Phasing Amendment Narrative.pdf
PDF 682 KB Posted
- Attached to
- N045--Replace Fire and Smoke Dampers Federal contract opportunity
- Solicitation number
- 36C24625B0002
About this file
This document is a phasing amendment narrative for the VA Asheville Replace Fire/Smoke Dampers Project (Project #21121). The project involves replacing fire and smoke dampers across multiple levels of a VA medical facility, with work strategically divided into four distinct phases (A, B, C, and D) based on specific building wing and chase configurations. Each phase will focus on different mechanical systems and duct work, with ground floor work designated as Phase A, and subsequent phases targeting south, east, and west wing chases.
Critical project details include specific requirements for work timing and location, with first-floor and Staff Room A272 work mandated to occur after hours. Mechanical sheets (47-M-200 through 47-M-206) have been updated to reflect phasing notes for levels 0-5 and the roof, detailing the precise scope and timing for each area. The project is part of VA solicitation 36C24625B0002 for the Asheville, NC VA Medical Center, overseen by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6, with a proposal request date of 03/06/2025.
View the file
Other files for this federal contract opportunity
Show all 32
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Proposal Request
Date: 03/06/2025
Project Name: VA Asheville Replace Fire/Smoke Dampers Project #: 21121
CPR#: 1
Description: Phasing notes were added to the mechanical sheets
Items: The mechanical sheets we modified to add phasing notes for the project. The project will be completed in four phases. The phasing hierarchy will be determined at the time of construction kickoff. All work completed on the ground floor will be phase A. All work on ducts entering and leaving the south wing chase will be phase B. All work on ducts entering and leaving the east wing chase will be phase C. All work on ducts entering and leaving the west wing chase will be phase D. All work done on the first floor shall be performed after hours. Preparation and ICRA barriers can be installed during normal work hours, however demolition and installation of new dampers shall be done after hours. The work in Staff Room A272 shall have the same after hours requirements as the first floor.
1. Sheet 47-M-200 – Level 0 – Mechanical – New Floor Plan
A. Added notes for phase A on the ground floor.
2. Sheet 47-M-201 – Level 1 – Mechanical – New Floor Plan
A. Added notes for the phasing of each of the wings. Added notes regarding the after hours requirements for the work.
3. Sheet 47-M-202 – Level 2 – Mechanical – New Floor Plan
A. Added notes for the phasing of each of the wings. Added notes regarding the after hours requirements for the work in the staff room.
4. Sheet 47-M-203 – Level 3 – Mechanical – New Floor Plan
A. Added notes for the phasing of each of the wings.
5. Sheet 47-M-204 – Level 4 – Mechanical – New Floor Plan
A. Added notes for the phasing of each of the wings.
6. Sheet 47-M-205 – Level 5 – Mechanical – New Floor Plan
A. Added notes for the phasing of each of the wings.
7. Sheet 47-M-206 – Level Roof – Mechanical – New Floor Plan
A. Added notes for phase B in the penthouse.
If any portion of this instruction involves an increase or decrease in contract price, scope, and/or schedule do not proceed with work without submitting a written change order request and receiving written instruction to proceed.
Submitted By: Nick Cesmat www.specializedeng.com
Phasing Amendment