About this file

This is a Solicitation (Standard Form 1442) for a construction services project to replace the Cardiac Cath Lab at the Washington DC Veterans Affairs Medical Center. The solicitation (No. 36C24525R0080) is exclusively set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) and seeks a contractor to perform interior renovations of approximately 2,200 square feet within the A Wing, 4th Floor of Building 1. The project involves selective demolition, architectural, structural, mechanical, electrical, and plumbing system renovations, with an estimated construction cost between $2,000,000 and $5,000,000.

Key details include a 240-calendar day performance period from Notice to Proceed, a site visit scheduled for July 16th, 2025, and request for information (RFI) submissions due by July 22nd, 2025. Proposals are due by 10:00 hrs EST on August 29th, 2025, and must include two sections: technical documentation with past performance questionnaire and a detailed itemized pricing breakdown. Contractors must be registered in SAM.gov and veterans.certify.sba.gov, with joint ventures allowed if meeting specific requirements. The project involves asbestos abatement and coordination with existing building systems under service contracts with Johnson Controls and Siemens.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C24525R0080 X 06-17-2025

TBD

TBD

688-CSI-013

Department of Veterans Affairs

VAMC (613)

VISN 5 Contract Satellite Office 510 Butler Avenue, Building 306A Martinsburg

WV

25405 Liana J Holland Contracting Officer Department of Veterans Affairs 510 Butler Avenue Martinsburg

WV

25405 Liana J Holland No Phone Calls, Email only IMPORTANT NOTE: Award is subject to the availability of FY 2026 funds.

This construction project is to provide Construction Services necessary for the Cardiac Cath Lab Replacement, Room 4A124 at the Veteran’s Affairs Medical Center in Washington DC (VAMCDC) located at 50 Irving Street, N.W., Washington DC 20422.

The contractor to provide a proposal to include all the necessary materials, labor, and equipment to complete all required construction work within all documented areas. Work consists of interior renovations of approximately 2,200 square feet, within the A Wing, 4th Floor in Building 1 of VAMCDC, according to Contract Documents (Drawings and Specifications) dated 05/20/2025.

The NAICS code for this procurement is 236220 [Commercial and Institutional Building Construction], size standard $45.0 million.

Magnitude of Construction is between $2,000,000 and $5,000,000.

Competition for this procurement is restricted to SERVICE-DISABLED VETERAN OWNED SMALL BUSINESS (SDVOSB).

All contractors are required to be registered with http://www.sam.gov, and registered with https://veterans.certify.sba.gov/ in accordance with 38 CFR Part 74 and VAAR 819.7003 to be eligible for award.

Note for Joint Venture (JV) Offerors: In accordance with VAAR 852.219-73(f) joint ventures may be eligible so long as the joint venture meets the requirements of 13 C.F.R. 128.402. In order to comply with 13 C.F.R. 128.402(e) JV offerors must include in their Volume I a certification, signed by an authorized official of each partner to the joint venture, stating that the parties to the joint venture (1) have entered into a joint venture agreement that fully complies with paragraph (c) of 13 CFR § 128.402 and (2) will perform the contract in compliance with the joint venture agreement.

Failure to submit the certification will render the offeror ineligible for award.

A highly-recommended site visit is scheduled for Wednesday July 16th, 2025, at 10:00hrs EST; Prospective bidders will meet at 10:00am in the Main Atrium / Lobby of the Washington DC VAMC located at 50 Irving Street, N.W., Washington DC 20422.

RFI's must be sent via email only to the Contracting Officer Liana Holland (Liana.Holland@va.gov) by no later than 10:00am on Tuesday July 22nd, 2025.

All interested parties should submit one package containing two (2) complete sections to the Contracting Officer via email (Liana.Holland@va.gov) by no later than 10:00hrs EST on Friday August 29th, 2025. Section number 1 will contain requested documentation for the technical evaluation including the Past Performance Questionnaire. Section number 2 will contain the detailed itemized pricing breakdown, including all subcontractors. The Evaluation Criteria lists how each section will be scored. Failure to provide both sections could render the package incomplete and ineligible for award. The Period of Performance is expected to be 240 days from the Notice to Proceed.

X X 52.211-10 X 10:00

EDT

08-29-2025 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

Department of Veterans Affairs

VAMC (613)

VISN 5 Contract Satellite Office 510 Butler Avenue, Building 308B Martinsburg

WV

25405

PAYMENT WILL BE MADE BY

FSC e-Invoice Payment Invoice must be submitted electronically http://www.fsc.va.gov/einvoice.asp http://www.fsc.va.gov/einvoice.asp

Liana J Holland

VA-VHA-RPOE-2025-0010

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 STATEMENT OF WORK5
A.4 EVALUATION CRITERIA28
A.5 CHECKLIST31
A.6 PRICE/COST SCHEDULE32
ITEM INFORMATION32
A.7 DELIVERY SCHEDULE32
A.8 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)33
A.9 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2025) (DEVIATION FEB 2025)33
A.10 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021)37
A.11 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)39
A.12 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)40
A.13 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)42
A.14 52.216-1 TYPE OF CONTRACT (APR 1984)43
A.15 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)43
A.16 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)43
A.17 52.223-21 FOAMS (MAY 2024)43
A.18 52.223-20 AEROSOLS (MAY 2024)44
A.19 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)45
A.20 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)50
A.21 52.232-19 AVAILABILITY OF FUNDS FOR THE NEXT FISCAL YEAR (APR 1984)51
A.22 52.233-2 SERVICE OF PROTEST (SEP 2006)51
A.23 52.236-4 PHYSICAL DATA (APR 1984)51
A.24 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)52
A.25 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)53
A.26 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)53
A.27 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)53
A.28 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)53
A.29 SUPPLEMENTAL INSURANCE REQUIREMENTS57
A.30 IT CONTRACT SECURITY57
A.31 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)67
A.32 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)69
A.33 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)69
A.34 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE (JAN 2008)69

A.3 STATEMENT OF WORK

Washington DC VAMC 50 Irving Street, N.W.

Washington DC 20422

STATEMENT OF WORK (SOW)

CARDIAC CATH LAB REPLACEMENT ROOM 4A124

PROJECT # 688-CSI-013

1. CONTRACTING OFFICER’S INFORMATION (CO).

Name:
Liana J Holland
Department:
Contracting Office, NCO 5
Address:
501 Butler Avenue, Martinsburg WV 25405
E-Mail Address:
Liana.Holland@va.gov

2. CONTRACT TITLE.

Cardiac Cath Lab Replacement Room 4a124

3. DEFINITIONS:

a. VA: Veterans Affairs.

b. COR: Contracting Officers Representative. VA employee of VAMC Facilities and Engineering Service officially assigned to act as a Project Manager and Inspector on behalf of VAMC and the Contracting Officer. COR shall be “First Point of Contact” on all matters concerning contract work for subject Project.

c. DCMR: District of Columbia Municipal Regulations

d. DOEE: Washington, D.C.’s Department of Energy and Environment

e. ICRA: Infection Control Risk Assessment. An ICRA form must be filled out and signed by Infection Control personnel prior to any work – coordinate with COR.

f. ILSM: Interim Life Safety Measures. Any series of Operational Actions taken to temporarily reduce hazards posed by Life Safety deficiencies which have been created by demolition, renovation, or construction works, and which are to remain in place and in effect for duration of Contract work.

g. NFPA-NFC: National Fire Protection Association – National Fire Codes.

h. NEPA; National Environmental Protection Act. An environmental law that requires all federal agencies to prepare environmental assessments (EAs) and environmental impacts statements (EISs) on any major construction project.

i. NEC: National Electrical Code, NFPA – NFC Standard 70

j. SDS: Safety Data Sheets.

k. SWMP: Storm Water Management Plan.

l. PROVIDE: Whenever used throughout the Scope of Work, term “Provide” is to be understood to mean – Purchase newly manufactured; Furnish delivered to VAMC work site in protective containers; Secure from tampering or theft; and Install in accordance with Contract Scope of Work, Drawings, Specifications and Manufacturer’s Instructions all required items of administrative submittals, labor, demolition, construction, equipment items, and installation works for entirety of Contract.

m. CONTRACT DOCUMENTS: Construction Drawings and Specifications distributed to bidders in hard copy or electronic format.

n. SIMILAR IN SCOPE: High-Cost High Tech construction projects.

o. SIMILAR IN SIZE: Meet the limits of the magnitude of projected construction costs or exceed the upper limit identified in the solicitation.

4. SCOPE.

The purpose of this project is to provide Construction Services necessary for the Cardiac Cath Lab Replacement, Room 4A124 at the Veteran’s Affairs Medical Center in Washington DC (VAMCDC) located at 50 Irving Street, N.W. Washington D.C. 20422.

Contractor to provide a proposal to include all the necessary materials, labor, and equipment to complete all required construction work within all documented areas. Work consists of interior renovations of approximately 2,200 square feet, within the A Wing, 4th Floor in Building 1 of VAMCDC, according to Contract Documents (Drawings and Specifications) dated 05/20/2025.

The work includes but it is not limited to selective demolition, interior Architectural, Structural, Mechanical, Electrical and Plumbing systems, renovation of existing flooring, ceiling, wall finishes and related Mechanical, Electrical and Plumbing work necessary for a complete renovation. The Contractor shall also coordinate the installation of all systems or items that in the Contract Documents are required to be installed “by others”.

The proposal shall include all costs for construction activities that may be performed, including work during non-clinical hours (evenings, nights, and weekends) to minimize impact to patients. Work shall be performed during normal working hours, unless requested by the COR and/or approved by the Contracting Officer.

