This document is a Standard Form 30 amendment to a solicitation for maintenance, inspection, and testing services of the electrical power distribution system at Tuscaloosa VA Medical Center. Amendment 0005, issued January 28, 2026, revises the Statement of Work to remove the contractor's requirement to provide load banks to attain minimum generator load percentages while retaining the mandatory 4-hour Essential Electrical System (EES) outage test. The solicitation closing date is extended to February 2, 2026, at 12:00 PM Eastern Standard Time. The amendment is issued by the Department of Veterans Affairs, Veterans Health Administration, Network Contracting Office (NCO) 7 in Atlanta, Georgia, under solicitation number 36C24726Q0147.
The Statement of Work describes comprehensive maintenance and testing requirements for qualified electrical contractors at the Tuscaloosa facility. Work is performed Monday through Friday, 7:00 AM to 3:30 PM, excluding federal holidays, with a 90-day contract duration from award. Contractors must hold NETA or equivalent certification, possess minimum five years' continuous experience with electrical power distribution systems in healthcare/industrial/commercial facilities, complete OSHA 10-hour construction safety training and NFPA 70E Qualified Person certification, and provide calibrated tools and personal protective equipment. Required work includes maintenance and testing of 22 categories of electrical equipment per NETA specifications and VHA Directive 1028, infra-red thermographic surveys to detect connection deficiencies, system function tests, and participation in the mandatory 4-hour EES outage test which includes opening all utility service connections. Contractors must include utility company costs in their bid proposal and assist VAMC staff with troubleshooting during the test. Deliverables include a comprehensive written report submitted within seven calendar days, documenting all work performed, test data, equipment information, contractor credentials, and recommended corrective actions in both hard copy and electronic format.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SOW Clarification.docx | DOCX document | |
| S06 Amendment 36C24726Q0147 0004 Triennial Electrical Contract.pdf | ||
| S06 Amendment 36C24726Q0147 0003.pdf | ||
| Combined Report.pdf | ||
| S06 Amendment 36C24726Q0147 0002 Triennial Electrical Contract.pdf | ||
| Amendment 36C24726Q0147 0001 Triennial Electrical Contract.pdf | ||
| Amendment 36C24726Q0147 0001 Triennial Electrical Contract.pdf | ||
| 36C24726Q0147_2.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 10
0005 01-28-2026
679-26-2-5056-0016
None
508A
DEPARTMENT OF VETERANS AFFAIRS
VETERANS HEALTH ADMINISTRATION
Network Contracting Office (NCO) 7 2957 CLAIRMONT ROAD NE, Suite 1200 Atlanta GA 30329
508A
DEPARTMENT OF VETERANS AFFAIRS
VETERANS HEALTH ADMINISTRATION
Network Contracting Office (NCO) 7 2957 CLAIRMONT ROAD NE, Suite 1200 Atlanta GA 30329
To all Offerors/Bidders
36C24726Q0147
X
X X
** HOUR & DATE for Receipt of Offers is EXTENDED to: 02-02-2026 12PM EST
679-3660162-5056-854100-2580 010055590 x 1
This amendment revises the Statement of Work to remove the requirement for the contractor to provide load banks to attain the minimum load percentage of the generator nameplate rating. The requirement for the 4-hour Essential Electrical System (EES) outage test remains unchanged.
The revised Statement of Work is attached and supersedes all previous versions. This amendment is issued for clarification purposes and to allow offerors adequate time to revise quotations.
The solicitation closing date is hereby extended to Monday, February 2, 2026, at 12:00 PM Eastern Standard Time.
All other terms and conditions remain unchanged.
Jessica Cummings Contracting Officer
Question:
Will the VA consider removing the 4-hour Essential Electrical System (EES) outage testing and related load bank requirements from the Statement of Work?
Answer:
The Statement of Work has been revised by amendment to remove the requirement for the contractor to provide load banks to attain the minimum generator load percentage.
The requirement for the 4-hour Essential Electrical System (EES) outage test remains required and has not been removed.
Offerors shall rely on the solicitation as issued and amended when preparing quotations.
DEPARTMENT OF VETERANS AFFAIRS
TUSCALOOSA VA MEDICAL CENTER
STATEMENT OF WORK
FOR
Maintenance, Inspection, and Testing of the Electrical Power Distribution System
1. Introduction:
A. This Statement of Work (SOW) describes the requirements for the maintenance, inspection, testing, and/or calibration of the Electrical Power Distribution System and all of its components at the Tuscaloosa VA Medical Center. These work items are referenced as “Maintenance and Testing” in this document, hereafter.
