36C24220R0038-005.xlsx

XLSX spreadsheet Posted

Attached to
Fire Dampers Repairs and Installation Federal contract opportunity
Solicitation number
36C24220R0038
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2

About this file

This document provides details for a federal contract solicitation for fire damper repairs, testing, and new installation at the Northport Veterans Affairs Medical Center in Northport, New York. The solicitation is a Veteran-Owned Small Business set-aside with a cost estimate range between $200,000 to $500,000. The scope of work includes inspecting, testing, repairing, and installing new fire dampers and tags at multiple buildings on site. The contractor must verify duct sizes, decommission unneeded dampers, install new dampers meeting specifications, and generate inspection reports. The contract period is 180 days with work potentially requiring off-hours to avoid impacts to patient care areas. The response due date and other solicitation details will be in the posted solicitation on SAM.gov on or around January 30, 2020.

36C24220R0038 Exhibit 3 Fire Smoke Dampers Rev 5 New as of 12-26-19.xlsx

View the file

Other files for this federal contract opportunity

Other files attached to Fire Dampers Repairs and Installation, newest first.
File Type Posted
36C24220R0038-007.pdf PDF
36C24220R0038-008.xlsx XLSX spreadsheet
36C24220R0038-001.docx DOCX document
36C24220R0038-004.pdf PDF
36C24220R0038-006.xlsx XLSX spreadsheet
36C24220R0038-003.docx DOCX document
36C24220R0038-002.txt TXT text file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Building 200 Exhibit 3

LocationDamper Number (Report)Damper ID (Plans)Damper LocationDamper TypeCurrent StatusRequired? (Y/N)VA Comments / NotesVA Walkthrough CommentsProject ScopeContractor Final ReportDamper Dimensions
Attic / PenthouseA-FD-16-0088 (NEW)Elevator machine room wall (adjacent to P3)FireNEWY2'x6' damper needed between shaft and passenger elevator machine room (adjacent to P3). Existing opening 2' x 6'.Install new 2'x6' 120 minute fire damper needed between shaft and passenger elevator machine room (adjacent to P3). Existing opening 2' x 6'. Supply and attach damper ID tag. Verify damper compliance to NFPA 101. Affix signed and dated test sticker to space provided on damper ID tag.
Attic / PenthouseA-FD-16-0099 (NEW)Elevator machine room wall (adjacent to S4)FireNEWY2'x3' damper needed alongside service elevator machine room (adjacent to S4). Existing opening 2' x 3'.Install 2'x3' 120 minute fire damper needed alongside service elevator machine room (adjacent to S4). Existing opening 2' x 3'. Supply and attach damper ID tag. Verify damper compliance to NFPA 101. Affix signed and dated test sticker to space provided on damper ID tag.
Forth Floor4-FD-16-04848 (NEW)See Exhibit 2FireNewYContractor to verify required damper size and install as required.Install new 120 minute fire damper at location referenced in Exhibit 2 and verified by COR. Assume 2' x 4' for bidding purposes. COR to be notified of Actual dimensions prior to start of damper installation. Supply and attach damper ID tag. Verify damper compliance to NFPA 101. Affix signed and dated test sticker to space provided on damper ID tag.
Forth Floor4-FD-16-04949 (NEW)See Exhibit 2FireNewYContractor to verify required damper size and install as required.Install new 120 minute fire damper at location referenced in Exhibit 2 and verified by COR. Assume 2' x 4' for bidding purposes. COR to be notified of Actual dimensions prior to start of damper installation. Supply and attach damper ID tag. Verify damper compliance to NFPA 101. Affix signed and dated test sticker to space provided on damper ID tag.
Forth Floor4-FD-16-05050 (NEW)See Exhibit 2FireNewYContractor to verify required damper size and install as required.Install new 120 minute fire damper at location referenced in Exhibit 2 and verified by COR. Assume 2' x 4' for bidding purposes. COR to be notified of Actual dimensions prior to start of damper installation. Supply and attach damper ID tag. Verify damper compliance to NFPA 101. Affix signed and dated test sticker to space provided on damper ID tag.
Forth Floor4-FD-16-05151 (NEW)See Exhibit 2FireNewYContractor to verify required damper size and install as required.Install new 120 minute fire damper at location referenced in Exhibit 2 and verified by COR. Assume 2' x 4' for bidding purposes. COR to be notified of Actual dimensions prior to start of damper installation. Supply and attach damper ID tag. Verify damper compliance to NFPA 101. Affix signed and dated test sticker to space provided on damper ID tag.

&"-,Bold"&24Exhibit 3. Building 200 Dampers. New Dampers to be Installed

Building 92 Exhibit 3

LocationDamper Number (Report)Damper ID (Plans)Damper LocationDamper TypeCurrent StatusRequired? (Y/N)Comments/NotesWalkthrough CommentsProject ScopeContractor Final Report
First Floor Generator Building1-FD-16-0044 (NEW)See Comments/NotesFireNEWYDamper needed in Generator Room. Assume both intake and radiator exhaust. Missing on LSS list as of 5-6-19Air intake damper 68" x 82" . All existing dampers are multi-blade horizontal configuration.Install new 90 minute fire damper at location referenced VA walkthrough comments and verified by COR. Actual dimensions are referenced in VA walkthrough comments. Installation of new fire dampers shall not interfere with the operation of existing dampers, which are opened upon generator startup. Supply and attach damper ID tag. Verify damper compliance to NFPA 101. Affix signed and dated test sticker to space provided on damper ID tag.
Generator Building1-FD-16-0054 (NEW)See Comments/NotesFireNEWYDamper needed in Generator Room. Assume both intake and radiator exhaust. Missing on LSS list as of 5-6-19Radiator damper 68" x 83" All existing dampers are multi-blade horizontal configuration.Install new 90 minute fire damper at location referenced VA walkthrough comments and verified by COR. Actual dimensions are referenced in VA walkthrough comments. Installation of new fire dampers shall not interfere with the operation of existing dampers, which are opened upon generator startup. Supply and attach damper ID tag. Verify damper compliance to NFPA 101. Affix signed and dated test sticker to space provided on damper ID tag.

&"-,Bold"&24Exhibit 3. Building 92 Dampers. New Dampers to be Installed