The Medical center will be operational during construction work and the Contractor shall provide a Safety/Infection Control Plan submittal for approval.

Additional modifications of existing building areas, where required by Contract Documents, shall be included to support the construction project.

Construction phasing is required per Contract Documents. Phasing should be coordinated, and approval must be provided by the CO/COR.

Staging and laydown areas will be finalized between the contractor and the VAMC. For any offsite, project specific, stored materials that the contractor is invoicing due to unexpected extensive government delays, the location must be pre-approved in writing by the Contracting Officer, with access to allow for onsite inspection by the COR. The invoice must include the following support documentation: Bill of Material, Paid Material Invoice copy, and Insurance Certificate for the materials stored at the stored location.

Asbestos abatement is a requirement of this contract, and it is included in the scope of work per Contract Documents. The Contractor is required to submit an Abatement Plan.

The Physical Access Control System shall be an extension of the existing Johnson Controls system. This system is under a service contract with Johnson Controls (POC: Mark Bradford. Tel: 571-287-1333. Email: Mark.K.Bradford@jci.com).

Direct Digital Control for the HVAC System and the Fire Detection and Alarm System shall be an extension of the existing SIEMENS system and is under service contract with SIEMENS Industries. (POC: Kevin Kidwell Tel: 301 837-2828. Email: kevinkidwell@siemens.com).

The existing warranty and service contract in-place, for the above-described systems shall be maintained and not voided by work performed under this project.

It is the responsibility of the Contractor to conduct site visits, verify existing conditions, quantities of materials, installation instructions of materials to be used, and discrepancies or conflicting requirements in the Statement of Work and/or Contract Documents before preparing the Final Proposal. Contract Documents (Construction Drawings and Specifications) take precedence and will govern other distributed documents if any conflicts arise. Notify COR immediately for such discrepancies and/or conflicts.

The Construction Progress Schedule/CPM schedule, Submittal Schedule, Cost Progress Schedule, Accident Prevention Plan, Life Safety Plan, QC Plan, ICRA, Preconstruction Checklist and Security Requirements documents for Badging shall be submitted for evaluation/approval before NTP is issued and within thirty (30) calendar days of receipt of Notice of Award, unless otherwise directed from Contracting Officer. The starting date of the schedule shall be the date the contractor receives the "Notice to Proceed". At a minimum, both the starting and ending dates shall be indicated on this schedule. The Construction Progress Schedule/ CPM schedule must include vendor lead times and all schedules to be updated when changes occur.

The Cost Progress Schedule shall indicate the anticipated installation of work for each activity, including phasing, and be approved from the contracting officer. The actual percentage completion will be based on the value of installed work divided by the current contract amount. The actual completion percentage will be indicated in the monthly progress report.

The Contractor shall also provide a 24”x36” construction sign attached to the entry of the construction site. The sign may contain a picture of the completed project in addition to other pertinent information like the A/E’s and Contractor’s name, Project Cost, Start Date, End Date, etc. Coordinate the sign requirements with the COR. See Attachment 1 for more information.

5. PERFORMANCE MONITORING

The contractor’s performance will be monitored by the Contracting Officer, Infection Control Risk Assessment Office, as well as the Safety Office during the contract period. The Contracting Officer will review the materials, workmanship, certification and expertise of the contractor and their sub-contractors to verify they are in compliance with the drawings/specifications of the contract documents and Construction Schedule. Non-compliance with specifications and drawings without prior written approval will require replacement to meet the contract documents at the contractor’s expense.

Coordinate all administrative and construction requirements exclusively with or through assigned Contracting Officer Representative (COR).

The Safety Office will review the operations and site construction conditions of the project to confirm that all Safety regulations relating to construction and healthcare facilities are being adhered to. Non-compliance may result in a job site shut down until compliance is met at the contractor’s expense.

The contractor shall furnish to the COR each day a consolidated report for the preceding workday in which is shown the number of laborers, mechanics, foremen/forewomen and pieces of heavy equipment used or employed by the contractor and subcontractors. The report shall bear the name of the firm, the branch of work which they perform such as concrete, plastering, masonry, plumbing, sheet metal work, etc. The report shall give a breakdown of employees by crafts, location where employed, and work performed. The report shall also list materials delivered to the site on the date covered by the report.

Contractor will submit their Daily Report form to the COR with an electronic copy to the Contracting Officer for approval, prior to construction beginning.

6. SECURITY REQUIREMENTS.

The contractor will not require access to confidential systems. The security requirements and impact for this project have been identified in VA Handbook 6500.6 Appendix A. The C&A (Certification and Accreditation) requirements do not apply, and a Security Accreditation Package is not required.

