This document includes a justification and approval for other than full and open competition and a pre-solicitation notice for a federal construction contract opportunity. The justification document details that the Department of Veterans Affairs requires HVAC controls from Delta Controls, valued at $206,115, for a construction project at the Lebanon VA Medical Center to create clinical space in Building 18. The total project value is $5.18 million. Delta Controls is deemed the only responsible source that can provide compatible controls for the existing facility-wide HVAC system without substantial duplication of costs. The pre-solicitation notice indicates the Veterans Integrated Service Network 4 will issue a request for proposal for construction services related to the project, with a period of performance of 930 calendar days from notice to proceed. The solicitation will be set aside 100% for service-disabled veteran-owned small businesses. The construction costs are estimated between $5-10 million. The solicitation is expected to issue on August 15, 2020.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF VETERANS AFFAIRS
Justification and Approval (J&A) For
Other Than Full and Open Competition (>SAT)
Acquisition Plan Action ID: 36C244-20-AP-3428
1. Contracting Activity: Department of Veterans Affairs, VISN 4, Lebanon VAMC, Facilities Service is requesting this J & A approval from the NCO4 Construction Team - West.
2. Nature and/or Description of the Action Being Processed: This is a Justification and Approval for Other Than Full and Open Competition, Brand Name Only, for Delta Controls HVAC controls which are a small portion of the construction materials for construction project 595-15-202 Create Clinic Space – Building 18, a new requirement to award a firm fixed price contract.
3. Description of Supplies/Services Required to Meet the Agency’s Needs: HVAC controls, sensors, installation, programming, commissioning, start-up and training to create a complete and usable Delta Controls HVAC control system that seamlessly integrates with our existing facility wide HVAC control system, as per Specificaiton Section 23 09 23 and related drawings. The total estimated value of the HVAC controls system is $206,115 out of a total estimated project value of $5,184,568.
4. Statutory Authority Permitting Other than Full and Open Competition: 41 USC §3304(a)(1), as implemented by FAR 6.302-1.
(X) (1) Only One Responsible Source and No Other Supplies or Services Will Satisfy
Agency Requirements per 41 USC §3304(a)(1) as implemented by FAR 6.302-1;
( ) (2) Unusual and Compelling Urgency per 41 USC §3304(a)(2) as implemented by FAR 6.302-2;
( ) (3) Industrial Mobilization, Engineering, Developmental or Research Capability or Expert Services per 41 USC §3304(a)(3) as implemented by FAR 6.302-3;
( ) (4) International Agreement per 41 USC §3304(a)(4) as implemented by FAR 6.302-4 ( ) (5) Authorized or Required by Statute per 41 USC §3304(a)(5) as implemented by FAR 6.302-5;
( ) (6) National Security per 41 USC §3304(a)(6) as implemented by FAR 6.302-6;
( ) (7) Public Interest per 41 USC §3304(a)(7) as implemented by FAR 6.302-7;
FAR13.5 Simplified Procedures for Certain Commercial Items: The authority for applying the Simplified Procedures for Commercial Items of FAR 13.5 is 41 U.S.C. 1901 and is implemented by for restricting competition on this procurement via FAR 13.106- 1(b)(2).
5. Demonstration that the Contractor’s Unique Qualifications or Nature of the Acquisition Requires the Use of the Authority Cited Above (applicability of authority):
Other Than Full and Open Competition (OFOC) SOP Attachment 2:
Request for Sole Source Justification Format >SAT
Only One Responsible Source (FAR 6.302-1) – Although there are other manufacturers of HVAC controls that can meet the same general performance standards as the Delta Controls equipment, they are not compatible with the Delta Controls system. The Delta Controls system is exclusively used at this facility. Use of additional manufacturers would result in the requirement to purchase and store additional spare inventory, have additional service contracts, duplicative monitoring equipment at multiple locations in the hospital, and additional training for our HVAC technicians and boiler plant maintenance personnel.
Accordingly, Delta Controls is the only firm capable of providing the supplies and services described in Section 3 above without the Veteran’s Health Administration experiencing substantial duplication of cost that could not be expected to be recovered through competition.
6. Description of Efforts Made to ensure that offers are solicited from as many potential sources as deemed practicable: A Notice of Intent to Sole Source HVAC Controls — Delta will be posted on SAM.GOV with the solicitation. Offerors will be able to obtain Delta Controls from various distributors and sources available in the open market.
7. Determination by the CO that the Anticipated Cost to the Government will be Fair and Reasonable: The contract is a firm fixed price construction contract with multiple bidders and the HVAC controls components are available from multiple vendors. Bid prices will be compared with the A/E prepared construction cost estimate to verify that the proposed contract cost is fair and reasonable.
8. Description of the Market Research Conducted and the Results, or a Statement of the Reasons Market Research Was Not Conducted: As described in Section 6 above, market research, in accordance with FAR Part 10, was conducted by synopsis of the proposed acquisition, advising industry of the pending acquisition and soliciting inquiries from interested parties.
9. Any Other Facts Supporting the Use of Other than Full and Open Competition: Proper temperature, humidity and pressure control are vital to maintaining the health of our veterans, staff and visitors and installing non-compatible equipment will lead to functionality issues that will reduce patient, staff and visitor safety. No other manufacturer makes a system that is guaranteed, as a whole, to be compatible with our installed Delta Controls sytem. System incompatibility can lead to the failure of operators and staff to receive timely and accurate notification of improper pressurization of isolation rooms and operating rooms, or improper humidity control throughout the hospital leading to infection control issues for our veterans, staff, or visitors.
10. Listing of Sources that Expressed, in Writing, an Interest in the Acquisition: See paragraph 6, above.
11. A Statement of the Actions, if any, the Agency May Take to Remove or Overcome any Barriers to Competition before Making subsequent acquisitions for the supplies or services required: If, in the future, there is a requirement to change the HVAC controls for
Other Than Full and Open Competition (OFOC) SOP Attachment 2:
Request for Sole Source Justification Format >SAT
OFOC SOP Revision 09 Page 3 of 3 Original Date: 03/22/11 Revision 09 Date: 04/17/2020 the entire facility, then we will consider all manufacturers of HVAC controls with the appropriate performance specifications.
12. Requirements Certification: I certify that the requirement outlined in this justification is a Bona Fide Need of the Department of Veterans Affairs and that the supporting data under my cognizance, which are included in the justification, are accurate and complete to the best of my knowledge and belief.
David C. Scharf Date Assistant Chief Engineer Lebanon VAMC
13. Approvals in accordance with the VHAPM Part 806.3 OFOC SOP:
a. Contracting Officer or Designee’s Certification (required): I certify that the foregoing justification is accurate and complete to the best of my knowledge and belief.
_____________________________ 06/30/2020 Donald J. Kalivoda Date Contracting Officer NCO4 West Construction Team
b. One Level Above the Contracting Officer (Required over SAT but not exceeding $700K): I certify the justification meets requirements for other than full and open competition.
Michelle Y. Lappen Date Chief, NCO4 West Construction Team
5/28/2020
David C.
Scharf 1024637
Digitally signed by David C. Scharf 1024637 Date: 2020.05.28 09:57:18 -04'00'
| 2020-06-30T16:16:43-0400 | |
| Donald J Kalivoda 252427 |
| 2020-07-01T08:29:31-0400 | |
| MICHELLE Y. LAPPEN 1635695 |
File details come from the government source that posted it. Updated .