280800 Commissioning of Electronic Safety and Security Systems.pdf

PDF 23 KB Posted

Attached to
CATH LAB Federal contract opportunity
Solicitation number
36C24720B0024
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 7

About this file

This document contains specifications for the commissioning of electronic safety and security systems for a federal construction project to replace equipment in the Cath Lab at the Ralph H. Johnson VA Medical Center. The project includes removing the existing Cath Lab equipment and replacing it with a new GE system, Stryker boom, and Cleansuite ceiling system. Commissioning requirements are defined for the fire alarm system and involve construction inspections, contractor testing, and systems functional performance testing witnessed by the commissioning agent. The specifications require pre-functional checklists, equipment startup reports, and training of VA operation and maintenance personnel. The contractor must coordinate testing and training with the commissioning agent and VA resident engineer according to the commissioning plan and provide seven days' notice of testing.

View the file

Other files for this federal contract opportunity

Other files attached to CATH LAB, newest first.
File Type Posted
Project 534-CSI-555 Cardiac Lab Prep Pre-Bid Sign-In.pdf PDF
PreBid Site Visit Sign In sheet.doc DOC document
Project No. 534-CSI-555 Card Cath Lab Questions from 8-26-2020.docx DOCX document
36C24720B0024 A00003.pdf PDF
Project 534-CSI-555 Answers to Questions.pdf PDF
28 13 00 Physical Access Control System.pdf PDF
26 08 00 Commissioning of Electrical Systems.pdf PDF
ED-100 - ELECTRICAL - SECOND FLOOR - DEMOLITION.pdf PDF
270800 Commissioning of Communications Systems.pdf PDF
01 91 00 Commissioning.pdf PDF
226300 - GAS SYSTEMS FOR LABORATORY AND HEALTHCARE FACILITIES.pdf PDF
EP-201 - ELECTRICAL - SECOND FLOOR - POWER SYSTEMS.pdf PDF
M-004 - MECHANICAL - SCHEDULES.pdf PDF
Addendum 2 - Project No. 534-CSI-555.pdf PDF
MD-100 - MECHANICAL - SECOND FLOOR - DEMOLITION - DUCTWORK.pdf PDF
MH-200 - SECOND FLOOR - NEW WORK - DUCTWORK.pdf PDF
S02 36C24720B0024 A00002.pdf PDF
MD-101 - MECHANICAL - SECOND FLOOR - DEMOLITION - PIPING.pdf PDF
230711 HVAC INSULATION.pdf PDF
000110 Specifications.pdf PDF
MP-201 - SECOND FLOOR - NEW WORK - PIPING.pdf PDF
M-005 - MECHANICAL - SCHEDULES.pdf PDF
Card Cath Lab Prep Dwgs ED100 ED10 EL200 EP-201.pdf PDF
36C24720B0024 Drawing Bid Documents.pdf PDF
20200511 - VAMC CHSSC - CLSP - Project Manual SPECS - BID DOCUMENTS - Combined - REV 3.zip ZIP file
Addendum 1.pdf PDF
20200508-VAMCCHSSC-CLSP-DRAWINGS-BIDDOCUMENTS-COMPLETE.pdf PDF
36C24720B0024 A00001.pdf PDF
20200511 - VAMC CHSSC - CLSP - Project Manual SPECS - BID DOCUMENTS - Combined - REV 3.pdf PDF
S02 36C24720B0024 CATH Lab Solicitation.pdf PDF
S02 36C24720B0024 Solicitation.pdf PDF
Bid Drawings Document.pdf PDF
SC Wage Determination SC20190023.pdf PDF
Specs Bid Documents.pdf PDF
Show all 34

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11-01-19 CATH LAB SITE PREP at

RALPH JOHNSON VAMC

534-CSI-555

ADDENDUM 2 08-12-20

28 08 00 - 1

SECTION 28 08 00

COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS

PART 1 - GENERAL

1.1 DESCRIPTION

A. The requirements of this Section apply to all se ctions of Division 28.

B. This project will have selected building systems commissioned. The complete list of equipment and systems to be commis sioned is specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREME NTS. The commissioning process, which the Contractor is resp onsible to execute, is defined in Section 01 91 00 GENERAL COMMISSIONIN G REQUIRMENTS. A

Commissioning Agent (CxA) appointed by the VA will manage the commissioning process.

1.2 RELATED WORK

A. Section 01 00 00 GENERAL REQUIREMENTS.

B. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS .

C. Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND S AMPLES.

1.3 SUMMARY

A. This Section includes requirements for commissio ning the Facility electronic safety and security systems, related sub systems and related equipment. This Section supplements the general re quirements specified in Section 01 91 00 General Commissioning Requireme nts.

B. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for more details regarding processes and procedures as well as roles and responsibilities for all Commissioning Team members .

1.4 DEFINITIONS

A. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for definitions.

1.5 COMMISSIONED SYSTEMS

A. Commissioning of a system or systems specified i n Division 28 is part of the construction process. Documentation and test ing of these systems, as well as training of the VA’s Operation and Maintenance personnel in accordance with the requirements of Se ction 01 91 00 and of Division 28, is required in cooperation with the VA and the

Commissioning Agent.

RALPH JOHNSON VAMC

28 08 00 - 2

B. The Facility Electronic Safety and Security Syst ems commissioning will include, but will not be limited to, the systems li sted below:

1. Fire Alarm System

1.6 SUBMITTALS

A. The commissioning process requires review of sel ected Submittals that pertain to the systems to be commissioned. The Com missioning Agent will provide a list of submittals that will be revi ewed by the

Commissioning Agent. This list will be reviewed an d approved by the VA prior to forwarding to the Contractor. Refer to Se ction 01 33 23 SHOP

DRAWINGS, PRODUCT DATA, and SAMPLES for further det ails.

B. The commissioning process requires Submittal rev iew simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 9 1 00 GENERAL

COMMISSIONING REQUIREMENTS.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 CONSTRUCTION INSPECTIONS

A. Commissioning of Electronic Safety and Security systems will require inspection of individual elements of the electronic safety and security systems throughout the construction period. The Co ntractor shall coordinate with the Commissioning Agent in accordan ce with Section 01

91 00 and the Commissioning plan to schedule electr onic safety and security systems inspections as required to support the Commissioning

Process.

3.2 PRE-FUNCTIONAL CHECKLISTS

A. The Contractor shall complete Pre-Functional Che cklists to verify systems, subsystems, and equipment installation is complete and systems are ready for Systems Functional Performance Testin g. The

Commissioning Agent will prepare Pre-Functional Che cklists to be used to document equipment installation. The Contractor shall complete the checklists. Completed checklists shall be submitte d to the VA and to the Commissioning Agent for review. The Commission ing Agent may spot check a sample of completed checklists. If the Com missioning Agent determines that the information provided on the che cklist is not accurate, the Commissioning Agent will return the m arked-up checklist to the Contractor for correction and resubmission. If the

RALPH JOHNSON VAMC

28 08 00 - 3

Commissioning Agent determines that a significant n umber of completed checklists for similar equipment are not accurate, the Commissioning

Agent will select a broader sample of checklists fo r review. If the

Commissioning Agent determines that a significant n umber of the broader sample of checklists is also inaccurate, all the ch ecklists for the type of equipment will be returned to the Contracto r for correction and resubmission. Refer to SECTION 01 91 00 GENERAL CO MMISSIONING

REQUIREMENTS for submittal requirements for Pre-Fun ctional Checklists, Equipment Startup Reports, and other commissioning documents.

3.3 CONTRACTORS TESTS

A. Contractor tests as required by other sections o f Division 28 shall be scheduled and documented in accordance with Section 01 00 00 GENERAL

REQUIREMENTS. All testing shall be incorporated in to the project schedule. Contractor shall provide no less than 7 calendar days’ notice of testing. The Commissioning Agent will wi tness selected

Contractor tests at the sole discretion of the Comm issioning Agent.

Contractor tests shall be completed prior to schedu ling Systems

Functional Performance Testing.

3.4 SYSTEMS FUNCTIONAL PERFORMANCE TESTING

A. The Commissioning Process includes Systems Funct ional Performance

Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare d etailed Systems

Functional Performance Test procedures for review a nd approval by the

Resident Engineer. The Contractor shall review and comment on the tests prior to approval. The Contractor shall prov ide the required labor, materials, and test equipment identified in the test procedure to perform the tests. The Commissioning Agent will witness and document the testing. The Contractor shall sign th e test reports to verify tests were performed. See Section 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS, for additional details.

3.5 TRAINING OF VA PERSONNEL

A. Training of the VA operation and maintenance per sonnel is required in cooperation with the Contracting Officer and Commis sioning Agent.

Provide competent, factory authorized personnel to provide instruction

RALPH JOHNSON VAMC

28 08 00 - 4 to operation and maintenance personnel concerning t he location, operation, and troubleshooting of the installed sys tems. Contractor shall submit training agendas and trainer resumes i n accordance with the requirements of Section 01 91 00. The instruct ion shall be scheduled in coordination with the VA Resident Engi neer after submission and approval of formal training plans. Refer to Section 01

91 00 GENERAL COMMISSIONING REQUIREMENTS and Divisi on 28 Sections for additional Contractor training requirements.

---END---