About this file

This document is an Amendment to a Solicitation for the Department of Veterans Affairs (VA) project titled "BB Install Continuous Water Quality for Legionella Directive Compliance" at the James A. Haley Veteran's Hospital in Tampa, FL. The amendment includes detailed responses to 61 Request for Information (RFI) questions covering various technical aspects of the water monitoring system installation, including device specifications, installation requirements, electrical connections, and project logistics. Key details include the use of ConCube V3 water monitoring devices to be installed in multiple buildings, wireless communication capabilities, and integration with the VA's BACnet system, with no commissioning required and VA Directive 1061 governing water quality monitoring standards.

The project involves installing continuous water quality monitoring devices at various locations within the hospital complex, with specific requirements for device placement, power connections, and communication protocols. Contractors can use devices from manufacturers other than Badger Meter as long as they meet or exceed current requirements and integrate into the Johnson Controls (JCI) system. The amendment clarifies staffing roles, allowing the project manager to serve as QA/QC and the superintendent to serve as SSHO, with specific restrictions on "triple hatting" roles. No additional ongoing services are included beyond the standard 1-year warranty, and the VA will handle future maintenance through a separate contract.

View the file

Other files

File Type Posted
36C24825R0164 0004.pdf PDF
36C24825R0164 0003.pdf PDF
Basis of Design TAB A.pdf PDF
Plumbing Drawings - Addendum 1.pdf PDF
Electrical Drawings - Addendum 1.pdf PDF
S06 36C24825R0164 0001 10.9.25.pdf PDF
S02 36C24825R0164_1 with Attchs.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 7

0002 10-28-2025

673-23-107

36C248

Department of Veterans Affairs Network Contracting Office 8 (NCO 8)

8875 Hidden River Pkwy Suite 525 Tampa FL 33637

36C248

Department of Veterans Affairs Network Contracting Office 8 (NCO 8)

8875 Hidden River Pkwy Tampa FL 33637

To all Offerors/Bidders

36C24825R0164

X

X X

X 1

Project Name: BB Install Continuous Water Quality for Legionella Directive Compliance Project Number: 673-23-107 Project Location: James A. Haley Veteran’s Hospital, 13000 Bruce B. Downs Boulevard, Tampa, FL 33612

See page 2 for amendment information.

Stacy Figlinski Contracting Officer

10-28-2025

PROJ: 673-23-107 BB Install Continuous Water Quality for Legionella Directive Compliance Solicitation 36C24825R0164 Amendment 0002

This amendment provides the remaining RFI answers below:

1. Please clarify if the project will require a full time QA/QC and/or a full time SSHO.

Response: No, will need a QA/QC (can duel hat as the PM) as the Superintendent/SSHO can’t triple hat.

2. Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO?

Response: Yes.

3. Please clarify if a project manager can be a dual hat to cover the requirements of QA/QC?

Response: Yes the PM can cover the requirements of the QA/QC.

4. Can a superintendent be a triple hat to cover the requirements of SSHO and QA/QC?

Response: No.

5. Do any of the existing spaces contain asbestos or hazardous material?

Response: No Known ACM/Hazardous material are in any of the spaces. Drawings are Available that show our current survey that happened. If anything is suspected to notify the

COR ASAP.

6. Will the wireless devices shown to be attaching to the domestic waterlines be able to communicate with the Metasys by themselves or will they need an additional piece of equipment to communicate with the system?

AE Response: Refer to schematic diagram on drawing P903. Confirm and coordinate with vendor.

7. Has a survey been completed to ensure that these wireless devices will be able to communicate to the monitoring system without the use of additional repeaters?

AE Response: No survey conducted. Provide additional repeaters as needed for complete installation.

8. If additional repeaters are required for communication connectivity, will those be part of this project scope?

AE Response: Provide additional repeaters as needed for complete installation.

9. Will this project schedule occur along with the scheduled completion of the new water tower or will the project need to extend in order to coincide with that completion?

Response: No, the Water tower will not be done before this project is completed. No we shouldn’t have to extend, at time of award we can discuss out we want to handle the Devices that is going at the new water tower.

10. Can you please clarify the location of where the monitoring device should be located in building 38? The photo shown on 6/P901 is difficult to identify an exact location.

