19-Outage Plan.pdf
PDF 231 KB Posted
- Attached to
- Correct Electrical Deficiencies
- Solicitation number
- 36C24627B0001
About this file
This document is Appendix 19 of the Construction Documents for a Department of Veterans Affairs electrical deficiencies correction project (SES Project #23087, VA Project #565-22-500). The appendix provides comprehensive outage plans and phasing narratives for electrical system replacements across multiple buildings at a VA facility.
The outage plan establishes mandatory requirements for all electrical distribution work, including compliance with VA Utility Outage Forms, Lock-Out Tag-Out procedures, and contingency provisions such as extension cables, battery-powered lighting, fire extinguishers, and spare tools. For temporary electrical panels, the contractor must provide panels with equivalent or greater pole capacity (minimum 60-pole breaker), pre-installed breakers (40 20A/1, 4 30A/1, 2 30A/2), lockable means on over half the breakers, pre-wired conductors one size larger than required with WAGO connectors, and a top gutter. Temporary generator installations require 8-foot grounding rods and walkway protection. The document details four phased outage plans: a medium voltage loop reconfiguration minimizing downtime through sequential circuit switches; Building 1 main electrical room work involving a 1000kVA generator, new 2000A switchboard, and multiple automatic transfer switches; Building 3 transformer switchover with new equipment installation; and Building 35 winter outage coordination with the utility provider. Building ancillary equipment replacement follows a standardized process using temporary panels to facilitate in-place equipment swaps while maintaining power to downstream systems. The document includes comprehensive equipment lists for all three buildings specifying panel locations, levels, and areas requiring replacement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sign-in sheet_12Nov2026.pdf | ||
| 18-Hazmat Survey.pdf | ||
| 21-21 Nov 2014 VACO ECA E24.pdf | ||
| 565-22-500 Combined Set 20251118.pdf | ||
| ATTACHMENT - BAA TAA COMPLIANCE CERTIFICATION.docx | DOCX document | |
| Correct Electrical Deficiencies Specifications.pdf | ||
| 36C24627B0001.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPENDIX 19
Outage Plan
Department of Veteran Affairs Correct Electrical Deficiencies Construction Documents (CD) Submission SES Project #23087 VA Project #565-22-500 www.specializedeng.com
Appendix 19 18 November 2025
Utility Shutdown All electrical distribution outages performed as part of this project shall comply with VA requirements to fill out, submit, and follow the VA Utility Outage Form. The contractor shall utilize this document as a guideline to perform electrical distribution outages. The contractor is responsible for development of an outage plan and successful execution thereof.
Safety All electrical distribution equipment work will require proper Lock-Out Tag-Out procedures.
Contractor shall provide all locking means as required for the project scope.
Contingency Items:
Contractor shall provide contingency items in the event that the Outage Plan Process is not done correctly and/or an outage leads to unforeseen events such as; causing outage in unexpected areas, causing an outage to area for longer than expected, causing outage to lights/receptacles serving the electrician’s efforts to continue the outage plan process.
Contingency items shall include:
• (5) 100’ extension cables with multiple outlets & (5) 25’ extension cables
• (3) battery powered headlamp (charged)
• (5) battery powered flashlights (charged)
• (1) battery powered work light (charged)
• (1) 5 gallon bucket of water, with lid
• (1) fire extinguisher suitable for electrical type fires and word-burning type fires
• Spare tools in the event that arcing causes failure to a tool:
o Socket/wrench set o Screwdriver set
Methods Where temporary electrical panel are utilized, the following must be included as part of the panel:
• Panel shall be of same or greater poles required to power the panel being replaces.
Provide minimum 60 pole breaker for general use.
Construction Documents (CD) Submission
• Install a gutter at the top of the electrical panel
• Panel shall have pre-installed the following breaker: (40) 20A/1, (4) 30A/1, (2) 30A/2.
• Panel circuit breakers shall have over ½ of circuit breakers with lockable means.
• Panel shall have space for assortment of breakers required for cut over of remaining circuit.
• Pre-wire conductors to circuit breakers at a wire size one-larger than required for the circuit breaker. (ex: 20A/1 shall be pre-wired with #10 CU). Wires shall run out of panel enclosure and be accessible within gutter at the top of the panel. Provide wire with two feet of slack. Each wire shall be clearly be labeled with circuit number. Each wire shall be provided with one 3-terminal WAGO style connector (or equivalent) to reduce circuit connection time.
Where temporary generator power generation is utilized, the following must be included as part of the temporary power system:
• all walkways to reduce pedestrian trip hazard.
• At each temporary generator install a 8-foot, ¾ inch diameter grounding rod.
OUTAGE PLAN PROCESS BY LOCATION:
MEDIUM VOLTAGE OUTAGE PLAN:
The intent of this phasing narrative is to minimize downtime of the VA medium voltage loop.
PHASE 1: PREPARATION
1. Maintain existing mv loop while new medium voltage Building (MVB) is Built.
2. Install new conduit and ductbank to the furthest extent possible Without connecting into existing, live medium voltage loop.
3. Install new medium voltage switchgear in new MVB.
PHASE 2: SWITCH HOFFER/F3D
1. Adjust existing sectionalizing switches such that entire mv loop is Being fed from circuit Tokay/F3A via the existing MVB.
2. Demolish portion of existing Hoffer/F3D circuit near new MVB.
3. Complete installation of Hoffer/F3D ductbanks and new handhole
HH-1.
4. Intercept and splice existing mv loop between Hoffer/F3D and existing
Construction Documents (CD) Submission
Sectionalizing switch-3 at new handhole HH-2.
5. Disconnect existing mv switchgear Hoffer main and F3D feeder.
6. Connect new mv switchgear at Hoffer main and F3D feeder.
7. Coordinate with PWC for work to be completed on Hoffer utility
Feed.
PHASE 3: SWITCH TOKAY/F3A
1. Adjust existing sectionalizing switches such that entire mv loop is Being fed from circuit F3D via the new MVB.
2. Complete installation of Tokay/F3A ductbanks and new handhole HH-3.
3. Disconnect existing mv switchgear Tokay main and F3A feeder.
4. Connect new mv switchgear at Tokay main and F3A feeder.
5. Coordinate with PWC for work to be completed on Tokay utility feed.
PHASE 4: DEMOLISH EXISTINGMVB
1. Maintain mv loop being fed from Hoffer/F3D circuit.
2. Demolish existing medium voltage switchgear Building.
3. Complete installation of Tokay/F3A ductbank near demolished MVB.
4. Connect Tokay/F3A line into existing sectionalizing switch ss-1.
Construction Documents (CD) Submission
BUILDING 1
Refer to site and Building 1 drawings for additional information
BUILDING 1 (D) MAIN ELECTRICAL ROOM EQUIPMENT OUTAGE PLAN
PHASE 1: SERIVCE FEEDERS, TEMP GEN, SWITCHBOARD 'MS', & ATS #3
1. Service feeders from transformer t-9 shall remain active and in tack for duration of this phase.
2. Provide temporary generator at approximate location indicated in floorplans. Generator will have road access. Utilize crawl space under this room to achieve access to panel as necessary. Generator shall be capable of the following:
a. 1000kVA - 480V
b. 2 output breakers
i. 5-sets of 500 kcmil, or equivalent 2000A power cable, feeders from generator to existing main panel 'MS'.
1. Modify panel MS existing dead front panel to remove 2" section of material from panel face and install a rubberized windowed flap to protect temporary cables and personal.
ii. ( spare )
c. Feeder length up to 150 feet.
3. ATS #4 *temp*: served ATS #3 loads temporarily
a. New ATS #4 will be placed as a temporary feed for ATS #3 during phasing.
b. Place new 400A bypass-isolation ATS #4(temp) in temporary location shown, tight to existing ats gear. Provide 400A temporary feed from normal and generator feeds until relocation of new electrical gear is in place. Once final location of upstream gear is in place, provide permanent feed routed tight to ceiling to upstream source.
c. Demolish old ATS #3.
4. New switchboard 'MS' location prep:
a. Use floorsaw to cut new pathway in boundary indicated. Scan floor for conflicting MEP equipment and structural members prior to cutting prior to floor.
5. During planned outage to Building 1(D) normal branch, disconnect existing service feeders from existing 'MS' and connect new temp generator feeders.
a. Cutting over of normal branch power shall be performed during planned outages at predetermined time on nights/weekends. Contractor shall receive written
Construction Documents (CD) Submission consent from owner and provide notice 48 hours prior to outage before conducting work.
PHASE 2: NEW SWITCHBOARD 'MS', ATS #1, ATS #2
1. New main service switchboard 'MS':
a. Provide new switchboard with the following:
i. Type 2 switchboard (refer to specifications)
ii. 2000A mains
iii. GFP
iv. 16 outgoing breakers rated as follows: (1) 1200A CB, (1) 800A CB, (14)
400A CB
v. Refer to oneline diagram and panel schedule.
b. Provide new service feed from transformer T-9 at (5-sets) 500kcmil. Connect to new 'MS' and energize panel.
c. Cut over feed from old ‘MS’ to new ‘MS’ in new location.
2. Disconnect generator feed to old 'MS' and demolish old 'MS'.
3. ATS #1: provide new 1000A bypass-isolation ATS #1 in new permanent location shown, tight to existing ats gear. Provide permanent feed from new normal switchgear 'MS' and temp feed to old gen panel 'ES', routed tight to ceiling to upstream source.
4. Demolish old ATS #1.
5. ATS-2: provide new 100A bypass-isolation ATS #2 in new permanent location shown, tight to new ATS #1. Provide permanent feed from new normal switchgear 'MS' and temp feed to old gen panel 'ES', routed tight to ceiling to upstream source.
6. Demolish old ATS-#.
PHASE 3: ATS #3, ATS #4, ATS #5 AND 'ES'
1. New ATS #3: provide new 400A bypass-isolation ATS #3 in permanent location shown, tight to other ats. Provide permanent feed from normal and temp feed to old gen panel 'es', routed tight to ceiling to upstream source. Once powered, this will relieve temporary ATS #4 (*temp*).
2. Disconnect feeds to temporary ATS #4 (*temp*). Remove from this temporary location.
This ats is now to be relabeled and utilized as new 'ATS #4'
3. ATS #4: relocate new ATS #4 to permanent location shown, tight to other ats. Provide permanent feed from normal temp feed to old gen panel 'es', routed tight to ceiling to upstream source.
4. Demo old ATS #4 and associated cabling.
Construction Documents (CD) Submission
5. New ATS #5: provide new 400A bypass-isolation ATS #5 in permanent location shown, tight to other ats. Provide permanent feed from normal and temp feed to old gen panel 'ES', routed tight to ceiling to upstream source.
6. Demo old ATS #5 and associated cabling.
7. Old generator panel 'es': (generator and planned outage)
a. Provide temporary generator at approximate location indicated. Generator will have road access. Generator shall be capable of the following:
i. 1000kVA - 480V
ii. 2 output breakers
iii. 3-sets of 500 kcmil, or equivalent 1600A power cable, feeders from generator to existing panel 'ES'
iv. Downstream ats branch distribution panel (max single load = 1200A) during ats cut-over.
v. Feeder length up to 150 feet
b. During planned outage to Building 1(d) generator backed branched, disconnect existing generator feeders from existing 'es' and connect new temp generator feeders.
i. Cutting over of generator branch power shall be performed during planned outages at predetermined time on nights/weekends. Contractor shall receive written consent from owner and provide notice 48 hours prior to outage before conducting work.
8. New generator switchboard 'es': (planned outage)
a. Provide new switchboard with the following:
i. Type 2 switchboard (refer to specifications)
ii. 1600A mains
iii. GFA
iv. 8 outgoing breakers rated as follows: (1) 1200A CB, (1) 800A CB, (6) 400A
CB
b. Provide new feed from generator control cabinet in adjacent generator room at
(3-sets) 500kcmil to new 'ES' and energize panel.
c. Provide new feeds to new ATS #1,2,3,4,5 in their permanent location.
i. Conduct cut-over to each ats, one ats at a time, with planned outages to each ATS.
ii. Utilize temporary generator to power downstream ats branch distribution panel.
Construction Documents (CD) Submission
9. Disconnect generator feed to old 'ES' and demolish old 'ES'
PHASE 4: PAENL LSD, ED, ECBD
1. Provide new panel in location indicated. Provide new permanent feeder from upstream source ats as indicated on oneline diagram. Cutting over of generator branch power shall be performed during planned outages at predetermined time on nights/weekends.
Contractor shall receive written consent from owner and provide notice 48 hours prior to outage before conducting work. Provide new electrical panels as described in panel schedule for the following: LSD, ECBD, ED (Feed from ATS #1)
2. Demo old panel 'LSD', 'ED', and 'ECBD'.
BUILDING 1 ANCILLARY EQUIPMENT OUTAGE PLAN
PROVIDE THE FOLLOWING PHASED OUTAGE PLAN FOR THE BUILDING 1 PANELS LISTED
BELOW:
• Contractor shall replace equipment with new code-compliant equipment. Equipment shall be replaced in-place utilizing temporary means of power to facilitate removal and reinstallation of equipment in same location. New equipment shall be compliant with all nec codes and clearances. Provide update to equipment documentation. New equipment shall satisfy all specification requirements. New equipment shall meet or exceed AIC rating of existing equipment, relevant for, but not limited to; panelboards, distribution panels, switchboards, disconnect switches, ats's, transformers. New low voltage dry-type transformers shall match existing equipment impedance rating so as to not exceed short circuit current rating of existing-to-remain downstream equipment.
Refer to oneline diagram for transformer '%Z'.
1. Provide temporary electrical panel of equivalent voltage, and not less than rated amperage and short circuit current rating of existing panel. Install on temporary unistrut rail in vicinity of existing panel. Energize temp panel mains from temporary power source.
2. Provide VA with intent to cut over circuits fed from existing panel to temp panel. Obtain written confirmation of VA's approval to proceed with circuit outages.
3. One circuit at a time, cut over all circuits being fed from existing panel.
4. De-energize existing panel and demolish.
5. Provide new electrical panel in same place, following all required clearances.
6. Provide VA with intent to cut over circuits fed from temp panel to new panel. Obtain written confirmation of VA's approval to proceed with circuit outages.
Construction Documents (CD) Submission
7. One circuit at a time, cut over all circuits being fed from temp panel into permanent position on new panel.
8. Provide all panel documentation including:
a. Permanent label showing panel name, and 'fed from' source and location.
b. Updated panel schedule directory.
