This document is an amendment to a solicitation for the renovation of a welcome center. The Department of Veterans Affairs is seeking to remove hazardous materials such as transite cement, pipe insulation, and metal stud walls at the exterior of the building. Bidders must price the removal of 512 square feet of transite behind radiators and 680 linear feet of pipe insulation. The site superintendent may also serve as quality control manager. The amendment provides responses to 30 questions from vendors to clarify the scope of work, which includes renovations to both interior and exterior walls. The bid due date remains unchanged. Bidders must acknowledge any amendments in their submissions.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 2

09-14-2023

565-20-203

Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667

Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667

To all Offerors/Bidders

36C24623B0061

08-02-2023

X

X X

X

The purpose of this Amendment is to provide Government responses to all Follow-Up Questions received from Vendors.

1. See the following pages for all Government responses. Questions and responses are numbered to continue from Amendment 0001. There are a total of 30 numbered questions and responses.

2. The due date and time for receipt of bids remains unchanged.

3. Please acknowledge this and any other Amendments to this solicitation by completing Block 18 of the SF 1442 on your submitted offer.

Daniel Dove Contracting Officer

36C24623B0061 – Renovation of Welcome Center Amendment 0002 - Responses to Follow-Up Vendor Questions (NOTE: Question Numbering continued from Amendment 0001)

25. Follow up on Response for Questions 6 and 7 from Amendment 0001: Question #7 response states that 2 full time Supervisors are not allowed to serve the roles of Superintendent, SSHO, and QCM which would imply the project requires (3) full time people on site. If this is the intent, please make this clear so that all bidders include this cost as it is a significant amount to add a person to the staff full time for the duration of the project.

Response: Site Superintendent can also be the Quality Control Manager, but the SSHO shall only have that one duty. If someone is a site superintendent whose qualifications meet requirements to be a SSHO, this would be acceptable for the SSHO position.

26. Follow up on the response to Question 16 from Amendment 0001:

a) The full hazmat report lists 512 SF of transite cement behind 32 radiators, but the table in the specifications is listing 256 SF at 32 radiators. Please confirm the amount we should figure for pricing.

Response: Use 512 square feet quantity.

b) Also, the full hazmat report lists approximately 680 LF of pipe insulation at exterior walls.

Has this material already been removed or are we figuring this as well?

Response: This has not been removed and is included in this project to be removed.

27. Please confirm that the Flow Control Device shown on Detail 4 of P-002 is needed for the hot water recirculation line.

Response: A flow control device should be anticipated for the hot water recirculation system. Also, for this project, assume one is currently installed balancing the system and an additional one is needed.

28. Follow up on the response to Question 13 from Amendment 0001: Is it possible to get an approximate routing distance to the switchboard from the work area?

Response: The switchboard referenced in Question 13 is located in Building #44. Building #44 is shown on the Electrical Partial Site Plan (EP-1-B-02) where the approximate routing distance can be determined by bidders.

29. Follow up on the response to Question 14 from Amendment 0001: Thank you for confirming all interior partitions are to be addressed as key note DE1 [unless noted otherwise].

Assuming key note DE28 is to be addressed as shown on the drawings at the exterior walls, please confirm that we should figure that none of these metal studs at the exterior wall are structurally significant to the brick.

Response: Metal Studs at the exterior wall are not Structurally Significant to the exterior wall system.

30. For the response to Question 14 from Amendment 0001, we are confused as to why Brick was mentioned in the response. We want to make sure the demo of the exterior Metal Stud wall and finishes is only referring to demo of the furred-out section of the exterior wall and not the actual Metal framing that is between the exterior windows that may have exterior sheathing and brick ties tied to it. The demo drawings appear to show a wall directly in front of the exterior wall which we assume to be metal stud furring.

Response: Interior furring is to be removed in its entirety. See the response to Question 29 above. Existing wall construction is a multi wythe brick, or stone wall system. Approximately sixty percent of the walls to be demolished must be assumed to be constructed of masonry floor to deck with metal stud/gypsum firring.