B. This SOW describes the requirements for the Qualified Electrical Contract Professionals – known as “Contractors” in this document, hereafter. Contractors who are contracted by VA Medical Center to perform maintenance and testing of the Electrical Power Distribution System, and all its components shall meet all requirements stated in Section 2 of this SOW.
C. This SOW describes the requirements to establish maintenance and testing reports.
D. Period Performance:
1) Monday through Friday 7am-3:30pm not to include federal holidays.
2) The contract will run for 90days beginning from the award date.
Site Visit:
52.237-1 SITE VISIT (APR 1984) Offerors or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
Schedule:
- December 29th, 30th & 31st from 7am-3:30pm
- January 2nd and 5th from 7am-3:30pm
Point of Contact:
- Shemeka Braggs, Program Analyst; shemeka.braggs@va.gov 205-554-3619.
(M-F; 8:30am til 5pm).
- Scott Klatt, Electrical Supervisor; scott.klatt@va.gov 205-554-2000 ext. 4111.
(M-F; 7am-3:30pm).
2. Qualifications of Contractors:
mailto:shemeka.braggs@va.gov mailto:scott.klatt@va.gov
A. Contractors shall be experienced Electrical Contractors, having properly trained and licensed permanent staff required to perform the proposed work.
Electrical Contracting (i.e. the construction, repair, testing and maintenance of industrial and commercial electrical distribution systems) shall be the primary interest/specialty of the Contractor’s business.
B. Contractors shall be certified by the International Electrical Testing Association (NETA) or equivalent certifying organization as Certified Technicians with each having completed the Occupational Safety & Health Administration (OSHA) approved 10-hour construction safety training.
C. Contractors shall have technical training and demonstrable track records of working experience in maintenance, inspection, and testing of the Electrical Power Distribution Systems and related components in healthcare, industrial, educational, and commercial facilities for a minimum of five (5) continuous years.
Electrical components on which the Contractors have experience shall include, but not be limited to, switchboards & switchgear (low and medium voltage); low voltage controls; emergency and standby generators; automatic transfer switches, wiring, transformers, meters, and other electrical appurtenances.
D. Contractors shall have safety trainings – either on-the-job or class-room type - in electrical safety outlined in the OSHA Standard 29 Code of Federal Regulations (CFR) 1910 Subpart S – Electrical, and the NFPA 70E – Standard for Electrical Safety in the Workplace. Training certification shall be provided indicating each technician is a Qualified Person as defined by NFPA 70E.
Training certifications shall be submitted to the VA Contracting Officer prior to work. If no training certifications are available, the contractor’s Employer shall certify that he/she has met this requirement in writing and submit it to the VA Contracting Officer prior to work.
E. Contractors shall have ready access to the latest versions of the following references in order to comply with referenced minimum compliance with these codes and/or regulations:
1) NFPA 70, National Electrical Code.
2) NFPA 70B, Recommended Practice for Electrical Equipment Maintenance.
3) NFPA 70E, Standard for Electrical Safety for the Workplace.
4) NFPA 110, Standard for Emergency and Standby Power System.
5) OSHA Standard 29 CFR 1910, Subparts I & S.
6) International Electrical Testing Association, Inc. (NETA) – Maintenance and Testing Specifications.
7) Operating /Maintenance manuals and specifications of the electrical equipment to be maintained and tested. These documents may be obtained from the VHA Medical Center, or the equipment manufacturers.
8) VHA Directive 1028, Electrical Power Distribution System
F. Contractors shall have and provide all necessary tools, equipment, and Personal Protective Equipment (PPE) to perform the work safely, effectively, and timely. Tools, equipment, and PPE shall comply with the requirements of OSHA Standard 29 CFR 1910, Subpart I, and NFPA 70E. Prior to initiating work, Contractor shall provide documentation that all instruments, test equipment, tools and PPE have current calibration. Dated calibration labels shall be visible on all instruments, test equipment, tools and PPE as appropriate.
3. Summary of Work:
A. The Contractor shall provide a proposed schedule with their bid proposal.
The schedule shall be in the form of a progress chart of suitable scale to indicate the work scheduled for completion by any given date during the work period. The proposed schedule shall be reviewed by Tuscaloosa VAMC, Engineering Service; any requirements for adjusting the schedule (e.g. to minimize disruption to the VAMC) shall be incorporated by the Contractor.
B. Contractors shall report deficiencies that are deemed critical or catastrophic immediately to the Contracting Officer and Chief, Engineering Service for immediate actions.
C. Work items, definitions, and references shall comply with the latest edition of the NETA – Maintenance Testing Specifications (MTS) and with the VHA Directive 1028, Electrical Power Distribution System. Below is a list of types of electrical equipment that shall be maintained and tested:
1) Switchgear and Switchboard Assemblies.
