Questions and Answers
1. Can you confirm this RLP is for SDVOSB proposals only? Yes
2. I do not believe occupancy by Oct 2023 is feasible if you are considering new construction (and probably not even for rehab given typical award timelines). Anticipating at least another 4-6 months before lease is awarded, a building of this size would need at least 18 months from lease award (2-4 months of A&E, 2 months permitting,12-14 months construction). Is this something that can be addressed upon award? Yes, estimated construction completion of
02/2024 and activation 05/2024.
3. Will this lease be a major lease (requiring congressional authorization) or minor lease? Minor
4. Can there be an extension on the RLP proposal submission deadline for an additional 30 days? It is very difficult to complete a legal purchase & sale agreement for land with a seller in less than 30 days. Especially since the expression of interest was submitted a year ago.
The solicitation has been extended through July 29, 2022, 3:00 pm EST.
5. Can we request a copy of your delineated area so we can ensure we plotted correctly? No, interested parties are responsible for using the delineated points in the solicitation to verify that his space is within the delineated.