36C24718R0653-001.docx
DOCX document 112 KB Posted
- Solicitation number
- 36C24718R0653
About this file
36C24718R0653 36C24718R0653.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24718R0653-0002001.pdf | ||
| 36C24718R0653-0002002.pdf | ||
| 36C24718R0653-0002000.docx | DOCX document | |
| 36C24718R0653-0001000.docx | DOCX document | |
| 36C24718R0653-007.pdf | ||
| 36C24718R0653-009.pdf | ||
| 36C24718R0653-002.pdf | ||
| 36C24718R0653-008.pdf | ||
| 36C24718R0653-006.pdf | ||
| 36C24718R0653-004.pdf | ||
| 36C24718R0653-010.pdf | ||
| 36C24718R0653-003.pdf | ||
| 36C24718R0653-005.pdf | ||
| 36C24718R0653-011.pdf | ||
| 36C24718R0653-000.docx | DOCX document |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C24718R0653
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24718R0653 X 08-24-2018 534-18-3-5927-0005 534-15-105 Department of Veterans Affairs W.J.B. Dorn VA Medical Center 6439 Garners Ferry Road Columbia
SC
29209-1639
Thaddeus Willoughby 803-776-4000 ext 5749
PROJECT 534-15-105 - RENOVATE COMMON AND SUPPORT AREAS
PROJECT LOCATION: RALPH JOHNSON VAMC, 109 BEE ST, CHARLESTON, SC 29407
SET-ASIDE INFORMATION: This solicitation will be issued pursuant to the authority under Public Law 109-461.
a small business under the relevant North American Industrial Classification Standard (NAICS) code and be registered and verifiable at http://www.vip.vetbiz.gov and www.sam.gov and VETS 4212 to be eligible for award. Offerors "MUST" ensure registration in these websites are accurate, complete and have not expired prior to proposal closing date.
GENERAL DESCRIPTION: Work includes renovations of selected areas within the scope of work common and support areas in Building 1., including the corresponding work for: fire protection, mechanical, plumbing, electrical, asbestos abatement work, and the removal of the project’s construction debris.
MAGNITUDE OF PROJECT: Between $5,000,000 and $10,000,000.
NAICS CODE: The applicable NAICS code is 236220 and the small business size standard is $36.5 Million
Site Visit: Only one site visit will be conducted and scheduled on September 6, 2018 at 10:00 AM EDT at 109 Bee St., Building 1 Front Lobby, Charleston, SC. Information provided at the site visit shall not alter the terms and conditions of the solicitation and Terms of the solicitation and specification remain unchanged unless the solicitation is amended in writing. Contractors are required to submit all questions in writing to the Contracting Officer following the site visit. All questions and responses will be posted on fedbizopps web site
Request for Information (RFI): RFI are due by 09/10/2018 at 4:00 pm EDT by email to thaddeus.willoughby@va.gov. Late RFIs may not be accepted and offerors are responsible of ensuring questions are received by the Contracting Officer.
X X 52.211-10 X
SEE PAGE 20
11:00 AM EST
09-25-2018 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
Department of Veterans Affairs W.J.B. Dorn VA Medical Center 6439 Garners Ferry Road Columbia
SC
29209-1639 Department of Veterans Affairs
FMS-VA-2(101)
Financial Services Center PO Box 149971 Austin
TX
78714-9971
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.1 PRICE/COST SCHEDULE | 5 |
| ITEM INFORMATION | 5 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 8 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 9 |
| A.2 PROPOSAL PREPARATION, EVALUATION, AND BASIS FOR AWARD | 9 |
| PROPOSAL SUBMISSION AND EVALUATIONS | 9 |
| 2.1 52.211-1 AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS, FPMR PART 101-29 (AUG 1998) | 15 |
| 2.2 52.215-5 FACSIMILE PROPOSALS (OCT 1997) | 15 |
| 2.3 52.216-1 TYPE OF CONTRACT (APR 1984) | 16 |
| 2.4 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 16 |
| 2.5 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 16 |
| 2.6 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 17 |