AE Response: The monitoring device to be mounted on the incoming water line anywhere just inside the pipe tunnel prior to entering the crawlspace/basement.

11. Will any of locations where conduit is to be installed be passing through an area containing asbestos?

AE Response: Asbestos was not observed on site during design. Asbestos report available upon request to the VA.

12. Referencing Drawing.pdf, Sheet E400, Keynote 2- states to provide a pathway for the BACnet -Modbus gateway device. For each monitoring location where should conduit be run back to for BACnet to tie-in?

AE Response: There will be only one Modbus Gateway needed for all monitoring devices to communicate to the VA BACnet system. Provide cabling and conduit as needed to tie into the VA BACnet. Coordinate tie-in location with VA. Confirm final requirements with vendor.

13. Does the "domestic water monitoring display" require conduit to be installed to bring cabling from a certain location to the display?

AE Response: A communication cable and conduit is required between the VA server and the Monitoring Panel. Refer to RFI 12 above for additional information.

14. Does the "domestic water monitoring display" require power source to be installed at its proposed location or is there a power source existing?

AE Response: Display shall be connected to the nearest local receptacle. Location shall be coordinated in field. Provide a new receptacle and connect to the nearest local receptacle circuit with available capacity, if one is needed.

15. Can a cut-sheet be provided for the Metasys device which lists the power and connections required for installation?

AE Response: “METASYS” should be removed and replace with Gateway Protocol. Refer to attached TAB A for data sheet on gateway device.

16. Does the monitoring device require 3 phase power? Page ES 100 Keynote 1. It's asking for 3 #12s plus 1 #12 Ground. Are they looking to have 3 phases or 2 phases and a neutral?

AE Response: It does not require 3-phase power. Please provide 2#12 + 1#12G in ¾” conduit.

17. On page ES 100, the plans call for a monitoring device at the site of the future water tower.

What are the plans for this device? Install this device after the tower's completion? Leave the job open until completion or assign a new job number once the tower is complete.

AE Response: VA to advise at what time to install the water monitoring system. Design intent is to provide power and communication at the water tower location.

18. Note 17 is dictating a different color scheme from the norm. Are we ignoring this note.

AE Response: Note shall be ignored.

19. Note 53 dictates that there needs to be an Arc Flash Hazard Analysis on the entirety of the distribution system. This has been done in the last 3 years. The prints call for a 20-amp breaker to be installed into an existing panel. Is this Arc Flash Hazard Analysis necessary?

AE Response: Arch flash study not required.

20. Will the VA accept VA healthcare projects as defined in the solicitation as a relevant project, if the projects do not have a water quality/VHA Directive 1061 component to the scope of work?

Response: Yes, however if there is no plumbing work/ Water management involved in Project will not score as high.

21. Please provide the Basis of Design (BOD) for the water sensors.

AE Response: Refer to water sensors Basis of Design or equal attachment.

22. Please provide the electrical design for power and communications to support the sensors and new head end equipment.

AE Response: Sheet ES100 show the location of the sensors and keynote #1 covers power and communication requirement. Nano units communicate wirelessly with gateway. Provide 20A circuit breaker and 2#12 + 1#12 G in 3/4"C to each location from the nearest power panel shown on E400. Field verify panel locations. Provide all conduits, wiring and appurtenances needed for complete installation. Contractor to verify existing panelboard capacity prior to installing new circuit breaker and circuiting new devices. Confirm and coordinate final requirements with vendor/manufacturer prior to procurement and installation.

23. Since this project is a Bid-Build project and not a Design-Build project, please confirm that there are no delegated design responsibilities for the General Contractor.

AE Response: Final wiring and cabling conduit paths are delegated to the contractor.

24. Please provide the parameters for the chemistry testing.

AE Response: No parameters required by the contractor. Water monitoring device reports chemistry for VA treatment. Refer to water sensors Basis of Design or equal attachment.

25. Do we include a maintenance contract for the system?

AE Response: Maintenance requirements to be confirmed by the VA.

26. Has the Concube V3 water monitoring device been approved by the VA and does it support 802.1X / EAP-TLS (enterprise Wi-Fi authentication)?

Response: Yes, and it will be integrated into JCI, so know need for WIFI.

27. Are wireless extenders/repeaters allowed to be used on the project if required for signal amplification?

AE Response: Yes, if additional repeaters are required.

28. If the new water tower is not completed by the time this project is completed, would the monitoring station be delayed or installed in a specific area (not to be damaged by construction).

AE Response: Monitoring device installation and water tower project completion will need to be coordinated with the VA. Refer to RFI 17 for additional information.

29. Will there be any monitoring requirements at the existing water tower?

AE Response: No monitoring devices to be installed at the existing water tower.

30. Is any commissioning required on this project?

AE Response: No commissioning required.

31. Can the Superintendent also be the Prime Contractor’s Commissioning Manager during commissioning?

Response: Yes

32. Can the Superintendent also be the quality control manager?

Response: Yes, as long as they are not Dual Hatting already as the SHHO/Superintendent.

33. As is typical for most VA projects can the QC plan be implemented by the onsite superintendent and administrated by the PM without additional staff (other than what is required for commissioning) as call for in 01 45 00.?

Response: Yes, as long as they are not Dual Hatting already as the SHHO/Superintendent.

34. Will any of this work have to be performed after hours or weekends?

AE Response: After hours/weekend work not anticipated. Confirm with VA.

35. Will this project be done in phases?

AE Response: No phasing included. VA to confirm.

36. Will each phase have to be fully completed before moving to the next or can some phases be completed simultaneously?

AE Response: No phasing included. VA to confirm.

37. Will we have to install any ICRA barriers for this project? If so, what openings can we use to vent our negative air to meet the ICRA requirements? If so, in ICRA areas that require Category B Level 1 or 2, can we use zip-walls or plastic sheeting as containment? If so, in any ICRA areas that require above Category B containment, can plastic wall panels be used for the ICRA walls, such as STARC Panels or Temporary Wall System’s panels?

AE Response: No barriers are anticipated. Work areas are not anticipated to be in locations accessed by the public. VA to confirm. If barriers are required by the VA, the AE takes no exception to STARC panel systems provided VA agrees.

38. Please provide contact name and phone number for who services the Johnson Controls METASYS BACNet system?

AE Response: VA response required for contact information.

39. How will the METASYS integration be handled?

AE Response: Integration will be via VA BACnet system. Coordinate integration requirements with vendor.

40. Will any housekeeping concrete pads be required?

AE Response: No.

41. What type of Water Monitor Device is required Amperometric or Colorimetric?

AE Response: Refer to water sensors Basis of Design or equal attachment.

42. Will the Government accept devices from manufacturers other than Badger Meter products?

Response: As long as they meet the Same requirements (or even more) as the current Badger and integrate into JCI.

43. Will the Monitoring devices be connected to any SCADA networks?

AE Response: VA input and direction required.

44. It appears that the Diagrams provided on P903 and E400 do not include the backflow preventer in building 54. Please revise these drawings to include the work in Building 54?

AE Response: Per detail 1/P903 monitoring device shown at building 54. Existing backflow preventer is already installed. Add building 54 to diagram on P903 and E400.

45. The locations shown on P901 all say “generically” Install Water Monitoring Device. The locations shown on P902 more specifically say install ConCube V3 water monitoring device and some also include PipeScan device. However, in the Diagrams on P903 and E400 it calls for Nano Monitoring Units and on the areas the call for Pipe Scan device it no longer calls for ConCube V3. There seems to be some contradictory information, can the Government please clarify exactly which devices they want at each location?

AE Response: Replace “Nano” with “ConCube V3”, typical.

46. Please provide the acceptable Electrical Panel name, location, approximate distance from the following locations?

a. Building 1 – Service Room BA-023b?

b. Building 30 – Mechanical Room 30-099?

c. Building 32 – Basement Corridor @ Col. J/10?

d. Building 38 – Pump Room B04-38? AE Response: Agreed. Refer to addendum No. 1 for correction.

e. Building 39 – Mezzanine #1 39-A209?

f. Building 52 – Mechanical Room 111-52?

g. Building 54?

h. Building 100 – Fire Pump Room GA006-100?

i. Backflow Preventer – 131 Avenue?

j. Backflow Preventer – Bruce B. Downs Blvd.?

k. Backflow Preventer – North of Parking Deck?

l. Elevated Tank Outlet AE Response: Units are low voltage and are to be connected to the nearest 208/120V power panel. Provide 20A circuit breaker and 2#12 + 1#12 G in 3/4"C Provide all conduits, wiring and appurtenances needed for complete installation. Contractor to verify existing panelboard capacity prior to installing new circuit breaker and circuiting new devices. Coordinate all requirements needed for complete installation of power to ConCube v3 system with mechanical contractor and vendor prior to procurement and installation. See E400 for available power panels provided for use by the VA. Field verify power location and distance.

