Answer to RFI Questions - 557-23-103 - Amendment 0001 - Attachment 1.xlsx
XLSX spreadsheet 37 KB Posted
- Solicitation number
- 36C24726Q0772
About this file
This file is a spreadsheet containing answers to Requests for Information (RFI) submitted by potential bidders for a federal construction contract. The document provides clarifications and responses to questions raised by interested vendors regarding the solicitation requirements, project specifications, and contractual terms for the generator replacement project at Carl Vinson Veterans' Administration Medical Center in Dublin, Georgia.
The RFI responses address technical, scheduling, and administrative questions from prospective bidders to ensure a clear understanding of project requirements before the revised quote submission deadline of 21 September 2026 at 1:00 PM EDT. As this is Amendment 0001 to Solicitation 36C24726Q0772, the RFI answers serve as an addendum clarifying the Statement of Work, project drawings, and other solicitation documents. The responses are critical for helping Service-Disabled Veteran-Owned Small Business (SDVOSB) firms—the exclusive eligible bidders for this 100% set-aside—to prepare accurate and compliant proposals for this commercial construction project valued between $5 million and $10 million with a 455-calendar-day performance period.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI Log
| RFI No. | Date Submitted | Submitted By | Discipline | Drawing / Spec Ref. | RFI Question | Assigned To | Response | Date Responded | Status | Days Open | Change Order / PCO Ref. |
| 1 | 08/18/2026 | BIC | Other | 01 00 00 | Can you verify if the utility outage request is 14 or 21 days for this project. | VA | 14 calendar days. | 08/20/2026 | Closed | 2 | |
| 2 | 08/20/2026 | BIC | Mechanical | MI-502 | The plans call out a Veeder-Root TLS-450+ under the LEAK DETECTION & AUTOMATIC TANK GAUGE MONITORING SYSTEM schedule on MI-502. Will the VA accept a Fuel Sentry Model TG-EL-D4B Tank Gauge and Leak Detection System as an approved equivalent to the TLS-450+? | VA | VA will not accept an approved equivalent to the Veeder-Root system; the facility currently utilizes Veeder-Root equipment for generator fuel leak detection and tank monitoring and maintains a service/maintenance contract for these systems for all site fuel tanks. To maintain consistency of equipment, compatibility with existing facility operations and maintenance practices, and standardized servicing across the campus, provide the Veeder-Root TLS-450+ system as indicated on Drawing MI-502. No substitution is authorized. | 08/21/2026 | Closed | 1 | |
| 3 | 08/20/2026 | BIC | Electrical | RFI: Once the generators are removed will the existing feeder and utility conduits be abandoned in place | VA | When new system online and fully functionally testing, all abandoned/existing feeders and utility conduits are to be removed in their entirety. | 08/21/2026 | Closed | 1 | ||
| 4 | 08/25/2026 | BlueCord | 1. Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO? | VA | Yes, only dual hat allowable, not triple. | 08/27/2026 | 2 | ||||
| 5 | 08/25/2026 | BlueCord | 2. If no to the question above, will the SSHO need to be full-time for this project? | VA | See above response | 08/27/2026 | 2 | ||||
| 6 | 08/25/2026 | BlueCord | 3. Please clarify if a superintendent can be a dual hat to cover the requirements of QA/QC? | VA | Only dual hat allowable, not triple. | 08/27/2026 | 2 | ||||
| 7 | 08/25/2026 | BlueCord | 4. If no to the question above, will the QA/QC need to be full time for this project? | VA | See response above | 08/27/2026 | 2 | ||||
| 8 | 08/25/2026 | BlueCord | 5. Can a superintendent be a triple hat to cover the requirements of SSHO and QA/QC? | VA | No, only dual hat allowable. | 08/27/2026 | 2 | ||||
| 9 | 08/25/2026 | BlueCord | 6. Please confirm the issued drawing set is the latest and complete set. | VA | Yes, most recent drawing set is dated 06/15/2026 and states "Bid Documents R1" | 08/27/2026 | 2 | ||||
| 10 | 08/25/2026 | BlueCord | 7. Please confirm the current design documents meet current VA TIL guidelines. | VA | Yes | 08/27/2026 | 2 | ||||
| 11 | 08/25/2026 | BlueCord | 8. Please provide the latest wage determination for this project’s county. | CO | This is attachment 4 in the solicitaton. Vendors must view all attachments. | 8 | |||||
| 12 | 08/25/2026 | BlueCord | 9. Past Performance: If we have a PPQ, requested for another opportunity, that is less than 12 months old, can we use it within our proposal? Or will a new PPQ need to be requested? | CO | No, New PPQ are required for this requirement. | 8 | |||||
| 13 | 08/25/2026 | BlueCord | 10. Is the use of temporary plastic wall panels (such as STARC panels) acceptable? | VA | Barrier must meet one-hour fire barrier. | 08/27/2026 | 2 | ||||
| 14 | 08/25/2026 | BlueCord | 11. Who is responsible for the terminal clean of the project area? | VA | Contractor. | 08/27/2026 | 2 | ||||
| 15 | 08/25/2026 | BlueCord | 12. Who is responsible for contracting the commissioning agent? | VA | Contractor. | 08/27/2026 | 2 | ||||
| 16 | 08/25/2026 | BlueCord | 13. Please confirm order of precedence for the contract documents. Does SOW prevail over the specifications and construction drawings? | CO | Specifications takes precedence over drawings. The SOW is for informationly purposes only and not construction guidance. | 8 | |||||
| 17 | 08/25/2026 | BlueCord | 14. Please confirm if the contractor is able to work on both generator enclosures concurrently. | VA | Yes, the contractor is able to work on both generatos enclsosures concurrently. | 8 | |||||
| 18 | 08/25/2026 | BlueCord | 15. Please confirm if the contractor will be able to work concurrently on the outside enclosures and inside renovations. | VA | Yes, coordinate with COR to ensure hospital functions are not impacted. | 08/27/2026 | 2 | ||||
| 19 | 08/25/2026 | BlueCord | 16. Please confirm if the contractor is responsible for draining the existing generator fuel tanks. | VA | Yes, contractor is responsible for draining existing fuel tanks prior to disposal. | 08/27/2026 | 2 | ||||
| 20 | 08/25/2026 | BlueCord | 17. Sheet FX-103 shows new fire sprinkler piping extending into the corridor. Are there any additional drawings showing the corridor work? Is the ceiling in the corridor a hardlid ceiling or an ACT system? | AE | Corridor is ACT system | 8 | |||||
| 21 | 08/25/2026 | BlueCord | 18. On sheet FX-102 please confirm if the ceiling is a hardlid drywall ceiling, or an ACT system. | AE | Corridor is ACT system | 8 | |||||
| 22 | 08/25/2026 | BZ Construction and Development LLC | 01 35 26 1.9 | Please confirm if Onsite Superintendent can cover safety role as long as qualifications are met. | VA | Yes, only dual hat allowable, not triple. | 08/27/2026 | 2 | |||
| 23 | 08/25/2026 | BZ Construction and Development LLC | Phasing | Confirm that Building 2 and Building 4 work can go on at the same time. | VA | Yes, coordinate with COR to ensure hospital functions are not impacted. | 08/27/2026 | 2 | |||
| 24 | 08/25/2026 | BZ Construction and Development LLC | ICRA | Can temporary wall systems like Starc walls be used in Lieu of Drywall construction barriers | VA | Barrier must meet one-hour fire barrier. | 08/27/2026 | 2 | |||
| 25 | 08/25/2026 | BZ Construction and Development LLC | A-103, A-101 | Confirm what door receives what Hardware type. | AE | Use HW2 for all doors this building | 09/02/2026 | 8 | |||
| 26 | 08/25/2026 | BZ Construction and Development LLC | FA-100 | Sheet notes missing or invalid reference. Confirm that no information is missing from this sheet. | AE | See updated FA-100 plan | 8 | ||||
| 27 | 08/25/2026 | GSI Construction | CU-100 | 1. Keynote 15 on drawing CU100 shows a proposed entry gate. Spec section 34 71 13, Passive Vehicle Barriers pertain to bollards and not the gate on CU100. Can a detail and/or specifications and a basis of design be provided for the proposed gate? | AE | See Drop Arm gate detail on Sheet CI100 | 8 | ||||
| 28 | 08/19/2026 | GSI Construction | 01 45 00 | Specification Section 01 45, 00 3.4.C. States that the Prime Contractor must employ specialized personnel to assist the CQC System Manager in the following areas: Electrical, Mechanical, Civil, Structural, Environmental, Architectural, Materials Technician Submittals Clerk, Commissioning Agent and Low Voltage Systems. It goes on to state that they must be employed by the GC and not by subs. It also provides a required Experience Matrix. The cost to the GC, and to the project, would become quite high if these specialized persons are to be employed by the GC and not by the GC’s Subcontractors. To manage costs and to utilize the expertise provided by the subcontractors, can these rolls be fulfilled by the Subcontractors? Please clarify as to whether the GC needs to employ a Commissioning Agent directly, but all other specialized personnel can be employed by subcontractors. | AE | It is acceptable for the GC to employ the Commissioning Agent directly and all other specialized personnel can be employed by the subcontractors. | 14 | ||||
| 29 | 08/19/2026 | GSI Construction | Is a temporary office trailer required, or will the GC be permitted space within the building for a small field office? | VA | Temporary Office trailer will be required. GC will not be permitted space within the building for a small field office. | 08/27/2026 | 8 | ||||
| 30 | 08/24/2026 | Luke Lamb Industries LLC | Request for Proposal Deadline Extension Given the complex mechanical and electrical coordination required to safely replace emergency generator infrastructure in active medical environments (Buildings 2 and 4), as well as the specialized engineering needed for the automated switchgear integration, will the VA grant a minimum 14-day extension to the current quote deadline of September 14, 2026? This extension will ensure all bidding SDVOSB primes can secure robust regional labor partnerships and highly accurate manufacturing quotes for the long-lead electrical components. | VA | Extension not warranted at this time. | 08/27/2026 | 3 | ||||
| 31 | 08/24/2026 | Luke Lamb Industries LLC | Clarification on Joint Venture Evaluation Criteria If an SDVOSB prime contractor submits a proposal as part of an SBA-approved Mentor-Protégé Joint Venture (JV), will the government explicitly evaluate and aggregate the past performance, financial depth, and multi-million dollar bonding capacity of the large business Mentor to satisfy the technical and responsibility requirements of this solicitation? | CO | For an SBA‑approved Mentor‑Protégé Joint Venture (MPJV), the Government will evaluate the JV in accordance with SBA regulations (13 CFR 125.18), the solicitation’s evaluation criteria, and applicable FAR/VAAR requirements. The Government may consider the past performance, financial resources, and bonding capacity of the Mentor to the extent the proposal demonstrates that the Mentor will meaningfully participate in performing the contract requirements. Responsibility determinations under FAR 9.104 may likewise be satisfied through the JV’s combined resources. The Government does not automatically aggregate the Mentor’s attributes; evaluation credit is applied only in proportion to the Mentor’s proposed roles, responsibilities, and contractual commitments within the JV. | 9 | |||||
