S06 Amendment 36C24726Q0147 0002 Triennial Electrical Contract.pdf

PDF 151 KB Posted

Attached to
H961--Triennial Electrical Power Distribution System Testing Services Federal contract opportunity
Solicitation number
36C24726Q0147
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 7

About this file

This is a Standard Form 30 Amendment of Solicitation/Modification of Contract for a Triennial Electrical Contract issued by the Department of Veterans Affairs Veterans Health Administration Network Contracting Office (NCO) 7 in Atlanta, Georgia. The solicitation number is 36C24726Q0147, and the amendment extends the closing date to January 26, 2026, at 12:00 PM EST to allow vendors to respond to questions and review a combined report providing general scope information. The contract is a Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside with NAICS code 541350 (Building Inspection Services), requiring inspection, testing, and evaluation of existing electrical power distribution systems. The previous contract was held by Slocum & Associates under contract number 36C24722P0492, with no changes in scope from the prior testing cycle.

The Questions and Answers section addresses 34 vendor inquiries regarding equipment specifications, testing methodologies, documentation requirements, and operational procedures. Key clarifications include: low-voltage circuit breakers may be tested by secondary injection if allowed by NETA standards; medium-voltage liquid-filled transformers testing may be limited to oil sampling and inspection; load banks are required for the four-hour Emergency Electrical Systems outage test; contractor-furnished load banks are required for the main outage; the VA is responsible for utility coordination; final reports are required in PDF format only; electronic submission is acceptable; NICET certification is not accepted in lieu of NETA; equipment inventory details and one-line drawings are available in the study documentation; the Arc Flash study is current; and outage work may occur outside normal Monday-Friday business hours with approved workarounds. The NAICS code was updated from 238210 to 541350 following vendor feedback and the Contracting Officer's determination that the principal purpose is inspection and testing services rather than installation work.

View the file

Other files for this federal contract opportunity

Other files attached to H961--Triennial Electrical Power Distribution System Testing Services, newest first.
File Type Posted
S06 Amendment 36C24726Q0147 0005 Triennial Electrical.pdf PDF
SOW Clarification.docx DOCX document
S06 Amendment 36C24726Q0147 0004 Triennial Electrical Contract.pdf PDF
S06 Amendment 36C24726Q0147 0003.pdf PDF
Combined Report.pdf PDF
Amendment 36C24726Q0147 0001 Triennial Electrical Contract.pdf PDF
Amendment 36C24726Q0147 0001 Triennial Electrical Contract.pdf PDF
36C24726Q0147_2.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 5

0002 01-20-2026

679-26-2-5056-0016

None

508A

DEPARTMENT OF VETERANS AFFAIRS

VETERANS HEALTH ADMINISTRATION

Network Contracting Office (NCO) 7 2957 CLAIRMONT ROAD NE, Suite 1200 Atlanta GA 30329

508A

DEPARTMENT OF VETERANS AFFAIRS

VETERANS HEALTH ADMINISTRATION

Network Contracting Office (NCO) 7 2957 CLAIRMONT ROAD NE, Suite 1200 Atlanta GA 30329

To all Offerors/Bidders

36C24726Q0147

X

X X

** HOUR & DATE for Receipt of Offers is EXTENDED to: 01-26-2026 12PM EST

679-3660162-5056-854100-2580 010055590

X 1

The purpose of this amendment is to extend the solicitation closing date and to respond to vendor questions.

The solicitation closing date is hereby extended to January 26, 2026

Questions and Answers:

Responses to vendor questions are provided in Attachment 1 – Questions and Answers.

Combined Report:

The Government is providing Attachment 2 – Combined Report for informational purposes only. The information contained in the Combined Report is intended to assist vendors in understanding the general scope of the requirement.

All other terms and conditions of the solicitation remain unchanged.

Jessica Cummings Contracting Officer

Questions

Triennial Electrical Contract, Solicitation 36C24726Q0147

1. Also, the Scope of work mentions “Government Furnished Attachments outlined in Section 3.D (Items 1, 2, and 3)” Let me know if it’s feasible to provide these attachments See study

2. Please provide a list of the equipment that needs to be tested. See study

3. Please provide the latest test report (I'm referring to the electrical test report, not the Arc Flash study report). Provided

4. Can low-voltage circuit breakers be tested by secondary injections only? If allowed by NETA.

5. Can MV Liquid Filled Transformers testing be limited to oil sampling, and inspection? Yes

6. If the answer to the previous question is no, should we perform tests for Polarization Index, Excitation Current, Turns Ratio, Insulation and Winding Resistance on the MV Transformers?