47. Please confirm whether all PWA units are located indoors. The contract documents do not clearly indicate the placement of each unit, and confirmation is needed to ensure proper coordination of structural supports, environmental conditions, access clearances, and code compliance. If any PWA units are intended to be installed outdoors, please provide the exact locations and any additional design requirements (weatherproofing, enclosures, or security measures) so that all bidders can include the same scope of work?

AE Response: The definition of “PWA” It is unclear. Provide clarify. If it’s related to water monitoring, they will be mounted inside and outside. Refer to manufacturer’s installation requirements.

48. Where can the contractor install the BACNet Modbus Gateway Device at each location?

Some of these locations are outdoors.

AE Response: There will be only one Modbus Gateway needed for all monitoring devices to communicate to the VA BACnet system. Confirm location with the VA.

49. Does the contractor have to paint any new electrical conduit?

AE Response: Match existing conduit painting where required. Coordinate final requirements with the VA.

50. TPA-13 New Elevated Tank, please provide a description of where this water monitoring device will have to be mounted.

a. Is it at ground level or above ground level? AE Response: Ground level.

b. What type of equipment will be required to reach the area where the monitor needs to be mounted?

AE Response: Coordinate equipment requirements with Vendor and VA.

51. Please provide a detail of the options that the contractor has for how the water monitoring devices need to be mounted (ie wall mounted, column mounted, floor mounted, etc..)

AE Response: Refer to manufacturer’s installation requirements. Coordinate with the VA.

52. How many software licenses does the Government require?

Response: None, as long as its not needed to integrate into JCI

53. Please confirm this contract only includes 1 semiannual maintenance performed and ongoing maintenance will be procured through a separate maintenance contract?

AE Response: Maintenance requirements to be confirmed by the VA.

54. Does this contract include any ongoing services for the units?

Response: No other than the standard 1 year warranty we get.

55. Is the contractor required to provide a color laser printer, as indicated in spec section 25 10 10-17?

AE Response: Color laser printer required.

56. Specification Section 25 10 10 refers to hooking the water monitoring devices up using Fiber Optic cable however the plan sheets indicate that the water monitoring devices will be on a wireless network. Please clarify if fiber optic cable will have to be run to each device?

a. If so, please provide a drawing or a distance that the nearest fiber optic cable is that the contractor will be allowed to splice into?

AE Response: Fiber optic cabling is not required. Communication via open-air, wireless.

57. What type probes will be required along with the water monitoring devices?

AE Response: Refer to water sensors Basis of Design or equal attachment for each probes measuring capability.

58. Please provide what measurements will be required to be monitored?

AE Response: Refer to water sensors Basis of Design or equal attachment for measurements to be monitored.

59. Cooling tower water-quality requirements (ES2019) are beyond the potable water requirements (Directive 1061). Please confirm:

a. are the same monitoring and treatment parameters required for all units/systems?

AE Response: Yes.

b. Which standard governs where 1061 and ES2019 conflict? To ensure consistent pricing and compliance, please issue a matrix identifying each system covered, the governing standard for that system, required parameter limits and test methods, sampling/recording frequency, control setpoints, and submittal/ commissioning requirements, including integration to BAS where applicable.

AE Response: VA directive 1061 governs. Water quality monitoring is continuous and provides real time reports to the VA potential Legionella treatment based on the data reported. Refer to water sensors Basis of Design or equal attachment for additional information. No commissioning required.

60. Can the government be more specific about where any administrative requirements are to be submitted in the proposal if there are any administrative requirements?

Response: This is up to the contractor.

61. For Technical Evaluation Factor 2 Schedule, what specific milestones would the government like to see in the preliminary schedules?

Response: This is up to the contractor.

See attached document: Basis of Design TAB A.

See attached document: Electrical Drawings - Addendum 1.

See attached document: Plumbing Drawings - Addendum 1.

2025-10-28T08:58:54-0400