| 32 | Luke Lamb Industries LLC | Availability of Detailed Site Visit Data & Sign-In SheetTo facilitate accurate subcontracting, engineering coordination, and regional labor sourcing for firms unable to attend the recent site visit on August 18th, will the government post the official site visit sign-in sheet, along with any historical single-line electrical drawings or photos of the existing switchgear rooms, as an amendment to SAM.gov? | CO | Site visit sign in sheet will not be provided. No historical drawings or photos will be provided. | 08/27/2026 | ||||||
| 33 | Luke Lamb Industries LLC | Extension of the RFI Clarification Window Because prospective sub-tier manufacturing partners and local electrical contractors require deeper technical review of the generator switchgear specs before finalizing pricing, will the government extend the RFI question deadline from August 25, 2026, to September 1, 2026? | VA | Extension not warranted at this time. | 08/27/2026 | ||||||
| 34 | 08/25/2026 | Valiant Construction | Will the Government accept Procore Project Management software as the primary submittal and data tracking tool for this project? | VA | Yes, the Contractor may utilize the project management software of his choosing | 08/27/2026 | 2 | ||||
| 35 | 08/25/2026 | Valiant Construction | Will the Government accept the “Primavera P6” for schedule submission and monthly updates? | VA | Contract may utilize the scheduling software of his choosing, however, submission to government must be gantt-style printed to PDF. | 08/27/2026 | 2 | ||||
| 36 | 08/25/2026 | Valiant Construction | Is this project tax-exempt (local, state, & federal), and will the CO/COR provide the necessary tax-exempt certificates? | CO | NO. The state of Georgia gives the government a sales tax exemption when it purchases property directly on its own behalf; but any contractor who purchases it under a construction contract is deemed to be the consumer of the property, and therefore must pay the tax. There is no exemption that VA can take for this in Georgia. | 8 | |||||
| 37 | 08/25/2026 | Valiant Construction | Will this project be required to follow 01 35 26 1.13 for TB-required protocols, and will it be required to follow the 90-day screening before beginning work on the project? | VA | Each employee on the job site will be required to submit evidence of a negative TB test. To be turned over to COR. PII can be redacted. | 08/27/2026 | 2 | ||||
| 38 | 08/25/2026 | Valiant Construction | What is the approximate duration between issuing the award and issuing the NTP? | VA | This will be dependent on contracting availability, but anticipated window is between 30 and 45 days. Work should begin on site within 60-90 days max. | 08/27/2026 | 2 | ||||
| 39 | 08/25/2026 | Valiant Construction | For planning the preliminary project schedule, please provide an anticipated award date. | VA | Anticipated award date is FY27, Q1 (September - December 2026). | 08/27/2026 | 2 | ||||
| 40 | 08/25/2026 | Valiant Construction | How many calendar days should be included in the critical-path method schedule for the Government and A/E to review and respond to RFIs? | VA | 10 business days | 08/27/2026 | 2 | ||||
| 41 | 08/25/2026 | Valiant Construction | How many calendar days should be included in the critical-path method schedule for Government and A/E submittal review? | VA | 14 calendar days. | 08/27/2026 | 2 | ||||
| 42 | 08/25/2026 | Valiant Construction | Will the Government provide the 3-D REVIT Design model in native file format for the creation of coordination drawings and use by the contractor? | VA | No. | 08/27/2026 | 2 | ||||
| 43 | 08/25/2026 | Valiant Construction | Please confirm that the project scope will be completed during normal working hours, not nights and weekends. | VA | All outages, including tie-in and testing activities, shall be scheduled and performed after normal working hours and/or on weekends. Other work may be performed during normal working hours, provided it is properly coordinated in advance between the Contractor and the COR. However, certain activities may also be required to be performed after hours to minimize impacts to VA operations, patients, staff, and visitors. Such activities may include, but are not limited to, heavy or noisy demolition in or adjacent to patient care areas, traffic disruptions or closures, and other work that could significantly interfere with normal facility operations. The Contractor shall coordinate these activities with the COR to determine appropriate scheduling. | 08/27/2026 | 2 | ||||
| 44 | 08/25/2026 | Valiant Construction | How many site visits do Government consultants have for MEP and systems coordination with GC, and will the Government have a designated MEP representative available on site? | VA | The A/E Construction Period Serivces contact includes site visits at various periods throughout the construction. These will be coordinated by the COR. | 08/27/2026 | 2 | ||||
| 45 | 08/25/2026 | Valiant Construction | Can you confirm that the Government will be contracting directly with a third-party commissioning agent for commissioning the project and that the Contractor is only to include participation/coordination with the Commissioning Agent? | VA | Contractor is responsible for Commissioning Agent. | 08/27/2026 | 2 | ||||
| 46 | 08/25/2026 | Valiant Construction | It is critical that the contractor's project superintendent have freedom of access and close proximity to the work. Can the Government provide a designated parking spot for the contractor project superintendent? | VA | It is anticipated that the Superintendent can park in the laydown area, or adjacent to the construction trailer. A designated parking spot will not be providedn. | 08/27/2026 | 2 | ||||
| 47 | 08/25/2026 | Valiant Construction | Where will the designated laydown area be for the GC? | VA | The designated laydown area will be adjacent to the area of construction. Further details can be provided post-award. | 08/27/2026 | 2 | ||||
| 48 | 08/25/2026 | Valiant Construction | Has the facility Operation & Maintenance team reviewed the Contract Documents for operability to avoid change orders? | VA | Yes | 08/27/2026 | 2 | ||||
| 49 | 08/25/2026 | Valiant Construction | Can the contractor use an existing office inside the building for a temporary construction office during construction instead of setting up a temporary trailer? | VA | No. | 08/27/2026 | 2 | ||||
| 50 | 08/25/2026 | Valiant Construction | Can the contractor use the existing restroom facilities in the work area or the adjacent ones nearby? | VA | No | 08/27/2026 | 2 | ||||
| 51 | 08/25/2026 | Valiant Construction | Can the contractor use the existing on-site utilities for temporary electrical and water free of charge? | VA | Yes | 08/27/2026 | 2 | ||||
| 52 | 08/25/2026 | Valiant Construction | Will the Government provide the fire watch during the period that the fire suppression and/or fire alarm system is not in service? | VA | If the contract has removed fire suppression and or fire alarm system, it is the contractor's responsibility to provide fire watch during the outage. | 08/27/2026 | 2 | ||||
| 53 | 08/25/2026 | Valiant Construction | Please provide detailed guidance for noise and vibration operations, including acceptable levels/duration, hours of operations for acceptable levels, and acceptable noise levels after hours. | VA | See Safety specification, 01 35 26. Contractor shall comply with all applicable contract requirements regarding noise, vibration, safety, infection control, and protection of VA operations. The VA has not established additional project-specific numerical noise or vibration limits beyond those identified in the Contract Documents and applicable codes and regulations. |
Work generating excessive noise or vibration that may adversely impact patient care, clinical operations, occupants, or normal facility operations shall be coordinated in advance with the COR. Based on the location, nature, intensity, and anticipated duration of the activity, the COR may require such work to be performed after normal working hours and/or on weekends.
| Performing work after hours does not constitute authorization for unrestricted noise or vibration. Noise and vibration shall be minimized to the greatest extent practicable, and activities that may impact occupied or sensitive areas shall be coordinated with the COR prior to execution. The Contractor shall include anticipated noise- and vibration-producing activities in its work planning and schedule to allow adequate coordination with affected VA services. | 08/27/2026 | 2 | |||||||
| 54 | 08/25/2026 | Valiant Construction | How long after the award will the Government provide the submittal register? | VA | Contractor is responsible for management of the submittal register. | 08/27/2026 | 2 | ||
| 55 | 08/25/2026 | Valiant Construction | Can the QA/QC dual-hat as the Superintendent? | VA | Only dual hat allowable, not triple. | 08/27/2026 | 2 | ||
| 56 | 08/25/2026 | Valiant Construction | Can the SSHO dual-hat as a Superintendent? | VA | Only dual hat allowable, not triple. | 08/27/2026 | 2 | ||
| 57 | 08/25/2026 | Valiant Construction | Can the SSHO dual-hat as the QA/QC? | VA | Only dual hat allowable, not triple. | 08/27/2026 | 2 | ||
| 08/25/2026 | Valiant Construction | Can the Government confirm that the General Contractor is not to include any Asbestos or Lead Removal? | VA / AE | No asbestos or lead paint removal is anticipated in the scope of work. AE confirms. | 08/27/2026 | 2 | |||
| 08/25/2026 | Valiant Construction | What is the Government's policy if asbestos products are encountered during construction that are not quantified in the construction documents? | VA | If suspected asbestos-containing material (ACM) not identified in the Contract Documents is encountered, immediately stop work in the affected area, do not disturb the material, and notify the COR/Contracting Officer. The Government will evaluate the condition and provide direction. Any associated cost or schedule impacts will be addressed by the Contracting Officer in accordance with the applicable Contract provisions. | 08/27/2026 | 2 | |||
| 08/25/2026 | Valiant Construction | Can the existing service and/or public elevators be used for construction activities? Are there any restrictions or time constraints? | VA | Existing service and/or public elevators may be used for construction activities, subject to coordination with the COR. Patient and VA operational use shall have priority at all times. Elevators shall be protected from damage and maintained in a clean condition. Construction debris shall be transported in fully enclosed or securely covered containers to prevent the spread of dust or debris. Any additional restrictions or scheduling requirements shall be coordinated with the COR based on facility operations. | 08/27/2026 | 2 | |||
| 08/25/2026 | Valiant Construction | How soon after NTP issuance will the Government and/or designer of record provide and confirm the COMPLETE set of contract documents, including all amendments? | VA / CO to confirm | A conformed award set will not be provided. The Contract Documents consist of the bid/solicitation documents, including drawings and specifications, as modified by all issued amendments. The Contractor is responsible for incorporating and complying with all amendments issued as part of the solicitation. | 08/27/2026 | 2 | |||
| 08/25/2026 | Valiant Construction | Please confirm that the most up-to-date prevailing wage determination has been provided | CO | This is attachment 4 in the solicitaton. Vendors must view all attachments. | 8 | ||||
| 08/25/2026 | Valiant Construction | Will the Government accept candidates with extensive relevant experience and CQM-C certification as meeting the qualification requirements in lieu of a formal degree, consistent with FAR and VA guidelines that allow for equivalent experience for technical roles? | VA | Yes | 08/27/2026 | 2 | |||
| 08/25/2026 | Valiant Construction | Please clarify whether QC Manager candidates with directly relevant QC experience on comparable Federal construction projects will be acceptable if their formal education differs from the degree described in the solicitation/specification/01 45 00, provided their qualifications are documented in the proposal/QC Plan submittal. | VA | Yes | 08/27/2026 | 2 | |||
| 08/25/2026 | Valiant Construction | Please confirm if the Government will accept a QA/QC organization in which the named QC Manager provides overall program management and decision-making authority, while on-site inspections and documentation are carried out by project-dedicated QC personnel reporting to that individual. | VA | Yes | 08/27/2026 | 2 | |||
| 08/25/2026 | Valiant Construction | May CQM discipline-specific staff (HVAC, plumbing, electrical, low voltage, civil, etc.) be provided by trade subcontractors performing the work, rather than directly by the CM, provided they meet the minimum experience requirements? | VA | Yes | 08/27/2026 | 2 | |||
| 08/25/2026 | Valiant Construction | Please clarify if a pre-demolition (pre-alteration) test and balance of HVAC system will be required on this project. | VA | No, not required. | 08/27/2026 | 2 | |||
| 08/25/2026 | Valiant Construction | If an office space is not available for the GC to use, please provide the location for the GC trailer area. | VA | No office space will be provided. Laydown area will be adjacent to the area of construction; exact location for trailer to be determined post-award. | 08/27/2026 | 2 | |||
| 08/25/2026 | Valiant Construction | Per the solicitation documents, Factor 3, Item 2, states "Identify all intended subcontractors performing specialized work, including electrical controls, fuel systems, and site work." Please confirm what classifies as "specialized. Is the owner only looking for electrical controls, fuel systems, and site work? | VA | Provide all intended subcontractors performing work for this contract, particularly focusing on MEP & civil disciplines. | 08/27/2026 | 2 | |||
| 08/25/2026 | Valiant Construction | Per the itemized cost breakdown sheet, confirm the owner is only wanting a lump sum cost per division. | VA | This is correct | 08/27/2026 | 2 | |||
| 08/25/2026 | Valiant Construction | Tab A: General information does not specify which volume this needs to be a part of please verify if this needs to be submitted separately? | CO | Tab A must be submitted as a separate administrative section, not combined with Volume I or Volume II. | |||||
| Submit three parts: Tab A, Volume I (Technical), and Volume II (Price). | 8 | ||||||||
| 08/25/2026 | GSI Construction | 1.) Keynote 15 on drawing CU100 shows a proposed entry gate. Spec section 34 71 13, Passive Vehicle Barriers pertain to bollards and not the gate on CU100. Can a detail and/or specifications and a basis of design be provided for the proposed gate? | AE | See Drop Arm gate detail on Sheet CI100 | 08/27/2026 | 2 | |||
| 08/25/2026 | BIC | 2.) RFI: Once the generators are removed will the existing feeder and utility conduits be abandoned in place? | VA | No, to be removed in entirety | 08/27/2026 | 2 | |||
| 08/25/2026 | BIC | 3.) What is the Carl Vinson VAMC standard time to request a Utility Outage Requests (UOR), 14 calendar days or 21 calendar days? | VA | 14 calendar days. | 08/27/2026 | 2 | |||
| 08/25/2026 | GSI Construction | 4.) Specification Section 01 45, 00 3.4.C. States that the Prime Contractor must employ specialized personnel to assist the CQC System Manager in the following areas: Electrical, Mechanical, Civil, Structural, Environmental, Architectural, Materials Technician Submittals Clerk, Commissioning Agent and Low Voltage Systems. It goes on to state that they must be employed by the GC and not by subs. It also provides a required Experience Matrix. The cost to the GC, and to the project, would become quite high if these specialized persons are to be employed by the GC and not by the GC’s Subcontractors. To manage costs and to utilize the expertise provided by the subcontractors, can these rolls be fulfilled by the Subcontractors? Please clarify as to whether the GC needs to employ a Commissioning Agent directly, but all other specialized personnel can be employed by subcontractors. | VA | The specialized personnel identified in Specification Section 01 45 00, Paragraph 3.4.C may be provided by qualified subcontractors and are not required to be direct employees of the Prime Contractor. The Prime Contractor remains responsible for the overall CQC program and coordination of these personnel. Relevant demonstrated experience will be accepted in lieu of the degree requirements identified in the Experience Matrix, subject to Government review and acceptance. The Commissioning Agent shall be provided in accordance with the applicable commissioning requirements of the Contract Documents. | 08/27/2026 | 2 | |||
| 08/25/2026 | GSI Construction | 5.) Is a temporary office trailer required, or will the GC be permitted space within the building for a small field office? From GSI | VA | GC will not be provided space within the building | 08/27/2026 | 2 | |||
| 08/25/2026 | SemperTek | 01 45 00 | Question: Section 01 45 00, paragraph 3.4.B states that “The CQC system Manager is required to be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of PM or SRE to determine qualifications based on project complexity at construction review with a minimum of 5/10 years construction experience on construction similar to the scope of this Contract as directed by VA COR. Construction person with a minimum of 5/10 years in related work as directed by VA COR.” Please confirm whether these requirements will be upheld concerning the CQC System Manager. | VA | The CQC System Manager requirements will be upheld; however, relevant construction experience may be accepted in lieu of the stated degree requirement. The proposed CQC System Manager shall demonstrate a minimum of five (5) years of relevant construction experience on projects of similar scope and complexity. Qualifications of the proposed individual are subject to Government review and acceptance. | 08/27/2026 | 2 | ||
| 08/25/2026 | SemperTek | 01 45 00 | Question: Section 01 45 00, paragraph 3.4.B, states that “The CQC System Manger is assigned as CQC System Manager but has duties as project superintendent in addition to quality control.” |
Please confirm that the Superintendent can function as a dual-hatter and fulfil the duties of the CQC System Manager.
| VA | Dual-hat allowable only, not triple hat (Superintendent, SSHO, and QA/QC) | 08/27/2026 | 2 | ||
| 08/25/2026 | SemperTek | 01 35 26 | Question: Section 01 35 26, paragraph 1.9.C, states: “However, the SSHO has to be a separate qualified individual from the Prime Contractor’s Superintendent and/or Quality Control Manager with duties only as the SSHO.” | ||
| Please confirm that the SSHO must be a separate individual apart from the Superintendent and/or Quality Control Manager. | VA | Dual-hat allowable only, not triple hat (Superintendent, SSHO, and QA/QC) | 08/27/2026 | 2 | |
| 08/25/2026 | SemperTek | 04 20 00 | Question: Section 04 20 00, paragraph 1.4.H states that the Delegated Design Drawings and Calculations need to be “Signed and sealed by responsible design professional.” |
Please confirm whether a responsible design professional is required to sign and seal the delegated design drawings and calculations.
| Please also confirm whether this responsible design professional is required to be a structural engineer or other P.E. | VA | Yes. Delegated design drawings and calculations required by Section 04 20 00 shall be signed and sealed by a licensed Professional Engineer qualified for the work being designed. A separate Structural Engineer designation is not specifically required; however, the responsible design professional shall be appropriately licensed and qualified to perform the applicable masonry design. | 08/27/2026 | 2 | |
| 08/25/2026 | SemperTek | 07 84 00 | Question: Section 07 84 00, paragraph 1.5.C states “Contractor to engage a qualified inspector to perform inspections and final reports. The inspector to meet the criteria contained in ASTM E699 for agencies involved in quality assurance and to have a minimum of two years’ experience in construction field inspections of firestopping systems, products, and assemblies. The inspector to be completely independent of, and divested from, the Contractor, the installer, the manufacturer, and the supplier of material or item being inspected. Submit inspector qualifications.” | ||
| Please confirm whether an independent firestop inspector is required for this project, and if so that the qualifications for the inspector are to be upheld. | VA | Yes. An independent firestop inspector is required in accordance with Section 07 84 00, Paragraph 1.5.C. The inspector shall meet the qualifications specified therein, including the minimum two (2) years of applicable firestopping inspection experience and independence requirements. Submit inspector qualifications for Government review and acceptance. | 08/27/2026 | 2 | |
| 08/25/2026 | SemperTek | 08 11 13 | Question: Section 08 11 13, paragraph 1.4.G.1 states to “Submit calculations for review and approval prepared by qualified blast consultant, with a minimum of 5 years of experience in design of blast resistant window systems, verifying door assembly including anchors comply with specified blast resistance performance.” The spec goes on to state that “It is the responsibility of the delegated engineer responsible for the design of blast resistant doors to request and obtain the Physical Security and Resiliency Design Data Standard Data Definitions from the VA Office of Construction and Facilities Management (CFM).” | ||
| Please confirm whether a qualified blast consultant/delegated engineer will be required to fulfill this spec requirement. | VA | Yes. A qualified blast consultant/delegated engineer is required in accordance with Section 08 11 13, Paragraph 1.4.G. The delegated design professional shall provide the required calculations demonstrating that the door assembly, including anchorage, complies with the specified blast-resistance performance. Qualifications and calculations shall be submitted for Government review and approval in accordance with the Contract Documents. | 08/27/2026 | 2 | |
| 08/25/2026 | SemperTek | 13 05 41 | Question: Section 13 05 41, paragraph 1.3.A.1 states that “Non-structural seismic restraint systems shop drawings and delegated design calculations shall be prepared by a professional structural engineer with a minimum of 5 years’ experience in the design and detailing of seismic force restraints. The professional structural engineer shall be registered in the state where the project is located and submit qualifications with list of projects illustrating compliance with the experience requirement of this section. |
| Please confirm whether a professional structural engineer will be required to fulfill this spec requirement. | VA | A professional structural engineer is not required for standard conduit supports and seismic restraint installations that comply with the prescriptive requirements and applicable standard details of the Contract Documents and referenced standards. Where project-specific delegated design, calculations, or non-standard seismic restraint details are required, such design and calculations shall be prepared and sealed by a qualified registered Professional Engineer in accordance with Section 13 05 41. | 08/27/2026 | 2 | |
| 08/25/2026 | SemperTek | 22 05 11 | Question: Section 22 05 11, paragraph 2.10.A states that “Submittals… will be stamped and signed by a professional engineer registered in the state where the project is located.” | ||
| Please confirm whether a professional engineer will be required to fulfill this spec requirement. | VA | A Professional Engineer stamp is not required for standard plumbing piping supports and restraint installations that comply with the prescriptive requirements, manufacturer's requirements, and applicable standard details of the Contract Documents. Where project-specific engineered supports, non-standard restraint systems, or delegated design calculations are required, the associated drawings and calculations shall be prepared and sealed by a qualified Professional Engineer registered in the state where the project is located. | 08/27/2026 | 2 | |
| 08/25/2026 | SemperTek | 26 05 73 | Question: Section 26 05 73, paragraph 1.3.B states that a Quality Assurance study “shall be prepared by the equipment manufacturer, and performed by the equipment manufacturer’s licensed electrical engineer. | ||
| Please confirm whether this quality assurance study is required and whether a licensed electrical engineer employed by the equipment manufacturer must carry out this study. | VA | The study required by Section 26 05 73 remains applicable. However, the requirement that the study be performed specifically by a licensed electrical engineer employed by the equipment manufacturer is waived. The study may be prepared by the equipment manufacturer or other qualified entity experienced in performing electrical system coordination studies. The study shall comply with the applicable requirements of Section 26 05 73 and shall be submitted for Government review and acceptance. | 08/27/2026 | 2 | |
| 08/25/2026 | SemperTek | 31 20 00 | Question: Section 31 20 00, paragraph 3.1.A.5 states that “The Contractor is required to hire a Professional Geotechnical Engineer to provide inspection of excavations and soil/groundwater conditions throughout construction. The Geotechnical Engineer shall be responsible for performing pre-construction and periodic site visits throughout construction to assess site conditions. The Geotechnical Engineer shall update the excavation, sheeting and dewatering plans as construction progresses to reflect changing conditions and shall submit an updated plan if necessary. A written report shall be submitted, at least monthly, informing the Contractor and COR of the status of the plan and an accounting of the Contractor's adherence to the plan addressing any present or potential problems. The Geotechnical Engineer shall be available to meet with the COR at any time throughout the contract duration.” |
| Please confirm whether a Professional Geotechnical Engineer will be required for this project and whether the listed responsibilities will be upheld. | VA | Not required. | 08/27/2026 | 2 | |
| 08/25/2026 | SemperTek | 31 20 00 | Question: Section 01 00 00, paragraph 1.12.A states that a “A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.” This is highlighted again in Section 31 20 00, paragraphs 1.5.A and 1.6.A. |
| Please confirm whether a Registered Professional Land Surveyor or Registered Civil Engineer is required to fulfill this spec requirement. | VA | The Registered Professional Land Surveyor/Registered Civil Engineer requirement is not required for this project. The Contractor shall be responsible for locating, identifying, and documenting existing underground utilities within the limits of work prior to excavation. Particular attention shall be given to the existing 4160V medium-voltage electrical lines and associated concrete-encased ductbanks located within the area of work. These utilities shall be positively located and properly protected from damage throughout construction. Coordinate all utility locating and excavation activities with the COR and applicable VA personnel prior to commencing excavation. The Contractor shall exercise appropriate care and utilize suitable excavation methods when working in proximity to existing utilities. | 08/27/2026 | 2 | |
| 08/25/2026 | SemperTek | 27 05 11 | Question: Section 27 05 11, paragraph 1.7.D.1 states to “Submit written certification from OEM indicating that proposed supervisor of installation and proposed provider of warranty maintenance are authorized representatives of OEM. Include individual's legal name, contact information and OEM credentials in certification.” | ||
| Please confirm if written certification from OEM indicating that proposed supervisor of installation and proposed provider of warranty maintenance are authorized representatives of OEM will be required. | VA | OEM is required to perform startup and warranty maintenance on equipment. | 08/27/2026 | 2 | |
| 08/25/2026 | SemperTek | 26 32 13 | Question: Section 26 32 13, paragraph 2.8.C states that “Batteries shall be nickel-cadmium high discharge rate type.” |
Please confirm that lead acid batteries can be provided in lieu of nicad batteries.
