARA in accordance with 36 CFR 1230.
5. The Contractor shall immediately notify the appropriate Government Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the [contract vehicle]. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to the Government’s control or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer who awarded the contract. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).
6. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts. The Contractor (and any sub-contractor) is required to abide by all Government guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.
7. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with the project location VA Medical Center’s written policy.
8. The Contractor shall not create or maintain any records containing any non-public Government information that are not specifically tied to or authorized by the contract.
9. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.
10. The Government owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S. Government and shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.
11. Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take VHA-provided records management training, Talent Management System (TMS) Item #3873736, Records Management for Records Officers and Liaisons. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training. All training shall be coordinate with the Contracting Officer’s Representative assigned to the contract.
END OF IMPORTANT BIDDER INFORMATION SECTION
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.4 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3 Million, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
2.5 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)
(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—
(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and
(2) Standard Form 28, Affidavit of Individual Surety.
(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.
(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.
(End of Provision)
2.6 52.240-90 SECURITY PROHIBITIONS AND EXCLUSIONS REPRESENTATIONS AND CERTIFICATIONS (NOV 2025) (DEVIATION)
(a) Definitions. As used in this provision— Backhaul, covered article, covered telecommunications equipment or services, critical technology, FASCSA order, Intelligence community, interconnection arrangements, national security system, roaming, sensitive compartmented information, sensitive compartmented information system, source, and substantial or essential component have the meanings provided in the clause 52.240-91, Security Prohibitions and Exclusions.
Business operations means engaging in commerce in any form, including by acquiring, developing, maintaining, owning, selling, possessing, leasing, or operating equipment, facilities, personnel, products, services, personal property, real property, or any other apparatus of business or commerce.
Marginalized populations of Sudan means—
(1) Adversely affected groups in regions authorized to receive assistance under section 8(c) of the Darfur Peace and Accountability Act (Pub. L. 109-344) (50 U.S.C. 1701 note); and
(2) Marginalized areas in Northern Sudan described in section 4(9) of such Act.
Restricted business operations means business operations in Sudan that…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .