This document provides details for a federal solicitation seeking replacement of domestic hot water systems at three buildings on the Castle Point VA Medical Center campus. The solicitation is for a service-disabled veteran-owned small business set-aside and seeks to remove existing systems and install new steam-fired water heaters utilizing an in-house steam supply. The scope of work includes phased removal and replacement to maintain domestic hot water, along with associated electrical, mechanical, and general construction work. The response due date is March 26, 2021 and the period of performance is 270 calendar days. The cost estimate range for the project is $500,000 to $1 million.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AIRTEK ENVIRONMENTAL CORP.

39 – 37 29th Street, Long Island City, New York, 11101 Phone (718) 937-3720 Fax (718) 937-3721 www.airtekenv.com

Lead-Based Paint Testing Report

Conducted At:

VA Hudson Valley Health Care System

41 Castle Point Rd

Building 19, 20, and 21

Wappingers Falls, NY 12590

Prepared For:

Watson Engineering, PC

1112 State Route 434

Owego, New York 13827

Prepared by:

Airtek Environmental Corp.

39-37 29 th

Street

Long Island City, NY 11101

Airtek Project No: 20-0257

May 27 th

, 2020

Lead Based Paint Testing Report – Watson Engineering - VA Castle Point Page 2 of 7

Airtek Project #:20-0257 May 27 th

Table of Contents

I. Executive Summary

II. Background

III. File Search Data

IV.Testing Procedures/Analytical Methodology

V. Results

VI. Conclusions

VII. Report Certifications

Attachments:

Attachment A. XRF Results

Attachment B: Positive Lead Shots Diagram

Attachment C: Lead Inspector/Risk Assessor, Company Certifications

Lead Based Paint Testing Report – Watson Engineering - VA Castle Point Page 3 of 7 th

I. Executive Summary

Airtek Environmental Corp. performed a lead-based paint inspection at the VA Hudson Valley Health Care

System - 41 Castle Point Road, Wappingers Falls, NY (the Property). The inspection was performed by

EPA Certified Lead Risk Assessor Anthony Dhanpat of Airtek Environmental Corp., who has been trained and certified in accordance with 40 CFR Part 745. All fieldwork associated with this inspection was performed on May 15

, 2020.

The intent of the inspection was to ascertain if the surface coatings on building components have a lead

Concentration greater than or equal to 1.0 mg/cm2 or 0.5 percent by weight.

According to the inspection, thirteen (13) of the tested components/surfaces contain lead-based paint above current regulatory thresholds. Please refer to Attachment A for detailed test results.

The report shows all the readings that were taken by Room and Wall sequence. As noted on the result

Spreadsheet, Wall 1 in each room is the wall where the door opening is. Going clockwise, Wall 2 will be

On your left, Wall 3 is straight ahead of you and Wall 4 is always on the right.

This report represents field data, observations and findings relating to the single testing performed at the property. The results and findings stated in this report are representative of the conditions observed at this property at the time of inspection. Airtek Environmental Corp. assumes no responsibility for any change in the conditions or circumstances that occurred subsequent to our performance of single testing.

Lead Based Paint Testing Report – Watson Engineering - VA Castle Point Page 4 of 7 th

II. Background

A. Property

VA Hudson Valley Health Care System - 41 Castle Point Road, Wappingers Falls, NY is a Public facility (Hospital).

B. Owner

Owner’s information was not provided to Airtek.

C. Lead Inspection Firm

Airtek Environmental Corp. USEPA # NY 1661-1

39-37 29 th

Street

Long Island City, NY 11101

Contact: Mike S. Zouak

Telephone: (718) 937-3720

D. Lead Inspectors (Certifications/Licenses)

Anthony Dhanpat

E. XRF Instruments/Serial Numbers

Heuresis Pb200i Serial # 2477

III. File Search Data

No prior documentation related to lead paint was provided by the client.

IV. Testing Procedures/Analytical Methodology

The primary lead detection technique utilized for this work was X-ray fluorescence analysis (XRF). The

XRF analysis was conducted on site, using a portable Pb200i XRF Lead Analyzer manufactured by Heuresis

Corporation. The Pb200i was utilized in accordance with the procedures specified by the manufacturer, Performance Characteristic Sheet (PCS), dated December 1, 2015 and Chapter 7 of the HUD Guidelines for the Evaluation and Control of Lead Based Paint Hazards in Housing.

Lead Based Paint Testing Report – Watson Engineering - VA Castle Point Page 5 of 7

V. Results

The data provided as Attachment A consists of data downloaded from the XRF to Microsoft Excel.

VI. Conclusions

According to the inspection, thirteen (13) of the tested components/surfaces contain lead-based paint above current regulatory thresholds.

Table 1: Positive Components

Shot # Component Color Location

9 Wall 1 Gray C-001

10 Wall 2 Gray C-001

12 Wall 4 Gray C-001

15 Wall 1 White Outside wall (C-001)

33 Wall 1 White B-001

34 Wall 2 White B-001

35 Wall 3 White B-001

36 Wall 4 White B-001

51 Wall 2 White A-001

52 Wall 3 White A-001

52 Wall 4 White A-001

56 Wall 1 White A-001

59 Wall 4 White A-001

Please refer to Attachment A for detailed test results and Attachment B for the location diagram.

The readings that are labeled “CALIBRATION” are the calibration readings only and they do not indicate a lead positive component in the subject space.

VII. Report Certifications:

Airtek certifies that the information contained herein is based on the physical and visual inspections conducted by Airtek and data collected during the inspection survey on the date noted.

Prepared by:

Airtek Environmental Corp.

EPA Certified Lead Risk Assessor

Attachement A:

XRF Results

Company Heuresis Corp.

Model Pb200i

Type XRF Lead Paint Analyzer

Serial Num. 2219

App Version Pb200i-4.1-11

Job Id Reading # ConcentrationUnits Result Date Time Analytic Mode Structure ComponentWall Substrate Color Paint ConditionRoom Site Address Floor/Apt # Room Inspector

1 1 mg/cm2 Positive 5/15/2020 10:32:47 Lead Paint Calibrate Metal White Poor VA Castle Point Anthony Dhanpat

2 1.1 mg/cm2 Positive 5/15/2020 10:33:01 Lead Paint Calibrate Metal White Poor VA Castle Point Anthony Dhanpat

3 1 mg/cm2 Positive 5/15/2020 10:33:16 Lead Paint Calibrate Metal White Poor VA Castle Point Anthony Dhanpat

4 0.1 mg/cm2 Negative 5/15/2020 10:33:33 Lead Paint Calibrate Metal White Poor VA Castle Point Anthony Dhanpat

5 0.1 mg/cm2 Negative 5/15/2020 10:33:40 Lead Paint Calibrate Metal White Poor VA Castle Point Anthony Dhanpat

6 0.1 mg/cm2 Negative 5/15/2020 10:33:47 Lead Paint Calibrate Metal White Poor VA Castle Point Anthony Dhanpat

7 0.2 mg/cm2 Negative 5/15/2020 10:34:20 Lead Paint Door Door Wall 1 Metal Gray Poor VA Castle Point Bldg 19 C-001 Anthony Dhanpat

8 0.7 mg/cm2 Negative 5/15/2020 10:34:37 Lead Paint Door Door Buck Wall 1 Metal Gray Poor VA Castle Point Bldg 19 C-001 Anthony Dhanpat

9 7.2 mg/cm2 Positive 5/15/2020 10:35:25 Lead Paint Room Wall Wall 1 Concrete Gray Poor VA Castle Point Bldg 19 C-001 Anthony Dhanpat

10 2.8 mg/cm2 Positive 5/15/2020 10:36:04 Lead Paint Room Wall Wall 2 Concrete Gray Poor VA Castle Point Bldg 19 C-001 Anthony Dhanpat

11 0.7 mg/cm2 Negative 5/15/2020 10:36:42 Lead Paint Room Wall Wall 3 Concrete Gray Poor VA Castle Point Bldg 19 C-001 Anthony Dhanpat

12 2.2 mg/cm2 Positive 5/15/2020 10:37:16 Lead Paint Room Wall Wall 4 Concrete Gray Poor VA Castle Point Bldg 19 C-001 Anthony Dhanpat

13 0.5 mg/cm2 Negative 5/15/2020 10:41:01 Lead Paint Angle Iron Angle Iron Floor Metal White Poor VA Castle Point Bldg 19 C-001 Anthony Dhanpat

14 0.7 mg/cm2 Negative 5/15/2020 10:44:37 Lead Paint Room Ceiling Ceiling Concrete White Poor Common AreaVA Castle Point Bldg 19 Anthony Dhanpat

15 1.9 mg/cm2 Positive 5/15/2020 10:45:23 Lead Paint Room Wall Wall 1 Concrete White Poor Common AreaVA Castle Point Bldg 19 Anthony Dhanpat

16 0.6 mg/cm2 Negative 5/15/2020 10:45:42 Lead Paint Room Wall Wall 2 Concrete White Poor Common AreaVA Castle Point Bldg 19 Anthony Dhanpat

17 0.1 mg/cm2 Negative 5/15/2020 10:45:56 Lead Paint Room Wall Wall 3 Concrete White Poor Common AreaVA Castle Point Bldg 19 Anthony Dhanpat

18 0.6 mg/cm2 Negative 5/15/2020 10:46:11 Lead Paint Room Wall Wall 4 Concrete White Poor Common AreaVA Castle Point Bldg 19 Anthony Dhanpat

19 0.2 mg/cm2 Negative 5/15/2020 10:48:32 Lead Paint Door Door Wall 1 Metal Blue Poor VA Castle Point 20 B-005 Anthony Dhanpat

20 0.2 mg/cm2 Negative 5/15/2020 10:48:47 Lead Paint Door Door Buck Wall 1 Metal Blue Poor VA Castle Point 20 B-005 Anthony Dhanpat

21 0.3 mg/cm2 Negative 5/15/2020 10:49:24 Lead Paint Room Wall Wall 1 Concrete Blue Poor VA Castle Point 20 B-005 Anthony Dhanpat

22 0.3 mg/cm2 Negative 5/15/2020 10:50:34 Lead Paint Room Wall Wall 2 Concrete Blue Poor VA Castle Point B-005 Anthony Dhanpat

23 0.3 mg/cm2 Negative 5/15/2020 10:50:49 Lead Paint Room Wall Wall 3 Concrete Blue Poor VA Castle Point B-005 Anthony Dhanpat

24 0.1 mg/cm2 Negative 5/15/2020 10:51:03 Lead Paint Room Wall Wall 4 Concrete Blue Poor VA Castle Point B-005 Anthony Dhanpat

25 0.2 mg/cm2 Negative 5/15/2020 10:52:39 Lead Paint Room Wall Wall 1 Concrete White Poor VA Castle Point 20 corridor Anthony Dhanpat

26 0 mg/cm2 Negative 5/15/2020 10:52:52 Lead Paint Room Wall Wall 2 Concrete White Poor VA Castle Point 20 corridor Anthony Dhanpat

27 0.1 mg/cm2 Negative 5/15/2020 10:53:13 Lead Paint Room Wall Wall 3 Concrete White Poor VA Castle Point 20 corridor Anthony Dhanpat

28 0.5 mg/cm2 Negative 5/15/2020 10:53:30 Lead Paint Room Wall Wall 4 Concrete White Poor VA Castle Point 20 corridor Anthony Dhanpat

29 0.5 mg/cm2 Negative 5/15/2020 10:53:48 Lead Paint Room Wall Wall 3 Concrete White Poor VA Castle Point 20 corridor Anthony Dhanpat

30 0.2 mg/cm2 Negative 5/15/2020 10:55:11 Lead Paint Door Door Wall 1 Metal Blue Poor VA Castle Point b001 bldg 20 B-001 Anthony Dhanpat

31 0.6 mg/cm2 Negative 5/15/2020 10:55:26 Lead Paint Door Door Buck Wall 1 Metal Blue Poor VA Castle Point b001 bldg 20 B-001 Anthony Dhanpat

32 0.1 mg/cm2 Negative 5/15/2020 10:55:54 Lead Paint Room Wall Wall 1 Concrete White Poor VA Castle Point b001 bldg 20 B-001 Anthony Dhanpat

33 2 mg/cm2 Positive 5/15/2020 10:56:04 Lead Paint Room Wall Wall 1 Concrete White Poor VA Castle Point b001 bldg 20 B-001 Anthony Dhanpat

34 1.9 mg/cm2 Positive 5/15/2020 10:56:19 Lead Paint Room Wall Wall 2 Concrete White Poor VA Castle Point b001 bldg 20 B-001 Anthony Dhanpat

35 2 mg/cm2 Positive 5/15/2020 10:56:39 Lead Paint Room Wall Wall 3 Concrete White Poor VA Castle Point b001 bldg 20 B-001 Anthony Dhanpat

36 2.8 mg/cm2 Positive 5/15/2020 10:57:05 Lead Paint Room Wall Wall 4 Concrete White Poor VA Castle Point b001 bldg 20 B-001 Anthony Dhanpat

37 0.2 mg/cm2 Negative 5/15/2020 10:59:18 Lead Paint Door Door Wall 1 Metal Blue Poor VA Castle Point a005 bldg 21 A-005 Anthony Dhanpat

38 0.3 mg/cm2 Negative 5/15/2020 10:59:32 Lead Paint Door Door Buck Wall 1 Metal Blue Poor VA Castle Point a005 bldg 21 A-005 Anthony Dhanpat

39 0.2 mg/cm2 Negative 5/15/2020 11:00:10 Lead Paint Room Wall Wall 1 Concrete White Poor VA Castle Point a005 bldg 21 A-005 Anthony Dhanpat

40 0.3 mg/cm2 Negative 5/15/2020 11:00:31 Lead Paint Room Wall Wall 2 Concrete White Poor VA Castle Point a005 bldg 21 A-005 Anthony Dhanpat

41 0.2 mg/cm2 Negative 5/15/2020 11:00:48 Lead Paint Room Wall Wall 3 Concrete White Poor VA Castle Point a005 bldg 21 A-005 Anthony Dhanpat

42 0.3 mg/cm2 Negative 5/15/2020 11:01:14 Lead Paint Room Wall Wall 4 Concrete White Poor VA Castle Point a005 bldg 21 A-005 Anthony Dhanpat

43 0.5 mg/cm2 Negative 5/15/2020 11:03:12 Lead Paint Room Wall Wall 1 Concrete White Poor Common AreaVA Castle Point bldg 21 Anthony Dhanpat

44 0.2 mg/cm2 Negative 5/15/2020 11:03:30 Lead Paint Room Wall Wall 2 Concrete White Poor Common AreaVA Castle Point bldg 21 Anthony Dhanpat

45 0.6 mg/cm2 Negative 5/15/2020 11:03:43 Lead Paint Room Wall Wall 3 Concrete White Poor Common AreaVA Castle Point bldg 21 Anthony Dhanpat

46 0.2 mg/cm2 Negative 5/15/2020 11:04:00 Lead Paint Room Wall Wall 4 Concrete White Poor Common AreaVA Castle Point bldg 21 Anthony Dhanpat

47 0.6 mg/cm2 Negative 5/15/2020 11:05:17 Lead Paint Door Door Wall 1 Metal Blue Poor Common AreaVA Castle Point bldg 21 a001 A001 Anthony Dhanpat

48 0.1 mg/cm2 Negative 5/15/2020 11:05:33 Lead Paint Door Door Buck Wall 1 Metal Blue Poor Common AreaVA Castle Point bldg 21 a001 A001 Anthony Dhanpat

49 0.2 mg/cm2 Negative 5/15/2020 11:06:07 Lead Paint Room Wall Wall 1 Concrete White Poor Common AreaVA Castle Point bldg 21 a001 A001 Anthony Dhanpat

50 -0.3 mg/cm2 Negative 5/15/2020 11:06:24 Lead Paint Room Wall Wall 1 Concrete White Poor Common AreaVA Castle Point bldg 21 a001 A001 Anthony Dhanpat

51 4.3 mg/cm2 Positive 5/15/2020 11:06:59 Lead Paint Room Wall Wall 2 Concrete White Poor Common AreaVA Castle Point bldg 21 a001 A001 Anthony Dhanpat

52 1.2 mg/cm2 Positive 5/15/2020 11:08:24 Lead Paint Room Wall Wall 3 Concrete White Poor Common AreaVA Castle Point A001 Anthony Dhanpat

53 3.9 mg/cm2 Positive 5/15/2020 11:08:55 Lead Paint Room Wall Wall 4 Concrete White Poor Common AreaVA Castle Point A001 Anthony Dhanpat

54 0.2 mg/cm2 Negative 5/15/2020 11:10:09 Lead Paint Door Door Wall 1 Metal Blue Poor Common AreaVA Castle Point A002 Anthony Dhanpat

55 0.4 mg/cm2 Negative 5/15/2020 11:10:21 Lead Paint Door Door Buck Wall 1 Metal Blue Poor Common AreaVA Castle Point A002 Anthony Dhanpat

56 3 mg/cm2 Positive 5/15/2020 11:10:59 Lead Paint Room Wall Wall 1 Concrete White Poor Common AreaVA Castle Point A002 Anthony Dhanpat

57 0.2 mg/cm2 Negative 5/15/2020 11:11:19 Lead Paint Room Wall Wall 2 Concrete White Poor Common AreaVA Castle Point A002 Anthony Dhanpat

