This document contains questions and responses related to a solicitation for replacing HVAC systems at various buildings on the Tuscaloosa VA Medical Center campus. Key details include that the contractor will be responsible for providing all labor, materials, and equipment to replace HVAC systems in buildings 46 and 2 per the contract drawings and specifications. The work must be completed within 365 days of receiving the notice to proceed. Safety requirements include employees being tested for tuberculosis and having completed OSHA training. The solicitation also outlines regulations regarding identification, parking, smoking, and obtaining a VA identification badge. Security requirements include complying with VA regulations and completing an online information security awareness course. The contracting agency is the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 7.

View the file

Other files

File Type Posted
36C24724R0009 0007.docx DOCX document
22-1081.pdf PDF
36C24724R0009 0006.docx DOCX document
Additional Bid RFI Q_A.pdf PDF
36C24724R0009 0005.docx DOCX document
36C24724R0009 0004.docx DOCX document
Appendix B - Building 2.pdf PDF
UPDATED DBA WAGES AL20240098.pdf PDF
Appendix S - Building 46.pdf PDF
ACM - Appendix P - Building 46.pdf PDF
Project Manual specs.pdf PDF
Replace HVAC Various buildings Site Visit.pdf PDF
CRL Mill 5 16 Aluminum Window Frame 144 CRL.pdf PDF
ACM - Appendix B - Building 2.pdf PDF
679-22-106 ICRA Final.pdf PDF
36C24724R0009 0003.docx DOCX document
36C24724R0009 0002.docx DOCX document
36C24724R0009 0001.docx DOCX document
Drawings.pdf PDF
DBA AL20230098 09-01-2023.pdf PDF
Attachment 1 - Experience Modification Rate Form 2022 Revised 2 2 2023.pdf PDF
Attachment 2 - 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING Jan 2023 Dev form.pdf PDF
Specifications.pdf PDF
Past Performance Questionnaire.docx DOCX document
36C24724R0009_1.docx DOCX document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C24724R0009 Tuscaloosa VAMC – Replace HVAC Various Buildings Pre-Proposal RFI

1. How much asbestos and where is it? – Hazardous waste plan shall be provided

2. How much lead paint and where is it? – Hazardous waste plan shall be provided

3. In addition, I have the question, is the Contractor responsible to identify asbestos and lead paint and other environmental hazards? – No, a hazardous waste plan shall be provided.

4. If such environmental hazards are located, is the Contractor responsible for the removal of such environmentally hazardous materials? – Yes.

5. If the Contractor is responsible for the removal of environmental hazards, is Contractor also responsible for the disposal of such environmentally hazardous materials? – Yes.

6. Which brings us back to the original questions - because how is the Contractor to price such environmental activities without information concerning where such environmental hazards may be encountered and in what quantity? – Hazardous waste plan shall be provided

7. Scope of work:

8. From the Site Visit and the Contract Documents, is it a correct understanding that the

Scope of this Project is limited to Buildings 46 (the Chapel) and 2 (the Credit Union) and to the areas in and around those two buildings? - Correct

9. In Building 2, are there any elevators available in which to deliver materials to the various floors and in particular the second floor? – There is a passenger elevator in Building 2 which leads to the 2nd floor.

10. How is the standing water in the basement of Building 2 related to this Project? – It does not relate to this project.

11. What is the source of that standing water? – There is a leaking condensate pump.

12. Is it the responsibility of the Contractor to remove the standing water? - No

13. Is the standing water potable? – It is not potable. It is not hazardous or caustic. It is from a leaking condensate pump.

14. From the comments at the Site Visit, is it a correct understanding that Building 46 is not at present in use. Will Building 46 be available to the Contractor to begin work in once a Contract is awarded and preliminary matters dispensed with? – Yes, reference the general construction notes on sheet G001.

15. In addition to the HVAC work in Building 46, it appears that there is work required to install new windows and doors, install new ductwork, and convert a 2 pipe network to a 4 pipe network? – Correct reference the architectural, mechanical, and electrical drawings for building 46.

16. Is this network of pipes to carry water? Or is it to provide refrigerant or some other liquid? – It is a hydronic system with chilled and hot water. Refer to Sheet M600 for schedules.

