The file is a Bid Form for the Steam & Condensate Mains Oval 1 Project (Project Number 542-18-104) at the Department of Veterans Affairs Medical Center in Coatesville, PA. The project involves replacing underground medium pressure steam and condensate piping for multiple buildings in Oval 1 (Buildings 1-9) and outlying facilities (Buildings 10-17 and 69). The bid form includes detailed cost breakdown categories such as general conditions, site removals, structural concrete, mechanical work, and various bid deduct options, with an example test entry showing a base bid subtotal of $55,555.00.
The federal contract opportunity is a 100% small business set-aside with a project budget between $20-50 million under NAICS Code 236220. Key requirements include maintaining facility operations during construction, providing mandatory safety training and certifications, and completing the project within 550 calendar days. Contractors must be registered in SAM, meet small business size standards, and provide 100% Performance and Payment Bonds. The solicitation documents will be available on SAM.gov around June 30, 2025, with a pre-proposal site visit strongly encouraged. The contract will be awarded based on best value trade-off selection procedures, subject to FY25 fund availability, with all technical and procedural questions directed to Contracting Officer Elizabeth Wilson.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT 0003 - Cancel.pdf | ||
| Sign In Sheet 07072025.PDF | ||
| Map-Stockpile.docx | DOCX document | |
| 36C24425R0060 0002.pdf | ||
| Tree Management Part 1.pdf | ||
| Tree Management 3 of 3.pdf | ||
| Map-Laydown Area.docx | DOCX document | |
| Picture of Trench-Building 17.docx | DOCX document | |
| Tree Management 2 of 3.pdf | ||
| Sign in Sheet 07222025.pdf | ||
| 36C24425R0060 0001.docx | DOCX document | |
| Attachment 2 - GEMS Contractor training.doc | DOC document | |
| S02 36C24425R0060.docx | DOCX document | |
| Attachment 1 - Bid Form - Oval 1 Steam Rev1_10-5-22.xlsx | XLSX spreadsheet | |
| Attachment 5 - Technical Specification Div 02 82 11 - Traditional Asbestos Abatement.pdf | ||
| Attachment 6 - FINAL BID DOCUMENTS Reissue - Drawings.pdf | ||
| Attachment 7 - QASP 542_18_104 Steam Oval 1.pdf | ||
| Attachment 3 - Construction Safety Standards.pdf | ||
| Attachment 4 - Final Bid Documents Reissue - Specifications.pdf | ||
| 36C24425R0060_2.docx | DOCX document |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Form
| Contractor Bid Form | Project Name: | Steam & Condensate Mains Oval 1 | |||||
| Project Number: | 542-18-104 | ||||||
| Contract Number: | |||||||
| Contractor Name: | |||||||
| Date: | |||||||
| To be filled out by the Contractor | |||||||
| Description | Qty | Unit | Matrl Subtotal | Labor Subtotal | Equipment Subtotal | Total | |
| Oval 1 | |||||||
| 2 | Steam Piping | LF | |||||
| 3 | Condensate Piping | LF | |||||
| 4 | Fittings and Valves | ||||||
| 5 | Trenching | ||||||
| 6 | Underground Utility Locating | ||||||
| 7 | Eletrical Ducts | LF | |||||
| 8 | Pipe Bedding | LF | |||||
| 9 | Roadway Repair | ||||||
| 10 | Manholes | ||||||
| 11 | Grounds Improvements | ||||||
| 12 | Mechanical Room PRV | ||||||
| 13 | Commissioning | ||||||
| Base Bid Subtotal | |||||||
| Bid Deduct II | |||||||
| 14 | Steam Piping | ||||||
| 15 | Condensate Piping | ||||||
| Base Deduct II Subtotal | |||||||
| Bid Deduct III | |||||||
| 16 | Steam Piping | LF | |||||
| 17 | Condesate Piping | LF | |||||
| 18 | Pipe Bedding | ||||||
| 19 | Roadway Repair | ||||||
| 20 | Manholes | ||||||
| 21 | Grounds Improvements | ||||||
| 22 | Commisioning | ||||||
| Base Deduct III Subtotal |
Subtotal (Direct Costs)
| Direct Overhead (first $20,000) | 10.0% |
| Direct Overhead (next $30,000) | 7.5% |
| Direct Overhead (over $50,000) | 5.0% |
| Direct Overhead Total |
| Profit (first $20,000) | 10.0% |
| Profit (next $30,000) | 7.5% |
| Profit (over $50,000) | 5.0% |
| Profit Total |
Insurance and Taxes %
Taxes on Material and Equipment %
Total Prime Contractor Cost
Bid Form (auto calc)
| Contractor Bid Form | Project Name: | Steam & Condensate Mains Oval 1 | ||||||
| Project Number: | 542-18-104 | |||||||
| Contract Number: | ||||||||
| Contractor Name: | ||||||||
| Date: | ||||||||
| To be filled out by the Contractor | ||||||||
| Description | Qty | Unit | Matrl Subtotal | Labor Subtotal | Equipment Subtotal | Total | ||
| Oval 1 | ||||||||
| 1 | General Conditions | |||||||
| 1.1 | General Conditions | $ 55,555.00 | EXAMPLE TEST | |||||
| 1.2 | Contract Management Labor | |||||||
| 1.3 | General Labor | |||||||
| 1.4 | Engineering and Surveying | |||||||
| 1.5 | Civil Site Work | |||||||
| 1.5 | Traffic Control |
| 2 | Site Removals & Restoration |
| 2.1 | Erosion & Sediment Control |
| 2.2 | Site Demolition |
| 2.3 | Site Restoration |
| 3 | Structural Concrete & Steel |
| 3.1 | Conctrete Manholes |
| 3.2 | Concrete Steam Vaults |
| 3.3 | Other Concrete Work |
| 4 | Mechanical | |
| 4.1 | Mechanical Demolition | |
| 4.2 | Abatement Testing and Remediation | |
| 4.3 | Earthwork for Piping (Bedding, Trenching, Shoring, Backfill, etc) | |
| 4.4 | Steam Piping | |
| 4.5 | Condensate Piping | |
| 4.6 | Fittings and Valves at Building Connections | |
| 4.7 | Fittings and Valves at Manholes | |
| 4.8 | Underground Utility Locating | |
| 4.9 | Testing, Adjusting, Balancing | |
| 4.10 | Controls Modifications | |
| 4.11 | Commissioning | |
| Base Bid Subtotal | $ 55,555.00 | |
| 5 | Bid Deduct I | |
| 5.1 | General Conditions | |
| 5.2 | Site Removals & Restoration | |
| 5.3 | Structural Concrete & Steel | |
| 5.4 | Mechanical | |
| Base Deduct II Subtotal | $ - 0 | |
| 6 | Bid Deduct II | |
| 5.1 | General Conditions | |
| 5.2 | Site Removals & Restoration | |
| 5.3 | Structural Concrete & Steel | |
| 5.4 | Mechanical | |
| Base Deduct II Subtotal | $ - 0 | |
| 7 | Bid Deduct III | |
| 5.1 | General Conditions | |
| 5.2 | Site Removals & Restoration | |
| 5.3 | Structural Concrete & Steel | |
| 5.4 | Mechanical | |
| Base Deduct II Subtotal | $ - 0 | |
| 8 | Bid Deduct IV | |
| 5.1 | General Conditions | |
| 5.2 | Site Removals & Restoration | |
| 5.3 | Structural Concrete & Steel | |
| 5.4 | Mechanical | |
| Base Deduct II Subtotal | $ - 0 | |
| 9 | Bid Deduct V | |
| 6.1 | General Conditions | |
| 6.2 | Site Removals & Restoration | |
| 6.3 | Structural Concrete & Steel | |
| 6.4 | Mechanical | |
| Base Deduct III Subtotal | $ - 0 |
Subtotal (Direct Costs) $ 55,555
| Direct Overhead (first $20,000) | 10.0% | $ 2,000.00 | Calculated value |
| Direct Overhead (next $30,000) | 7.5% | $ 2,250.00 | Calculated value |
| Direct Overhead (over $50,000) | 5.0% | $ 277.75 | Calculated value |
| Direct Overhead Total | $ 4,527.75 |
Subtotal (Direct + Overhead $ 60,082.75
| Profit (first $20,000) | 10.0% | $ 2,000.00 | Calculated value |
| Profit (next $30,000) | 7.5% | $ 2,250.00 | Calculated value |
| Profit (over $50,000) | 5.0% | $ 504.14 | Calculated value |
| Profit Total | $ 4,754.14 |
Insurance and Taxes %
Taxes on Material and Equipment %
Total Prime Contractor Cost $ 64,836.89