58 0.1 mg/cm2 Negative 5/15/2020 11:11:33 Lead Paint Room Wall Wall 3 Concrete White Poor Common AreaVA Castle Point A002 Anthony Dhanpat

59 2.7 mg/cm2 Positive 5/15/2020 11:11:51 Lead Paint Room Wall Wall 4 Concrete White Poor Common AreaVA Castle Point A002 Anthony Dhanpat

60 0.4 mg/cm2 Negative 5/15/2020 11:13:08 Lead Paint Angle Iron Floor Metal Gray Poor Common AreaVA Castle Point A002 Anthony Dhanpat

61 1 mg/cm2 Positive 5/15/2020 11:15:42 Lead Paint Calibrate Metal Gray Poor Common AreaVA Castle Point Anthony Dhanpat

62 1.1 mg/cm2 Positive 5/15/2020 11:15:57 Lead Paint Calibrate Metal Gray Poor Common AreaVA Castle Point Anthony Dhanpat

63 1 mg/cm2 Positive 5/15/2020 11:16:12 Lead Paint Calibrate Metal Gray Poor Common AreaVA Castle Point Anthony Dhanpat

64 0.1 mg/cm2 Negative 5/15/2020 11:16:31 Lead Paint Calibrate Metal Gray Poor Common AreaVA Castle Point Anthony Dhanpat

65 0.1 mg/cm2 Negative 5/15/2020 11:16:41 Lead Paint Calibrate Metal Gray Poor Common AreaVA Castle Point Anthony Dhanpat

66 0 mg/cm2 Negative 5/15/2020 11:16:48 Lead Paint Calibrate Metal Gray Poor Common AreaVA Castle Point Anthony Dhanpat

Appendix B:

Positive Lead Shots Diagram

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

F i l e

P a t h

P

M

DESIGN DEVELOPMENT

Office of

Construction and Facilities

Management U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEER

WATSON ENGINEERING

1112 STATE ROUTE 434

OWEGO NY, 13827

(607)-223-4334

REPLACE DOMESTIC HOT

WATER SYSTEMS

CASTLE POINT VA CAMPUS

620A4-19-122

19 - 20 - 21 Project Director

04/30/2020 EMW CDPRevisions: Date:

BUILDING 19, 20, 21

ARCHITECTURAL PLAN

A-101

KEYED NOTES

SCALE: 3/8" = 1'-0"

BUILDING 19 ARCHITECTURAL PLAN

F1

SCALE: 1" = 100'-0"

KEY PLAN

SCALE: 3/8" = 1'-0"

BUILDING 20 ARCHITECTURAL PLAN

F5

SCALE: 3/8" = 1'-0"

BUILDING 21 ARCHITECTURAL PLAN

C5

REPLACE EXISTING DOOR AND FRAME. SEE

DOOR SCHEDULE.

EXISTING FLOORS SHALL BE REFINISHED WITH

STONHARD STONGARD MR OR EQUIVALENT

3 EXISTING WALLS IN ROOM SHALL BE PAINTED.

REFER TO SCHEDULES FOR DETAILS.

SCALE: 3/8" = 1'-0"

BUILDING 20 ARCHITECTURAL PLAN

F8

2 3

DOOR HARDWARE SCHEDULE

SET NO. HINGES LOCK SERIES

PUSH

PLATES CLOSERS HOLDERS PLATES REMARKS

11C

A8111

/A5111 F07 J302

C02011/

C02021 L02121 J102

MECHANICAL ROOM - REFER TO

SPECIFICATION

DOOR SCHEDULE

NO. ROOM SIZE MATERIAL TYPE FRAME LABEL HARDWARE REMARKS

1 A-001 4'-0" X 7'-0" X 1 3/4" HOLLOW METAL HOLLOW METAL 1-HR 11C

2 A-002 3'-6" X 7'-0" X 1 3/4" HOLLOW METAL HOLLOW METAL 1-HR 11C

3 B-001 3'-6" X 7'-0" X 1 3/4"

HOLLOW METAL HOLLOW METAL 1-HR 11C

4 B-005 3'-6" X 7'-0" X 1 3/4" HOLLOW METAL HOLLOW METAL 1-HR 11C

5 C-001 3'-6" X 7'-0" X 1 3/4" HOLLOW METAL HOLLOW METAL 1-HR 11C

ROOM FINISH SCHEDULE

RO

O

M N

U M

BE

R

ROOM NAME FL

O

O R

FI

N

IS

H

WALL FINISH CEILINGS

RE

M

AR

KS

PL

AN

N O

RT

H

PL

AN

E

AS

T

PL

AN

S O

U

TH

PL

AN

W

ES

T

C O

V E

B

A S

E

A

L L

W

A L L S

FI

N

IS

H

A-001 TANK RM

STONGARD MR

PEWTER WHITE WHITE WHITE WHITE

S T

O N

G A

R D

O

V E

R L A

Y M

E N

T

P E

W T

E R

EXISTING

A-002 MECHANICAL

STONGARD MR

PEWTER WHITE WHITE WHITE WHITE EXISTING

B-001 TANK RM

STONGARD MR

PEWTER WHITE WHITE WHITE WHITE EXISTING

B-005 MECHANICAL

STONGARD MR

PEWTER WHITE WHITE WHITE WHITE EXISTING

C-001 TANK RM

STONGARD MR

PEWTER WHITE WHITE WHITE WHITE EXISTING

4 INSTALL NEW EQUIPMENT PADS. REFER TO

DETAIL 7/P-501. L & W DIMENSIONS SHALL BE 6"

GREATER THAN THE EQUIPMENT BASE PLATE.

F1

F5

F8

C5

AutoCAD SHX Text

UP

AutoCAD SHX Text

TANK

AutoCAD SHX Text

TUNNEL

AutoCAD SHX Text C-001

AutoCAD SHX Text

MECH ROOM

AutoCAD SHX Text C-002

AutoCAD SHX Text

ELECT.

AutoCAD SHX Text B-005

AutoCAD SHX Text

MECHANICAL

AutoCAD SHX Text B-006

AutoCAD SHX Text

UP

AutoCAD SHX Text

TANK

AutoCAD SHX Text B-001

AutoCAD SHX Text

STEAM RM

AutoCAD SHX Text B-002

AutoCAD SHX Text

TUNNEL

AutoCAD SHX Text

TANK RM

AutoCAD SHX Text A-001

AutoCAD SHX Text

MECHANICAL

AutoCAD SHX Text A-002

AutoCAD SHX Text

STORAGE

AutoCAD SHX Text A-003

AutoCAD SHX Text A-003

AutoCAD SHX Text A-003

AutoCAD SHX Text A-003

AutoCAD SHX Text A-003 mrive Rectangle mrive Rectangle mrive Rectangle mrive Callout mrive Callout mrive Callout mrive Callout mrive Rectangle mrive Callout mrive Callout mrive Callout mrive Callout mrive Rectangle mrive Rectangle mrive Rectangle mrive Callout mrive Callout mrive Callout mrive Rectangle mrive Rectangle mrive Callout mrive Callout mrive Text Box Building 19, 20, and 21 Positive Lead Shot Locations

Appendix C:

Lead Inspector/Risk Assessor, Company Certifications

Lead Shot Locations.pdf
Replace Domestic Hot Water-T-001
Sheets and Views
Replace Domestic Hot Water-T-001
Replace Domestic Hot Water-G-001
Sheets and Views
Replace Domestic Hot Water-G-001
Replace Domestic Hot Water-A-001
Sheets and Views
Replace Domestic Hot Water-A-001
Replace Domestic Hot Water-A-101
Sheets and Views
Replace Domestic Hot Water-A-101
Replace Domestic Hot Water-P-001
Sheets and Views
Replace Domestic Hot Water-P-001
Replace Domestic Hot Water-PD101
Sheets and Views
Replace Domestic Hot Water-PD101
Replace Domestic Hot Water-PD102
Sheets and Views
Replace Domestic Hot Water-PD102
Replace Domestic Hot Water-PD103
Sheets and Views
Replace Domestic Hot Water-PD103
Replace Domestic Hot Water-P-101
Sheets and Views
P-101
Replace Domestic Hot Water-P-102
Sheets and Views
P-102
Replace Domestic Hot Water-P-103
Sheets and Views
P-103
Replace Domestic Hot Water-P-501
Sheets and Views
Replace Domestic Hot Water-P-501
Replace Domestic Hot Water-P-601
Sheets and Views
Replace Domestic Hot Water-P-601
Replace Domestic Hot Water-E-001
Sheets and Views
Replace Domestic Hot Water-E-001
Replace Domestic Hot Water-E-101
Sheets and Views
Replace Domestic Hot Water-E-101
Replace Domestic Hot Water-E-201
Sheets and Views
Replace Domestic Hot Water-E-201
Replace Domestic Hot Water-E-501
Sheets and Views
Replace Domestic Hot Water-E-501