Upon receipt of the Notice of Award and prior to attending the pre-construction conference where NTP will be issued, the successful bidder shall have submitted the Security Requirements documents. This process includes the completion and submission of Background Investigation Request Worksheet to the VHA Service Center Personnel Security Office. Each contract employee is required to undergo a Special Agreement Check (SAC) background investigation which equates to being fingerprinted.

Upon successful completion of fingerprinting, all contract employees will be required to obtain a non-Personal Identity Verification (non-PIV) badge. Contractor staff working on site will be required to wear the badges at all times while on site. Contractors will be required to immediately notify the Contracting Officer of any changes in staff performing work on site. Upon completion of the contract all identification badges must be returned to the Contracting Officer before final payment can be made. See attached Security Package for more information.

7. PERIOD OF PERFORMANCE.

The construction period for this project is 240 calendar days from Notice to Proceed (NTP) barring any unforeseen incidents with inclement weather.

8. DELIVERY SCHEDULE.

SOW Task#
Deliverable Title
Format
Number
Calendar Days After CO Start
1
Daily Reports
Contractor-Determined Format/COR Approved
1 copy
Daily
2
Status Report/Meeting
Contractor-Determined Format/COR Approved
1 Copy to COR; 1 copy to CO
Weekly
3
Project Schedules
Contractor-Determined Format/COR Approved
1 Copy
Monthly
3
Submittals/Samples
Per Specifications
Per Specifications
Per Specifications
3
Construction Photos
Contractor-Determined Format/COR Approved
1 copy
Monthly
4
As-Built Drawings
Per Specifications
Per Specifications
14 Days after Completion

9. SUBMITTAL REQUIREMENTS.

The Contractor shall furnish to the Contracting Officer, for his/her approval, an electronic, PDF version of all shop drawings, product data, Safety Data Sheets (SDS), and catalogue cuts, of all equipment furnished under this contract, before purchase, manufacture or construction. The Contracting Officer will examine these submittals, and one copy will be returned to the Contractor if approved or require correction.

It is the responsibility of the Contractor to set up a FTP site that complies with VA requirements, like PROCORE or NEWFORMA, to publish the required information like submittals, shop drawings, RFIs, cut sheets, etc.

The Contracting Officer shall return the submittals approved or disapproved within 14 calendar days after receipt.

Warranties and operating instructions are required at the completion of the Contract work per Specifications.

10. SAFETY PRECAUTIONS.

a. The Contractor shall comply with all applicable Federal, State and Local legal requirements regarding workers health and safety. The requirements include, but are not limited to, NFPA, EPA, and those found in Federal and State Occupational Safety and Health Act (OSHA) statutes and regulations, such as applicable provision of Title 29, Code of Federal Regulations (CFR) Parts 1910 and 1926. Contractor is solely responsible for following/complying with the legal requirements that apply to activities and shall ensure safe and healthful working conditions for its employees.

b. Contractor shall assume the responsibility to guard against causing fires and/or explosions and to protect Government Property, reference NFPA 241 and OSHA 29 CFR 1926.

c. Follow Interim Life Safety Measures (ILSM). Any series of Operational Actions taken to temporarily reduce hazards posed by Life Safety deficiencies which have been created by demolition, renovation, or construction works, and which are to remain in place and in effect for duration of Contract work. Provide interim life safety measures (ILSM) where fire protection, fire suppression and/or smoke/fire partitions will be shut down or rendered ineffective during construction. Coordinate with the VA safety Office through COR. ILSM must be posted outside work area at all times.

d. The Contractor shall perform the work in a manner consistent with the area security and fire safety regulations especially with regard to exits and exit way access. All utility shutdowns shall be coordinated through the COR and not compromise security, communication or fire safety for occupants.

e. All construction fire barriers that separate the construction area from the rest of the Medical Center to be 1-hour rated. Once all 1-hour construction fire barriers are in place, Safety & Infection Control will inspect with the CO/COR to ensure all protective measures are in place to start. After all Safety, Infection Control, Security, and other things are in place a “Pre-Construction Checklist Assessment” will be signed by Safety, Infection Control, and COR. Then the document shall be posted outside of the main entrance door throughout the duration of the project.

f. The necessary number and appropriate types of portable fire extinguishers are required per National Fire Protection Association (NFPA) 10 and NFPA 41 must be provided and be operational.

g. The Contractor must obtain a burn permit from VA Safety Office thru the COR prior to any cutting, welding, brazing, grinding, and soldering. All permits shall be prominently displayed outside of the entrance door(s) during all construction.

h. The Contractor shall notify the COR of any Utility Outages, and a Utility Outage request must be completed by FMS prior to taking any Utilities out of service. Contractor shall allow ample time for FMS to coordinate and schedule such events.

i. All necessary precautions shall be taken by the contractor to prevent activation of any existing smoke detectors or sprinkler heads.

j. The Contractor shall at all times keep the work area free from accumulation of waste materials. Contractor is responsible for the removal of all materials and debris from the premises utilizing Contractor’s waste bin under the guidance of state, federal, and local laws and regulations. Use of owner’s waste bins is prohibited. Upon completing construction, the Contractor shall remove all temporary facilities and leave the project site in a clean and orderly condition acceptable to the COR.

k. Any repair of damage caused as a result of this project will be the responsibility of the Contractor.

l. General Requirements For Abatements

1. The Contractor shall provide a quantity of construction personnel, equipment, materials, tools and supervision as needed to complete the services and technical requirements in the Statement of Work (SOW). It is expected that the Contractor shall partner closely with facility personnel to verify asbestos containing material, lead paint, mold, etc. All abatements will be coordinated, requested, and vetted through the facility Safety Office.

2. The Contractor must be approved by applicable authorities to provide abatement services in the District of Columbia. All work and disposal shall be done according to state, federal and local laws and regulations.

3. The Contractor shall designate and make available a representative to meet with the Contracting Officer’s Representative (COR) weekly or a previously agreed upon alternative schedule to discuss the Progress Report, or other matters pertaining to the project. The contractor shall follow up all telephone conversations affecting the scope of work with an email summary of the conversation sent to the COR.

4. The Contractor shall NOT conduct any work that is beyond this Statement of Work unless directed in writing by the CO. Any work done by the Contractor beyond this SOW without direction from the Contracting Officer (CO) will be at the Contractor’s own risk and at no cost to the Washington D.C. Veteran Affairs Medical Center or U.S. Government.

5. The Contractor shall prepare and maintain a Project Schedule and Abatement Plan to address the cost and schedule for the project. The Project Schedule and Abatement Plan is intended to document the entire project from beginning to end.

6. Any cost associated with services subcontracted by the Contractor shall be borne by and be the complete responsibility of the Contractor under this contract.

7. The Contractor shall survey the facility areas where construction will take place with the facility designated subject matter expert and become thoroughly familiarized with the existing conditions and conditions that will affect the construction. The Contractor will coordinate verification of existing conditions and conditions that affect the abatement by properly vetting the hazards through the designated facility subject matter expert.

8. The Contractor shall ascertain all local permit requirements, licensing requirements, and the quality and availability of materials, sub-contractors, and equipment that may be needed to execute the contract.

9. The Contractor shall inspect and evaluate all available drawings and reports pertaining to the project. The Contractor shall field verify all dimensions for construction relevant to the project.

10. All materials and equipment incorporated into the project shall be brand new. The Contractor shall transport and safeguard all materials and equipment required for construction as instructed by the manufacturer’s instructions. The contractor shall include all transportation and installation costs in the bid price.

11. The Contractor shall maintain continuous usage of approved existing systems during construction, including providing temporary cooling units if necessary. Request must be listed in the Abatement Plan and approved in writing by the facility designated subject matter expert

12. Deliverables to accompany completion of construction: The Contractor shall provide one copy of proof of proper disposal of hazardous materials to COR.

13. It is the responsibility of the Contractor to submit a written abatement plan that list at a minimum the site specifics like:

· Brief description of the estimated quantities of asbestos containing materials to be abated (for example 10 linear meters (feet) of <50 mm (2") diameter pipe insulation).

· Description of removal procedures for ACM that includes description of removal procedures of contaminated soil (if applicable).

· Description of encapsulation procedures for ACM and description of disposal of ACM waste/equipment procedures.

· Security & Safety procedures that includes an Emergency Action Plan/ Contingency plans and arrangements. Regulated Area Decontamination/Clean –up procedures.

· List of personnel identifying their assigned roles including an identified qualified competent person(s) in 30-hour OSHA construction safety course and all personnel must obtain 10-hour OSHA Construction safety course certificate. Include a copy of their most recent certificate as verification.

· Asbestos training (i.e. EPA/AHERA Asbestos Inspector, EPA/AHERA Supervisor, EPA/AHERA Worker, Collecting & Analyzing Air Samples - NIOSH 582 equivalent etc.).

· Letter on company letterhead, identifying the Respiratory Protection Program Coordinator (RPPC).

· The RPPC must submit a signed statement attesting to the fact that the program meets the retirements of 29 CFR 1926.1101 and 29 CFR 1910.134 subpart I or Submit a copy of company of the company Respiratory Protection Program.

· The Contractor must provide a list of personnel that will perform abatement services and provide a current Respirator Fit test Record of employee, Medical written opinion, proof of Respiratory Protection Training,

· A List of equipment that will be used to perform abatement services. If the items are rentals, include rental company information. Include maintenance procedures.

· The Contractor must provide a Decontamination Facilities set-up/layout, using a CAD diagram provided by the facility indicating where the decontamination chamber will be placed and the dimensions of the chambers. Decontamination entry/Exit procedures must include negative pressure systems requirement that include a digital monometer.