| 2.7 52.228-1 BID GUARANTEE (SEP 1996) | 18 |
| 2.8 52.233-2 SERVICE OF PROTEST (SEP 2006) | 19 |
| 2.9 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 20 |
| 2.10 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 20 |
| 2.11 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (JAN 2008) | 20 |
| 2.12 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 21 |
| 2.13 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (JAN 2008) | 21 |
| 2.14 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (JAN 1998) | 21 |
| 2.15 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 22 |
| REPRESENTATIONS AND CERTIFICATIONS | 23 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2018) | 23 |
| 3.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (JUL 2013) | 26 |
| GENERAL CONDITIONS | 28 |
| 4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 28 |
| 4.2 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (JUL 2013) | 28 |
| 4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) | 29 |
| 4.4 52.219-14 LIMITATIONS ON SUBCONTRACTING (JAN 2017) | 29 |
| 4.5 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013) | 30 |
| 4.6 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (OCT 2015) | 31 |
| 4.7 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010) | 32 |
| 4.8 52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-DESIGNATED ITEMS (MAY 2008) | 33 |
| 4.9 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014) | 33 |
| 4.10 SUPPLEMENTAL INSURANCE REQUIREMENTS | 36 |
| 4.11 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 37 |
| 4.12 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUL 2014) | 38 |
| 4.13 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 40 |
| 4.14 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2016)(DEVIATION) | 40 |
| 4.15 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 41 |
| 4.16 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2012) | 41 |
| 4.17 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (JUL 2002) | 42 |
| 4.18 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (JUL 2002) ALTERNATE I | 43 |
| 4.19 VAAR 852.236-74 INSPECTION OF CONSTRUCTION (JUL 2002) | 43 |
| 4.20 VAAR 852.236-76 CORRESPONDENCE (APR 1984) | 43 |
| 4.21 VAAR 852.236-77 REFERENCE TO "STANDARDS" (JUL 2002) | 44 |
| 4.22 VAAR 852.236-78 GOVERNMENT SUPERVISION (APR 1984) | 44 |
| 4.23 VAAR 852.236-79 DAILY REPORT OF WORKERS AND MATERIAL (APR 1984) | 44 |
| 4.24 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 1984) | 44 |
| 4.25 VAAR 852.236-83 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (INCLUDING NAS) (JUL 2002) | 45 |
| ADDITIONAL REQUIREMENTS FOR BAR CHART SCHEDULE | 48 |
| 4.26 VAAR 852.236-85 SUPPLEMENTARY LABOR STANDARDS PROVISIONS (APR 1984) | 48 |
| 4.27 VAAR 852.236-86 WORKER'S COMPENSATION (JAN 2008) | 49 |
| 4.28 VAAR 852.236-87 ACCIDENT PREVENTION (SEP 1993) | 49 |
| 4.29 VAAR 852.236-88 CONTRACT CHANGES--SUPPLEMENT (JUL 2002) | 49 |
| 4.30 VAAR 852.236-89 BUY AMERICAN ACT (JAN 2008) | 51 |
| 4.31 VAAR 852.236-91 SPECIAL NOTES (JUL 2002) | 51 |
| 4.32 VAAR 852.246-74 SPECIAL WARRANTIES (JAN 2008) | 52 |
| 4.33 LIMITATIONS ON SUBCONTRACTING-- MONITORING AND COMPLIANCE (JUN 2011) | 52 |
| 4.34 MANDATORY WRITTEN DISCLOSURES | 53 |
| 4.35 IT CONTRACT SECURITY | 53 |
A.1 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| __________________ |
| __________________ |
RALPH H. JOHNSON VA MEDICAL CENTER – RENOVATION OF COMMON AND SUPPORT AREAS IN BUILDING 1 - GENERAL INTERIOR RENOVATION SELECTED DEMOLITION AND CONSTRUCTION: Work includes renovations of selected areas within the scope of work common and support areas in Building 1., including the corresponding work for: fire protection, mechanical, plumbing, electrical, asbestos abatement work, and the removal of the roject’s construction debris.
0001A
| 1.00 |
| JB |
| __________________ |
| __________________ |
Deductive Alternate - Include all work in Base bid, but deduct all work associated with Buildings E and F
0001B
| 1.00 |
| JB |
| __________________ |
| __________________ |
Deductive Alternate - Include all work in Base bid, but deduct all work associated with Buildings E, F, and G.
| GRAND TOTAL |
| __________________ |
Renovate Common & Support Areas Bldg. 1, Ralph Johnson VAMC, Charleston, SC
PRICE PROPOSAL BREAKDOWN
CLIN 0001 – Renovate Common & Support Areas Bldg. 1
| Division |
| Description |
| Totals |
| 01 |
| GENERAL REQUIREMENTS |
| 02 |
| STRUCTURE DEMOLITION |
| 03 |
| CONCRETE |
| 04 |
| MASONRY |
| 05 |
| METALs |
| 06 |
| WOOD, PLASTICS, AND COMPOSITES |
| 07 |
| THERMAL & MOISTURE PROTECTION |
| 08 |
| OPENINGS |
| 09 |
| FINISHES |
| 10 |
| SPECIALTIES |
| 11 |
| EQUIPMENT |
| 12 |
| FURNISHINGS |
| 13 |
| SPECIAL CONSTRUCTION |
| 14 |
| CONVEYING EQUIPMENT |
| 21 |
| FIRE SUPPRESSION |
| 22 |
| PLUMBING |
| 23 |
| HVAC |
| 26 |
| ELECTRICAL |
| 27 |
| COMMUNICATIONS |
| 28 |
| ELECTRONIC SAFETY & SECURITY |
Total – CLIN 0001 – BASE BID
Statement of Work for Construction NRM Project 534-15-105, Renovate Common and Support Areas
1. Scope.
a. The scope of this work involves all construction services required to fully renovate the areas specified in the construction contract. Construction services include, but are not limited to: various restrooms, corridors, drinking fountains, waiting rooms, elevator lobbies, stairwells, Histology, and other areas of the facility.
b. Staging and phasing are absolute necessities to complete all work such that facility services are uninterrupted.
c. All interim life safety measures, infection control requirements, security requirements, etc. shall be followed, as necessary within these documents and through the Contracting Officer’s Representative.
d. Contractor shall provide all material, labor, equipment, tools, etc. as necessary to fully renovate specified areas, including plumbing, mechanical, electrical, asbestos abatement, carpentry
2. Locations.
a. Work will be required throughout various areas of Building 1.
b. 1st Floor
i. G-Building, Engineering and Housekeeping restrooms (G106, G111)
ii. Corridors:
1. 1A1, 1A2, 1A3, 1A4, 1A5, 1A6, 1A7, 1A8, 1A9, 1B1, 1B4, 1B6, 1B7, 1B8, 1B10, 1AB1, 1AB2, 1BD1, 1BD2, 1CC5, 1CD1, 1CD2, Common Corridor 1, Common Vestibule 2, Common Vestibule 7, Common Vestibule 8, Common Vestibule 9, Specialty Care Corridor 1, Specialty Care Corridor 3, Specialty Care Corridor 4, Specialty Care Corridor 5, D133
iii. Nutrition/Kitchen offices (D103A, D103B, D109E, D109D)
iv. Elevator Lobby
v. Stairwell 3
vi. Green-team restrooms (B152/CC118)
vii. ED/Green-team Waiting Room (CC119)
viii. Eye Clinic Waiting Room (A131)
ix. Primary care restroom (B136)
x. Specialty Care Waiting Rooms (D105, D120)
xi. Various water coolers per drawings
xii. Various expansion joints per drawings
c. 2nd Floor
i. Elevator Lobby
ii. Remove E and F Building work from the scope of the project
iii. G-Building restrooms (G203, G204)
iv. Radiology Restrooms (D201A, D202, D239, D239A, D239B, D242B, D242C)
v. Specialty Clinic Restrooms (D234, D235)
vi. Nuclear Medicine Restrooms (B205, B207, B207A, B207B)
vii. Chemistry/Dialysis Restrooms (BB211B, BB201)
viii. Histology Restrooms (B238, B239)
ix. Education Restrooms (CC213, CC214)
x. Corridors:
1. 2A3, 2A5, 2A6, 2B1, 2B2, 2B2A, 2B3, 2B4, 2B5, 2B6, 2D2, 2D3, 2D4, 2D5, 2D6, 2D7, 2D8, 2D9, 2G2, 2G1, 2AB1, 2AB2, 2BB1, 2BB2, 2BB3, 2BB4, 2BD1, 2CC1, 2CC2, 2CC3, 2CC4, 2CD1, D206, D266
xi. ICU/Cardiology Waiting Rooms (A202A, A244)
xii. Nuclear Medicine Waiting Room (B203)
xiii. Dialysis Waiting Room (B256)
xiv. Lab Special Chemistry Lab (BB211F, BB211E)
xv. Histology Renovation (B233, B234, B235, B236, B240, B228A)
xvi. Various water coolers per drawings
xvii. Various expansion joints per drawings
d. 3rd Floor
i. Elevator lobby
ii. Stairwell 3
iii. 3B Nurse’s Station
iv. Various water coolers per drawings
v. Various expansion joints per drawings
vi. Corridors:
1. 3A1, 3B1, 3B2, 3B3, 3B4, 3B5, 3B6, 3B7, 3C1
e. 4th Floor
i. Elevator Lobby
ii. Stairwell 3
iii. 4B Nurse’s Station
iv. Various water coolers per drawings
v. Various expansion joints per drawings
vi. Corridors:
1. 4A1, 4B1, 4B2, 4B3, 4B4, 4B5, 4B6, 4B7, 4C1
f. 5th Floor
i. Elevator Lobby
ii. Stairwell 3
iii. Various expansion joints per drawings
iv. Various water coolers per drawings Page 1 of Page 1 of
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
A.2 PROPOSAL PREPARATION, EVALUATION, AND BASIS FOR AWARD
PROPOSAL SUBMISSION AND EVALUATIONS
This part describes proposal submission instructions, description of evaluation factors, and basis for award for Project #534-15-105, entitled “Renovate Common and Support Areas of Building 1”.
1. PROPOSAL SUBMISSION INSTRUCTIONS:
Prospective offerors must submit:
ONE (1) ELECTRONIC copy to thaddeus.willoughby@va.gov no later than time and date specified in solicitation or as amended.
Interested firms are responsible for ensuring electronic delivery of submission by the time and the date specified. It will be highly recommended interested firms confirm electronic submissions have been received by the Contracting Officer.
Prospective offerors will be advised that Size limits of e-mails are restricted to 10MB.
Prospective offeror will be required to provide three (3) hardcopies of proposal; with the original bid guarantee to the contracting officer. Bid Guarantee and hardcopies should be mailed to the following address:
W.J.B. Dorn VA Medical Center Attn: Thaddeus Willoughby 6439 Garners Ferry Road Bldg. 22, Room 3B108 Columbia, SC, 29209-1639
All offers shall clearly identify the procurement number, project title and subject line of their electronic submission, and will be responsible for ensuring electronic delivery of offers.
To assure timely and equitable evaluation of proposals, offeror must follow the instructions contained herein. Proposals must be complete, self-sufficient, and respond directly to the requirement of this solicitation.
Offerors must provide all requested information for each factor and sub-factor. Proposals must separately address each element of each factor and sub-factor as applicable to be considered responsive to this RFP. Factor and sub-factors headings must be highlighted in yellow or typed in bold text for identification. It is the contractor’s responsibility to ensure the submitted proposal is in the proper format, the provided information is clearly understood and free of ambiguities.
Offeror proposal shall consist of both a technical and price proposal, as described below, and shall be submitted by email to: thaddeus.willoughby@va.gov. and also mailed to the address above.
A. TECHNICAL PROPOSAL - Technical proposal shall be submitted separately from the price proposal of the solicitation requirements identified below. The following format shall be used:
TAB A. General Information
· Cover Page with Solicitation Number, Project Title,
· Table of Contents
· Company particulars to include DUNS Number, Cage Code, Tax ID number, principal points of contact, address, phone numbers, etc.
TAB B: Technical Evaluation Factors:
· Factor 1 - Relevant Management and Technical Experience – See attachment 1
· Factor 2 - Key Personnel
· Factor 3 - Project Schedule
· Factor 4 - Past Performance – See attachment 2
B. PRICE PROPOSAL – Price proposal shall be submitted separately from the technical proposal of the solicitation requirements identified below: The following format shall be used:
TAB A: General Information, Cover Sheet
· Page with Solicitation Number, Project Title,
· Table of Contents
· SF 1442 Signed offer/Amendments – Complete Blocks 17-20C
· Vet Biz Certification
· Offer Guarantee Bond
· Acknowledgement of Amendments
· Certifications
· General Contractor License
· EMR - See attachment 3 TAB B: Price/Cost and Bid Breakdown Schedules
2. TECHNICAL EVALUATION FACTORS:
A. Factor 1 - Relevant Management and Technical Experience Provide details of prime contractor’s experience of at least two (2) recent and relevant construction projects above $2,000,000. Contractor experience form shall be completed and submitted with proposal and will be used to verify award/completion date. See attachment 1.
1) To be considered “Technically Acceptable”, the relevant construction projects submitted shall have a value greater than $2,000,000.
2) To be considered “Technically Acceptable” a minimum of one (1) construction project submitted shall be a renovate project having a value greater than $2,000,000.
3) To be considered “Technically Acceptable” the relevant construction projects submitted shall have been awarded and completed or in-progress within the last 5 years from the date of issuance of this solicitation.
4) To be considered “Technically Acceptable” the relevant construction projects submitted must have been completed or in-progress by the contractor submitting the proposal in response to the solicitation. The Dun & Bradstreet Number (DUNS) of the contractor submitting the proposal in response to the solicitation shall be the same as the prime contractor used on the relevant construction projects submitted.
5) Failure to submit all the data indicated in this section will be cause for determining a proposal incomplete. Incomplete proposals will not be considered for evaluation and rejected as unacceptable for failure to submit all material requirements of proposal.
B. Factor 2 - Key Personnel
Provide resumes for the following key personnel which must include/show the minimum requirements as stated for each as follows:
1) Project Manager (Overall Manager for the Project – onsite 25%) shall have:
(a) At a minimum, 5 years of experience working at VA Medical Centers, medical centers, federal facilities, medical facilities; and
(b) At a minimum 5 years of experience working with and near sensitive medical areas and equipment, such as Pharmacy, ICUs, Community Living Centers, Operating Rooms, Procedure Rooms, Emergency Departments, Radiology, and other areas of a functioning hospital; and
(c) At a minimum, 5 years of experience implementing and maintaining infection control barriers, dust control measures, Interim Life Safety Measures, providing negative pressure environments, and other related safety and environmental controls; and
(d) Shall possess broad working knowledge of applicable codes, regulations, and standards, such as ACI, IBC, EPA, NFPA, VAAR, FAR, VA specifications, CFM standards, etc.; and
(e) Shall possess experience managing construction contracts up to $2 million; and
(f) Shall have demonstrated the ability to manage multiple construction contracts at the same time and
(g) Shall have completed, at minimum, a 30-hour OSHA-certified training course in the past 5 years and
(h) Attach documentation identifying person is a current full-time employee of the Prime Contractor or a letter of intent signifying their employment for this project.
2) Construction Superintendent (onsite full time) shall have:
(a) At a minimum, 3 years of continuous experience working at VA Medical Centers, medical centers, federal facilities, medical facilities; and
(b) At a minimum, 3 years of experience working with and near sensitive medical areas and equipment, such as Pharmacy, ICUs, Community Living Centers, Operating Rooms, Procedure Rooms, Emergency Departments, Radiology, and other areas of a functioning hospital; and
(c) At a minimum, 3 years of continuous experience implementing and maintaining infection control barriers, dust control measures, Interim Life Safety Measures, providing negative pressure environments, and other related safety and environmental controls; and
(d) Knowledge and experience coordinating with and working near hospital employees, patients, and visitors; and
(e) Shall possess a working knowledge of applicable codes, regulations, and standards, such as ACI, IBC, EPA, NFPA, ASME, FAR, VA specifications, CFM standards, etc.; and
(f) Shall have demonstrated the ability to manage multiple construction contracts at the same time and
(g) Shall have completed, at minimum a 30-hour OSHA-certified training course in the past 5 years
(h) Attach documentation identifying person is a current full-time employee of the Prime Contractor or a letter of intent signifying their employment for this project.
3) Safety Manager/Officer:
(a) Shall possess the qualifications listed in the specification section 01 35 26 paragraph 1.8 Training.
(b) Shall have completed specialized training related to job-specific work requirements
4) The offeror SHALL provide documentation identifying each person as a current full-time employee of the Prime Contractor or a Letter of Intent signifying their employment for this project. Documentation of full-time employment can be provided by a current paystub, employee hire form, or an affidavit signed by the Prime Contractor CEO, president, or owner attesting to the key person’s employment status. Leased employees will not be considered as full-time employees of prime. Additionally, a simple statement attesting to employment status will not be accepted. Actual Documentation of employment must be provided.
5) Failure to provide current, accurate, and verifiable data will render the resume as unacceptable. The identified personnel must be used on the project. Any substitution of these persons will not be permitted without prior approval of the Contracting Officer. Identification of two individuals proposed for a single position will result in the evaluation of the least-qualified person.
6) Failure to submit all the data indicated in this section will be cause for determining a proposal incomplete. Incomplete proposals will not be considered for evaluation and rejected as unacceptable for failure to submit all material requirements of proposal.
C. Factor 3 - Project Schedule - In order to be technically acceptable, the contractor shall submit with the proposal a “draft” project schedule which shall include the following:
1) 550 calendar days period of performance submitted in a Gantt chart format.
2) Include at a minimum – Submittals, mobilization, temporary environmental control installation, site work, concrete, tower install, plumbing, and equipment install, final punch list.
D. Factor 4 - Past Performance - The offeror shall provide past performance information for in one of two formats.
1) The offeror shall provide a description of relevant and recent projects, a minimum of three but no more than five examples of similar work completed in the past five years (construction projects in-progress may be included). Include as a minimum, a description of the work (including role played), the project size, cost, type of contract (e.g. task order) Client contact information and duration.
Present/Past performance questionnaires will be sent to client chosen by the offeror. Past/present performance questionnaires should be sent by client directly to Thaddeus Willoughby from the clients via email to Thaddeus.willoughby@va.gov Past/present performance questionnaires should be received via emailed before the closing date and time. Any past/present performance questionnaires received after the closing time will not be accepted. FAR 15.208(b) will apply to past/present performance questionnaires. See attachment 2.
It is the offeror’s responsibility to ensure the Government will be able to contact the POCs using the contact information provided. Offerors are encouraged to send their request to the POC as soon as possible once a project is identified for experience under Factor 1.
OR
2) Copies of Contractor Performance Assessment Reporting System (CPARS) for projects performed for the U.S. Government. If the project provided has a CPARS, it must be used by the offeror to demonstrate past performance. If CPARS submission is used to validate past performance, it will be the most recent evaluation in the system (i.e. for projects submitted as completed, the final 100% completed CPARS will be provided). If the offeror submits a CPARS, they are not required to submit a separate Past Performance Questionnaire for the specific project.
(a) If the CPARS is used, the Government reserves the right to check the Past Performance Information Retrieval System (PPIRS) to verify the accuracy of the CPARS submitted. CPARS submitted by the offeror which do not match those in the system, or for which there is a more current CPARS available, may cause the offeror to receive an “Unacceptable” for this factor.
(b) The Government reserves the right to use past performance information obtained from sources other than those identified by the offeror.
(c) The Government may obtain information from any or all of the listed contract references and/or may not contact all of the identified POCs
In order to receive an “Acceptable” rating from the evaluation team, the offeror’s past performance submitted to the Contracting Officer in response to Factor 3 must show an overall rating equivalent to satisfactory or higher (See note below).
Offeror’s past performance submitted to the Contracting Officer in response to Factor 3 which show an overall rating equivalent to marginal/fair or lower will receive a rating of “unacceptable” by the evaluation team.
Note: In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305 (a) (2) (iv)). Therefore, the offeror shall be determined to have unknown past performance. In the context of acceptability/unacceptability, “unknown” shall be considered “acceptable.”
E. Cost/Price: Price/Cost will not be rated or scored, but will be evaluated for fairness and reasonableness. In accordance with FAR 15.404-1(b)(2) the government may use various price analysis techniques and procedures to ensure a fair and reasonable price. It shall be noted that an unrealistically low, or high proposed price may be grounds for rejecting an offeror’s proposal on the basis that the offeror does not understand the requirement or has submitted an unrealistic proposal.
3. BASIS FOR CONTRACT AWARD
A. Source Selection Using Lowest Price Technically Acceptable Process (LPTA): This will be a competitive Request for Proposal (RFP) conducted under FAR Part 15.102-2 Lowest Price Technically Acceptable (LPTA) source selection process. Award will be made on the basis of the lowest evaluated price proposal meeting the acceptability standards for non-cost factors.
