This scope of work document outlines requirements for a design-build project to prepare site work for an MRI D-Stream upgrade at the Stratton VA Medical Center in Albany, New York. The selected contractor will provide all design, construction, labor, materials, equipment, and services to complete the project, including upgrading existing rooms that house MRI equipment. Key requirements include conducting on-site investigations to verify existing conditions; developing design drawings using project specifications and manufacturer documentation; complying with applicable building codes and safety standards; and completing construction within a 90-calendar day period of performance. The contractor must protect existing infrastructure and operations during the work without service disruptions. The project value is estimated between $500,000 to $1,000,000. The solicitation will be set aside for small businesses only and issued on April 9, 2020.
36C24220R0072 528A8-18-806 SOW D-Stream Upgrade R2 3-19-20.pdf
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK:
Project 528A8-18-806 D-Stream Upgrade Site Preparation
Bldg. 1 VAMC, 113 Holland Ave., Albany, NY
I. PROJECT DESCRIPTION
The Stratton VA Medical Center (VAMC) in Albany, NY is upgrading its existing 1.5T MRI machine. Philips
Healthcare is contracted with the Stratton VA Medical Center to furnish and install a D-Stream upgrade to the existing MRI. This upgrade will essentially replace all the MRI system’s components excluding the magnet. This contract will cover the site preparation work that will prepare the [MRI Computer (A209), MRI Scan (A210), MRI
Control (A212), Supply Room (A213) and other] areas for Philips’ installation.
This Scope of Work shall only be bid on by design/build contractors who are competent in Philips MRI construction site preparation design and have completed 4 MRI projects in the last 5 years within the VAMC system. Within the
Contractor’s bid, the Contractor shall provide their portfolio detailing the Philips MRI systems they have installed meeting these criteria. To maximize the design’s accuracy, the design/build contractor shall perform a full depth, on-site investigation to fully verify existing conditions. The Contractor shall use Philips’ Final Site Preparation
Support Document as their primary basis for design/construction. The Contractor shall extensively review Philips’ document and the rest of this Scope of Work for accuracy and make any appropriate corrections to provide the result, a properly functioning, upgraded Philips MRI. The Contractor shall comply with all applicable (VA) design manuals and codes for design and construction. The VA has included the most relative VA Design Manuals
(Electrical, HVAC, Lighting & Plumbing) for reference.
The Period of Performance for Design shall NOT exceed 90 calendar days. To ensure the VA is provided a suitable design, the Contractor/Designer shall conduct an on-site Concept Review with the VA. Afterwards, the
Contractor/Designer shall submit a 60% and (upon approval a) 95% design for the VA to review. If corrections to the work listed below or Philip’s documents are required, the Contractor shall contact the VA COR and Philips to verify and approve the correction(s). Once the 95% design is complete and approved, the Contractor shall coordinate with the VA and Philips to prepare for demolition/construction.
Throughout the Contractor’s work, the magnet shall be ramped down. Philips states the magnet will not produce a magnetic field but will continue to require cooling. The existing chiller (located in mechanical areaway adjacent to
A-wing) and cryocooler chiller/cryocompressor (located in Computer Room) shall remain active throughout most of the site preparation (further details provided below). Philips will occasionally be on site to monitor progress and conduct simpler installations (further details provided below). The MRI upgrade site preparation work must be complete and approved by Philips prior to Philips’ delivery of the remaining upgrade/installation. Please note the construction timeframe is very time-sensitive because this is the station’s only MRI and it will not be substituting its services with a mobile unit during construction. Due to the time-sensitive matter, construction shall NOT exceed the Period of Performance of 90 calendar days. It is critical for the Contractor to stay on track with the agreed upon construction schedule/performance dates and Period of Performances.
Specific work requirements include, but are not limited to the following:
1. Protect all items and finishes to remain. Repair any damage caused by construction to the original state or better.
2. Contractor shall provide professional, full-time on-site supervision of the work.
3. Contractor shall develop a schedule and conduct weekly construction meetings and prepare the meeting minutes.
4. Contractor shall provide all required survey and testing work.
5. Contractor shall utilize the Philips’ Final Site Preparation Support Document as the basis for construction drawings.
6. Contractor shall review all shop drawings, submittals and RFIs prior to submitting to VA COR.
7. Note, all construction in the MRI Scan Room shall be composed of non-ferromagnetic material.
8. Once the construction is complete, the Contractor shall provide two fully signed and sealed sets of hard copy as-built drawings to the VAMC for their records and use. Contractor shall also provide CADD files formatted for AutoCAD 2019 and PDF files.
9. All work shall be performed and accomplished according to Albany VAMC’s specifications, including
General Requirements, Safety and Infection Control requirements.
a. Coordinate power and other utility shutdowns with the VA COR. Provide the VA COR a minimum 2-week notice.
b. Construct and maintain all Infection Control requirements, especially proper temporary construction barriers to ensure the safety of patients in adjacent areas.
i. Construction barriers shall be one-hour fire rated.
ii. Temporary doors on a closer shall be 45-minute fire rated.
iii. Anteroom(s) shall be constructed outside of each construction entrance.
1. All construction workers shall use the anteroom(s) to clean off dust and debris from themselves and their equipment and to change out of any work-related equipment before exiting the construction site.
2. The Radiology department on 2A will remain active throughout demolition/construction. The Contractor shall ensure the hazards of construction (equipment, trash, dust/debris, etc.) do not get tracked outside the construction area(s).
iv. Implement negative air pressure machines.
1. Maintain a minimum of -0.02” WC in area(s) of construction.
v. The Contractor shall be mindful of walking through the corridors leading to the construction areas. The Contractor will immediately clean (dirt, dust, debris, etc.) marks caused by construction in these active, patient corridors.
vi. Although there will not be a magnetic field during demolition/construction, contractors shall practice MRI safety procedures when working around the MRI:
1. Comply with all applicable MRI safety procedures.
2. All construction workers must complete VA MRI Safety Training or (with COR’s acceptance) equivalent course before beginning demolition/construction work.
3. All contractors under this project shall take the safety training (~1 hour) performed by the VA’s Safety department. Once the contractor(s) has passed the training, they will receive a personal contractor badge (free of charge) that he/she must always wear while on the VA campus. The contractors shall obtain this badge prior to demolition/construction. In the case the contractor loses his/her badge, the contractor must file a report to the VA Police and request a new badge. There may be a fee for the replacement badge.
4. All contractors shall be screened for ferromagnetic implants prior to demolition/construction.
c. Any work causing significant noise or vibration will be performed within designated off-hours.
5:30pm-1am weekdays, or 7am-10pm weekends. These timeframes will be the designated off-hours unless otherwise specified herein or ordered by the VA COR. Off-hour work shall be coordinated with the VA COR. The Contractor shall verify Radiology is complete with patient care before beginning such work.
10. Notable work including some from Philips’ drawings (Contractor shall conduct the MRI upgrade site preparation requirements in the exact format as noted on Philips’ drawings):
a. MRI Computer Room
i. Prior to the Contractor’s demolition/construction work, Philips will disconnect and remove most of Philips Healthcare MRI equipment in the MRI Computer Room. These items include the existing Gradient Amplifier, Data Acquisition and Control Cabinet, Mains Distribution Cabinet, System Filter Box (SFB), UPS Cabinet, Battery Cabinet, FA
Series Three Phase Filter and A/C chiller.
1. There are notable items that Philips and the Contractor shall not remove and will remain in operation until the very end of construction to limit the magnet from losing its helium. These items include the cryocooler chiller (cryocooler compressor), cryocooler chiller’s plumbing lines and the exterior chiller including its lines (located in the areaway between 2A and the Emergency
Department circle).
2. Prior to Contractor’s demolition/construction work, the VA (FMS & Radiology departments) will claim any small items not intended to be discarded. The VA will store them until the end of construction. Once construction has concluded, the items will be reinstalled within the site.
ii. The Contractor shall protect the cryocooler chiller and its plumbing lines (noted above) throughout construction until they are ready to be replaced by the Liquid Cooling
Cabinet (LCC) and Chiller Interface Panel (CIP). The Contractor shall also protect the exterior chiller (and its lines) and lines (including He gas and gradient ventilation and gradient cooling lines) that are connected to the magnet’s assembly.
iii. The Contractor shall remove ceiling grid and ceiling tiles.
1. Existing position of sprinkler lines will conflict with new work. The Contractor shall modify/move the sprinkler lines (height & distance) as needed and comply with the Life Safety Code 2018 and all referenced publications.
a. Contractor shall coordinate with the VA to de-energize the sprinkler line(s) within the MRI Computer Room. The VA will de-energize the lines. Once the lines have been de-energized, the Contractor shall isolate the line (going into the room) from the rest of the system.
Coordinate this work with the other rooms. The Contractor shall cap the existing system and the VA will re-energize the lines to restore fire protection to the wing.
b. The Contractor shall also paint the sprinkler lines (within the room) red.
c. The Contractor shall pressure test the modified sprinkler line.
d. Once the renovation in the MRI Computer Room has been completed, the Contractor shall coordinate with the VA to de-energize the sprinkler lines. The Contractor shall reconnect the branch line to the existing system. The VA will energize the lines.
2. The Contractor shall move light fixtures if they are obstructing new work.
Properly support relocated fixtures and light fixtures to remain in place if they aren’t properly supported.
a. If the sprinkler heads are raised, raise the light fixtures to be on the same plane or higher than the sprinkler heads.
iv. The Contractor shall install the new Chiller Interface Panel (CIP) in the designated location and install its plumbing lines and valves.
1. Philips will furnish a Liquid Cooling Cabinet (LCC) that will ultimately replace the
A/C chiller and cryocooler chiller for the upgrade. The Contractor shall install
Philips’ LCC. The Contractor shall install all piping, controls and electrical from the new chiller (noted later under Miscellaneous) to CIP. Philips will make the final connections between the CIP and LCC. Once the new LCC and new exterior chiller are operational, a mechanical shutdown will need to be coordinated with the VA COR. The Contractor shall disconnect the cryocooler chiller and
Philips should claim it. Once the LCC is in operation, the Contractor can also remove the existing lines once tied to the A/C chiller (Computer Room) and cryocooler chiller (Computer Room).
a. For all shutdowns on the cryocooler chiller and exterior chiller, the maximum downtime shall be 6 hours. If the Contractor’s work exceeds the allotted time and/or conducts work outside the normal scope, the
Contractor will be liable for the cost of refilling the helium the magnet had lost.
v. The Contractor’s radio frequency (RF) shield vendor shall make an opening between the
MRI Computer Room and MRI Scan Room for the new SFB. Install opening at Philips’ specified location. Once the opening has been made, the Contractor’s RF shield vendor shall install the interface plate that will be connected to the new SFB. The interface plate and SFB are shown on Drawing SD2. The Contractor shall cut the studs blocking the penetration.
1. The Contractor shall block off the existing letterbox style feedthrough at the existing SFB opening, install the missing studs and patch/repair the wall
(including RF shield).
2. Once the RF shield vendor has installed the interface plate in the new opening, Philips will furnish and install the new SFB.
3. The Contractor’s RF shield vendor shall also relocate the external/internal PE bus bar or “passthrough ground plate” from above the existing SFB to above the new SFB. The external/internal PE bus bar is shown on Drawing ED1.
a. The Contractor’s RF shield vendor shall make another hole for the relocation and repair/patch the existing location.
4. The Contractor shall coordinate the work with the RF shield vendor to ensure the RF shield remains functional after the work has been completed.
vi. The Contractor shall relocate existing electrical filters as needed. Ground electrical filters to the nearby bus bar.
vii. The Contractor shall install all required raceways including the cable trays for the new
Philips Healthcare MRI equipment, as shown on Philips’ drawings.
1. The Contractor shall make connections to Philips equipment that does not have its installation covered by Philips, refer to Philips’ Drawing AL.
2. The Contractor shall utilize the newly installed cable tray for the cabling.
viii. Philips will remove Power Distribution Unit (PDU), also referred to as the transformer, located next to 10-ton Liebert unit. The Contractor shall remove all associated cabling/raceways to its electrical panel.
ix. Philips will furnish a Mains Distribution Unit (MDU), the Contractor shall install.
x. The Contractor shall use the existing Circuit Breaker for System (CBS) for the upgrade.
xi. Philips will furnish a UPS and its Remote Status Panel (RSP), the Contractor shall install.
xii. Philips will furnish a Battery Cabinet (BC), the Contractor shall install.
xiii. Philips will furnish a FA Series Three Phase Filter (FAF), the Contractor shall install.
xiv. The Contractor shall remove and replace gradient exhaust fan. The Contractor shall provide test, adjust and balance (TAB) and commission the new exhaust fan.
1. The Contractor shall rework (as needed) the exhaust fan’s ductwork “cooling lines” above the ceiling to make room for the cable tray’s design and around the MRI’s bonnet (Scan Room).
2. The Contractor shall also clean and correctly route the cooling lines.
3. If the Contractor modifies the cooling lines, the Contractor shall furnish and install aluminum fittings for the cooling lines.
xv. According to Philips, Philips will provide a new Patient Ventilation (PV) and a new set of hoses. The Contractor shall remove and replace the PV and hoses. Drawing SD3 provides more information.
1. The Contractor shall remove and replace the PV and its hoses.
2. The Contractor shall make all appropriate connections for the hoses.
a. The Contractor shall replace the grill and air filter – Located in Scan
Room.
3. Just a note, the PV’s lines shall be removed. The Gradient Ventilation lines shall remain.
xvi. Contractor shall remove and replace the 10-ton Liebert package-cooling unit with an approved equivalent (capacity and size – dimensions).
1. Contractor shall also remove and replace its associated condensing unit, refrigerant lines, refrigerant and equipment supports – install appropriate equipment rails located on 2nd floor’s low roof and electrical and controls.
a. The spaces for the cooling and condensing unit are very limited.
Contractor shall verify size requirements with a site visit.
b. The low roof was installed by an approved Tremco manufacturer and currently carries a warranty. If the section of the low roof by the condensing unit is damaged, the Contractor shall have an approved
Tremco-installer repair the section prior to full installation of the condensing unit and equipment rails.
2. Existing unit: Liebert FH125A-A00 A/C unit and condensing unit.
3. New Unit:
a. Nominal 10-ton capacity
b. Dual Compressors and 2 independent refrigeration circuits.
c. Downflow underfloor configuration
d. 4” MERV 8 Filters (2 sets)
e. Forward Curved Blower
f. Infrared humidifier
g. Electric Reheat
h. Capable of operating to -10F outdoor
i. Variable speed compressor
j. Microprocessor controls with Bacnet interface
k. Cool, Heat, Dehumidify, Humidify modes
l. Condensate Pump
m. Floor stand (existing may be re-used if in good condition and properly sized)
4. Connect AHU to Building Management System (BMS) with Automated Logic
DDC controls.
a. Contractor shall be responsible for the tie-in of the control system to the BMS. This includes the building of all graphics on the BMS. Provide
Bacnet gateway if required.
b. Furnish and install a temperature & humidity monitoring device(s) located within the room to provide feedback for modulating the discharge air temperature and humidity of the AHU.
c. Provide water sensor alarm (local and BMS) in the event of water leakage below the floor
5. Re-connect electric to AHU and condensing unit.
a. Provide new disconnects and fuses as required
6. Provide ventilation air to the equipment room from an existing branch supply duct of AHU-2A in the adjacent corridor. Extend a 10x8 duct with balancing damper from AHU-2A branch duct to an 8x8 ceiling mounted supply grille and balance for 250 CFM. Provide fire damper and access panel in corridor wall.
7. TAB and commission the newly installed AHU.
8. Evacuate/reclaim refrigerant gases – provide report.
9. Condensing unit located on 2nd floor’s low roof – Rigging required.
a. Referring to note above, remove and replace condensing unit’s supports with equipment rails that mount to the roof.
b. The Contractor shall hire a Tremco-certified installer to aid in equipment rail installation and roof repair.
10. Remove and replace cooling condensate drain and condensate pump.
11. Re-connect DCW to humidifier
xvii. Once the work to the walls has been completed (openings in the RF shield have been repaired and the gypsum board wall(s) has been closed/repaired), repaint all walls affected by the work. The Contractor shall coordinate with the VA for the specific color selection.
a. After prime coat, minimum of 2 coats for finish coat.
b. Contractor shall paint with Benjamin Moore Eco Spec WB Interior
Latex Paint.
b. MRI Scan Room
i. Prior to the Contractor’s construction work, Philips will disconnect the Patient Support and the magnet’s covers.
ii. Prior to the Contractor’s construction work, the VA will claim any small items not intended to be discarded. The VA will store them until the end of construction. The
Contractor shall remove (pre-demolition), salvage and reinstall the scan room’s vertical blinds (post-construction).
iii. The Contractor shall secure a tarp over the magnet’s assembly to prevent any dust or debris from contaminating it throughout demolition/construction. The Contractor shall also protect the existing helium exhaust pipe (HEP) and lines (including gas) connected to the magnet’s assembly.
iv. The Contractor shall coordinate with the VA to de-energize the sprinkler line(s) within the MRI Scan Room. The VA will de-energize the lines. Once the lines have been de-energized, the Contractor shall isolate the line (going into the room) from the rest of the system. Coordinate this work with the other rooms. The Contractor shall cap the existing system and the VA will re-energize the lines to restore fire protection to the wing. Once renovation work in the MRI Scan Room has been completed, the Contractor shall coordinate with the VA to de-energize the sprinkler lines. The Contractor shall reconnect the branch line to the existing system. The VA will energize the lines.
v. The MRI Scan Room’s ceiling (grid) will remain intact and shall be protected by the
Contractor. The Contractor shall remove the ceiling (including grid as necessary) nearby the MRI Scan Room’s existing cable tray to conduct required work. Once above-ceiling work in the MRI Scan Room has concluded, the Contractor shall (reinstall areas of removed ceiling grid and) replace all ceiling tiles within the Scan Room.
1. Once the new SFB has been installed between the MRI Computer and MRI Scan
Room, the Contractor’s electrician shall evaluate the MRI Scan Room’s cable tray and determine whether the tray needs to be moved, modified and/or replaced.
vi. The Contractor shall remove and replace the anti-static flooring system within the MRI
Scan Room. Ensure the replacement product(s) is MRI compatible. For more information, please refer to Drawing SD1.
1. Philips shall raise the magnet by ¼” to meet the height of the new D-Stream table.
2. The Contractor shall furnish and replace the Patient Support’s mounting plates as needed.
vii. The HEP within the RF shield and exterior to the building will need to be modified.
1. Within the RF shield, Philips has informed the VA the HEP needs to be straightened to comply with their requirements. Philips has included a picture
(IMG_3359.JPG) that shows the HEP sloping down before it reaches the helium wave guide (HWG).
a. Philips will straighten the HEP within the RF shield. The Contractor shall insulate the HEP once the line has been reworked.
A. Before Philips can straighten the HEP, the Contractor shall move existing obstructions (including HEP supports) in the
HEP’s path. The work also includes the Contractor enlarging the circle in the gypsum board to allow the HEP to exit the wall horizontally. Photos of the existing condition of the
HEP are shown on IMG_0575 and IMG_0586.
1. To do the work noted above, the Contractor shall remove and reinstall the ceiling grid (and replace tiles – noted earlier) within the working space of the
HEP. Store removed ceiling grid (and supports as needed) in a secure location.
2. On the exterior of the building, the Contractor shall construct a HEP specific box that will serve as the helium’s primary containment if the magnet ever quenches. The HEP-specific box shall be constructed to prevent helium from flooding the mechanical areaway below the HEP. Containment requirements are provided on file: Helium vent pipe outside_rev01_outershield.pdf. This document was provided by Philips’ Field Engineer and will serve as the requirements for the custom-made box. The Contractor shall rework the HEP discharge as needed to meet all requirements of the provided document.
a. Refer to the PDF document for all requirements.
b. Several highlighted requirements are:
A. The containment shall have an accessible service hatch.
B. The containment shall be made of material able to withstand temperatures as low as -406 degrees Fahrenheit, handle a working pressure of 1 Bar and is non-ferromagnetic (most contractors use stainless steel).
C. The containment shall be wall-mounted to the building.
D. The Contractor shall route the box’s drainage piping to one of the floor drains in the mechanical areaway.
viii. The Contractor shall remove and replace the existing lighting fixtures in the MRI Scan
Room.
1. The Contractor shall remove existing incandescent light fixtures in MRI Scan
Room and replace them with MRI-compatible, dimmable LED high-hat fixtures.
2. The Contractor shall furnish and install an MRI-compatible, non-ferromagnetic, ceiling-mounted, surgical swing light for patient injection. The Contractor shall remove existing recessed cove lighting fixture above soffit containing overhead image and could repurpose the lighting’s power for this ceiling mounted, swing light.
a. Furnish and install light switch for the surgical light. Light switch shall be wall-mounted and located at the entrance to the room. Verify location with on-site visit.
A. Light switch that once powered the cove lighting can be reused if still operational (located in Control Room).
b. Install surgical light fixture in location where it is not in the way of injection procedures but provides adequate lighting for technician;
verify on-site.
A. Construct non-ferromagnetic ceiling support structure as needed.
ix. The Contractor’s electrician will need to verify locations of existing conduits and comply with Philips’ requirements. The electrician may need to snake guide wire and implement guide poles.
x. The electrician’s wiring shall meet the associated cabling going towards the MRI Control
Room (for electrical work between Scan and Control Rooms).
xi. Contractor shall cut openings in the supply/return HVAC ductwork in the locations of the RF filters. Construct access panels large enough to clean off the debris. Contractor shall clean the filters while the access panels are open.
xii. Contractor shall rework the fingers on both MRI Scan Room doors.
xiii. Contractor shall repair damaged/marked door thresholds between MRI Control/MRI
Scan Room & MRI Scan Room/corridor.
1. Sand down the thresholds as needed.
xiv. Contractor shall install an emergency pressure relief grid RF feedthrough: RF-protected opening in wall between MRI Scan/MRI Control Room; location of opening to be verified on site.
xv. The Contractor’s RF shield vendor shall install all required penetrations and seal any gaps around them (the work includes the new and existing SFB, the gradient passthrough and emergency pressure relief grid). The SFBs and gradient passthroughs are located between the MRI Scan and MRI Computer Room. The emergency pressure relief grid is located between the MRI Scan and MRI Control Room.
1. The vendor shall rework all deficient areas of the shield to ensure the shield meets Philips’ specifications. The existing shield is stainless steel.
2. Once the RF shield vendor has fully sealed the MRI Scan Room’s RF shield, the vendor shall conduct a RF test. This test shall be conducted prior to the magnet being brought up to field strength. The test shall be witnessed by Philips personnel and is required to meet or exceed Philips’ specifications.
3. Once the RF shield passes the test, the RF shield vendor shall implement alarms to sound if any work comes in contact/damages the shield. For clarification, Philips can provide a more descriptive requirement.
4. The VA is providing the results of Philips’ RF shielding test they conducted in
2018.
xvi. The Contractor shall install gypsum board on the open penetrations in the wall after the
RF test has been passed. Referring to the previous note, the Contractor must be wary when doing this work to not damage the RF shield. The RF shield vendor’s alarms shall sound if the RF shield is damaged.
1. If the shield is damaged, the Contractor shall notify the VA COR and repair the
RF shield (and wall). The repair(s) will be conducted at the cost of the
Contractor.
2. Once the wall(s) has been closed, repaint all walls affected by the work. The
Contractor shall coordinate with the VA for the specific color selection.
a. After prime coat, minimum of 2 coats for finish coat.
b. Contractor shall paint with Benjamin Moore Eco Spec WB Interior
Latex Paint.
xvii. Philips will remove existing Emergency Run-Down Button (ERB). Philips will furnish new
ERB, Philips will install.
1. The Contractor shall supply pull wire as needed.
xviii. The Contractor shall remove the removable panels, panels’ supports (including gypsum board framing) and trim around MRI’s bonnet.
1. Current height of panels is 8’-4” above finished floor (AFF).
2. The Contractor shall furnish and install MRI-compatible ceiling grid and ceiling tiles. Contractor shall install Armstrong Prelude XL – Aluminum 15/16” in White around new bonnet at maximum height of 8’-2 1/8” AFF (per Philips’ Drawing
AD3). Ceiling tiles shall be Armstrong 1728.
xix. Philips will remove existing speakers. Philips will furnish new speakers, Philips will install.
1. The Contractor shall provide guide wires as needed.
2. The Contractor shall cut/provide new spaces in ceiling for speakers. Contractor shall also patch/restore areas of old speakers.
xx. The Contractor shall reinstall vertical blinds on MRI Scan Room window post-construction.
c. MRI Control Room
i. Prior to the Contractor’s construction work, the VA will claim any small items not intended to be discarded. The VA will store them until the end of construction.
ii. The Contractor shall secure a tarp over the operator’s tables to prevent any dust or debris from falling on it throughout demolition/construction.
iii. The Contractor shall coordinate with the VA to de-energize the sprinkler line(s) within the MRI Control Room. The VA will de-energize the lines. Once the lines have been de-energized, the Contractor shall isolate the line (going into the room) from the rest of the system. Coordinate this work with the other rooms. The Contractor shall cap the existing system and the VA will re-energize the lines to restore fire protection to the wing. Once renovation work in the MRI Scan Room has been completed, the Contractor shall coordinate with the VA to de-energize the sprinkler lines. The Contractor shall reconnect the branch line to the existing system. The VA will energize the lines.
iv. Philips will remove existing ERB. Philips will furnish new ERB, Philips will install.
1. The Contractor shall supply pull wire as needed.
v. The Contractor to install Code Blue button in Control Room. The button shall be located near the technician’s desk and doorway leading to Scan Room. Exact location within room to be determined by VA COR and Radiology staff.
1. Install cabling to nearest control board. There is a control board in the branch corridor.
vi. The Contractor shall repaint the wall(s) affected by demolition/construction, including the work to install an emergency pressure relief grid RF feedthrough.
1. After prime coat, minimum 2 coats for finish coat.
2. The Contractor shall paint with Benjamin Moore Eco Spec WB Interior Latex
Paint.
a. The Contractor shall consult with the VA for specific color selection.
d. Supply Room
i. Prior to the Contractor’s construction work, the VA will claim any items not intended to be discarded. The VA will store them until the end of construction.
ii. There is no construction scheduled in the restroom behind the Supply Room.
iii. The Contractor shall coordinate with the VA to de-energize the sprinkler line(s) within the Supply Room. The VA will de-energize the lines. Once the lines have been de-energized, the Contractor shall isolate the line (going into the room) from the rest of the system. Coordinate this work with the other rooms. The Contractor shall cap the existing system and the VA will re-energize the lines to restore fire protection to the wing. Once renovation work in the MRI Scan Room has been completed, the Contractor shall coordinate with the VA to de-energize the sprinkler lines. The Contractor shall reconnect the branch line to the existing system. The VA will energize the lines.
iv. The Contractor shall remove and replace 3-ton Liebert unit with an approved equivalent
(capacity and size – dimensions).
1. The Contractor shall also remove and replace its associated condensing unit, refrigerant lines, refrigerant and equipment supports, electrical and controls – install appropriate equipment rails located in sub-grade mechanical areaway.
2. New Unit:
a. Nominal 3-ton capacity
b. Upflow, ducted supply and return air configuration
c. 2” MERV 8 Filters (2 sets)
d. Infrared humidifier
e. Electric Reheat
f. Capable of operating to -10F outdoor
g. Microprocessor controls with Bacnet interface
h. Cool, Heat, Dehumidify, Humidify modes
i. Variable speed compressor
j. Condensate Pump
3. Connect AHU to Building Management System (BMS) with Automated Logic
DDC controls.
a. Contractor shall be responsible for the tie-in of the control system to the BMS. This includes the building of all graphics on the BMS. Provide
Bacnet gateway if required.
b. Provide water sensor alarm (local and BMS) in the event of water leakage below the floor
c. Replace existing remote temperature and humidity sensors in return duct with new
d. Provide condensate drain pan overflow sensor
4. Re-connect electric to AHU and condensing unit.
a. Provide new disconnects and fuses as required
5. Reconnect supply, return and outside air ducts. Provide motorized damper in
OA duct.
6. TAB and commission the newly installed AHU including all supply, return, and
OA outlets
7. Re-commission the existing electric reheat coils in supply duct
a. TAB on the existing bypass duct
8. Evacuate/reclaim refrigerant gases – provide report.
9. Condensing unit located in sub-grade mechanical areaway next to A-wing –
Rigging required.
10. Remove and replace cooling condensate drain and condensate pump.
11. Re-connect DCW to humidifier
e. Miscellaneous
i. Contractor/Philips to remove and replace exterior chiller and associated piping and controls.
1. Referring to a previous note, the existing chiller must remain in operation throughout most of the construction.
a. Furnish and install new chiller stand in sub-grade mechanical areaway, next to existing chiller stand.
A. Height and position of new stand must comply with manufacturer’s recommendation. Stand shall be braced to exterior wall.
B. Chiller minimum requirements:
1. Capacity of 154,000 BTUH operating between -20F and 105F ambient air
2. Dual compressors with independent refrigerant circuits, filter drier, sight glass, HI and Low-pressure switches
3. Hot gas bypass
4. Phase and low voltage protection
5. Dual circulating pumps with isolation valves, pressure and temperature gauges, strainers, check and balancing valves, flow switch, pressure relief bypass if needed
6. On board microprocessor controls and diagnostics
C. Provide new chilled water piping between chiller and LCC
1. Provide new customer interface panel (CIP) complete with isolation and bypass valves, pressure and temperature gauges, flow meter, provisions for backup cooling
2. Locate CIP adjacent to LCC
3. New chiller piping to run parallel with existing
4. Insulate chiller lines with elastomeric or foam glass insulation and install metal covers over the lines to conceal them/protect insulation.
5. Chilled water system to use 50/50 propylene glycol
6. Provide buffer tank in chilled water system if recommended by manufacturer or Phillips.
D. Provide remote chiller monitoring device in Equipment
Room
E. Make final tie-in to system after construction [including CIP and Chiller Remote Controller (RDP)] has been completed – fill new chiller with appropriate fluids and bleed system.
F. TAB and commission the newly installed chiller.
G. Evacuate/reclaim fluids from old chiller – provide report.
H. Remove and dispose of old chiller and old chiller lines.
Repair existing penetrations from old chiller lines.
I. Rigging required for installing new chiller and removing old chiller.
b. Connect chiller to BMS with Automated Logic DDC controls.
A. Chiller will operate on internal stand alone controls with monitoring by BMS via Bacnet connection. Provide Bacnet gateway and required network wiring and devices as required.
B. Contractor shall be responsible for the tie-in of the control system to the BMS. This includes the building of all graphics on the BMS.
ii. Contractor shall install warning sign(s) on HEP’s physical barrier; mark 25’-0” radius exclusion zone.
Background: The Samuel S. Stratton VA Medical Center was constructed in the late 1940’s based upon plans by
Green & James, Architects & Engineers, Buffalo, New York and Eggers & Higgins Architects & Engineers, New York, New York dated December 10, 1947. The MRI suite was last renovated in the early 2000s with the installation of the existing Philips 1.5T MRI.
The Radiology department shall remain operational throughout construction. Coordinate with the VA COR and
Radiology Program Director to schedule all work that may be disruptive to hospital operations.
The D-Stream Upgrade site preparation shall ensure that all work necessary which may disturb any adjoining rooms/areas shall be brought back to original or better conditions. All required restorations and repairs to these areas shall include but not be limited to radio frequency protection, walls, doors, frames, ceilings and floors. The
Contractor shall coordinate with VA COR to incorporate remediation measures to correct these deficiencies, repair of damages and necessary work. Roadway closures will not be permitted at any time or for any reason except with the written approval of the VA COR.
Perform all work to the specifications & drawings and provide construction period services for the subject project.
II. REFERENCES
Applicable design and construction standards are listed in Appendix A. Criteria specified throughout the solicitation shall be taken from the most current references as of the date of the solicitation. The list is not intended to include all criteria that may apply or to restrict design and construction to only those references listed. As part of the close-out documentation, the Contractor/Designer shall provide as-built drawings in Adobe PDF and AutoCAD 2019 format.
III. WORK COVERED BY CONTRACT DOCUMENTS
GENERAL
The construction services and contract documents shall cover the design and construction for the rehabilitation of the VAMC, Albany, NY, Building 1 MRI D-Stream Upgrade Site Preparation, consisting of all building components, site modifications and improvements needed to turn over to the government a fully functional facility that meets or exceeds the government requirements as set forth herein. The Contractor shall provide all labor, supervision and materials necessary to perform the work as indicated in this scope of work, project specifications and drawings. The building and site elements shall be accommodated in the given project site. Develop and construct the facility within the budgeted funds that will be negotiated with the government.
A. EXISTING ELEMENTS
The proposed site is located on the 2nd floor of Building 1 Radiology (2A) at the Samuel S. Stratton VAMC, Albany, NY campus at 113 Holland Avenue. There are existing utilities in and around the proposed work area. In addition to following “FAR 52.236-9, Protection of Existing, Structures, Equipment, Utilities and Improvements” the contractor shall remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work, which is to remain. The contractor shall repair or replace portions of the existing work, which have been altered or damaged during construction operations to match or adjoining work, as approved by the Contracting
Officer and at no additional cost to the government. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
The Contractor shall verify all existing conditions on the site and in the facility infrastructure that the proposed project may affect before the commencement of any construction. This includes but is not limited to, verifying the location and elevations of existing utilities, verifying site items as shown on the project drawings and taking appropriate field measurements. The government will not be held responsible for bidding errors made or the failure to adequately inspect the job site for existing conditions, dimensions or to fully review manufacturer’s information related to the project. All bidders are strongly encouraged to inspect the job site prior to submitting bids.
All discrepancies between the scope of work, drawings, specifications and manufacturer’s recommendations shall be brought to the attention of the Contracting Officer’s Representative prior to the commencement of work. The
Contractor shall abide by the Scope of Work regardless of whether a manufacturer calls for the task, level of preparation, etc. in question. The only exception is where the Contracting Officer agrees in writing that the item or task specifically voids a manufacturer’s warranty and may be omitted. A credit for the work not performed may be due to the government in such circumstances at the discretion of the Contracting Officer.
The Contractor shall review the drawings to determine if they are responsible for providing the specific material and/or labor associated to complete the task or phase of the project as well as the project overall.
As part of the project, the Contractor shall:
1. Provide a project schedule that addresses the needs of any area of the VAMC facility that will or may be impacted by the work.
2. Prepare and execute a well-managed plan to mitigate service disruptions.
3. Prepare a contingency plan to provide power in the event of a service disruption.
4. Perform the necessary work without altering the existing infrastructure unless specifically shown on the project drawings.
B. SITE PLANNING AND ENGINEERING
The Contractor shall maintain existing adjacent areas and all areas not designated for a new finish, disturbed during construction shall be patched, repaired or restored to original conditions.
C. LIFE SAFETY AND BUILDING COMPONENT FIRE RATINGS
All life safety codes shall be adhered to as they pertain to the built environment of this project. Egress routes shall be delineated to meet the requirements of the governing codes. All existing means of egress shall be fully accommodated during construction.
Proper temporary partitions shall be constructed and maintained during all phases of work and shall comply with all current VA Safety and Infectious Control standards.
D. COLORS
The color, texture and pattern selections for the finishes of the renovations shall provide an aesthetically pleasing, comfortable, easily maintainable and functional environment of the occupants (including contractor’s ante rooms).
The government will provide finish standards of the facility. Coordination of the new finishes and color selections shall match or compliment with existing buildings adjacent and shall be necessary for a cohesive design. Color selection shall be appropriate for the building type on this campus.
IV. GOVERNMENT PROVIDED EQUIPMENT
A. CONTRACT DOCUMENTS
The government is providing Philips’ drawings and diagrams to indicate the scope of work for site preparation.
These documents are to be used to complete the requirements in their exact format. The Contractor’s shall comply with governing codes noted in the drawings and specifications.
V. SCHEDULES
The Period of Performance for Design is 90 days after the Notice to Proceed. The VA shall be allowed a minimum of
15 working days to review the 95% design. Once the VA (with Philips guidance) has approved the
Contractor’s/Designer’s design, the parties shall determine a start date for demolition/construction. The first day of demolition/construction shall start the Period of Performance for Construction. The demolition/construction work shall be substantially complete within 90 calendar days of the Notice to Proceed unless otherwise agreed to in writing with the Contracting Officer. Provide the government with a design development and construction project timeline that includes but is not limited to submittal submission dates, start of construction, milestones, completion of construction, performance testing and final hand over to the government for occupancy that is less than or equal to 180 calendar days plus 15 working days design review.
Rescheduling of any activities shall be done at no cost to the government unless negotiation and authorization of the rescheduled activity has been agreed upon by the government. Notify the government at least 72 hours prior to starting demolition work, large deliveries or any event that may impact the normal operations of the facility.
Utility shut downs require a minimum 14-day notice.
VI. PROJECT ENERGY PERFORMANCE
The intent of this project is to meet the energy requirements as set forth in the governing codes and regulations for this type of building. There are no LEED requirements for this project.
VII. OCCUPANCY OF SITE
This project is on a fully operational campus. All activities being performed shall maintain the safety and wellbeing of the occupants that operate within the campus. Before work is started, arrange with the government a sequence of procedures, means of approach and space for storage of materials and equipment. The Contractor is responsible for the security of the proposed site during construction.
VIII. CONTRACTOR PERFORMANCE
Use good construction practices and standards in completing all work. All work shall be performed by laborers that are fully versed and experienced in the trade that they are employed to do. Coordination with the government, of project progress and scheduled items, shall be a regular occurrence, initiated by the Contractor.
Appendix A
Drawings and information concerning existing conditions as required.
1) All reproduction services of bidding documents for prospective bidders.
2) Recommendations on priority of deduct alternates if any.
3) VA Design submission guidance at https://www.cfm.va.gov/til/aeDesSubReq.asp
4) VA Master Specifications for copying and editing. Available on the Internet at https://www.cfm.va.gov/til/spec.asp.
5) VA Signage Design Guide at http://www.cfm.va.gov/til/spclRqmts.asp#SIGN
6) VA Standard Details Handbook PG-18-4 for copying. Available on the Internet at http://www.cfm.va.gov/TIL/sDetail.asp
7) VA Construction Standards PG-18-4 as determined by the COTR to be necessary for the specific needs of this project http://www.cfm.va.gov/TIL/cPro.asp.
8) Other VA design information at the VA Technical Information Library http://www.cfm.va.gov/TIL/
9) VA recommendations, as applicable including those for meeting security, safety, and infection control standards required during construction.
10) Original construction documents marked “As Built” but not updated. A/E must field verify “As Built” drawings.
11) Other project documents as applicable, which have renovated these areas.