This document provides details for a federal contract opportunity to construct clinical space at a Veterans Affairs medical center. The Department of Veterans Affairs Veterans Health Administration VISN 04 Contracting Office will issue a Request for Proposal for construction services related to the Create Clinical Space Bldg. 18 project located at the Lebanon VA Medical Center in Pennsylvania. The contractor will provide all labor, materials, equipment, and supervision to complete the construction as specified in the drawings and specifications over a 930 calendar day period of performance. The opportunity is set aside as a total small business service-disabled veteran-owned small business set-aside, with a NAICS code of 236220 and estimated value between $5-10 million. The solicitation will be issued on August 15, 2020, with questions due to the contracting officer and pre-bid site visit scheduled after posting. Offerors must be registered in SAM and verified in CVE at time of proposal submission to be eligible for award.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT C - CALCULATION OF SELF-PERFORMED WORK
EXHIBIT C - CALCULATION OF SELF-PERFORMED WORK
SUBMITTED IN RESPONSE TO Request For Proposal 36C24420R0086
Use a format similar to the following to identify and calculate cost of the work to be self-performed. Refer to the definitions pertaining to “Self-performance of work”, “On the Site” and “Total amount of work to be performed under the contract”.
Explain in detail how you will perform the minimum percentage required (15% GC) with your own resources. Note: An offeror who has the capability to perform both as a General contractor and self-perform a major element of construction, for example, pre-fabricated concrete, may be afforded additional consideration in the evaluation. You should address your general self-performance capability.
(Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor’s own employees; only those materials which will be both purchased and installed by the prime’s own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor’s own employees; and the contractor’s own job overhead costs.)
Clearly describe the work to be self-performed:
Show Calculation of Self-Performed work:
B.1 Total Offer Price: $
B.2 If applying for consideration as a General Contractor subtract Specialty Trades (Unless being self performed)
B.3 Subtract G&A, home office overhead, prime contractor’s markups for profit, bond, state use tax, etc. ($)
B.4 Remainder is “Total amount of work to be performed under the Contract” = $
B.5 “Work to be self-performed”: = $ Amount shown on this line should match the amount shown for “Show Calculation of Self-Performed work”?
(Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor’s own employees; only those materials which will be both purchased and installed by the prime’s own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor’s own employees; and the contractor’s own job overhead costs.)
B.6 15 % Self-performed Work = Line B.5 / B.4 X 100% = %