2) Transformers, Dry Type, Air-Cooled, Low-voltage, Small.
3) Transformers, Dry Type, Air-Cooled, Low-voltage, Large.
4) Transformers, Liquid-Filled.
5) Metal–Enclosed Busways.
6) Switches, Air, Low-Voltage.
7) Switches, Air, Medium-Voltage, Metal-Enclosed.
8) Switches, Oil, Medium-Voltage.
9) Switches, Vacuum, Medium-Voltage.
10) Switches, SF6, Medium-Voltage.
11) Circuit Breakers, Air, Insulated-Case/ Molded-Case.
12) Circuit Breakers, Air, Low-Voltage Power.
13) Circuit Breakers, Oil, Medium and High-Voltage.
14) Circuit Breakers, Vacuum, Medium-Voltage.
15) Circuit Breakers, SF6.
16) Protective Relays, Mechanical, and Solid State.
17) Protective Relays Microprocessor Based.
18) Grounding Systems.
19) Ground-fault Protection Systems.
20) Motor Control, Motor Starters, Low-Voltage.
21) Emergency Systems, Engine Generators.
22) Emergency Systems, Automatic Transfer Switches.
D. Attachments. Government Furnished.
1) Inventory of Electrical Power Distribution System equipment to be maintained, inspected, and tested under this Scope of Work.
2) One-line and other informational drawings of the Electrical Power Distribution System. These drawings are not certified as-built drawings.
3) Electrical Power System study information relevant to the scope of this effort, such as coordination study data, short-circuit analysis, arc-flash hazard analysis and available protective device setting information are available from a 2014 study.
E. Infra-Red Scanning/Thermographic Survey shall be performed on electrical equipment.
1) Use an infra-red scanning camera to detect hot spots in the Electrical Power Distribution System. Objective of this work is to detect any loose, broken, or corroded connections in the system. Problem connections shall be replaced with new connectors, and/or tightened with torque wrench to meet the equipment manufacturers’ specifications.
2) Note that since this work item must be done while the Electrical Power Distribution System is energized, appropriate safety precautions must be taken before, during and after scanning the system.
F. System Function Tests. Provide function tests for all equipment listed in this Scope of Work.
G. Test conditions shall be coordinated with the technical point of contact.
H. 4-Hour Power Outage Test
The Contractor shall be present for and will participate in the VAMC 4-hour test of the Essential Electrical System (EES). This test shall fulfill the requirements of VHA Directive 1028, Electrical Power Distribution System, NFPA 110 (e.g. Para. 8.4.9.) and The Joint Commission (TJC). This test will include opening all utility service connections serving the VAMC for a minimum of 4 hours. During the test period, verify operation of all EES components including the transfer to emergency power and return to normal service. The Contractor shall include in their bid proposal all costs associated with the services of the local utility company for the duration of the test. The estimated duration of the Contractor’s involvement is between 8 – 12 hours. The Contractor shall assist the VAMC staff with troubleshooting and correcting malfunctioning electrical equipment discovered during the test. Contractor shall make any required adjustments and/or re-calibrations to all equipment which has been otherwise maintained, inspected, and tested under this Scope of Work.
Buildings included are 1, 2, 3, 4, 5, 6, 7, 8, 12, 15, 17, 18, 33, 38, 39, 40, 41, 46, 61, 63, 101, 135, 137, 138, 143, 146, 147, and 149. Generators include 61, 62, 135, 139, 140, 141, 146, 147, 149 and Mobile Generator.
4. Deliverables after completion of work:
A. A complete written report of the work performed shall be provided to the VA within 7 days of completion. Information shown in the report shall be as follows:
1) Company’s name, addresses, telephone, & FAX numbers.
2) Name and signature of contractors who perform the maintenance and testing.
3) VA Work Contract Number, name and number of VA Contracting Officer.
4) Date and time of work.
5) Copies of contractors’ valid licenses, professional and training certificates.
6) Descriptions and model number of specialized tools and equipment used, such as torque wrench or infra-red scanning camera and calibration certifications.
7) Location, Type, Name, and nameplate information of electrical equipment to be maintained and tested.
8) Descriptions of work items.
9) Test data.
10) Reference materials such as equipment manufacturer’s specifications, coordination study, etc.
11) Remarks on conditions of electrical equipment. List all deficiencies, if any.
12) Recommended corrective actions, if any.
B. Submit one (1) hard copy of the complete written report, and one (1) CD- ROM or DVD of the electronic version of the report in Microsoft Word format to the Chief, Engineering Service within seven (7) calendar days of visit. All reference materials shall be included in the electronic version of the report, either through scanning or other means of electronic text import methods.
END OF STATEMENT OF WORK