9. De-energize temp panel. Disassemble and relocate temp panel to next panel being replaced.
Construction Documents (CD) Submission
ELECTRICAL PANELS, TRANSFORMERS, AND SWITCHES:
PANEL BUILDING LEVEL AREA
B1 T-11 01 BASEMENT A
B1 XFMR L1R 01 FIRST D
B1 PNL EDP 01 BASEMENT A
B1 PNL L1 01 BASEMENT C
B1 PNL A 01 BASEMENT A
B1 PNL ESDB 01 BASEMENT B
B1 PNL ECBB 01 BASEMENT B
B1 PNL A3 01 BASEMENT C
B1 PNL ESBB 01 BASEMENT C
B1 PNL ECBD-5L 01 BASEMENT D
B1 PNL ECBD-5R 01 BASEMENT D
B1 PNL ECBD-2 01 BASEMENT D
EDA 01 BASEMENT D
B1 PNL ERA 01 BASEMENT D
B1 PNL ECBD-3R 01 BASEMENT D
B1 PNL ECBD-3L 01 BASEMENT D
B1 PNL ECBD-4 01 BASEMENT D
B1 PNL CBL 01 BASEMENT D
CBLB 01 BASEMENT D
CBD 01 BASEMENT D
B1 PNL MDC 01 FIRST C
B1 PNL AC-C1 01 FIRST C
B1 PNL M2 01 FIRST C
B1 PNL ES1B 01 FIRST B
B1 PNL ES1A 01 FIRST A
B1 PNL L1R 01 FIRST D
B1 PNL EC1D 01 FIRST D
B1 PNL MRR 01 FIRST D
B1 PNL CIL 01 FIRST D
B1 PNL CIR 01 FIRST D
B1 PNL L1L 01 FIRST D
B1 PNL EC1D-1 01 FIRST D
B1 PNL EC1D-2 01 FIRST D
B1 PNL XD 01 FIRST D
B1-PNL-NEW LAB PANEL 01 FIRST D
B1 PNL EC1D-3R 01 FIRST D
Construction Documents (CD) Submission
B1 PNL EC1D-3L 01 FIRST D
B1 PNL EEDP 01 SECOND A
B1 PNL AC-C2-2 01 SECOND C
B1 PNL 2IR 01 SECOND D
B1 PNL ELV 01 SECOND D
B1 PNL C2R 01 SECOND D
B1 PNL D-B 01 SECOND D
B1 PNL N3C 01 THIRD C
B1 PNL ES3C 01 THIRD C
B1 PNL T1 01 THIRD C
B1 PNL L-A 01 SIXTH C
Construction Documents (CD) Submission
BUILDING 3
Refer to Site and Building 3 drawings for additional information.
BUILDING 3 TRANSFORMER OUTAGE PLAN
PHASE 1: SITE PREPARATION
1. Maintain existing connection to Building 3 via sectionalizing switch ss-5 and t-6.
2. Install new cabling, conduit, ductbanks, and new transformer t-6.
3. Existing sectionalizing switch ss-5 has an open output. Connect to new transformer t-6.
4. Connect transformer t-6 secondaries to new 208v service entrance gear in Building 3.
PHASE 2: TRANSFORMER SWITCHOVER
1. Open ss-5 load switch to existing T-6.
2. Close ss-5 load switch to new T-6.
PHASE 3: TREANSFORMER DEMOLITION
1. Demolish existing cabling, conduit, ductbank, and transformer T-6.
BUILDING 3 MAIN ELECTRICAL ROOM EQUIPMENT OUTAGE PLAN
(DRAFT - OUTAGE PLAN TO COME)
BUILDING 3 ANCILLARY EQUIPMENT OUTAGE PLAN
PROVIDE THE FOLLOWING PHASED OUTAGE PLAN FOR THE BUILDING 3 PANELS LISTED
BELOW:
• Contractor shall replace equipment with new code-compliant equipment. Equipment shall be replaced in-place utilizing temporary means of power to facilitate removal and reinstallation of equipment in same location. New equipment shall be compliant with all nec codes and clearances. Provide update to equipment documentation. New equipment shall satisfy all specification requirements. New equipment shall meet or exceed AIC rating of existing equipment, relevant for, but not limited to; panelboards, distribution panels, switchboards, disconnect switches, ats's, transformers. New low voltage dry-type transformers shall match existing equipment impedance rating so as
Refer to oneline diagram for transformer '%z'.
Construction Documents (CD) Submission
1. Provide temporary electrical panel of equivalent voltage, and not less than rated amperage and short circuit current rating of existing panel. Install on temporary unistrut rail in vicinity of existing panel. Energize temp panel mains from temporary power source.
2. Provide VA with intent to cut over circuits fed from existing panel to temp panel. Obtain written confirmation of VA's approval to proceed with circuit outages.
3. One circuit at a time, cut over all circuits being fed from existing panel.
4. De-energize existing panel and demolish.
5. Provide new electrical panel in same place, following all required clearances.
6. Provide VA with intent to cut over circuits fed from temp panel to new panel. Obtain written confirmation of VA's approval to proceed with circuit outages.
7. One circuit at a time, cut over all circuits being fed from temp panel into permanent position on new panel.
8. Provide all panel documentation including:
9. Permanent label showing panel name, and 'fed from' source and location.
10. Updated panel schedule directory.
11. De-energize temp panel. Disassemble and relocate temp panel to next panel being replaced.
ELECTRICAL PANELS, TRANSFORMERS, AND SWITCHES:
PANEL BUILDING LEVEL AREA
B3 PNL M 03 BASEMENT -
MCB-SB-3 03 BASEMENT -
MCB-SB-3-SECT 1 03 BASEMENT -
B3 PNL W 03 BASEMENT -
DP 03 BASEMENT -
MIDP 03 BASEMENT -
B3 PNL KPPA 03 FIRST -
B3 PNL MCC 03 FIRST -
B3 PNL K3 03 SECOND -
B3 PNL K3A 03 SECOND -
B3 PNL K1A 03 SECOND -
B3 PNL K1B 03 SECOND -
B3 PNL ES32 03 SECOND -
B3 PNL EC32 03 SECOND -
Construction Documents (CD) Submission
BUILDING 35
Refer to site and Building 35 drawings for additional information.
BUILDING 35 OUTAGE PLAN
1. Building wide outage will be performed during predictably cold weather (winter) months.
2. Preparation shall take place to
3. Co/gen plant will be taken offline during this time. Contractor shall coordinate with utility provider (PWC) prior to taking distribution equipment offline.
BUILDING 35 ANCILLARY EQUIPMENT OUTAGE PLAN
PROVIDE THE FOLLOWING PHASED OUTAGE PLAN FOR THE BUILDING 3 PANELS LISTED
BELOW:
• Contractor shall replace equipment with new code-compliant equipment. Equipment shall be replaced in-place utilizing temporary means of power to facilitate removal and reinstallation of equipment in same location. New equipment shall be compliant with all nec codes and clearances. Provide update to equipment documentation. New equipment shall satisfy all specification requirements. New equipment shall meet or exceed AIC rating of existing equipment, relevant for, but not limited to; panelboards, distribution panels, switchboards, disconnect switches, ats's, transformers. New low voltage dry-type transformers shall match existing equipment impedance rating so as
Refer to oneline diagram for transformer '%Z'.
1. Provide temporary electrical panel of equivalent voltage, and not less than rated amperage and short circuit current rating of existing panel. Install on temporary unistrut rail in vicinity of existing panel. Energize temp panel mains from temporary power source.
2. Provide VA with intent to cut over circuits fed from existing panel to temp panel. Obtain written confirmation of VA's approval to proceed with circuit outages.
3. One circuit at a time, cut over all circuits being fed from existing panel.
4. De-energize existing panel and demolish.
5. Provide new electrical panel in same place, following all required clearances.
6. Provide VA with intent to cut over circuits fed from temp panel to new panel. Obtain written confirmation of VA's approval to proceed with circuit outages.
Construction Documents (CD) Submission
7. One circuit at a time, cut over all circuits being fed from temp panel into permanent position on new panel.
8. Provide all panel documentation including:
9. Permanent label showing panel name, and 'fed from' source and location.
10. Updated panel schedule directory.
11. De-energize temp panel. Disassemble and relocate temp panel to next panel being replaced.
ELECTRICAL PANELS, TRANSFORMERS, AND SWITCHES:
PANEL BUILDING LEVEL AREA
B35-PNL-SWBD 35 FIRST -
B35-MCC 35 FIRST -
CT #1 35 FIRST -
CT #2 35 FIRST -
CT #3 35 FIRST -
CT #4 35 FIRST -