Specifications - Emergency Roofing Replacement 679-23-101.pdf
PDF 14 MB Posted
- Attached to
- Z1DA--679-23-101 | Special Roofing Replacements Federal contract opportunity
- Solicitation number
- 36C24724R0067
About this file
This document is the Specifications for the Emergency Roofing Replacement 679-23-101 project. The relevant federal contract opportunity is Solicitation Number 36C24724R0067, titled "Z1DA--679-23-101 | Special Roofing Replacements".
The solicitation is for a contractor to provide all materials, supervision, and labor to complete the roofing replacement project on Buildings 1, 4, 5, 12, 17, 18, 61, and 135 at the Tuscaloosa VA Medical Center. The work includes construction and replacement of the roofs, as well as necessary trades such as carpentry, plumbing, electrical, fire piping, HVAC, and other tasks. The contractor must comply with VA safety rules, NFPA, EPA, and NEC codes, and ensure employees have completed required OSHA training. The contract performance period is 365 calendar days from the date of award. The agency is the Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 7.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24724R0067 0003.docx | DOCX document | |
| 36C24724R0067 0002.docx | DOCX document | |
| 36C24724R0067 0001.docx | DOCX document | |
| Roof Investigation Report - all combined.pdf | ||
| Pre- Bid Site Visit 6-3-24.pdf | ||
| Past Performance Questionnaire.docx | DOCX document | |
| Attachment 2 - 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING Jan 2023 Dev form.pdf | ||
| Drawings 679-23-101.pdf | ||
| UPDATED DBA WAGES AL20240098.pdf | ||
| Attachment 1 - Experience Modification Rate Form 2022 Revised 2 2 2023.pdf | ||
| 36C24724R0067_1.docx | DOCX document |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF VETERAN AFFAIRS
ATLANTA VAMC
3700 Crestwood Parkway, Suite 310 Duluth, GA 30096
1009 Bayou Place Alexandria, LA 71303
(318) 445-6571
Specifications
Emergency Roofing Replacement
Tuscaloosa VAMC
Tuscaloosa, AL
Buildings:
1, 4, 5, 12, 17, 18, 61, and 135
Contract Number:
36C246723R0135
Issue for Bidding
January 10, 2024
Project Number: 679-23-101
SPECIFICATIONS
AND
CONTRACT DOCUMENTS
FOR
EMERGENCY ROOFING REPLACEMENT
TUSCALOOSA VAMC
TUSCALOOSA, AL
PROJECT NO. 679-23-101
BALLARD CLC, INC.
PROJECT NO. 232900
BALLARD CLC, INC.
CONSULTING ENGINEERS
1009 BAYOU PLACE
ALEXANDRIA, LA 71303
January 10, 2024
William R Aldridge, AIA, NCARB Ballard CLC, Inc.
Reg. Architect No. 9349 State of Alabama
This specification is the property of Ballard CLC, Inc., and is submitted on the condition that it shall not be reproduced or copied in whole or in part without prior written consent of Ballard CLC, Inc.
