This solicitation is for construction services to improve the potable water distribution system at the Department of Veterans Affairs Medical Center in Batavia, New York. The contractor will be responsible for asbestos abatement, removing dead legs from the system, insulating piping, installing new water quality monitoring equipment and controls, replacing water fountains with bottle fillers, and other upgrades. The period of performance is 12 months from notice to proceed. The project magnitude is between $1,000,000 and $5,000,000, and the NAICS code is 238220 with a $16.5 million small business size standard. This is a 100% set-aside for service-disabled veteran-owned small businesses. The bid submission deadline is November 15, 2022.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sign in Sheet_11.04.22.pdf | ||
| 36C24222B0077 0003.pdf | ||
| Sign in Sheet_10.18.22.pdf | ||
| Key Points Pre Bid Solicitation_10.18.22.pdf | ||
| 36C24222B0077 0002.pdf | ||
| 36C24222B0077 0001.docx | DOCX document | |
| Specs 1 of 10.pdf | ||
| Specs 4 of 10.pdf | ||
| Specs 2 of 10.pdf | ||
| Drawings 5 of 9.pdf | ||
| Specs 9 of 10.pdf | ||
| Drawings 9 of 9.pdf | ||
| Specs 7 of 10.pdf | ||
| Specs 8 of 10.pdf | ||
| Drawings 1 of 9.pdf | ||
| VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors rev2.docx | DOCX document | |
| Specs 5 of 10.pdf | ||
| Drawings 3 of 9.pdf | ||
| Specs 10 of 10.pdf | ||
| Specs 6 of 10.pdf | ||
| Drawings 6 of 9.pdf | ||
| Drawings 8 of 9.pdf | ||
| Drawings 2 of 9.pdf | ||
| Drawings 7 of 9.pdf | ||
| Specs 3 of 10.pdf | ||
| Drawings 4 of 9.pdf |
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24222B0077 X 09-29-2022 528-23-1-4375-0001 528A4-16-205 Department of Veterans Affairs Network Contracting Office (NCO) 2 2875 Union Road Suite 3500 Cheektowaga
NY
14227 Tanya Baldwin Department of Veterans Affairs Network Contracting Office (NCO) 2 2875 Union Road, Suite 3500 Cheektowaga
NY
14227 Baldwin, Tanya Contractor shall provide all labor, equipment, materials, and supervision necessary to perform all work required for “Improve Potable Water Distribution System-Batavia”, in accordance with (IAW) all drawings, specifications, and the scope of work. This project is located at the Batavia New York Veterans Hospital at 222 Richmond Avenue, Batavia
NY 14020.
Project magnitude: between $1,000,000 and $5,000,000. The NAICS code is 238220. Small Business size standard is $16.5.
As set forth in 38 U.S.C 8127 the requirement is a 100% set aside to Service-Disabled Veteran Owned Small Business.
See VAAR 852.219-10, Notice of Total Service-Disabled Veteran Owned Small Business Set-Aside of this VERIFIED by the Department of Veterans Affairs Center for Verification and Evaluation (CVE) at time of submission of bid and at time of award. Failure to be both VERIFIED by CVE and VISIBLE in VetBiz prior to contract award will result in the bidder's proposal being deemed non-responsive. All offerors are urged to contact the CVE and submit the required documents to obtain CVE verification of their SDVOSB status if they have not already done so.
In accordance with FAR 52.204-7, System for Award Management (SAM), prospective contractors shall be registered in the SAM database prior to award of a contract or agreement.
See full solicitation text for information related to pre-bid site visit, requests for information, bidding materials, and public bid opening.
Note: In accordance with FAR 36.209 and VAAR 836.209, an A/E firm cannot be awarded any construction contract for which it provided design services unless approved by the head of the agency.
The site visit is schedule on Tuesday October 18, 2022, at 11: 00A.M at the Batavia VAMC.
X X 52.211-10 X 13:00
EDT
11-15-2022 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
528-3630162-4375-854200-3255 23NR2BR12
Department of Veterans Affairs Network Contracting Office (NCO) 2 2875 Union Road Suite 3500 Cheektowaga
NY
14227 Tungsten Network https://www.tungsten-network.com/ customer-campaigns/veteransaffairs/
X Tanya Baldwin Contracting Officer
Table of Contents
| PART I - THE SCHEDULE | 1 | |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 | |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 | |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 | |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 6 | |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 8 | |
| 1 | General Information | 9 |
| 1.1 | Location | 9 |
| 1.2 | Background | 10 |
| 1.3 | Purpose | 10 |
| 1.4 | Scope | 11 |
| 1.4.1 | Site Conditions, As Built and Record Documents | 12 |
| 1.4.2 | Quality Assurance/Quality Control Plan | 12 |
| 1.4.3 | Hazardous Materials | 12 |
| 1.4.4 | Personal Protective Equipment (PPE) | 12 |
| 1.5 | Approach | 12 |
| 1.5.1 | General | 12 |
| 1.5.2 | Phasing | 13 |
| 1.6 | Site Information | 13 |
| 1.6.1 | Safety | 13 |
| 1.6.2 | Access | 13 |
| 1.6.3 | Photography | 13 |
| 2 | Applicable Documents | 14 |
| 2.1 | Government Documents | 14 |
| 2.2 | Veterans’ Health Administration Western New York Documents | 14 |
| 2.3 | Non-Government Publications | 15 |
| 2.4 | Order of Precedence | 15 |
| 3 | Requirements | 16 |
| 3.1 | General | 16 |
| 3.1.1 | Status Updates | 16 |
| 3.1.2 | Meetings | 16 |
| 3.1.2.1 | Meeting Scheduling | 16 |
| 3.1.2.2 | Meeting Agenda | 16 |
| 3.1.2.3 | Meeting Presentation Materials | 16 |
| 3.1.2.4 | Meeting Minutes | 17 |
| 3.2 | Construction | 17 |
| 3.2.1 | Kick-off Meeting and Site Survey | 17 |
| 3.2.2 | Submittals | 17 |
| 3.2.3 | Preconstruction Conference and Requirement | 18 |
| 3.2.4 | General Construction | 19 |
| 3.2.5 | Status Meetings | 19 |
| 4 | Verification | 20 |
| 5 | Delivery | 21 |
| 5.1 | Technical POC | 21 |
| 5.2 | Schedule and Submittals | 21 |
| 6 | Government Furnished Information, Materials, & Equipment | 22 |
| 1.1 52.216-1 TYPE OF CONTRACT (APR 1984) | 22 | |
| 1.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 22 | |
| 1.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 22 | |
| 1.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 23 | |
| 1.5 52.228-1 BID GUARANTEE (SEP 1996) | 24 | |
| 1.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021) | 25 | |
| 1.7 52.233-2 SERVICE OF PROTEST (SEP 2006) | 25 | |
| 1.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 26 | |
| 1.9 52.246-26 REPORTING NONCONFORMING ITEMS (NOV 2021) | 26 | |
| 1.10 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 29 | |
| 1.11 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 30 | |
| 1.12 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 30 | |
| REPRESENTATIONS AND CERTIFICATIONS | 31 | |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2022) (JUL 2020) (DEVIATION) | 31 | |
| 3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) | 35 | |
| 3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 37 | |
| 3.4 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021) | 39 | |
| GENERAL CONDITIONS | 42 | |
| 4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 42 | |
| 4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (NOV 2021) | 42 | |
| 4.3 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 43 | |
| 4.4 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) | 44 | |
| 4.5 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (SEP 2021) | 44 | |
| 4.6 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020) | 48 | |
| 4.7 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010) | 48 | |
| 4.8 52.223-99 ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR FEDERAL CONTRACTORS (OCT 2021) (DEVIATION) | 50 | |
| 4.9 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (NOV 2021) | 50 | |
| 4.10 SUPPLEMENTAL INSURANCE REQUIREMENTS | 54 | |
| 4.11 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 55 | |
| 4.12 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020) | 56 | |
| 4.13 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION) | 58 | |
| 4.14 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 60 | |
| 4.15 VAAR 852.219-77 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (SEP 2021) (DEVIATION) | 61 | |
| 4.16 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 63 | |
| 4.17 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 64 | |
| 4.18 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 65 | |
| 4.19 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) ALTERNATE I (APR 2019) | 65 | |
| 4.20 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 66 | |
| 4.21 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 67 | |
| 4.22 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 68 | |
| 4.23 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 69 |
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
(a) Bidding materials consisting of Invitation for Bids, drawings, specifications and contract forms will be available on http://www.Beta.Sam.gov in electronic format only. All interested parties (subs & primes) should register at http://www.Beta.Sam.gov as an “Interested Vendor” so that others will know of your interest in participating in this procurement. A Bidder’s mailing list WILL NOT BE prepared by the Contract Specialist. SOLICITATION AMENDMENTS: Amendments to the solicitation will be posted at http://www.Beta.Sam.gov. Paper copies of the amendments will NOT be individually mailed. By registering to “Receive Notification”, you will be notified by e-mail of any new amendments that have been issued and posted. No other notification of amendments will be provided. Offerors are reminded that they are responsible for obtaining and acknowledging all amendments to this solicitation prior to the time for receipt of offers.
(b) If bid exceeds $150,000 a bid bond must be submitted. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.
(c) If the contract will exceed $150,000 (see FAR 28.102-1 for lesser amount), the bidder to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of SFs 25 and 25A may be obtained upon application to the issuing office.
(d) If the bid/offer is between $30,000 - $150,000 The bidder/offeror to whom award is made will be required to furnish a Payment Bond, Standard Form 25A or alternative payment protection which conforms to the requirements set forth in FAR Clause 52.228-13, Alternative Payment Protections, as noted in the General Conditions of this Specification. Copies of the Standard Form of Payment Bond may be obtained upon application to the Issuing Office.
PROJECT BID ITEMS
A single award will be made on the Base Bid.
BASE BID: All work required in the construction documents (including but not limited to drawings, specifications, addenda, and contract documents).
Fill in price SF 1442 BOX 17, BASE BID (use ink) The construction magnitude is between $1,000,000 and $5,000,000
BID SUBMISSION
The following documents are to be included in the bid submission:
1. One (1) signed SF 1442 page 2, Offer page, with blocks 14-20c completed.
1. Acknowledgment of all amendments must be accomplished either via entering data in block nineteen (19) of the SF1442 or completing blocks fifteen (15) a, b, and c of the amendment and attaching it to the SF 1442 Offer page.
1. One (1) original completed/signed SF24 Bid Bond and Power of Attorney as required.
1. Safety or Environmental Violations and Experience Modification Rate:
1. All Bidders/Offerors shall submit the following information pertaining to their past Safety and Environmental record. The information shall contain, at a minimum, a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.
1. All Bidders/Offerors shall submit information regarding their current Experience Modification Rate (EMR) equal to or less than 1.0. This information will be obtained from the bidder’s/offeror’s insurance company and be furnished on the insurance carrier’s letterhead.
1. Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead may obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR will obtain their EMR rating from their state-run worker’s compensation insurance rating bureau.
1. Bidders are responsible for ensuring and verifying their bid and all required bid documents are received at the address designated in block eight (8) of the SF 1442 solicitation and by the date and time specified in block thirteen (13)a of the SF 1442 solicitation (subject to amendment).
DELIVERY OF BIDS
Due to COVID-19 concerns and direction from the NYS Governor for social distancing, there will not be a face-to-face public bid opening. In accordance with FAR 14.202-8, send all submission documents via email to Tanya.Baldwin@va.gov no later than (NLT) 1:00 PM (Eastern Time), Tuesday, November 15, 2022. All Contractors providing an electronic bid submission must still meet all requirements listed under “Bid Submission” in the solicitation. The bid opening and public reading of the bids will be via OfficeTeams/Conference call. Bidders may call 1 347-566-4838 at 1:15 PM Eastern Time and enter phone conference ID 963 562 252# to join.
**The bid submission emails will be kept in an electronic folder unread until 1:15 PM when they will be opened and read to the public**
**NOTE: PLEASE ALLOW AT LEAST 30 MINUTES FOR BIDS TO ARRIVE IN EMAIL**
After all bids have been read, the apparent low bidder shall submit the signed original copy of the bid and all required documents, including bonds via mail to:
Tanya Baldwin at Tanya.Baldwin@va.gov.
Files should be in Adobe* PDF (Portable Document Format) Files: Size: Maximum size of the e-mail message shall not exceed five (5) megabytes. If the size limits are exceeded, the VA may not receive the file and/or you may not be considered. Only one email is permitted. This email should contain at least three separate attachments:
· One (1) signed SF1442 with amendments acknowledged.
· Include response to FAR 52.204-8(2) (i) or (ii) Annual Representations and Certifications
· Response to FAR 52.209-13(b)(1) or (2) Violation of Arms Controls Treaties or Agreements
· Response to VAAR Part 852.219-77
· One (1) complete signed SF 24 Bid Bond and Power of Attorney.
· One (1) safety or environmental violations and experience modification rate.
Bids received after this time may be rejected.
Any exception to the terms and conditions of this Invitation for Bid (IFB) will result in a nonresponsive bid.
Failure to provide a definitive price will result in a nonresponsive bid.
Receipt of bids must be in accordance with terms and conditions of this IFB.
Bidders must acknowledge (in writing only) amendments to this solicitation, otherwise a bid may be determined nonresponsive.
The winning bidder must be determined as "responsible" by the Contracting Officer in accordance with FAR Part 9, Contractor Qualifications.
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
GENERAL INTENTION
Contractor will provide services to include all tools, labor, materials, equipment, services, and supervision necessary for the “Improve Potable Water Distribution System” at 222 Richmond Avenue in Batavia N.Y. 14020, for Project 528A4-16-205.
SITE VISIT
Bidders are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of performing these services. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
There will only be one (1) organized site visit. It will be held on Tuesday, October 18, 2022 @ 11:00 AM (Eastern Time). Participants will meet at the Batavia VAMC, Engineering Department (by building 2 loading dock right off of the main parking lot) Attendance is not mandatory; however, all bidders are strongly encouraged to attend.
REQUESTS FOR INFORMATION (RFI):
To obtain clarifications and/or additional information concerning the contract requirements or specifications, submit a written RFI via email to Tanya.Baldwin@va.gov.
RFIs will be responded to as necessary in amendment format which will be posted on https://beta.sam.gov/.
The deadline for submission of RFIs for this solicitation is Thursday, October 25, 2022 at 3:30 PM (Eastern Time). No questions will be answered after this date/time unless determined to be in the best interest of the Government as determined by the Contracting Officer. Telephone RFIs will not be accepted or returned.
BASIS FOR AWARD
Contract award will be made to the responsive, responsible bidder submitting the lowest price in accordance with FAR Part 14 – Sealed Bidding.
RESPONSIBILITY REQUIREMENTS
A Determination of Responsibility shall be accomplished for the apparent awardee prior to processing the award. The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases will be used to make the Determination of Responsibility. Failure to affirm being within the guidelines above or submit this information may result in a determination of “Non-Responsibility” for the bidder/offeror. NOTE: Any information received by the Government that would cause for a negative Determination of Responsibility may make the bidder/offeror ineligible for award.
This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.
Page 1 of Page 1 of Construction Scope of Work Improve Potable Water Distribution Systems Project 528A4-16-205 08 Jun 2022
General Information
1.1 Location
Work performed under this scope will be for and conducted within VA Western New York Healthcare System (VAWNYHS) at the Batavia VA Medical Center (VAMC) located at 222 Richmond Avenue, Batavia NY 14020 under VA Project Number 528A4-16-205.
1.1.1 Period of Performance
· Contractor is expected to work 40 hours per week to remain on schedule and staff this project to meet the period of performance.
· Total of Twelve (12) months from Notice to Proceed to project acceptance. This shall include project submittals to be completed prior to start of work and close out documents.
· Two (2) months total for Asbestos Abatement. All work pertaining to abatement is the PRIORITY until completed as we will have an air monitor on site to accomplish this work. The contractor will NOT be allowed in areas to perform non-abatement work if there is abatement work to be completed. This is to keep asbestos removal on schedule while we have the air monitor on site.
1.1.2 Work Hours - Hours of Operation
Not All work on this project is Monday through Friday 7:30AM to 4:00PM. It is expected that the contractor work 40 hours per week to remain on schedule. There are some areas identified on the ICRA drawings and the 010000 GENERAL REQUIREMENTS where we cannot enter until later than 7:30AM, seven (7) days per week as we will be in Veteran Population. Off hours work includes 2nd shift [after 5pm Weekdays and Weekend work (Saturday and Sunday starting at 7:30AM)]. Refer to the ICRA Drawings and the VA 010000 GENERAL REQUIREMENTS Specifications for off hours work AND regular hours work (What is provided below is NOT all inclusive of off hours work).
· Dental (Building 1, 1st floor east side)
· Radiology (Building 1, 1st floor east side)
· Physical Therapy / Occupational Therapy (Building 1, 1st floor east side)
· Medical Clinics (Building 1, Ground Floor east side)
1.1.3 COVID-19 and Influenza REQUIREMENTS
The contractor and sub-contractors shall review the VA Requirements in specification section 010000 GENERAL REQUIREMENTS part 1.1 GENERAL INTENTION subpart D COVID-19 AND INFLUENZA.
· All contractors and sub-contractors shall adhere to the requirements as per VA Policy for COVID-19 and Influenza or they will NOT be permitted inside of any building at the Batavia VA healthcare Facility.
· There are attachments A,B and C at the end of the 010000 GENERAL REQUIREMENT specification that are the official VA Policy.
· Paperwork is required as a submittal for ALL individuals who will enter the Batavia VA facility.
1.2 Background
Batavia VAMC was built in 1932. Many renovations and modifications had been done to the domestic water system to accommodate the usage space. During the renovations and modifications, much of the plumbing was cut, cap, valve shut off leaving piping behind that allows stagnation in the piping system. The current domestic water is prone of a bacteria outbreak without any additional safety measure to prevent it from happening.
1.3 Purpose
The purpose of this effort is to perform modifications to the domestic water system for compliance with the VA directive 1061 on Legionella mitigation in building 1, 2, 3, 4, 6, and 30 at the Batavia VAMC.
The Batavia VAMC requires a Contractor to perform construction work necessary to accomplish this goal.
1.4 Scope
The scope of construction work is fully described in the construction documents (drawings and specifications). Additional administrative and management related requirements are described in Section 3: Requirements. A brief overview of the construction work is included but not limited to below:
Prepare and implement ICRA measures and containment in work area.
Remove “Type A” dead legs as noted on drawings Properly remove asbestos insulation and dispose of hazardous material according to specifications.
The contractor shall be responsible to build Asbestos Containments for all areas called out on the drawings for asbestos containing material (ACM) work.
The contractor shall provide a schedule and work plan to meet the Asbestos requirements on drawing PL030 and demolition drawings. There will be an air monitor to support this work and the contractor shall concentrate on asbestos related work to utilize the air monitor. The Asbestos Abatement Air Monitor will only have a two (2) month contract and ALL work asbestos related shall be the priority to meet the two (2) month requirement. The contractor shall complete the asbestos contract work in the two-month period allocated.
Plumbing Contractors and Prime Contractors working in Asbestos Containing Areas. THE PLUMBING CONTRACTORS SHALL BE PREPARED TO WORK IN AN ASBESTOS CONTAINING MATERIAL (ACM) CONTAINMENT CALLED OUT ON DRAWINGS PL-030 AND LOCATED ON THE DEMOLITION DRAWINGS. THE PLUMBING CONTRACTORS WILL HAVE TO REMOVE THE DEAD LEGS AND PERFORM ALL OTHER PLUMBING WORK IN A CONTAINMENT FOR ALL WORK THAT IS NEAR EXISTING (ACM) AREAS. THE PLUMBERS SHALL BE CERTIFIED AS PER THE VA ASBESTOS SPECIFICATIONS FOR WORKING IN AN ACM AREA JUST AS THE ASBESTOS WORKERS Insulate piping identified as “uninsulated”. Insulate the piping to meet the current VA Plumbing Design guideline requirements and specifications.
Provide new hose-end atmospheric vacuum breaker on all service sink faucets noted on drawings.
Provide new inline vacuum breaker on all outside spigot/hose bibbs noted on drawings.
Provide new water quality monitoring panel, secondary chlorine injections, and associated sensors for domestic CW, HW, and HWR. Interface into building management system as noted on drawings.
Provide new master mixing valve stations for the existing hot water generators as noted on drawings.
There are electrical (120-volt) controls, Building Management System (with U&S Services of Tonawanda) work on this contract to support the water equipment being installed.
There is electrical work to support this project pertaining to water bottle fillers, controls, etc. the contractor shall provide a competent electrical contractor that meets the VA electrical specifications.
Remove existing water fountains as indicate on drawings and provide new water fountain/bottle fillers in place of the removed fountains as noted on drawings.
Install a new kitchen sink in the Food Preparation are of building 2.
Re-Certify the backflow preventers as called out on the contract drawings.
What is provided in the Scope for this document is NOT all inclusive. This is a summary, and the contractor shall review the contract drawings and specifications thoroughly prior to bidding on the project.
1.4.1 Site Conditions, As Built and Record Documents
Although the VA makes every effort to keep drawings current to existing conditions, changes and updates are sometimes not recorded. It is therefore the Contractor’s responsibility to perform field investigation and verify of the accuracy of the drawings with the actual conditions.
The contractor shall check existing conditions at the project site prior to bidding.
1.4.2 Quality Assurance/Quality Control Plan
The Contractor is responsible for reviewing the work done by any subcontractors that the Contractor has hired to assist with the completion of this SOW. The Contractor must provide the Government with a Quality Assurance/Quality Control (QA/QC) Plan that documents the methods, processes, procedures that are going to be implemented by the Contractor to validate the work their subcontractors perform.
1.4.3 Hazardous Materials
Hazardous material removal is required for this project. Refer to the contract Drawings and Specifications, particularly the Specifications for General Requirements, Safety, Asbestos, and drawings PL030 that has abatement references for the plan views.
· Both the Asbestos Remediation AND the Plumbing contractors shall have a valid and current Asbestos Certification to work inside of an Asbestos Containment Area. Example: The Plumbing contractor will be required to remove the dead leg inside of the containment area.
1.4.4 Personal Protective Equipment (PPE)
The Contractor is responsible for obtaining/providing, inspecting, and maintaining any required Personal Protective Equipment (PPE) and access equipment (lifts, scaffolding, etc...) necessary to perform services identified in this SOW. Refer to the Safety Specification for further information.
· Containment Booth with HEPA filtration required.
· Asbestos Remediation equipment; respirators, Tyvek suits, etc.
1.5 Approach
1.5.1 General
This Scope of Work has been broken down into general requirements that are applicable to the entire contract and the specific construction effort:
General (Section 3.1) Construction (Section 3.2) The bidding Contractor(s) will have to conduct a brief pre award site survey of the campus. This will be arranged through the contracting officer and conducted as a group or individually as per the contracting officer.
1.5.2 Phasing
This is a phased project. See phasing drawings and PG-18-1: MASTER CONSTRUCTION SPECIFICATIONS, SECTION 01 00 00 GENERAL REQUIREMENTS - 528A4-16-205 for phasing requirements. The contractor shall also refer to Asbestos Drawing PL030 and Asbestos specifications for planning and scheduling ALL asbestos work to be completed prior-to working on any non-asbestos area.
1.6 Site Information
1.6.1 Safety
All Contractor personnel working onsite at the Medical Center will be required to attend a 1- hour Buffalo VAMC site specific safety training class. This class will be held on site and will be taught by a member of the Buffalo VAMC safety office. Attendance to this class and proof of the 10- hour OSHA (30-hour for supervisors, refer to General Requirements and Safety Specifications for the complete contract requirements). Participation in this class is mandatory and must be done prior to the commencement of work on-site.
1.6.2 Access
All visits and access requests to the VAWNYHS under this scope of work shall be coordinated through the Contracting Officer Representative (COR) and approved as per the schedule submission requirements in the drawings and specifications. The contractor shall pay close attention to the ICRA Drawings for days and times to work in each critical area, Asbestos Drawings PL-030, the General Requirements Specifications, Asbestos Specifications and Project Schedules Specifications.
1.6.3 Photography
PG-18-1: MASTER CONSTRUCTION SPECIFICATIONS, Section 01 00 00 (General Requirements - 528A4-16-205), Article 1.31 requires the contractor to obtain the services of a professional photographer to document the entire construction process.
As a reminder, it is VHA policy to respect the privacy of all persons (e.g., Veterans, patients, residents, members of the VHA workforce, and visitors) consistent with the needs of operating a national health care system. Privacy protections on VHA premises vary according to the needs and purposes of different types of areas, the persons included, and the purpose of the production and use of photographs, digital images, and video or audio recordings (excerpt from VHA Directive 1078).
The Contractor shall ensure that any photographs taken do NOT include any VHA patients, members of the VHA workforce, or visitors to the VAMC facility.
Applicable Documents The following documents are applicable to this Scope of Work (SOW) to the extent specified herein. While every effort has been made to ensure the completeness of this list, document users are cautioned that they must meet all specified requirements of documents cited in sections 3 of this SOW, whether they are listed here.
1.7 Government Documents
The following directives, guides, handbooks, and drawings form a part of this document to the extent specified herein. Unless otherwise specified, the latest revisions available shall be used.
Copies of construction related Department of Veterans Affairs directives, guides, and handbooks are available from the Office of Construction and Facilities Management website:
http://www.cfm.va.gov/til/index.asp
DEPARTMENT OF VETERANS AFFAIRS
DIRECTIVES
| 1078 |
| PRIVACY OF PERSONS REGARDING PHOTOGRAPHS, DIGITAL IMAGES, AND VIDEO OR AUDIO RECORDINGS |
1.8 Veterans’ Health Administration Western New York Documents The following drawings and documents form a part of this document to the extent specified herein.
Documents identified as “AS MODIFIED FOR VA PROJECT 528A4-16-205” are base VA documents that have been tailored to the needs of this specific effort. While the base VA documents are available on the Office of Construction and Facilities Management website listed above, the Contractor shall use the modified version listed below, NOT the base document. Copies of these documents are available from the KO, COR, or Technical POC.
VA WESTERN NEW YORK HEALTHCARE SYSTEM, BATAVIA VA MEDICAL CENTER
DRAWINGS
PG-18-1: MASTER CONSTRUCTION SPECIFICATIONS, SECTION 00 01 15 LIST OF DRAWING SHEETS (AS MODIFIED FOR VA PROJECT 528A4-16-205) lists all drawings for this construction effort.
SPECIFICATIONS (AS MODIFIED FOR VA PROJECT 528A4-16-205)
PG-18-1: MASTER CONSTRUCTION SPECIFICATIONS, SECTION 00 01 10 TABLE OF CONTENTS (AS MODIFIED FOR VA PROJECT 528A4-16-205) lists all relevant and modified construction specifications for this construction effort.
1.9 Non-Government Publications
All work shall be accomplished in strict accordance with the latest codes and standards. The Contractor shall follow any/all applicable standards and codes, including, but not limited to applicable NFPA standards, NEC, JCAHO, OSHA, ANSI, ASHRAE, and all other codes.
1.10 Order of Precedence
In the event of a conflict between the text of this document and the references cited herein, the text of this document takes precedence. Nothing in this document, however, supersedes applicable laws and regulations unless a specific exemption has been obtained.
Requirements The Contractor shall provide personnel, material, services, and facilities to perform, accomplish, and deliver the required services detailed in this scope of work.
1.11 General
This section contains general information that is applicable for the duration of the contract (i.e. applies to all Parts of this effort).
1.11.1 Status Updates
The Contractor shall prepare and submit periodic status reports throughout the duration of the contract. The reporting period will begin at Notice to Proceed. The contents of status reports shall include but is not limited to the following information/topics:
Summary and Current Status of Project Progress Accomplished (for the previous month) Refer to Project Schedules Specifications Progress Anticipated (for the next three months) Refer to Project Schedules Specifications Updated Schedule Refer to Project Schedules Specifications Problems Encountered and Anticipated Technical, Schedule, and Cost Risk Assessment Risk Mitigation Strategy Financial Data (i.e., allocated funding, obligations, expenditures, etc.)
Status reports may be organized in Contractor specified format. Status reports will be supplied as a digital product to the Government in a Microsoft Word compatible format (*.DOC, *.DOCX) or Portable Document Format (*.PDF). Status reports shall be submitted via email to the KO and COR by the 5th business day of every month.
1.11.2 Meetings
Several different meetings are identified under this contract. Information contained within this section is relevant to all meetings identified in this contract. Any meeting specific details can be in its respective section of this SOW.
1.11.2.1 Meeting Scheduling
All meetings identified within this SOW are to be coordinated and scheduled with the COR. See Section 1.6.2 and Section 5.1 for more details.
1.11.2.2 Meeting Agenda
The Contractor shall provide a meeting agenda 5 business days prior to the scheduled date of the meeting.
Meeting agendas may be organized in Contractor specified format. Meeting agendas will be supplied as a digital product to the Government in a Microsoft Word compatible format (*.DOC, *.DOCX) or Portable Document Format (*.PDF). Meeting agendas shall be submitted via email to the COR.
1.11.2.3 Meeting Presentation Materials
Any required presentation materials (e.g., handouts, slide presentation, design information, drawings, schedules, cut sheets, etc.…) shall be provided to the Government at the same time as the meeting agenda.
Meeting presentation materials may be organized in Contractor specified format. Meeting presentation materials will be supplied as a digital product to the Government in a Microsoft Office compatible format (*.DOC, *.DOCX, *.PPT, *.PPTX), Portable Document Format (*.PDF), or AutoCAD (*.DWG, *.DXF) as applicable to the specific document and meeting.
While email is acceptable method to receive this information, note that the VA has a size restriction for attachments on email. No email can be sent or received by the VA that is larger than 5MB. If meeting presentation materials are larger than this size, the Contractor must determine an alternate method to submit the required materials by the due date (e.g., FTP website, optical digital media, etc.…).
1.11.2.4 Meeting Minutes
The Contractor shall provide meeting minutes to document the discussion had during the meeting. The VA COR may provide their notes from the meeting in the form of an email and the contractor shall incorporate those notes into the minutes. he contents of meeting minutes shall include but is not limited to the following information/topics:
Meeting attendees Narrative to describe contents of meeting (will likely mirror the meeting agenda) List of action items (for both the Government and the Contractor) Presentation materials used during the meeting should be included as enclosures Meeting minutes may be organized in Contractor specified format. Meeting minutes will be supplied as a digital product to the Government in a Microsoft Word compatible format (*.DOC, *.DOCX) or Portable Document Format (*.PDF).
The Contractor shall provide draft meeting minutes within 5 business days of the meeting. The Government will review and provide comments back to the Contractor within 3 business days of receipt of the draft meeting minutes. The Contractor shall finalize the meeting minutes and submit the final meeting minutes to the Government within 3 business days of receipt of Government comments.
1.12 Construction
The Contractors scope of work for Construction shall include, but is not limited to the following:
1.12.1 Kick-off Meeting and Site Survey
The Contractor shall conduct a kick-off meeting at the VAMC. During the kick-off meeting the Contractor shall address their plan to meet the design intent, review the schedule, and review their plan to address any risks associated with the effort.
This meeting shall comply with the terms of Section 3.1.2 of this SOW.
See section 5.2 for the timing of this meeting.
Site surveys shall be conducted in accordance with Section 1.6.2.
1.12.2 Submittals
In accordance with the terms of PG-18-1 MASTER CONSTRUCTION SPECIFICATIONS; SECTION 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES (528A4-16-205), the contractor shall provide submittals and shop drawings for review prior to starting work. All submittals shall be provided and approved prior to mobilization.
A submittal log has been generated for this effort and represents a list of the minimum required submittals based upon the current construction documents. Although every attempt has been made to ensure that this list is complete, additional submittals not listed may be required.
1.12.3 Preconstruction Conference and Requirement
Once the submittals have been approved, the Contractor shall attend a Preconstruction Conference and Requirement. This meeting will be a follow-up to the Kick-off Meeting and Site Survey. In preparation for this meeting the Contractor shall submit:
An updated work plan that adds additional details based upon approved submittal information.
Revised or new Activity Hazard Analysis (AHA) based on approved submittals Any additional clarifying details about the work to be performed that have been updated bases upon the approved submittals.
Any action items resulting from this meeting shall be addressed prior to ordering any materials or beginning the actual construction work.
This meeting shall comply with the terms of Section 3.1.2 of this SOW and the terms of PG-18-1 MASTER CONSTRUCTION SPECIFICATIONS; SECTION 01 35 26 SAFETY REQUIREMENTS (528A4-16-205); Article 1.6 Preconstruction Conference.
See section 5.2 for the timing of this meeting.
The Pre-Construction Risk Assessment (PCRA) has been completed by the VA for this project and it mirrors what is required in the contract documents for this project. As stated above and in the contract documents, the contractor shall provide all documentation outlined in the contract documents including but NOT limited to the following.
· Refer to specifications 010000 GENERAL REQUIREMENTS and 013526 SAFETY REQUIREMENTS
· As per the Pre-Construction Risk Assessment, safety department want the contractor to be prepared to submit all listed items, as part of their safety plan, infection control plan, confined space plan and plan to drill through concrete as follows but not limited to:
· When creating dust, the contractor shall have Negative Air with HEPA filtration going out the window.
· When creating dust, the contractor shall provide a work plan to the VA to shut down the Air Handling Unit in the basement of building and cover all ventilation (supply, return and exhaust).
· When drilling through concrete the contractor shall have in their work plan to have shrouds with HEPA filtration.
· Lock out and tag out any electrical panels to do electrical work
· Bypass fire alarm daily for the devices when creating dust.
· Provide a confined space plan for all work to be conducted in crawlspaces.
· Provide a shutdown noticed and tentative duration prior to shutdown.
· Provide work plan on all water/sanitary disruption prior to any shutdown.
· All work plans are subject for approval from the VA
1.12.4 General Construction
The Contractors scope of work for General Construction shall include, but is not limited to, the procedures outlined in PG-18-1: MASTER CONSTRUCTION SPECIFICATIONS (528A4-16-205).
Work includes, but not limited to, all labor, material, equipment, and supervision to perform the required demolition, modification, construction, and/or installation of the walk-in coolers and freezers and their subsystems as described in the drawings, specifications, and this SOW.
1.12.5 Status Meetings
The Contractor shall attend periodic status meetings with the VA to discuss construction progress, submittals, and RFIs during the project. The construction phase is anticipated to be no longer than 1 year. This time estimate includes the time required to perform the preparatory administrative work (e.g., plans, schedules, submittals, etc...)
Status meetings will commence after the Preconstruction Conference is held (section 3.2.3). Status meetings shall be held every two weeks for the remainder of the effort. At a minimum, status meeting attendees shall be the VAMC COR and one person from the prime Contractor. Additional personnel may be invited to the meeting as required.
As part of the last status meeting the resurvey of the site will be conducted (see PG-18-1: MASTER CONSTRUCTION SPECIFICATIONS, Section 01 00 00 (General Requirements - 528A4-16-205), Article 1.8, Paragraph C).
The Contractor and/or Sub Contractor shall provide meeting minutes in accordance with the terms of Section 3.1.2.
Verification Final functional verification of the installed equipment shall be conducted jointly before final acceptance of the constructed product. The groups that will participate in the verification process include:
· Prime Contractor
· Subcontractor (as applicable)
· VA Engineering / AE consultant These functional tests will be based upon manufacturer data and will be checked against VA regulatory requirements as applicable.
All equipment installed will be subject to these tests. For any equipment that does not pass the functional verification test, the Contractor shall troubleshoot the issue and determine if the root cause of the problem.
If the root cause is the result of the construction work, the Contractor shall repair and/or replace the faulty construction work and any subsequently damaged equipment at no additional cost to the Government.
If the root cause is the result of faulty equipment (manufacturer defect), the Contractor shall coordinate with the fabricator to repair and/or replace the faulty equipment and any subsequently damaged equipment at no additional cost to the Government.
Delivery
1.13 Technical POC
The Contractor shall coordinate all visits and meetings with and provide the required quantity of submittals to Bao Nguyen
VA Western New York Healthcare System
Batavia VA Medical Center
222 Richmond Avenue
Batavia, NY 14020
| Phone: |
| (585) 297-1186 |
| Cell: |
| (716) 220-0370 |
| Email: |
| Bao.nguyen5@va.gov |
1.14 Schedule and Submittals
The Period of Performance for the total effort will not exceed 360 calendar days.
Independent of the not to exceed period of performance, the Contractor shall comply with the individual relative and absolute timelines identified in this SOW.
The Contractor is responsible for submitting a detailed schedule in accordance with PG-18-1 MASTER CONSTRUCTION SPECIFICATIONS; SECTION 01 32 16.15, PROJECT SCHEDULES (528A4-16-205). This schedule must include all administrative work (preparatory as well as any permitting or shut down requests) and must also show associated predecessor and successor logic associated with all tasks performed under this contract.
Government Furnished Information, Materials, & Equipment The government shall supply the following information:
All BATAVIA VAMC drawings and modified program guides and specifications from section 2.2.
Government Furnished Materials (GFM) and Government Furnished Equipment (GFE) are not required and will not be provided for this effort.
1.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
1.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
1.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
| Goals for minority participation for each trade |
| Goals for female participation for each trade |
| % |
| 6.9 % |
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects.