36C24218B0572-0005001.docx
DOCX document 14 KB Posted
- Attached to
- 528A8-18-805 RENOVATE ONCOLGY LAB FOR USP 800
- Solicitation number
- 36C24218B0572
About this file
36C24218B0572 0005 M-002 Revisons explained.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24219C0026-000.docx | DOCX document | |
| 36C24218B0572-0005000.docx | DOCX document | |
| 36C24218B0572-0005002.pdf | ||
| 36C24218B0572-0004000.docx | DOCX document | |
| 36C24218B0572-0004002.pdf | ||
| 36C24218B0572-0004003.pdf | ||
| 36C24218B0572-0004001.docx | DOCX document | |
| 36C24218B0572-0003002.pdf | ||
| 36C24218B0572-0003001.docx | DOCX document | |
| 36C24218B0572-0003000.docx | DOCX document | |
| 36C24218B0572-0003003.pdf | ||
| 36C24218B0572-0002001.docx | DOCX document | |
| 36C24218B0572-0002003.pdf | ||
| 36C24218B0572-0002002.pdf | ||
| 36C24218B0572-0002000.docx | DOCX document | |
| 36C24218B0572-0002004.pdf | ||
| 36C24218B0572-0001000.docx | DOCX document | |
| 36C24218B0572-005.pdf | ||
| 36C24218B0572-003.pdf | ||
| 36C24218B0572-001.docx | DOCX document | |
| 36C24218B0572-002.docx | DOCX document | |
| 36C24218B0572-004.zip | ZIP file | |
| 36C24218B0572-000.docx | DOCX document |
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REVISIONS TO DRAWING M-002:
Renovate Oncology Lab for USP-800 Project 528A8-18-805 Bldg. 1 VAMC Albany, NY
The following were revised on drawing M-002. All changes are clouded:
Rev 1- RFI #2 Dated 10-11-2018:
1. 11A PART PLAN ROOM A1105b: An existing abandoned duct was included above the corridor ceiling directly outside room A1105b. A note concerning this duct is also included.
2. 11A MECHANICAL ROOM PART PLAN: The note concerning the sprinkler shut off valve was revised.
Rev 2 – Addendum #1 Dated 10-16-2018:
1. 11A MECHANICAL ROOM PART PLAN: The paragraph near condensing unit ACCU-1-11A Oncology has been revised. The additional lines point out that the recently installed roof is warrantied by A.R.M Roofing for the next two years. Any revisions to this roof must maintain this warranty. After these two years the warranty is picked up by Tremco. Any revisions to this roof shall be compatible with ARM and Tremco requirements so that the warranties are retained.
2. The room number was revised from A1106b to A1106g.
End of Document