B. Evaluation Overview:
1) The Government reserves the right to evaluate only the technical proposal of the lowest price offeror. Proposals will be evaluated and ranked according to price, from lowest to highest. Other technical proposals may not be evaluated unless the Government determines the lowest price offeror to be unacceptable or non-responsive. In the event the Government determines the lowest price offeror to be unacceptable, the technical proposal of the next lowest price offeror will be evaluated. This process will continue until a technical proposal is determined to be acceptable.
2) This is a firm-fixed price award. It is the Offeror’s responsibility to ensure the submitted cost proposal includes all costs for total project requirements and completion in accordance with the specifications and drawings herein. The Offeror assumes all risk for omissions in subcontractor proposals.
3) Technical acceptability is an assessment of each offeror’s ability to successfully accomplish the technical requirements. The technical acceptability factors and sub-factors shall be rated as acceptable or unacceptable based on the information submitted by the offeror in response to the criteria of the evaluation factor. Note: All factors and sub-factors must be rated acceptable in order to be considered technically acceptable. If one factor or sub-factor is rated unacceptable, then the government will move onto the next proposal.
4) Offerors must provide all requested information for each factor and sub-factor. Proposals must separately address each element of the factors and sub-factors as applicable to be considered responsive to this RFP. Factors headings must be highlighted in yellow or typed in bold text for identification. Recommend each titled factor heading in the submitted proposal be stated in the chronological order shown below. This format establishes a direct correlation between the information provided and the factors for evaluation. It is the contractor’s responsibility to ensure the submitted proposal is in the proper format, the provided information is clearly understood and free of ambiguities.
5) Award will result in a firm-fixed price contract. It is the Offeror’s responsibility to ensure the submitted price proposal includes all costs for total project requirements and completion in accordance with the specifications and drawings herein. The Offeror assumes all risk for omissions in subcontractor proposals.
6) The Government evaluation team will consider all information provided in the proposal individually. Once these individual analyses are completed, the team will meet and determine a rating by consensus decision.
7) Exceptions to the contractual terms and conditions of the solicitation (e.g., standard company terms and conditions) may result in a determination to reject a proposal.
8) Failure to submit all the data indicated in this section will be cause for determining a proposal incomplete. Incomplete proposals will not be considered for evaluation and rejected as unacceptable for failure to submit all material requirements of proposal.
C. SDVOSB Verification- The Government will review VetBiz (https://www.vip.vetbiz.gov/) to confirm Service Disabled Veteran-owned Small Business (SDVOSB) status verification for the submitted proposals. Evaluations will be performed on proposals submitted by verified SDVOSBs only. Subsequent confirmation of SDVOSB verification status will be performed for the apparent award.
D. EMR Rating: As indicated above, as part of the technical proposal, the offeror must provide documentation to substantiate a current EMR rating of 1.0 or less. Failure to do so may result in the overall proposal being considered non-responsive. See attachment 3.
E. Discussions: The Government intends to evaluate proposals and award a contract without discussions. Communication between the Government and offerors will be limited to exchanges for clarification as described in FAR 15.306(a). The Government reserves the right to enter into discussions if necessary. Thus, an offeror’s proposal should contain the offeror’s best terms from a price and technical standpoint. Communication conducted to resolve minor or clerical errors would not constitute discussions and the Contracting Officer reserves the right to award a contract without the opportunity for proposals revisions or discussions.
F. Contract Type: Any resultant contract awarded in response to this solicitation will be firm-fixed price. It is the offeror’s responsibility to ensure the submitted cost proposal includes all costs for total project requirements and completion in accordance with the specifications and drawings herein. The offeror assumes all risk for omissions in subcontractor proposals.
G. Responsibility Determination: A Determination of Responsibility will be accomplished for the apparent awardee prior to processing the award. The above information, along with other information obtained from Government and commercial systems, such as Duns & Bradstreet report, will be used to make the Determination of Responsibility. Any information received by the Government that would be cause for a negative Determination of Responsibility will be referred to SBA for a determination before award.
H. Public Announcement of Contract Award: Offerors submitting price proposals in response to this solicitation do so with the complete and full understanding that the Government reserves the right to publicly announce the total contract award amount.
2.1 52.211-1 AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS, FPMR PART 101-29 (AUG 1998)
(a) The GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29, and copies of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained for a fee by submitting a request to— GSA Federal Supply Service Specifications Section, Suite 8100 470 East L'Enfant Plaza, SW Washington, DC 20407 Telephone (202) 619-8925 Facsimile (202) 619-8978.
(b) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a single copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained free of charge by submitting a request to the addressee in paragraph (a) of this provision. Additional copies will be issued for a fee.
(End of Provision)
2.2 52.215-5 FACSIMILE PROPOSALS (OCT 1997)
(a) Definition. "Facsimile proposal," as used in this provision, means a proposal, revision or modification of a proposal, or withdrawal of a proposal that is transmitted to and received by the Government via facsimile machine.
(b) Offerors may submit facsimile proposals as responses to this solicitation. Facsimile proposals are subject to the same rules as paper proposals.
(c) The telephone number of receiving facsimile equipment is: thaddeus.willoughby@va.gov.
(d) If any portion of a facsimile proposal received by the Contracting Officer is unreadable to the degree that conformance to the essential requirements of the solicitation cannot be ascertained from the document—
(1) The Contracting Officer immediately shall notify the offeror and permit the offeror to resubmit the proposal;
(2) The method and time for resubmission shall be prescribed by the Contracting Officer after consultation with the offeror; and
(3) The resubmission shall be considered as if it were received at the date and time of the original unreadable submission for the purpose of determining timeliness, provided the offeror complies with the time and format requirements for resubmission prescribed by the Contracting Officer.
(e) The Government reserves the right to make award solely on the facsimile proposal. However, if requested to do so by the Contracting Officer, the apparently successful offeror promptly shall submit the complete original signed proposal.
(End of Provision)
2.3 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.4 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.5 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
| Goals for minority participation for each trade |
| Goals for female participation for each trade |
| 30.7 % |
| 6.9 % |
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is
CHARLESTON
CHARLESTON COUNTY
SOUTH CAROLINA
(End of Provision)
2.6 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.7 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or 3,000,000.00, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
2.8 52.233-2 SERVICE OF PROTEST (SEP 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Robert Holbrook robert.holbrook3@va.gov Hand-Carried Address:
Robert Holbrook, Bldg 22, Rm 3B100 Department of Veterans Affairs W.J.B. Dorn VA Medical Center 6439 Garners Ferry Road Columbia SC 29209-1639 Mailing Address:
Robert Holbrook, Bldg 22, Rm 3B100 Department of Veterans Affairs W.J.B. Dorn VA Medical Center 6439 Garners Ferry Road Columbia SC 29209-1639
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of Provision)
2.9 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for— September 6, 2018 at 10:00 AM EST
(c) Participants will meet at— RHJ VAMC Front Lobby (End of Provision)
2.10 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/ http://farsite.hill.af.mil/ (End of Provision)
| FAR Number |
| Title |
| Date |
| 52.204-7 |
| SYSTEM FOR AWARD MANAGEMENT |
| OCT 2016 |
| 52.204-16 |
| COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING |
| JUL 2016 |
| 52.204-22 |
| ALTERNATIVE LINE ITEM PROPOSAL |
| JAN 2017 |
| 52.215-1 |
| INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION ALTERNATE II (OCT 1997) |
| JAN 2017 |
| 52.236-28 |
| PREPARATION OF PROPOSALS—CONSTRUCTION |
| OCT 1997 |
2.11 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (JAN 2008)
The supplies or equipment required by this invitation for bid or request for proposal must conform to the standards of the Dept. of Veterans Affairs and Construction & Faciulities Management as to https://www.cfm.va.gov/TIL/. The successful bidder or offeror will be required to submit proof that the item(s) he/she furnishes conforms to this requirement. This proof may be in the form of a label or seal affixed to the equipment or supplies, warranting that they have been tested in accordance with and conform to the specified standards. Proof may also be furnished in the form of a certificate from one of the above listed organizations certifying that the item(s) furnished have been tested in accordance with and conform to the specified standards.
(End of Provision)
2.12 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN…