Additional Bid RFI Q_A.pdf
PDF 132 KB Posted
- Attached to
- Z2AA--679-22-106 Replace HVAC Various Buildings
- Solicitation number
- 36C24724R0009
About this file
This document contains responses to contractor questions regarding a federal solicitation for HVAC replacement at various buildings on the Tuscaloosa VA Medical Center campus. The solicitation requires contractors to provide all labor, materials, and supervision to remove and replace HVAC systems per contract drawings and specifications. Key details include that the work includes general construction and alterations to meet a 365-day completion schedule from notice to proceed. Safety requirements include evidence of negative tuberculosis tests and OSHA training for all employees. The responses clarify that contractors shall determine necessary light fixture and conduit removals. Existing materials may be reused if specification compliant. Asbestos pipe insulation quantities and locations are provided. Speakers in the chapel are to be disconnected and reinstalled. No commissioning is required for this project.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C24724R0009 Tuscaloosa VAMC – Replace HVAC Various Buildings
Bid RFI
Additional Request for Information
1. Per Sheet A-101, Demolition Keynote #5 states that the light fixtures should be removed and reinstalled, but they are not identified by fixture on this sheet to do so. The electrical demolition pages do not have any marks on the lights. The electrical demolition pages for the chapel do not mention any demolition of these lights and in fact the electrical pages state that fixtures with “E” next to them are existing to remain. (see sheet EL-101 – Building 46). On sheet EL-101 every light in the chapel has an “E”, including wall mounted fixtures. Please advise which lights need to be removed and reinstalled. Will the wall sconces need to be removed for new ceiling install? We realize that Note C on sheet ED-101 states “The Contractor is responsible for determining which items must be removed to facilitate new construction, see Architectural plans for exact limits of demolition and construction.” But we are just looking for a clear understanding on the scope of work to eliminate the ambiguity on the sheets as stated above. Please provide clarification. Contractor shall remove and reinstall light fixtures as determined necessary by Contractor to facilitate new construction.
2. On sheets ED-100, ED-101, & ED-102 (Building 2), Note 1 states to remove all conduit and conductors back to source, while on sheet EP-101 (Building 2), it only calls for a new breaker. Please confirm that we can utilize existing conduit and/or wire (Building 2) for equipment that is to remain in the same location. Existing conduits and wires can be reused as long as it meets specifications. If it does not meet specifications, provide new wire and conduit. Reach out to EOR, if new wire and conduit size needs to be provided.
3. On sheet ED-101 (Building 46), Note 3 states to “site clear” conduit and conductors to the source, while note 1 says to reuse the circuit. Please confirm that we can utilize existing conduit and/or wire (Building 46) for equipment remaining in the same location. Existing conduits and wires can be reused as long as it meets specifications. If it does not meet specifications, provide new wire and conduit. Reach out to EOR, if new wire and conduit size needs to be provided.
4. There is no specification for the T&G ceiling. Please provide wood species and grade.
Bidders should reference spec section 06 20 00; Part 2 – Products / 2.2 Materials / B.
Lumber: 3. Softwood: b. Prime
5. On sheet MD-100 (Building 2), the notes call for demolition back to main, but the main, nor branch piping is shown, thus the Contractors bidding this project cannot quantify the material to be removed. Please advise if the mechanical piping or insulation,…contains any hazardous materials for both locations and on the routing and/or quantity the materials to be removed. Annual Asbestos Re-Inspection Report documents the extent of existing pipe insulation as ACM in Building 2. The mains are routed in the crawl space below the ground floor. Assume 60 linear feet of 3/4" branch piping from the mains to (D) FCU. Assume 10 linear feet of branch piping from the steam and condensate mains to (D) AHU-16B. Assume 8 linear feet of branch piping from the steam and condensate mains (D) AHU-18.
6. The Asbestos specification section refers to the drawings for asbestos quantities, types, and location but there are no drawings indicating such information. Additionally, after review of the RFI responses, RFIs’ #1, 2, 3 and 6 state a “Hazardous Waste Plan” will be provided but it was not with the RFI Responses and/or Amendment 004. The “Annual Asbestos Re-inspection Documentation” and Lead Paint Removal documents provided in Amendment 004 are open for interpretation between bidding Contractors making bidding unfair and impossible to ensure all Contractors are bidding the same scope since there is no way to quantify the hazardous materials. Can the hazmat asbestos abatement and lead paint removal be assessed and priced post award, or can the VA quantify the asbestos abatement and lead paint removal scopes of work to ensure all Contractors are pricing the same scopes of work which should ensure consistent bidding practices amongst all contractors? The potential ACM pipe insulation abatement is noted in the response to RFI 5. ACM – Appendix B – Building 2 notes ACM in HA 06 on the Ground Level, Electrical room 20 and in HA 13 on the second floor, Office room 212B. HA 06 and HA 13 ACM are VCT and mastic, which are not expected to be disturbed by normal construction activities in the surrounding area.
Disturbance to ACM or suspected ACM shall be reported to the COR and managed according to specification sections 02 82 13.13 Glovebag Asbestos Abatement and 02 83 33.13 Lead- Based Paint Removal and Disposal.
7. During the site walk we noticed metal speakers on the ceiling in the Chapel, but they were not noted on the Bid Documents. Please advise on the scope for these items. Disconnect, remove, and reinstall speakers on the ceiling in the Chapel.
8. The RFI 39 response in Amendment 004 references an “attached” letter from the historical commission but is not provided. Please provide letter. See attached file titled “22-1081.pdf”
9. RFI Responses for 43 and 44 in Amendment 004 states no commissioning will be completed on this project but RFI Response 51 states “yes” in response to asking who is responsible for Cx agent. Please clarify if commissioning is required on this project. Commissioning is not required on this project.