01/10/24
01/10/2024
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 11-21
01 33 23 Shop Drawings, Product Data, and Samples 02-23
01 35 26 Safety Requirements 10-22
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 57 19 Temporary Environmental Controls
01 58 16 Temporary Interior Signage
01 74 19 Construction Waste Management 04-22
01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 82 13.21 Asbestos Roofing Abatement 01-21
Asbestos Roofing Abatement - Building 1 Report
Asbestos Roofing Abatement - Building 4 Report
Asbestos Roofing Abatement - Building 5 Report
Asbestos Roofing Abatement - Building 12 Report
Asbestos Roofing Abatement - Building 17 Report
Asbestos Roofing Abatement - Building 18 Report
02 83 33.13 Lead-Based Paint Removal and Disposal 01-21
Appendix A-Bldg 1-Asbestos/Lead Paint Inspection Report-
Appendix D-Bldg 4-Asbestos/Lead Paint Inspection Report
Appendix E-Bldg 5-Asbestos/Lead Paint Inspection Report
Appendix I-Bldg 12-Asbestos/Lead Paint Inspection Report
Appendix K-Bldg 17-Asbestos/Lead Paint Inspection Report
Appendix L-Bldg 18-Asbestos/Lead Paint Inspection Report
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
06 20 00 Finish Carpentry 01-21
06 40 00 Architectural Wood Columns
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 01 50.19 Preparation for Re-Roofing 01-21
07 21 13 Thermal Insulation 01-21
07 22 00 Roof and Deck Insulation 01-21
07 31 13 Asphalt Shingles 01-21
07 31 90 Polymeric Slate
07 40 00 Roofing and Siding Panels 01-21
07 54 23 Thermoplastic Polyolefin (TPO) Roofing 01-21
07 60 00 Flashing and Sheet Metal 01-21
07 71 00 Roof Specialties 01-21
07 72 00 Roof Accessories 01-21
07 92 00 Joint Sealants 04-22
01/10/2024
00 01 10-2
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 08 – OPENINGS
08 90 00 Louvers and Vents 01-21
DIVISION 09 – FINISHES
09 91 00 Painting 01-21
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 01-23
22 14 00 Facility Storm Drainage 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
(HVAC)
23 05 11 Common Work Results for HVAC 03-23
23 07 11 HVAC and Boiler Plant Insulation 02-23
23 23 00 Refrigerant Piping 03-23
23 34 00 HVAC Fans 03-23
23 81 00 Decentralized Unitary HVAC Equipment 03-23
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-22
26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22
26 05 26 Grounding and Bonding for Electrical Systems 11-22
26 05 33 Raceway and Boxes for Electrical Systems 11-22
26 41 00 Facility Lightning Protection 11-22
26 51 00 Interior Lighting 11-22
VA 05-01-20
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
ARCHITECTURAL
G-100 Cover Sheet, Index of Drawings, Maps
G-200 Abbreviations, Symbol Legend
G-201 General Notes Sheet
G-300 Overall Site Plan
1-S-100 Design Wind Load Plan & Uplift Pressures
4-S-100 Design Wind Load Plan & Uplift Pressures
5-S-100 Design Wind Load Plan & Uplift Pressures
12-S-100 Design Wind Load Plan & Uplift Pressures
17-S-100 Design Wind Load Plan & Uplift Pressures
18-S-100 Design Wind Load Plan & Uplift Pressures
61-S-100 Design Wind Load Plan & Uplift Pressures
135-S-100 Design Wind Load Plan & Uplift Pressures
1-G-400 Architectural Site Plan
1-AD100 Roof Plan – Demolition
1-AD200 Exterior Building Elevations - Demolition
1-A-100 Roof Plan – New Work
1-A-200 Exterior Building Elevations – New Work
1-A-800 Reference Photos
1-A-801 Reference Photos
1-A-802 Reference Photos
4-G-400 Architectural Site Plan
4-AD100 Roof Plan – Demolition
4-AD200 Exterior Building Elevations – Demolition
4-AD201 Exterior Building Elevations – Demolition
4-A-100 Roof Plan – New Work
4-A-200 Exterior Building Elevations - New Work
4-A-201 Exterior Building Elevations - New Work
4-A-800 Reference Photos
4-A-801 Reference Photos
00 01 15 - 2
5-G-400 Architectural Site Plan
5-AD100 First Floor Plan(s) – Demolition
5-AD101 Second Floors Plan(s) – Demolition
5-AD102 Roof Plan & Section – Demolition
5-A-100 First Floor Plans – New Work
5-A-101 Second Floor Plans – New Work
5-A-102 Roof Plan – New Work
5-A-200 Exterior Building Elevations – New Work
5-A-201 Exterior Building Elevations – New Work
5-A-300 Porch Sections & Details
5-A-800 Reference Photos
5-A-801 Reference Photos
12-G-400 Architectural Site Plan
12-AD100 Roof Plan – Demolition
12-AD200 Exterior Building Elevations – Demolition
12-AD201 Exterior Building Elevations – Demolition
12-A-100 Roof Plan – New Work
12-A-200 Exterior Building Elevations - New Work
12-A-201 Exterior Building Elevations - New Work
12-A-800 Reference Photos
12-A-801 Reference Photos
17-G-400 Architectural Site Plan
17-AD100 Roof Plan – Demolition
17-AD200 Exterior Elevations – Demolition
17-A-100 Roof Plan – New Work
17-A-200 Exterior Elevations – New Work
17-A-800 Reference Photos
18-G-400 Architectural Site Plan
18-AD100 Roof Plan – Demolition
18-AD200 Exterior Elevations – Demolition
18-A-100 Roof Plan – New Work
18-A-200 Exterior Elevations – New Work
18-A-300 Canopy Plans and Details
18-A-800 Reference Photos
00 01 15 - 3
61-G-400 Architectural Site Plan
61-AD100 Roof Plan – Demolition
61-AD200 Exterior Elevations – Demolition
61-AD201 Exterior Elevations – Demolition
61-A-100 Attic Plan – New Work
61-A-101 Overall Roof Plan – New Work
61-A-102 Area “A” Roof Plan – New Work
61-A-103 Area “B” Roof Plan – New Work
61-A-104 Area “C” Roof Plan – New Work
61-A-200 Exterior Elevations – New Work
61-A-201 Exterior Elevations – New Work
61-A-300 Roof Details - Building 61
61-A-800 Reference Photos
135-G-400 Architectural Site Plan
135-AD100 Roof Plan - Demolition
135-AD101 Upper Roof Plan - Demolition
135-AD200 Exterior Building Elevations - Demolition
135-AD201 Exterior Building Elevations – Demolition
135-A-100 Roof Plan – New Work
135-A-101 Upper Roof Plan – New Work
135-A-200 Exterior Building Elevations – New Work
135-A-201 Exterior Building Elevations – New Work
135-A-800 Reference Photos
A-600 Typical Roof Details Asphalt Shingle Roof
A-610 Typical Roof Details Polymeric Slate Tile Roof
A-620 Typical Roof Details TPO Roof System
A-621 Typical Roof Details TPO Roof System
A-622 Roof Details
A-623 Roof Details
A-630 Lightning Protection Details
- - - END - - -
VA 01-01-21
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing items shown on the drawings, and furnish labor and materials and perform work for the
Emergency Roof Repairs at the Tuscaloosa VAMC as required by drawings and specifications.
B. Offices of Ballard-CLC, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
C. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
The scope of this project includes emergency roofing replacement on 8 existing buildings. These roofs consist of five buildings with flat roofs using a TPO membrane for a new roof, two buildings that will replace existing slate tile, and one building with an asphalt shingle roof replacement as described and shown on the drawings. The buildings included as part of this effort include:
BUILDING #1
The original building was designed and constructed circa 1931-1933.The scope of work consists of replacing the existing upper roof located over the elevator penthouse and replace three (3) existing roof drains, replacing the roofing on a narrow area surrounding the base of the penthouse tower, and replacing the roof over an outdoor patio area located on the 4th floor. In addition, the existing wood balustrade surrounding the perimeter of the upper penthouse roof will be repaired and reconstructed to match the original historic design. Existing antenna and telecom equipment mounted on the upper penthouse roof level
01 00 00 -2 will need to remain in place and the contractor will be responsible for removing the existing roof assembly and install the new roof assembly without disturbing this equipment. The total area of work is approximately 2,633 SF for the three (3) roof areas.
BUILDING #4
The original building was designed and constructed circa 1931-1933 with a subsequent addition in 1936-38 on the southwest and a later ground floor addition (date unknown) was constructed on the northwest side.
The scope of work consists of replacing the existing roof located over six (6) existing flat roofs areas at different levels above the ground elevation on the north, south, and west sides of the building. The existing wood balustrade surrounding the perimeter of the north and south roof areas will be repaired and reconstructed to match the original historic design. The total area of work is approximately 3,565
SF for the combined roof areas.
BUILDING #5
The original building was designed and constructed circa 1931-1933.The scope of work includes replacement of two walkable flat roof porch covers with railings facia, ceilings, trim, and columns to be replaced.
Painting the faces of 7 dormers and a entry porch is included. The existing decks will be removed along with supports columns. The non-rotted columns will be salvaged for reuse. The porches will then be rebuilt to match the existing historic original size and character. New structural columns to match the existing Doric architectural style columns will be added. The new porch will be sloped ¼ inch per foot to improve drainage from the deck. New perimeter copper gutters will be installed with an additional downspout. The new deck will have an
80mil. TPO roofing installed with walking pads for durability. The existing railing will be constructed and a guard rail at the top of the perimeter railing will be added for code and safety compliance. The lightning protection system will then be replaced with new conductor cabling and air terminals. New lighting will be reinstalled under the underside of the porch.
BUILDING #12
The original building was designed and constructed circa 1931-1933. The scope of work consists of replacing the existing slate roof and reconstructing deteriorated eaves, gutters, and downspout roof drainage system. The roof on this building is a pitched gable form with a slope of 7/12. The existing wood deck at the eave overhangs with exposed rafter tails and copper gutter will be repaired to match the original historic design. Additional downspouts will be located to improve the flow of roof storm water discharge collected by the gutters. The total area of work is approximately 5,760 SF.
A warehouse addition (date unknown) was constructed on the south side of the original building, and metal canopies were constructed on the
01 00 00 -3 north side of the original building circa 2009. These metal roof areas are not in the scope of work for this project.
BUILDING #17
The original building was designed and constructed circa 1931-1933. The scope of work consists of replacing the existing slate roof and reconstructing deteriorated eaves, gutters, and downspout roof drainage system. The roof on this building is a pitched gable form with a slope of 7/12. The existing wood deck at the eave overhangs with exposed rafter tails and copper gutter will be repaired to match the original historic design. Additional downspouts will be located to improve the flow of roof storm water discharge collected by the gutters. The total area of work is approximately 6,466 SF.
A warehouse addition (date unknown) was constructed on the south side of the original building, and metal canopies were constructed on the north side of the original building circa 2009. These metal roof areas are not in the scope of work for this project.
BUILDING #18
The scope of work will replace the existing flat “L” shaped roof totaling 6,850 SF. The original “Laundry Services” facility was designed and constructed circa 1933 with two subsequent additions added to the facility in 1959 and again in 1985 on the north and northwest side. The scope of work consists of replacing the existing roof located over two (2) existing flat roofs areas at different levels above the ground elevation on the north, and west sides of the building. The west flat roof has a concrete deck, and the north flat roof has a metal deck. Both roofs will require tapered poly-iso insulation slopped at ¼ inch per foot for water to drain off the building. The north roof has two internal drains and the west roof drains into gutters on the roof edge. The new roof is to be an 80 mil TPO system with some walking pads for mechanical equipment to be serviced located on the roof. The total area of work for these two flat roofs is approximately 3,190 SF for the combined roof areas. In addition to the flat roof work, some rotten wood replacement has been identified to be repaired on the sloped roof.
These areas incudes the fascia on the gabled ends and about 100 square feet of wood deck under the imitation slate roofs. This imitation slate has been identified as Eco-Star product.
BUILDING #61
This facility is a hipped asphalt shingle roof which is to be replaced totaling 60,000 SF. The original facility was constructed between 1974
-1975 with a flat roof. This facility was retrofitted in 1993 from a flat roof facility to a sloped roof with asphalt shingles. The building has since received two additions, one in 1994 and a second in 2009 with similar sloped asphalt shingle roofs. It is estimated that 25% - 30% of the plywood sheathing is sagging between the pre-engineered wood joist due to improper ventilation of the attic. This project proposes to
01 00 00 -4 replace the sagging decking, with new structural grade ½: plywood decking to match existing thickness. The attic will be properly insulate the attic with R-38, 12 inch thick, batt insulation, to ASHRAE
90.1 standards for zone 3A. New underlayment will be provided with flashing ridge vents and architectural grade asphalt shingles. The lightning protection system will then be replaced with new conductor cabling and air terminals. New lighting will be reinstalled under the underside of the porch. Lastly, several of the roof hatches will be repaired as they were found to not be accessible due to the original poor installation.
BUILDING #135
The original building was designed and constructed circa 1983-1987 and the building is a non-contributing resource within the historic district. The scope of work consists of replacing the existing roof located over multiple existing flat roofs areas at different levels above the ground elevation on the north and south sides of the building. The existing skylights on the south roof area will remain in place with new roof curb flashing installed at the existing skylight curbs. An existing exhaust system located on the northwest roof area at the second-floor level will be removed and temporarily stored on site during installation of the new roof system in this area. The contractor will be required to reinstall this existing exhaust system equipment back to working service condition after the new roofing work is complete. The VA will need to provide temporary accommodations for the space served by this unit while the exhaust system is temporarily out of service. The total area of work is approximately 17,400 SF for the combined roof areas.
ALTERNATE NO.1: BASE BID except delete all work associated with the
Reroof of Building 18 and Building 4.
ALTERNATE NO.2: ALTERNATE 2 except delete all work associated with the
Reroof of Building 12 and Building 17.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
01 00 00 -5
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for the safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
01 00 00 -6
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer, COR, and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of permits shall be issued for General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center Facility Manager.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work.
01 00 00 -7
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as shown on the drawings, or as determined by the COR .
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
COORDINATE with the COR prior to storing materials.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire
01 00 00 -8 protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved.
I. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor, as follows:
Phase I: N/A
J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
K. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air
01 00 00 -9 pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR
ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned
01 00 00 -10 but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.
Provided the contract work is changed by reason of this subparagraph B, 01 00 00 -11 the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR
52.243-4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
2. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by
01 00 00 -12 the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (FAR 52.236-9)
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is
01 00 00 -13 disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.11 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.12 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the
Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it
01 00 00 -14 suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc. if used on this project.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
01 00 00 -15
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.
C. Following written notification by the Contracting Officer, the
Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.
Include within the report the cause of the problem, date reported, 01 00 00 -16 corrective action taken, and when the repair was completed. If the
Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
a) Code 1-Life Safety Systems
Fire suppression systems.
Fire alarm system(s).
b) Code 1-Air Conditioning Systems
Air conditioning leak in part of the building, if causing damage.
Air conditioning system not cooling properly.
c) Code 1 Doors
1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.
d) Code 3-Doors
Interior/exterior personnel doors or hardware not functioning properly.
e) Code 1-Electrical
Power failure (entire area or any building operational after
1600 hours).
Security lights.
Smoke detectors.
f) Code 2-Electrical
Power failure (no power to a room or part of building).
Receptacle and lights not operational (in a room or part of building).
g) Code 1-Gas
Leaks and pipeline breaks.
01 00 00 -17
h) Code 1-Heat
Power failure affecting heat.
i) Code 1-Plumbing
Hot water heater failure.
2) Leaking water supply pipes
j) Code 2-Plumbing
Flush valves not operating properly
Fixture drain, supply line or any water pipe leaking.
Toilet leaking at base.
k) Code 3- Plumbing
Leaky faucets.
l) Code 3-Interior
Floors damaged.
Paint chipping or peeling.
Casework damaged.
m) Code 2-Water (Exterior)
No water to facility.
n) Code 2-Water (Hot)
No hot water in portion of building listed.
o) Code 3
All work not listed above.
1.13 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.14 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipment.
01 00 00 -18
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014
Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
1.15 TEMPORARY USE OF EXISTING ELEVATORS
A. Use of existing elevators for handling building materials and
Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the COR for use of elevators.
The COR will ascertain that elevators are in proper condition.
Personnel for operating elevators will not be provided by the
Department of Veterans Affairs.
01 00 00 -19
2. Contractor covers and provides maximum protection of following elevator components:
a) Entrance jambs, heads soffits and threshold plates.
b) Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
c) Finish flooring.
1.16 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections. Keep such places clean and free from flies and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1. *Contractor may have for use of Contractor's workers, such toilet accommodations as may be assigned to Contractor by Medical Center.
Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workers. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.
1.17 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and
01 00 00 -20 damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
1. Obtain heat…