7. In the STATEMENT OF WORK, in section “3. Summary of Work”, part “D. Attachments. Government Furnished”, the specifications state that the government should provide the inventory of electrical equipment, one-line drawing, and 3) an Electrical Power System study, but these documents were not found. Please provide the files. See study

8. How many panels are there in total? This will be important for estimating the time spent on the IR Scan. See study.

9. Could you provide us with the quantity of each piece of equipment that needs to be tested See study.

10. We see a list of the equipment expected to be included, but there aren't any quantities, could you please provide us with the exact quantities?

See study.

11. Can the Government provide the previous contract number(s) for the triennial electrical testing services? 36C24722P0492

12. Who was the incumbent contractor, and what was the previous contract value? Slocum & Associates

13. Were there any changes in scope from the prior testing cycle? No.

14. Are electrical one-line diagrams available for: See study report

• Emergency Electrical System (EES)

• Normal power distribution

• Load bank connection points

15. Will short-circuit, coordination, or arc-flash studies be provided, or is validation expected as part of this effort? See study.

16. Can the Government provide a detailed equipment inventory identifying switchgear, breakers, relays, and ATS units? See study.

17. Are load banks required to be contractor-furnished for the four-hour EES outage test? Yes for the main outage.

18. Please clarify which equipment requires: Please reference NETA for guidance.

• Primary injection testing

• Secondary injection testing

• Functional or visual inspection only

19. Are any devices excluded from primary testing due to operational or risk concerns? Not that we are aware of.

20. What is the maximum allowable outage window for the four-hour EES test? 4 hours

21. Is coordination with the serving utility the responsibility of the contractor or the VA? VA

22. Is the final report required in editable Word format in addition to PDF?

PDF

23. Are hard copies and physical media (CD/DVD/USB) still required, or is electronic submission acceptable? Electronic is acceptable

24. Regarding Solicitation 36C24726Q0147, will the government accept NICET certification in lieu of NETA? No.

25. Can you please provide the 3 items listed in section 3 subsection “D” 1- 3? (Government Furnished Attachments) See study

26. Do we have drawings for this location? Need to know how much equipment is being tested at this site. Study provided to get the amount of equipment.

Switchgear and Switchboard Assemblies.

Transformers, Dry Type, Air-Cooled, Low-voltage, Small.

Transformers, Dry Type, Air-Cooled, Low-voltage, Large.

Transformers, Liquid-Filled.

Metal–Enclosed Busways.

Switches, Air, Low-Voltage.

Switches, Air, Medium-Voltage, Metal-Enclosed.

Switches, Oil, Medium-Voltage.

Switches, Vacuum, Medium-Voltage.

Switches, SF6, Medium-Voltage.

Circuit Breakers, Air, Insulated-Case/ Molded-Case.

Circuit Breakers, Air, Low-Voltage Power.

Circuit Breakers, Oil, Medium and High-Voltage.

Circuit Breakers, Vacuum, Medium-Voltage.

Circuit Breakers, SF6.

Protective Relays, Mechanical, and Solid State.

Protective Relays Microprocessor Based.

Grounding Systems.

Ground-fault Protection Systems.

Motor Control, Motor Starters, Low-Voltage.

Emergency Systems, Engine Generators.

Emergency Systems, Automatic Transfer Switches.

27. What is the deadline for submitted questions? January 9, 2025, The solicitation states January 9th. Yes

28. Period of Performance is listed as Monday-Friday 0700-1530. Will all outage work be completed during normal business hours? Yes work arounds are acceptable.

29. Will the onelines be provided? Latest study doc provided

30. Is the Arc Flash study current? Yes.

31. Can you provide the previous cycle test reports? No.

32. Will the previous schedule be provided? It's nearly impossible for the contractor to predict how and when the VA can perform outages throughout the facility. We would need previous schedules and/or directions from the electrical staff. Electrical shop assisted in escorting and previous schedule is unavailable.

33. Will the VA provide nameplate data from all generators requiring load banking? Yes.

34. Upon reviewing the solicitation, we noted that the assigned NAICS code is 238210 (Electrical Contractors and Other Wiring Installation Contractors), with a small business size standard of $19.0 million. We respectfully request that this be changed to NAICS code 811211 (Consumer Electronics Repair and Maintenance), which has a small business-size standard of $22.5 million. NAICS code was updated 541350 Following review of vendor feedback and the statement of work, the Contracting Officer determined that the principal purpose of the requirement is inspection, testing, and evaluation of existing electrical power distribution systems. In accordance with FAR 19.303(a), the NAICS code was updated to 541350 (Building Inspection Services) via solicitation amendment. The requirement remains a SDVOSB set-aside.

work, the Contracting Officer determined that the principal purpose of the requirement is inspection, testing, and evaluation of existing electrical power distribution systems. In accordance with FAR 19.303(a), the NAICS code was updated to 541350 (Building Inspection Services) via solicitation amendment. The requirement remains a SDVOSB set-aside.

File details come from the government source that posted it. Updated .