17. On Page 11 of the Solicitation discussing Factor 2 - Technical Solutions,, item b) requires a description of the firm's "experience working with the selected HVAC subcontractor on projects involving health care facilities." Is it a requirement of this Contract that the Contractor have prior experience working with the selected HVAC subcontractor? It is not a requirement; it is an evaluation factor. And in particular, is it a requirement that one or more of the projects involve work on buildings at a health care facility even if the buildings themselves (a chapel and a credit union building) are not involved in the delivery of the health care services? It is not a requirement; it is an evaluation factor.

Any buildings that are part of the healthcare facility.

18. On Pages 9 and 10 of the Solicitation, the identification of the HVAC and Electrical subcontractors is required. Does this proscribe the Contractor from changing these firms if in the several months between submission of the Bid and award of the Contract that the Contractor finds a better situated firm to provide such services? The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price and technical standpoint. The Contracting Officer reserves the right to award a task order without the opportunity for proposals revisions or discussions.

19. On these same pages, information on the personnel choices of the Contractor and key subcontractors is scrutinized as if nothing changes between December and May. What happens if one or more of the persons identified get promoted to different positions or otherwise becomes unavailable for this Project? – Post-award, The contracting officer needs to be notified. Contractor is to make the best good faith effort to provide the team that would work on the construction.

20. On these same pages, specific information is required concerning personnel having

OSHA 30 or OSHA 10 hour certifications. Are these certifications required before the Bid is submitted? Or can these certifications be updated and/or obtained after award of the Contract? – They are required with Bid package.

21. Please provide Hazmat Survey & Abatement Plan identifying locations of ACM and Lead-based paint materials to be removed as referenced in the specifications. – Hazardous waste plan shall be provided

22. VA to confirm if mold remediation is anticipated or required. – Mold remediation of the buildings is not included in this contract.

23. Please provide As-Built Architectural documents for Building 2, to confirm wall cavity dimensions for new piping/insulation. – Wall cavity is 9” deep.

24. Please confirm if any phasing is required between buildings 2 & 46.

a. As per Specification Section 1.6. Operations & Storage Areas (FAR 52.236-10):

J. Building(s) No.(s)46 will be vacated by Government in accordance with above phasing beginning immediately after date of receipt of Notice to Proceed and turned over to Contractor.

K. Building(s) No.(s) 2 will be occupied during performance of work.

Building 46 will be unoccupied. Building 2 will require coordination with the occupants.

Contractor to minimize the downtime required to install equipment.

25. Please confirm if Group Room 113B (located on the 1st floor) & Office 212B (located on the 2nd floor) will be vacated for the duration of Demo & Construction within those spaces. – Contractor to coordinate with VA on room closures. Contractor to minimize the downtime required to install equipment.

26. Please confirm if the hours of operation of the Credit Union located on the 1st floor of

Building 2 are the same as noted on sheet G001? - Their hours are Monday – Friday 8:00 am - 4:00 pm.

27. Please confirm designated working hours for construction activities. -7am to 5pm are the typical working hours for construction. Any Weekend, Holiday, Evening, or Night work shall be coordinate with the COR.

28. Please provide details for window attachment and installation for the (5) five assemblies located within the nave of Building 46.

a. As per Sheet A-101, New Work Keynote (9): contractor is to clean the existing windows to remain. Install new window infill system per manufacturer’s instructions. Basis of Design: CRL Fallbrook fixed frame w/ 5/16" glass. See attached cut sheet from BOD manufacturer. No detail information available for installation from manufacturer.

29. Please confirm the new automatic sliding glass doors will re-utilize existing power circuitry and are to be activated by motion sensors only with no push-button actuators, hand wave sensors, or access control components required. GC to provide new automatic sliding doors to match existing as close as possible that will connect to existing power circuitry and sensors.

30. Please provide a Door Schedule to confirm existing door openings and sizes. Existing door sizes are based on drawings provided by the VA. Opening sizes need to be field verified by GC prior to ordering or fabrication of new doors.

31. Please confirm the window assemblies to be installed are for insulating purposes and are not intended for exterior wind load or water intrusion resistance. Correct.

