S02 36C24720B0024 A00002.pdf

PDF 190 KB Posted

Attached to
CATH LAB Federal contract opportunity
Solicitation number
36C24720B0024
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 7

About this file

This document consists of an amendment to a solicitation and responses to questions from potential offerors. The solicitation is for a project at the Columbia VA Healthcare System to remove an existing cath lab and replace it with a new GE system, Stryker boom, and Cleansuite ceiling system. The amendment extends the bid due date to August 28, 2020 at 10:00 AM EST and requires emailed bids to be received by that time. It clarifies that commissioning will be performed by Charlotte Engineers and provides several specifications to be incorporated into the requirements. The responses provide additional details on ceiling and flooring specifications, commissioning responsibilities, personnel requirements, and mechanical, electrical, and controls drawings.

The amendment and question responses provide relevant details to help offerors fully understand the project requirements and prepare responsive bids for the solicitation for cath lab replacement at the Columbia VA Healthcare System, with a bid due date of August 28, 2020.

View the file

Other files for this federal contract opportunity

Other files attached to CATH LAB, newest first.
File Type Posted
Project 534-CSI-555 Cardiac Lab Prep Pre-Bid Sign-In.pdf PDF
PreBid Site Visit Sign In sheet.doc DOC document
Project No. 534-CSI-555 Card Cath Lab Questions from 8-26-2020.docx DOCX document
36C24720B0024 A00003.pdf PDF
26 08 00 Commissioning of Electrical Systems.pdf PDF
28 13 00 Physical Access Control System.pdf PDF
Project 534-CSI-555 Answers to Questions.pdf PDF
MD-100 - MECHANICAL - SECOND FLOOR - DEMOLITION - DUCTWORK.pdf PDF
MH-200 - SECOND FLOOR - NEW WORK - DUCTWORK.pdf PDF
EP-201 - ELECTRICAL - SECOND FLOOR - POWER SYSTEMS.pdf PDF
280800 Commissioning of Electronic Safety and Security Systems.pdf PDF
M-004 - MECHANICAL - SCHEDULES.pdf PDF
Addendum 2 - Project No. 534-CSI-555.pdf PDF
ED-100 - ELECTRICAL - SECOND FLOOR - DEMOLITION.pdf PDF
270800 Commissioning of Communications Systems.pdf PDF
01 91 00 Commissioning.pdf PDF
226300 - GAS SYSTEMS FOR LABORATORY AND HEALTHCARE FACILITIES.pdf PDF
MD-101 - MECHANICAL - SECOND FLOOR - DEMOLITION - PIPING.pdf PDF
230711 HVAC INSULATION.pdf PDF
000110 Specifications.pdf PDF
MP-201 - SECOND FLOOR - NEW WORK - PIPING.pdf PDF
M-005 - MECHANICAL - SCHEDULES.pdf PDF
Card Cath Lab Prep Dwgs ED100 ED10 EL200 EP-201.pdf PDF
20200508-VAMCCHSSC-CLSP-DRAWINGS-BIDDOCUMENTS-COMPLETE.pdf PDF
36C24720B0024 A00001.pdf PDF
20200511 - VAMC CHSSC - CLSP - Project Manual SPECS - BID DOCUMENTS - Combined - REV 3.pdf PDF
36C24720B0024 Drawing Bid Documents.pdf PDF
20200511 - VAMC CHSSC - CLSP - Project Manual SPECS - BID DOCUMENTS - Combined - REV 3.zip ZIP file
Addendum 1.pdf PDF
S02 36C24720B0024 Solicitation.pdf PDF
S02 36C24720B0024 CATH Lab Solicitation.pdf PDF
Bid Drawings Document.pdf PDF
SC Wage Determination SC20190023.pdf PDF
Specs Bid Documents.pdf PDF
Show all 34

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

534-CSI-555

Department of Veterans Affairs Columbia VA Healthcare System Network Contracting Office 7 6439 Garners Ferry Road Columbia SC 29209-1639

Department of Veterans Affairs Columbia VA Healthcare System Network Contracting Office 7 6439 Garners Ferry Road Columbia SC 29209-1639

To all Offerors/Bidders

36C24720B0024

X

X X

The purpose of this amendment is to correct solicitation for Main Bid Base item and Deduct Alternate I to Bid Item 001 Deduct stainless steel lab casework and provide plastic laminate surfaces. The bid due date has been extended to August 28, 2020 @ 10:00AM EST. All emailed bids must be received by 10:00AM to be responsive.

All other terms and conditions of the solicitiation remain the same.

Chantel Guest Contracting Officer

CONTINUATION PAGE

Addendum 2

Project No. 534-CSI-555

Clarifications

8-13-2020

This Addendum is issued to clarify and/or modify issues with the Contract Drawings and/or Specifications as needed for the Solicitation of the Above-mentioned Project.

Question is:

1. On Drawing AS-101.1, first floor ceiling work is noted. What is ACT basis of design?

ANSWER: ACT basis of design for the 1st floor Ceiling work is Manufacturer: USG color: Mars High-NRC) Size 2’ 0” X 2’ 0”; Grid USG DONNE Brand DX/DXL 15/16”;

Edge: Shadowline with ¾” Reveal.

2. On Drawing AS-202.1 Note 9 states to verify lead lining. Contractors need to know if additional lead lined sheetrock is required. If so what quantity?

ANSWER: Note that all ductwork and other components/utilities shall be located/routed above the ceiling of Room AA223 Cardiac Cath Lab Number 2 in the new Mechanical Room (Room AA237A); and as such, no verification of the lead lining as stated by that Note 9 on Drawing AS-202.1 is required and no quantity will be required; thus the note can be deleted with the clarity provided in this answer on the routing of utilities.

pg. 3 of 5

3. Is Commissioning required? If so, will commissioning agent be hired by the VA or Contractor?

ANSWER: Commissioning is required. Commissioning services shall be performed by Charlotte Engineers, LLP (The MEP A/E that designed to project.) Contact information is Chelsea Hadsel at CHadsel@charlotteengineers.com and telephone Number (704) 531-3000, x108.

4. If Commissioning is required, please provide Commissioning Specification 01 91 00.

ANSWER: Commissioning Specification 01 91 00 is provided as an Attachment to this Addendum. Commissioning Specification 27 08 00 and 28 08 00 are also added and incorporated into the requirements of this Solicitation as an Attachment to this Addendum. NOTE: Commissioning is required of only components installed in this Solicitation.

5. Is there a requirement to have 3 different GC personnel onsite to fill the roles of Superintendent, QC, and SSHO? If roles may be combined, which roles or may all 3 be combined under one competent person?

ANSWER: It is a requirement that 2 different GC personnel be onsite to fill the roles of Superintendent, QC, and SSHO. If two personnel are used, one must be both the Superintendent and SSHO and the other personnel is the QC.

6. Regarding the poured resinous flooring, the finish legend calls out a broadcast flake system and the specification call out a poured resilient system. There are two different systems. Which system is required?

ANSWER: The broadcast Quartz system on the Finish Plan is correct except for a small modification is being made for further clarifications. The Finish Schedule for will change from “ACCELERA HC” to “ACCELERATA Q” and read on Drawing AS-601, under the “STYLE/FINISH” portion of the “FINISH LEGEND”.

mailto:CHadsel@charlotteengineers.com

pg. 4 of 5

7. No HVAC insulation spec was included, can you please provide this specification?

ANSWER: HVAC Insulation Specification has been added. Specification 23 07 11 is attached to this Addendum and shall be used.

8. Two questions were submitted on this issue. One is 8a. and the other is 8b.

8.a The drawings appear to have been formatted for an 8X11 size document, while printing in large scale or trying to use takeoff software the file does not work correctly. Can you please provide an updated drawing.

8.b. Also the plans don’t appear to be sized correctly. Would you see if you could request they be sent to the correct size and scale?

ANSWER: Drawings were revised previously to meet the scale and requirements.

9. Regarding CAV-2, the following

a. This VAV is shown to be removed (18.VAV.18) VAV Box 18.VAV18 currently serves AA237a only. Or at least it should only feed AA237a.

b. I am not sure why this box is shown to be relocated serving AA239a.

c. AA239A is currenting served by FC3-AA239a that was installed in 2015 under the Non Sterile HVAC project.

ANSWER: It is correct that CAV/VAV #2 can be removed along with all utilities and utilities capped. Please see revised Drawing Sheets M-004, MD-100, MD- 101, MH-200, MP 201, and EP-201. Note that CAV/VAV #2 Electrical to the VA can be removed to nearest junction box.

pg. 5 of 5

10. Regarding AHU-16 Control Schematic.

a. I do not see any control dampers in the OA and RA. That does not seem correct. I would think at a minimum there should be manual volume dampers or Automatic Dampers in the OA/RA to ensure that you have the proper OA for Room pressurizations.

b. Flow Sensor on Each Fan shown in between the coil.? Is it the intent to simply monitor the total flow of the unit. If so, I would suggest a flow station in the SA duct of the unit. The biggest issue here is having enough straight duct for proper airflow measurement. Is Airflow Measurement truly required. If Airflow is a requirement, can the A”HU manufacturer provide the Fan piezo rings. That would be a much better solution for airflow measurement. Airflow measurement shall be provided.

c. HS – High Static? Do we really need Duct High Static on a 2600 CFM unit with no FSD’s.

d. Sequence of operation indicates SA Temperature Control and Static Pressure Control – This is a Constant Volume Zone Unit which should be controlled by Space Temperature and Humidity. The Fan Speed will not need to be adjusted. Its Constant Volume!

ANSWER: For info, Controls Information is located on Sheet M-005. Please

See Revised Drawing M-005 attached to this RFI. That Information shall clarify the question to this Request with the additional following information. Revised M-005 supercedes any information from below which is provided for clarity if duplicate or conflicting.

a. A manual damper is required to be installed in the OA duct to control volume of OA. Balancing dampers should be installed at each return air branch line to control the individual airflow to each grille. This is covered on General Note G – on MH200 drawing.

b. Mechanical and Controls Subcontractor shall coordinate as needed with General Contractor (GC) and provide a fan piezo ring from unit manufacturer. GC, through Mechanical and Controls Subcontractor shall coordinate any and all utilities necessary to provide Piezo ring in AHU.

c. High static is not needed. Remove this from the Controls requirements; and note on Sheet M-005 during as-built note.

pg. 6 of 5

d. Provide SA temperature sensor and static pressure as indicated.

Note that the AHU fan speed shall also be controlled by a Space Temperature and Humidity to meet requirement. “The intent is that the T&B the unit will be set to run based on SP setpoint established

– and by the fan controlling to this setpoint, even as filters get dirty airflow will be maintained to the space via this process and/or Space Temperature and Humidity controllers.

11. Not a RFI question but this one comes from the A/E and VA as information and requirement to be incorporated.

ANSWER: Dwg ED-100 was changed to add clarity to the requirements.

12. Not a RFI question but a point of clarification on Table of Contents for Specifications.

ANSWER: Specification Section 00 010 10 Table of Contents of Specifications was updated and attached to this Addendum and shall be incorporated into the requirements for this Solicitation.

13. The specs do not include gas systems (22 63 00) but this scope appears to be included in the plans. Please verify this scope.

ANSWER: Specification Section 22 63 00 is required for this project and is

Attached for use by the contractor with this Addendum and incorporated into the requirements for this Solicitation.

14. Please verify that we are to provide only the vertical ‘L’ supports, bracing, and screw anchors for the boom system on S1.0. who will be providing the welding and will vendor drawings be provided.

pg. 7 of 5

ANSWER: On Construction Drawing S1.0, it specifies in Addendum 1 to the solicitation on Note V. the only portion of the project that the “Equipment” Manufacturer will be doing. All other work specified on Construction Drawing S1.0, the Construction Contractor that is awarded this solicitation will be providing all supports, bracing, screw anchors, welding, etc., etc. needed for the boom system as reflected on Construction Drawing S1.0, unless specified elsewhere. (NOTE: Equipment Booms will be provided and final installation will be coordinated between Equipment Manufacturer to Construction Contractor supports unless otherwise specified in Contract Documents.)

Vendors drawings were provided as References to the project in the original Solicitation and shown on the Cover Sheet of the Drawing (X-100).

15. Verify how many network drops per location.

ANSWER: Network drops have been shown as “Existing to Remain” in the walls and the boom network drops are reflected on Reference “4” to the drawings as to the Requirements.

- END -

See attached document: MP-201 - SECOND FLOOR - NEW WORK - PIPING.

See attached document: MH-200 - SECOND FLOOR - NEW WORK - DUCTWORK.

See attached document: MD-101 - MECHANICAL - SECOND FLOOR - DEMOLITION -

PIPING.

See attached document: MD-100 - MECHANICAL - SECOND FLOOR - DEMOLITION -

DUCTWORK.

See attached document: M-005 - MECHANICAL - SCHEDULES.

pg. 8 of 5

See attached document: M-004 - MECHANICAL - SCHEDULES.

See attached document: EP-201 - ELECTRICAL - SECOND FLOOR - POWER SYSTEMS.

See attached document: ED-100 - ELECTRICAL - SECOND FLOOR - DEMOLITION.

See attached document: 280800 Commissioning of Electronic Safety and Security Systems 100_.

See attached document: 270800 Commissioning of Communications Systems 100_.

See attached document: 230711 HVAC INSULATION.

See attached document: 226300 - GAS SYSTEMS FOR LABORATORY AND

HEALTHCARE FACILITIES.

See attached document: 000110 Specifications.

See attached document: 01 91 00 Commissioning.

File details come from the government source that posted it. Updated .