| AE | Nickel-cadmium are the specified | ||||||||||
| battery type. | 08/27/2026 | 2 | |||||||||
| 08/25/2026 | SemperTek | M-101 | Question: Drawing Sheet M-101, Keynote 1 references sheet PL-500 for fuel information regarding bulk fuel tank information / size. There was no PL-500 sheet provided in the drawings. | ||||||||
| Please provide Drawing Sheet PL-500. | AE | Drawing note should read, "See M-500 series drawings for fuel tank details" | 8 | ||||||||
| 08/25/2026 | SemperTek | Please provide a specification or spec section for the docking station. | AE | See basis of design or equal for equipment information. Additional information can be provided per direction of VA COR. | 8 | ||||||
| 08/25/2026 | SemperTek | 16. | Please provide contact information for the current Fire Alarm company currently on contract with the Carl Vinson VAMC. | VA | There is no current Fire Alarm contract holder. Fire alarm is Honeywell Notifier | 08/27/2026 | 2 | ||||
| 08/25/2026 | SemperTek | 17. | Please confirm that remote monitoring of new generators is to be at the building 12A nurse station per drawing notes. | VA | 12A Nurse's Station for Building 4 Generator and 15B for Building 2 Nurses' Station | 08/27/2026 | 2 | ||||
| 08/25/2026 | SemperTek | 18. | Please confirm whether conduit and cabling are required for the remote monitoring or is Mod Bus connection via Ethernet acceptable? | AE/VA | Contractor shall provide conduit and cabling. | 8 | |||||
| 08/25/2026 | SemperTek | 19. | Please confirm who is responsible for removal of existing fuel? Does the government want the fuel for other tanks? | VA | Contractor to remove fuel prior to disposal. Contractor to dispose of fuel tanks. | 08/27/2026 | 2 | ||||
| 08/25/2026 | SemperTek | 20. | Please confirm who is responsible for fueling the new generators? | VA | Contractor to provide fuel for all testing and commissioning and fill tanks prior to final acceptance. | 08/27/2026 | 2 | ||||
| 08/25/2026 | SemperTek | 21. | Please confirm whether the government wants possession of the existing generators or is contractor responsible for removal from site? | VA | Contractor responsible for proper disposal of existing generators. | 08/27/2026 | 2 | ||||
| 08/25/2026 | SemperTek | 22. | Please confirm whether the government wants possession of the existing fuel tanks or is contractor responsible for removal from site? | VA | Contractor responsible for proper disposal of fuel tanks. | 08/27/2026 | 2 | ||||
| 08/25/2026 | SemperTek | 23. | Please confirm whether new ATS switches are required to have load shed capability? | VA | Yes, the ATS switches should have this capability. | 08/27/2026 | 2 | ||||
| 08/25/2026 | SemperTek | 24. | Drawing Sheet A-101 shows that the top of the blast wall is to be 24” above the top of equipment in Detail 4. Detail 2 General Note A states “Contractor to coordinate final enclosure height with final equipment selections. Enclosure wall shall be a minimum of 24” above the top of associated equipment within enclosure…” The height of the new equipment will not be known at bid time. | ||||||||
| For bidding purposes, please provide a wall height for bidders to price and please confirm that any differences between bidding height and actual required height (which is unknown) will be handled with a contract modification. | AE | The estimated wall height shall be 14'-6". It shall be the contractors responsibility to coordinate final enclosure height with equipment dimensions as per contract documents. Any alternate equipment dimensions for final equipment selections and modifications to the screen wall height shall be the responsibility of the contractor. Contract modification will not be accepted. Contractor shall coordinate with their final equipment selections. | 8 | ||||||||
| 08/25/2026 | BIC | 23 10 00 | Spec section 23 10 00 part 2.1.A calls for the generator main AST to be “horizontal cylindrical configuration”, but the Tank Area Detail on drawing M-501 seems to call for a horizontal rectangular configuration. Please clarify what type of tank is required. | AE | The tank/generator enclosures have been designed based on the rough dimension requirements of horizontal cylindrical 5,000-gal tanks, as illustrated on sheets A-101 & A-103. Provide horizontal cylindrical tanks. | 8 | |||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 | ||||||||||
| 08/25/2026 | 8 |
Instructions RFI Log - Quick Guide
| Field | Use |
| RFI No. | Project RFI identifier (e.g., RFI-001). |
| Date Response Required | Contractual or project target response date. |
| Status | Open, Pending, Answered, Closed, or Void. |
| Days Open | Calculated automatically from Date Submitted through Date Responded (or today). |
| Cost / Schedule Impact | Use Yes, No, or TBD to flag potential impacts. |
| Change Order / PCO Ref. | Cross-reference any resulting pricing/change documentation. |