32. Plans & Equipment Schedule shows IT Closet 13A receiving a new ductless mini-split HVAC system. The existing fan coil unit is floor mounted under the window with what appears to be a vent to the exterior. The new work plan shows the split system air handler being installed over the door; however, this is a storefront system with a transom over the door.

a. Is the old fan coil unit to be removed completely from the space? The old fan coil unit shall be removed completely from the space, refer to sheet MD100.

b. If the old FCU is to be removed please provide details and specifications to remove the existing vent and fully seal and weatherproof the opening.

Contractor shall in-fill the existing opening with similar, adjacent materials. Paint the entire wall, floor to ceiling, corner to corner. Color match adjacent walls.

c. If the existing FCU is removed can the new split system air handler be mounted to the floor in the location of the old FCU? No, the new mini-split system shall not be installed on the floor in the location of the removed FCU. The new mini-split system shall be installed on an adjacent wall.

33. There appears to be an error with the AHU elevation view compared to the controls diagram. It should be selected the way the control diagram is laid it out. However, please note that as per subcontractor review, if the OA damper is not moved this would not work in the matter that the elevation view in the plans is setup. Please provide confirmation that this is to be selected the way the controls diagram has been laid-out?

Confirmed. The AHU shall be selected in the arrangement shown in the control diagram.

34. Please confirm if there are any specifications that may be provided on the FCUs. No Fan Coil Unit specification was found within the specifications.

Fan coil shall be provided with the following:

Inlet style shall be front bar grille type and outlet shall be top quad grille type.

Unit color to be selected later by owner.

Outside air damper shall be manual, back opening and align with the existing opening in the building exterior.

Provide with manual coil air vent.

Fan shall be free discharge electronically commutated motor (ECM).

Provide with unit mounted disconnect switch.

Provide polymer drain pan.

Provide 1-inch MERV 8 filter.

35. Within the mechanical room located on the ground floor of Building 2, disconnects on

AHU 16B are to be replaced and drainage designated into crawl space below. VA to confirm if configurations from AHU equipment are pneumatic or stacked lines. – Drainage shall utilize existing drain to crawlspace. Disconnect switches are being replaced.

36. As per Sequence of Operation on Sheet M700 stating, “VFD RESET: in case of VFD fault detection, the DDC system shall wait 30 seconds (adjustable) and then call the VFD to start. If the VFD does not start, the DDC system shall call a second time. If the VFD still has not started, an alarm shall be sent to the operator interface”.

a. The VFDs for the AHU or Pumps in building 46 are not located on the project documents. Please confirm the location(s) of the VFD’s within Building 46 on the project documents. – VFDs shall be wall mounted or Unistrut mounted at equipment location.

b. On Sheet M600 for Building 46, under the Air Handling Unit Schedule, Note 2 specifies to “Provide with Integral VFD with single point power connection.” Upon review of the project specifications, there is no specification for Motor Controllers.

Please provide the 26 29 11 Motor Controllers specification. – Specification provided.

c. Please confirm if Pump 46-P-1 requires a VFD for operation. – VFD is required for pump.

37. Project documents for Building 2 do not specify if a new VFD is required for the new 2- AHU-1 or 2-AHU-2. Please confirm if the existing are to remain or if new VFDs are required for each AH. 1-AHU-1 and 2-AHU-2 do not require new VFDs, motors’ basis of design are Electronically Commutated Motors.

38. What level of infectious control is required on this project? Is the government providing the ICRA? – ICRA plan is attached.

39. Building 46 is a block building which requires the removal of existing fan coils. Drawing ED101 note I references patch and repair per existing condition. Does the patching and repair need to meet historical standards? If so, what standards and will the VA provide the SPEC requirements? – See attached letter from Historical Commission. Contractor shall patch and repair work with similar, adjacent materials to match existing conditions.

40. The inside walls of Building 2 seem to have furred walls constructed over existing brick construction. Upon inspecting the walls, the finish appears to be of an architectural stucco type, similar to the walls at the entry of the sunroom. SPEC 09 29 00, which references gypsum board finishes to be at level 4 for public view, raises a question: Is this specification section applicable to this project? – The furred-out walls consist of studs and gypsum board. There is no stucco. The gap is 9” deep.