11. INFECTION CONTROL RISK ASSESSMENT.

a. Follow all Infection Control Risk Assessment (ICRA) guidelines for dust control during all construction work. A construction dust “Risk Assessment” will be conducted by the Medical Center’s Infection Control Personnel. Temporary “dust” barriers will be installed based on this assessment. Bi-weekly inspections of barriers and work areas will be conducted by Infection Control Personnel, Safety Manager, and COR to enforce implementation of risk assessment.

b. Contractors shall provide negative air pressure controlled with digital manometer and dust partitions in all areas of work to prevent dust from getting into patient and employee occupied areas.

Digital Manometer - Omniguard 6 Differential Pressure Monitor Particulate Monitor - Waporich T7-TC-8200 Particle Counter

All ventilation ducts shall be capped, and any used ducts shall be approved by FMS HVAC Shop to ensure proper duct work is utilized correctly.

12. HAZARDOUS MATERIAL REPORTING.

a. The Contractor shall maintain hazardous inventories and safety data sheets (SDS) for all hazardous materials (as defined in CFR 1910.120, 40 CFR’s 355, 370, & 372) to be stored on the construction site, and used at this Medical Center. Hazardous materials must be inventoried when received and when the project is completed.

b. Hazardous Materials Inventories, Safety Data Sheets and Material Quantities used shall be submitted to the Contracting Officer, COR, and the Safety Office for approval.

c. In the event of a spill, Contractor shall immediately notify the COR as well as the Contracting Officer. The Contractor shall be solely responsible for the expense of any cleanup of such spill, and the cleanup shall be in accordance with the applicable provision of 40 CFR Part 761.

d. Comply with EPA, OSHA, DOEE, VHA construction safety, and VHA Master Specification requirements for demolition of structures. Comply with EPA, DOEE, and VHA requirements for proper handling (such as bagging, sealing and recycling) Mercury-Containing Devices (may include but are not limited to thermometers, manometers, pressure stats, gauges, float or level controls, load meters, supply relays, phase splitters, and sink traps) per 40 CFR 273, and Title 20 DCMR.

e. All hazardous waste expected as a result of renovation, demolition or construction activities (including but not limited to mercury-containing, fluorescent bulbs, electrical devices that contain PCBs) must be properly managed and disposed in accordance with EPA’s 40 CFR 262, -The contractor is solely responsible for filling out and signing any hazardous (or non-hazardous waste) manifest for waste generated on the construction site. The contractor must use their own company’s EPA ID number. All hazardous waste transported off the medical campus will be packed in suitable containers and must have a label that is in compliance with DOT 49 CF 173.

f. In a hospital setting, mercury is commonly found in sink traps. Proper caution and use of Personal Protective Equipment (PPE) should be practiced when dismantling sinks which may contain mercury. Material should be collected and properly disposed of or recycled at the expense of the contractor. Records of proper disposal should be submitted to the COR and maintained in the projects file.

g. In accordance with EPA’s 40 CFR and DOEE’s 20 DCMR, the contractor as the generator of the waste is responsible for filling out, and signing any hazardous or non-hazardous waste manifests, and they will use their own EPA ID number. Copies of waste manifest shall be submitted to the COR.

h. All hazardous chemicals that need to remain at the job site must be stored and handled from VA in accordance with EPA and DOEE requirements.

13. ENVIRONMENTAL PROTECTION.

In order to provide for abatement and control of all environmentally hazardous materials arising from demolition and/or construction activities, the Contractor shall comply with all applicable environmentally hazardous material control and abatement and all applicable provisions of EPA, and the facility’s construction safety policy as well as the specific requirements stated elsewhere in the Contract Documents.

All hazardous and universal waste resulting from contractor demolition and construction shall be removed and properly disposed of in accordance with 40 CFR 261 through 265, 40 CFR 273 and 40 CFR 279. Also, 20 DCMR 261 through 265, 273, and 279 by the contractor at no additional cost to the VA. This will include the disposal of ballasts, fluorescent bulbs, used oil, mercury switches and any hazardous material. Copies of disposal manifests must be provided to the COR. Contractor must comply with Federal Executive Order 13693 and project specifications by developing a waste management plan to divert the demolition debris from the solid waste stream.

14. CONSTRUCTION REQUIREMENTS.

a. Complete a Pre-Construction Checklist with Safety, Infection Control, and COR.

b. Provide daily on-site Superintendent or General Foreman to coordinate all building trades and provide liaison for the COR and Contracting Officer. General Foreman will be designated and be on-site at all times.

c. All equipment and materials shall be approved by the COR or Contracting Officer prior to being brought onto the job site.

d. Provide and install BEST, 7-pin, Interchangeable Core, Small Format, Lockset to all construction temporary doors. VA will pin and install cores. Coordinate with COR.

e. When using special keys for access to roof, mechanical and electrical areas, doors must be kept closed and locked while in such spaces.

f. OSHA and VA CONSTRUCTION SAFETY STANDARDS will be enforced. The contractor must have completed the 30-hour OSHA Construction Safety course.

g. The Contractor, subcontractors, suppliers, or anyone else employed by the contractor cannot park in the VA premises.

h. Contractors will maintain their own dumpster at an approved location for removal of waste materials.

i. Utility services will not be disrupted without prior approval. It is anticipated that the existing utilities will be adequate for any new service, addition and/or remediation of the areas is not included unless otherwise specified in this Scope of Work or Contract Documents.

j. Where cutting of existing surfaces or removal of existing finishes is required to perform the work under this contract, fill resulting openings, patch the surface and finish to match the adjacent existing surfaces. Holes, penetrations and other openings caused by the demolition or new construction shall be filled with approved fire stopping material. Catalog data on all fire stopping material to be used shall be submitted to the Contracting Officer Representative (COR) for review and approval prior to installation.

k. Do not disturb any wiring whose origin, function or utility are unknown without prior approval from the Contracting Officer Representative (COR).

l. The contractor shall protect and maintain all items indicated to be reused.

m. The Contractor shall repair or replace any damage to the existing conditions caused by his actions. Repair and replacement of damaged conditions shall match the integrity of the adjacent area. All required work shall be provided at no additional cost to the Government.

n. The Contractor shall be responsible for all final paint and touch-up work which shall be completed after the installation of all systems and components.

o. The medical center facility (VAMCDC) will be occupied and functioning operational during construction. Each phase of construction will need to be coordinated with the COR to determine the acceptable hours of construction. Protect patients, government property, personnel and visitors at all times.

p. Work is to be performed so as not interfere with patient access at any time.

q. All construction work and installed equipment and any Installation shall be warranted for a period of at least one (1) year from Substantial Completion approved date unless noted otherwise in individual Specification Sections. Substantial Completion shall be identified at such a time that all Close Out deliverables (as described in Specifications) are provided and accepted by the COR or Contracting Officer.

15. ACQUISITION CONSIDERATION.

The Government will utilize the Best Value - Trade Off source selection method. Award selection will be based on the proposals evaluated with the highest ranking received from the evaluation of the technical factors as described in the Evaluation Criteria. The highest ranked proposals will be evaluated for the best fair and reasonable pricing. The VA anticipates the award of a single contract as a result of the solicitation as the Contracting Officer deems to be in the best interest of the Government.

The Technical Evaluation (Volume I) consists of:

Factor 1 – Professional Qualifications Factor 2 – Specialized Experience Factor 3 – Firm Capacity and Availability Factor 4 – Past Experience and Past Performance Factor 5 – Proximity of Firm Factor 6 - Service-Disabled Veteran Owned Small Business.

Those that pass the technical evaluation and came within the competitive range will then have their Price Quote Volume II evaluated for price reasonableness.

- End –

Attachment 1

General Decision Number: DC20250002 06/13/2025

Superseded General Decision Number: DC20240002

State: District of Columbia

Construction Type: Building

County: District of Columbia Statewide.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).

|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.75 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2025. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $13.30 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2025. |

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/03/2025 1 01/10/2025 2 01/24/2025 3 02/14/2025 4 02/21/2025 5 05/30/2025 6 06/13/2025

ASBE0024-007 10/01/2024

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR........................$ 40.77 20.17+a

Includes the application of all insulating materials, protective coverings, coatings and finishes to all types of mechanical systems

a. PAID HOLIDAYS: New Year's Day, Martin Luther King Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day,the day after Thanksgiving and Christmas Day provided the employee works the regular work day before and after the paid holiday.

ASBE0024-008 10/01/2024

Rates Fringes

ASBESTOS WORKER: HAZARDOUS

MATERIAL HANDLER.................$ 24.46 10.19+a

Includes preparation, wetting, stripping, removal, scrapping, vacuuming, bagging and disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems

a. PAID HOLIDAYS: New Year's Day, Martin Luther King Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day,the day after Thanksgiving and Christmas Day provided the employee works the regular work day before and after the paid holiday.

ASBE0024-014 10/01/2024

Rates Fringes

FIRESTOPPER......................$ 30.21 10.43+a

Includes the application of materials or devices within or around penetrations and openings in all rated wall or floor assemblies, in order to prevent the pasage of fire, smoke of other gases. The application includes all components involved in creating the rated barrier at perimeter slab edges and exterior cavities, the head of gypsum board or concrete walls, joints between rated wall or floor components, sealing of penetrating items and blank openings.

a. PAID HOLIDAYS: New Year's Day, Martin Luther King Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day,the day after Thanksgiving and Christmas Day provided the employee works the regular work day before and after the paid holiday.

BRDC0001-002 04/27/2025

Rates Fringes

BRICKLAYER.......................$ 38.80 15.17

CARP0197-011 05/01/2024

Rates Fringes

CARPENTER, Includes Drywall Hanging, Form Work, and Soft Floor Laying-Carpet..............$ 34.41 14.33

* CARP0219-001 05/01/2025

Rates Fringes

MILLWRIGHT.......................$ 39.50 17.32

CARP0474-006 05/01/2024

Rates Fringes

PILEDRIVERMAN....................$ 36.60 14.47

ELEC0026-016 06/05/2023

Rates Fringes

ELECTRICIAN, Includes Installation of HVAC/Temperature Controls........$ 53.00 21.35

ELEC0026-017 09/02/2024

Rates Fringes

ELECTRICAL INSTALLER (Sound & Communication Systems).........$ 32.60 12.92

SCOPE OF WORK: Includes low voltage construction, installation, maintenance and removal of teledata facilities (voice, data and video) including outside plant, telephone and data inside wire, interconnect, terminal equipment, central offices, PABX, fiber optic cable and equipment, railroad communications, micro waves, VSAT, bypass, CATV, WAN (Wide area networks), LAN (Local area networks) and ISDN (Integrated systems digital network).

WORK EXCLUDED: The installation of computer systems in industrial applications such as assembly lines, robotics and computer controller manufacturing systems. The installation of conduit and/or raceways shall be installed by Inside Wiremen. On sites where there is no Inside Wireman employed, the Teledata Technician may install raceway or conduit not greater than 10 feet. Fire alarm work is excluded on all new construction sites or wherever the fire alarm system is installed in conduit. All HVAC control work.

ELEV0010-001 01/01/2025

Rates Fringes

ELEVATOR MECHANIC................$ 57.16 38.435+a+b

a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, Christmas Day and the Friday after Thanksgiving.

b. VACATIONS: Employer contributes 8% of basic hourly rate for 5 years or more of service; 6% of basic hourly rate for 6 months to 5 years of service as vacation pay credit.

IRON0005-005 06/01/2024

Rates Fringes

IRONWORKER, STRUCTURAL AND

ORNAMENTAL.......................$ 37.86 25.86

IRON0005-012 05/01/2024

Rates Fringes

IRONWORKER, REINFORCING..........$ 31.88 23.78

LABO0011-009 06/01/2024

Rates Fringes

LABORER: Skilled................$ 29.66 8.29

FOOTNOTE: Potmen, power tool operator, small machine operator, signalmen, laser beam operator, waterproofer (excluding roofing), open caisson, test pit, underpinning, pier hole and ditches, laggers and all work associated with lagging that is not expressly stated, strippers, operator of hand derricks, vibrator operators, pipe layers, or tile layers, operators of jackhammers, paving breakers, spaders or any machine that does the same general type of work, carpenter tenders, scaffold builders, operators of towmasters, scootcretes, buggymobiles and other machines of similar character, operators of tampers and rammers and other machines that do the same general type of work, whether powered by air, electric or gasoline, builders of trestle scaffolds over one tier high and sand blasters, power and chain saw operators used in clearing, installers of well points, wagon drill operators, acetylene burners and licensed powdermen, stake jumper,demolition.

MARB0002-004 04/27/2025

Rates Fringes

MARBLE/STONE MASON...............$ 45.65 21.21

INCLUDING pointing, caulking and cleaning of All types of masonry, brick, stone and cement EXCEPT pointing, caulking, cleaning of existing masonry, brick, stone and cement (restoration work)

MARB0003-006 04/27/2025

Rates Fringes

TERRAZZO WORKER/SETTER...........$ 34.34 14.20

MARB0003-007 04/27/2025

Rates Fringes

TERRAZZO FINISHER................$ 28.85 12.55

MARB0003-008 04/27/2025

Rates Fringes

TILE SETTER......................$ 34.34 14.20

MARB0003-009 04/27/2025

Rates Fringes

TILE FINISHER....................$ 28.85 12.55

PAIN0051-014 06/01/2023

Rates Fringes

GLAZIER

Glazing Contracts $2 million and under...........$ 30.52 13.85 Glazing Contracts over $2 million.....................$ 34.76 13.85

PAIN0051-015 06/01/2023

Rates Fringes

PAINTER

Brush, Roller, Spray and Drywall Finisher............$ 27.46 11.56

PLAS0891-005 07/01/2023

Rates Fringes

PLASTERER (Including Fireproofing)....................$ 31.83 8.96

PLAS0891-006 02/01/2024

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 30.25 13.60

PLUM0005-010 08/01/2024

Rates Fringes

PLUMBER..........................$ 51.25 22.46+a

a. PAID HOLIDAYS: Labor Day, Veterans' Day, Thanksgiving Day and the day after Thanksgiving, Christmas Day, New Year's Day, Martin Luther King's Birthday, Memorial Day and the Fourth of July.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .