This document contains responses to questions regarding a federal solicitation for improvements to the potable water distribution system at the Batavia Veterans Affairs Medical Center in New York.
The solicitation seeks a contractor to complete asbestos abatement and upgrades to the potable water infrastructure, including replacing sections of water mains. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2 is the contracting agency.
The contractor will be provided a designated laydown area on site but no trailers or portable offices. Temporary power is unavailable. All asbestos work must be completed within the allotted time period and take priority over other work. Non-asbestos work can occur simultaneously in separate buildings as long as it does not impede asbestos work and tradespeople have the required certifications. The response clarifies areas requiring work outside normal hours and confirms phasing between buildings is permitted.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sign in Sheet_11.04.22.pdf | ||
| 36C24222B0077 0003.pdf | ||
| Sign in Sheet_10.18.22.pdf | ||
| Key Points Pre Bid Solicitation_10.18.22.pdf | ||
| 36C24222B0077 0001.docx | DOCX document | |
| Specs 1 of 10.pdf | ||
| Specs 4 of 10.pdf | ||
| Specs 2 of 10.pdf | ||
| Drawings 5 of 9.pdf | ||
| Specs 9 of 10.pdf | ||
| Drawings 9 of 9.pdf | ||
| Specs 7 of 10.pdf | ||
| Specs 8 of 10.pdf | ||
| Drawings 1 of 9.pdf | ||
| VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors rev2.docx | DOCX document | |
| Specs 5 of 10.pdf | ||
| Drawings 3 of 9.pdf | ||
| Specs 10 of 10.pdf | ||
| Specs 6 of 10.pdf | ||
| Drawings 6 of 9.pdf | ||
| Drawings 8 of 9.pdf | ||
| 36C24222B0077.docx | DOCX document | |
| Drawings 2 of 9.pdf | ||
| Drawings 7 of 9.pdf | ||
| Specs 3 of 10.pdf | ||
| Drawings 4 of 9.pdf |
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 3
TBD
528A4-16-205
Department of Veterans Affairs Network Contracting Office (NCO) 2 2875 Union Road Suite 3500 Cheektowaga NY 14227
Department of Veterans Affairs Network Contracting Office (NCO) 2 2875 Union Road Suite 3500 Cheektowaga NY 14227
To all Offerors/Bidders
36C24222B0077
X
X X
TBD
See Continuation Page for Instructions
Tanya Baldwin Contracting Officer
This amendment is to change/correct the date for the additional site visit and to provide response to RFI questions received.
The additional site visit changed from Tuesday November 3, 2022, at 1:00 PM Eastern Time, to Friday November 4, 2022, at 1:00 PM Eastern Time
RFI Questions – Batavia, NY VAMC – Improve Potable Water Distribution System Solicitation Number: 36C2422B0077 DUE: October 25, 2022 @ 3:30pm EDT RFI Contact, Ms. Tanya Baldwin at Tanya.Baldwin@va.gov ================================================================== In review of the documents and in speaking with several sub-contractors, please find below questions for clarification. If any items shown below requires additional information, please contact us directly.
1. Will the Contractor be permitted to have a laydown area in the same general vicinity as the work to be completed? YES – THERE WILL BE ASSIGNED LOCATIONS FOR
LAYDOWN AREA. CONTRACTOR IS RESPONSIBLE FOR ALL RESTORATION OF ANY
DAMAGES THE LAYDOWN MIGHT CAUSED. THE VA WILL ALLOW A LOCATION FOR AN
EXTERIOR CONEX BOX BUT NO TRAILERS OR PORTABLE OFFICES ON SITE. THE CONEX BOX
WILL BE FOR STORED MATERIALS ONLY. a. Is temporary power available for Contractor’s trailer and general equipment usage? NO TEMPORARY POWER IS AVAILABLE AND NO
TRAILERS. ONLY A CONEX BOX FOR STORING MATERIALS. THE VA IS NOT RESPONSIBLE
FOR ANY MATERIALS OR TOOLS THAT ARE LOST OR STOLEN, THE CONTRACTOR SHALL BE
RESPONSIBLE FOR THEIR OWN SECURITY.
2. Specification 01 35 26, Article 1.9.C states that the Prime Contractor must provide an individual to fulfill the role of SSHO who is separate from the Site Superintendent;
however, considering the limited trades involved on this project, would the Government consider allowing the prime’s Site Superintendent to complete both of these roles, so long as they are able to fulfill all specified requirements of each position? DUE TO THE
PRESENCE OF HIGH HAZARD WORK IN THE PROJECT (ASBESTOS, CONFINED SPACE) WE
WOULD NOT BE ABLE TO CONSIDER ONE INDIVIDUAL PERFORMING DUAL ROLES
SUFFICIENT IN FOR THIS PROJECT.
3. What areas within this project’s scope of work area, in addition to those listed in 1.1.2 of the solicitation documents, will require work outside of normal business hours? PLEASE
REFER TO ICRA DRAWINGS FOR WORK OUTSIDE NORMAL BUSINESS HOURS AND THE
SPECIFICATION SECTION 010000 GENERAL REQUIREMENTS.
4. Will there be any phasing requirements in addition to those related to the requirement to complete all abatement work prior to starting non-abatement work? a.
The project documents reference phasing by building as directed by the COR but provides no specifics. Will work be permitted in multiple buildings at once so long as adequate supervision is provided? YES
b. Will all work has to be approved in one building before the contractor can proceed to the next building? NO, CONTRACTOR/SUB CAN WORK ON
MULTIPLE BUILDINGS SIMULTANEOUSLY AS LONG AS THEY’RE APPROPRATELY SUPERVISED.
THE ASBESTOS WORK IS WRITTEN INTO THE CONTRACT THAT ALL WORK SHALL BE
COMPLETED IN THE TIME ALLOCATED FOR ASBESTOS WORK. WHEN THE ASBESTOS WORK
HAS COMMENCED THIS SHALL BE THE PRIORITY OF THE CONTRACTOR. THEY CAN WORK
AT BOTH PLACES SIMULTANEOUSLY HOWEVER THE ASBESTOS IN UNDER A STRICT
TIMEFRAME DUE TO THE NEED FOR THE VA TO PROVIDE A PROFESSIONAL AIR MONITOR.
c. Can non asbestos work begin in a building which has passed all abatement requirements, so long as the work does not impede the progress of remaining abatement work? THERE IS A REQUIREMENT ON THIS CONTRACTOR FOR THE PLUMBER TO
EXECUTE THEIR WORK IN A CONTAINMENT AREA UNDER POSSIBLY ASBESTOS CONDITIONS
AS THIS PROJECT IS NOT A FULL-BLOWN ABATEMENT PROJECT, WE ARE ONLY REMOVING
ENOUGH ASBESTOS TO REMOVE THE DEAD LEG. THE PLUMBER WILL NEED ASBESTOS
CERTIFICATION AND PROPER PPE.
5. The project drawings show limited areas in which ICRA Class III will be applicable and no areas which are to be ICRA Class IV; please confirm there are no Class IV ICRA areas included within this project? ALL ICRA CLASSIFICATIONS ARE LISTED ON THE ICRA
DRAWINGS.
6. Will temporary barriers (i.e. STARC, Edge Guard, etc.) be permitted for use in all areas where hard wall barriers are required in accordance with the ICRA classification? IF THE
CONTAINMENT BOOTH CANNOT BE USED THE CONTRACTOR SHALL BUILD THE PROPER
CONTAINMENT BARRIER AS PE THE CONTRACT.
File details come from the government source that posted it. Updated .