41. The specifications (SPECS) included in the Request for Proposal (RFP) are the Veterans Health Administration (VHA) master specifications. Given the scope of these specifications, is the entire document applicable to this particular solicitation? – The specifications in the RPF are the applicable specifications.

42. The master specs include Division 23, specifically Section 23 09 23. What are the Direct Digital Control (DDC) requirements? Will the Veterans Administration (VA) provide DDC as-built drawings? All monitored parameters and controls shall be integrated into the existing JCI Metasys BAS.

43. The specifications call for commissioning and a Commissioning Authority (CxA) to be appointed by the Veterans Administration (VA), as outlined in Section 23 08 00. Could you please confirm the accuracy of this statement? – There will be no commissioning.

44. Assuming the government provides a Commissioning Authority (CxA), what will be the roles and responsibilities of the contractor during the commissioning process? – There will be no commissioning.

45. What are the working hours for Building 46 and Building 2? – Reference the general construction notes on sheet G001.

46. The SPECS include section 02 83 33.13 for glove bag asbestos removal and 02 83 33.13 for Lead. Is there an existing hazardous material survey that the relevant authority can provide? – Hazardous waste plan shall be provided

47. Will the contractor superintendent be allowed to fulfill the roles of Site Safety and Health Officer (SSHO) and Quality Control Manager? – Yes

48. According to the details provided below, the water lines are to be installed between the existing walls. Our understanding is that the existing walls were constructed over the original brick. Assuming this is the case, that would leave no space inside the wall cavity.

Will the contractor be allowed to install these water lines above the ceiling and provide raceways to the new wall-mounted Fan Coil Units (FCUs)? Additionally, will the contractor be permitted to install stainless steel raceways on the exterior of the building from the first to the second and third floors? – In building 2, piping shall be installed above ceiling and within the walls. Raceways on the exterior are not acceptable.

49. Is this project sales tax exempt? If the project is sales tax exempt, can the Government provide a sales tax exemption certificate? No

50. Can the required SSHO and Quality Control Manager positions be fulfilled by the qualified superintendent? – Yes

51. Will the Owner or GC be responsible for hiring the commissioning agent? – Yes.

52. Will the Owner or GC be responsible for purchasing testing and lab services? – This RFI does not seem applicable to this project.

53. Will the Owner accept the use of the industry leading Procore Project Management software as the primary submittal and data tracking tool for this project? – Yes

54. How soon after the award is NTP expected to be issued? TBD based on scheduling Kickoff Pre-Construction meeting and after receipt of payment and performance bonds which are due within 10 calendar days after award.

55. Due to the current economic inflation, Will the Government reduce the amount of time that contractors must hold their numbers to 60 days? By reducing the inflation risk, the Government will avoid escalations costs that general contractors and subcontractors must account for. No

56. Will the Government consider the inclusion of an Economic Price Adjustment Clause in accordance with Federal Acquisition Regulations (FAR), Subpart 16.203 "Fixed-price contracts with economic price adjustment" and the related contract clause language in FAR 52.216-2, 3, 4? We believe such a clause is appropriate for the followings reasons:

a. The contract involves an extended period of performance with significant costs to be incurred beyond 1 year after performance begins;

b. The contract amount subject to significant fluctuations in price is substantial; and

c. The economic variables for labor and materials are too unstable to permit a reasonable division of risk between the Government and the contractor, without this type of clause."

- No. This will remain Firm Fixed Price.

57. Are there sufficient licenses on the Access Control system to support new devices or are new licenses required? – This RFI does not seem applicable to this project.

58. Is the internal data center cabling between MDA/HDA and HDA/ED cabinets included as shown on sheet EY501? There are spec sections for Division 27, but this effort is not captured in Attachment 1 – SOW. – This RFI does not seem applicable to this project.

There is no Sheet EY501.

59. Spec section 27 16 19 identifies patch cord requirements, however, it does not quantify how many patch cords are to be provided. Please define the quantities of patch cords for both fiber optic cabling and Cat 6A cabling systems? – This RFI does not seem applicable to this project.

60. It appears in the Mechanical drawings that the network cabinets are to have a ducted return, is this correct and, is there any forced air into the network cabinets? – This RFI does not seem applicable to this project.