S02 - Attachment_11_ VACHS Operational Requirements for Hurricane Recovery Efforts Ph2 (2 Pages).pdf

PDF 425 KB Posted

Attached to
Z2DA--Hurricane Recovery Project Phase 2
Solicitation number
36C24822R0038
Issued by

About this file

This document outlines requirements for the Hurricane Recovery Project Phase 2 federal contract opportunity. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8 is seeking design-build services through a $5 million to $10 million contract to repair damages from Hurricanes Irma and Maria in 2017 at the VA Caribbean Healthcare System facility in San Juan, Puerto Rico. The scope of work follows recommendations from the VA Central Office Damage Assessment Team findings. The solicitation will be issued on December 29, 2021 via beta.SAM.gov and is set aside only for verified Service-Disabled Veteran-Owned Small Businesses. Proposals are due by January 28, 2022 at 4:30 PM Atlantic Standard Time. Interested firms must be registered in the System for Award Management.

View the file

Other files

File Type Posted
S02 - Solicitation 36C24822R0038_Final Version 1-19-2022.pdf PDF
S02 - Attachment_2 Mechanical Final Referenced Drawings_DB_672-21-000_(2 Pages).pdf PDF
S02 - Attachment_12_Proposed Staging Area - Site Plan - Hurricane Recovery Ph2 (1 Page).pdf PDF
S02 - Attachment 13 VHA Supplemental Contract Req Combatting COVID-19 REV_12-14-21 (2 Pages).docx DOCX document
S02 - Attachment_6_Experience Information Sheet_(MANDATORY) DB_672-21-000_(4 Pages).docx DOCX document
S02 - Attachment_8_ Base Offer Cost Breakdown_(MANDATORY)_DB_672-21-000_(2 Pages).pdf PDF
S02 - Attachment_14_Station_672_Local Protocols for COVID-19 (1 Page).docx DOCX document
S02 - Attachment_9_ Release of Claim (ROC) Form DB_672-21-000_(2 Pages).doc DOC document
S02 - SPECIFICATION - 01 00 00_DB_672-21-000_(24 Pages).docx DOCX document
S02 - SPECIFICATION - 01 42 19_DB_672-21-000_(9 Pages).docx DOCX document
S02 - Attachment_10_ Infection Control Guidelines on Construction and Renovation 11B-17-05 (11 Pages).docx DOCX document
S02 - Attachment_1 Architectural Final Referenced Drawings_DB_672-21-000_(16 Pages).pdf PDF
S02 - SPECIFICATION - 01 32 16 17_DB_672-21-000_(34 Pages).docx DOCX document
S02 - SPECIFICATION - 01 35 26_DB_672-21-000_(27 Pages).docx DOCX document
S02 - Attachment_7_EMR_(MANDATORY)_DB_672-21-000_(1 Page).docx DOCX document
S02 - SPECIFICATION - 01 32 16 16_DB_672-21-000_(23 Pages).docx DOCX document
S02 - SPECIFICATION - 01 33 23_DB_672-21-000_(8 Pages).docx DOCX document
S02 - Attachment_3 Electrical Final Referenced Drawings_DB_672-21-000_(7 Pages).pdf PDF
S02 - Attachment_5_Past Performance_(MANDATORY)_DB_672-21-000_(4 Pages).pdf PDF
S03 - 36C24822R0038_2_MODIFIED PRE-SOLICITATION NOTICE 1-19-2022.docx DOCX document
S02 - SPECIFICATION - 00 11 21_DB_672-21-000_(11 Pages).docx DOCX document
S02 - Attachment_4 - LOS CERTIFICATION (FILL-IN_MANDATORY) Vs-12-17-20_DB_672-21-000_(1 Page).doc DOC document
36C24822R0038_1.docx DOCX document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VACHS Hurricane Recovery Projects - Phase 2 San Juan VAMC

Num Bldg System/Building/Item ACM Potential Service Impact Impact Mitigation

Strategies/Requirements Preferred Shift

A.1.3 – Replace all second floor roof system.

Testing Required

Various Areas and Services Provide charcoal filtering at rooftop units. Attenuate sound to the greatest extent possible.

2nd/3rd Shift for all work that will generate continuous noise and vibration

E1.1-Replace entire lightning protection system on roof

N/A Various Areas Alternate Shifts

2nd/3rd Shift for all work that will generate continuous noise and vibration

E1.2-Replace damaged lighting fixtures second floor

N/A Various Areas

Work required to be performed in several phases. To be coordinated with abatement of floor tile (HZ.1.1), replacement of the second floor ceiling (HZ.1.2), and replacement of damaged interior finishes (I.1.2) in the same areas.

Egress and life safety to be considered.

2nd/3rd Shift for all work that will generate continuous noise and vibration

HZ.1.1-Abate ACM floor tile-10% of second floor

Confirmed Various Areas

Work required to be performed in several phases. To be coordinated with replacement of damaged lighting fixtures on the second floor (E.1.2), abatement of the second floor ceiling (HZ.1.2), and replacement of damaged interior finishes (I.1.2) in the same areas.

Egress and life safety to be considered.

2nd/3rd Shift for all work that will generate continuous noise and vibration

HZ.1.2-Abate ACM fireproofing/ceiling @ second floor

Confirmed Various Areas

Work required to be performed in several phases. To be coordinated with replacement of damaged lighting fixtures on the second floor (E.1.2), and replacement of damaged interior finishes (I.1.2) in the same areas. Egress and life safety to be considered.

2nd/3rd Shift for all work that will generate continuous noise and vibration

HZ.1.3-Abate ACM floor tile @ of first floor

Confirmed Various Areas

Work required to be performed in several phases. To be coordinated with replacement of the first floor ceiling (HZ.1.4), and replacement of damaged interior finishes (I.1.3) in the same areas.

Egress and life safety to be considered.

2nd/3rd Shift for all work that will generate continuous noise and vibration

VACHS Operational Requirements Bldg 1: Main

VACHS Hurricane Recovery Projects - Phase 2 San Juan VAMC

HZ.1.4-Abate ACM fireproofing/ceiling -25% of first floor

Confirmed Various Areas

Work required to be performed in several phases. To be coordinated with abatement of floor tile (HZ.1.3),replacement of damaged interior finishes (I.1.3) in the same areas.

Egress and life safety to be considered.

2nd/3rd Shift for all work that will generate continuous noise and vibration

I.1.2-Replace damaged finishes- 35% of second floor

Confirmed Various Areas

Work required to be performed in several phases. To be coordinated with abatement of floor tile (HZ.1.1), abatement of fireproofing of the second floor ceiling (HZ.1.2), and replacement of damagedlight fixtures (E.1.2) in the same areas. Egress and life safety to be considered.

2nd/3rd Shift for all work that will generate continuous noise and vibration

I.1.3-Replace damaged finishes- 20% of first floor

Confirmed Various Areas

Work required to be performed in several phases. To be coordinated with replacement of the first floor ceiling (HZ.1.4), and abatement of floor tile (HZ.1.3) in the same areas. Egress and life safety to be considered.

2nd/3rd Shift for all work that will generate continuous noise and vibration

M.1.2 – Replace damaged pipe insulation and jacketing various diameters and lengths.

Testing Required

Roof/Various Areas

Work after regular working hours If work requires any activity that will produce fumes contractor to Install

Carbon Filters for all AHU within 50ft radius of work area.

2nd/3rd Shift for all work that will generate continuous noise and vibration

M.1.3 – Repair/Replace damaged kitchen ductwork assembly at 3 locations.

Confirmed Food and Nutrition Service

Work after regular working hours If work requires any activity that will produce fumes contractor to Install

Carbon Filters for all AHU within 50ft radius of work area.

2nd/3rd Shift

Num Bldg System/Building/Item ACM Potential Service Impact Impact Mitigation

Strategies/Requirements Preferred Shift

I.2.1 – Replace damaged ceiling assdembly in office/toilet

N/A Laundry Service Alternate Shits 2nd/3rd Shift

Bldg 2: Laundry

File details come from the government source that posted it. Updated .