36C24718R0307-0002003.pdf

PDF 280 KB Posted

Attached to
VISN 7 CONSTRUCTION MATOC - BLUE CORD DESIGN AND CONSTRUCTION Federal contract opportunity
Solicitation number
36C24718R0307
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 7

About this file

This document provides details for a Multiple Award Task Order Contract (MATOC) solicitation for construction services within Veterans Integrated Service Network (VISN) 7. The solicitation will be issued by the Department of Veterans Affairs VISN 7 Network Contracting Office and is set aside entirely for Service-Disabled Veteran Owned Small Businesses. Approximately eighteen indefinite delivery indefinite quantity contracts will be awarded for a period of up to five years, with a total value not to exceed $500 million across all task orders. Task orders will range from $2,000 to $20 million for requirements such as interior and exterior renovations, HVAC, plumbing, electrical work, communications, site work, and construction of new facilities. The solicitation is expected to be released on or around March 30, 2018 and will include seed projects for pricing and technical evaluation purposes.

36C24718R0307 0002 Attachment #3 - Revised Seed Project Price Offer Schedule.pdf

View the file

Other files for this federal contract opportunity

Other files attached to VISN 7 CONSTRUCTION MATOC - BLUE CORD DESIGN AND CONSTRUCTION, newest first.
File Type Posted
36C24718D0134-001.docx DOCX document
36C24718D0134-000.docx DOCX document
36C24718R0307-0004000.docx DOCX document
36C24718R0307-0003000.docx DOCX document
36C24718R0307-0002000.docx DOCX document
36C24718R0307-0002001.pdf PDF
36C24718R0307-0002005.pdf PDF
36C24718R0307-0002004.pdf PDF
36C24718R0307-0002002.pdf PDF
36C24718R0307-0001004.docx DOCX document
36C24718R0307-0001001.pdf PDF
36C24718R0307-0001002.pdf PDF
36C24718R0307-0001003.docx DOCX document
36C24718R0307-0001005.pdf PDF
36C24718R0307-0001000.docx DOCX document
36C24718R0307-040.docx DOCX document
36C24718R0307-038.docx DOCX document
36C24718R0307-039.docx DOCX document
36C24718R0307-042.pdf PDF
36C24718R0307-037.docx DOCX document
36C24718R0307-044.pdf PDF
36C24718R0307-036.docx DOCX document
36C24718R0307-041.pdf PDF
36C24718R0307-043.pdf PDF
36C24718R0307-000.docx DOCX document
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C24718R0307 0002 ATTACHMENT #3

1.5 SEED PROJECT PRICE OFFER SCHEDULE – REVISED AMENDMENT 0002

ITEM DESCRIPTION: SEE SPECIFICATIONS AND DRAWINGS FOR DETAILS PRICE

ITEM I, GENERAL CONSTRUCTION: Removal of indicated sections of walls, indicated doors, and indicated ceilings; replacements of doors, installation of interior walls and ceilings, modifications to existing air conditioners and controls and installation of new direct expansion ductless split air conditioners along with required electrical and controls support work and reinstallation of existing Ethernet and telephone system cabling, switches, servers, and power supplies all as indicated on drawings and specifications for the purpose of correcting existing deficiencies in information technology infrastructure.

DEDUCTIVE ALTERNATE 1 – Deduct all work associated with Building 26.

Projected calendar days off schedule: ____________

DEDUCTIVE ALTERNATE 2 – Deduct all work associated with Building 29.

DEDUCTIVE ALTERNATE 3 – Deduct all work associated with Building 4.

DEDUCTIVE ALTERNATE 4 – Deduct all work associated with Building 6.

(Listed as Item 2 in addendum to specifications)

a. Asbestos floor tile and tile mastic testing:

10 samples (tests) @ $_________ unit price for a total of $___________.

b. Asbestos floor tile and tile mastic abatement:

500 sf @ $_________ unit price for a total of $___________.

c. Lead paint testing:

25 samples (tests) @ $_________ unit price for a total of $___________.

d. Lead paint abatement:

7500 sf @ $_________ unit price for a total of $___________.

e. Asbestos containing plaster/Drywall & Joint Compound (wall and ceiling) testing:

50 samples (tests) @ $_________ unit price for a total of $___________.

f. Asbestos containing plaster/Drywall & Joint Compound (wall and ceiling) abatement:

Total for

Asbestos Line

Item

36C24718R0307 0002 ATTACHMENT #3

7500 sf @ $_________ unit price for a total of $___________.

g. Asbestos pipe and pipe fitting insulation testing:

25 samples (tests) @ $_________ unit price for a total of $___________.

h. Asbestos pipe and pipe fitting insulation up to 2” abatement:

200 linear feet @ $_________ unit price for a total of $___________.

i. Asbestos pipe and pipe fitting insulation 2”-4” abatement:

400 linear feet @ $_________ unit price for a total of $___________.

j. Asbestos Heat Shield Abatement testing:

10 samples (tests) @ $_________ unit price for a total of $___________.

k. Asbestos Heat Shield Abatement:

200 sf @ $_________ unit price for a total of $___________.

l. Asbestos Ceiling Tile testing:

5 samples (tests) @ $_________ unit price for a total of $___________.

m. Asbestos Ceiling Tile Abatement:

500 sf @ $_________ unit price for a total of $___________.

n. Asbestos Daily Personal and Area Air Sampling:

15 days @ $_________ unit price for a total of $___________.

o. Asbestos Final Clearance Air Sampling by PCM:

7 days @ $_________ unit price for a total of $___________.

p. Asbestos Final Clearance Air Sampling by TEM 7 days @ $_________ unit price for a total of $___________.

A single award will be made on Item 1 AND Item 6, but in the event the offer exceeds the funds available for those items, a single award will be made with Item 2, 3, 4, and/or 5, based on available funding. Offerors shall price each item. Deductive Alternates, Items 2 through 5, are to be the amount to be deducted from Item 1.

The Period of Performance for the base proposal is established as 540 Calendar days and includes the completion of all punch list items. For each deduct alternate listed (Item 2 through Item 5), each offeror is to provide the time that it will save to complete the work.

ATTACH YOUR ITEMIZED COST BREAKDOWN

***Offerors are to include a cost breakdown to include a detailed line item cost breakdown (materials, labor, and equipment) by trade, include overhead, profit, bond costs and breakdown of G&A expenses inclusive of all Project Staff and General Requirements OF THE PRIME CONTRACTOR, which exhibits the 15% of contract performance that will be incurred for SDVOSB personnel in accordance with FAR 52.219-27 – Limitations on Subcontracting. Failure to do so may render proposal non-responsive***