This document is a plan for infection control procedures for a construction project related to the renovation of a third-floor laboratory at the Manchester, VAMC. The plan outlines a multi-level approach to infection control based on the risk category of the work, including requirements for physical containment barriers, negative air pressure, HEPA filtration, worker PPE, and cleaning protocols. Key details include:
The project involves construction on the third floor of a building at the Manchester, VAMC. The work is designated as a Risk Category III project, requiring enhanced infection control measures. Requirements include constructing physical containment barriers, maintaining negative air pressure with HEPA-filtered exhaust, controlling worker access and PPE, and following stringent cleaning protocols. The contractor is responsible for providing all necessary containment and control equipment and submitting a detailed plan for approval prior to commencing work. Failure to comply with the infection control plan could result in work stoppages or other remedial actions.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
382 SF
CALL CENTER
W347 303 SF
OFFICE
W348
185 SF
STAIR NO.3
W349
CH
AS
E
31 SF
UTILITY RM
W352
182 SF
MALE TLT
W353
152 SF
STORAGE
W354
159 SF
EXAM ROOM
W355
83 SF
LACTATION RM
W357
61 SF
BIOHAZARD
W356 22 SF
ELEC.
W357A
FIRE CL
382 SF
BIOMED
W346
297 SF
OFFICE
W345
146 SF
OFFICE
W341
289 SF
OFFICE
W342
286 SF
OFFICE
W343
283 SF
STORAGE
W344
34 SF
TOILET
W340
384 SF
OFFICE
W339
LC
CORRIDOR
CORRIDOR
AREA NOT IN SCOPE
A B C D F
H I K LJ
NOT IN SCOPE
NOT IN SCOPE
285 SF
EXAM ROOM
N363
269 SF
EXAM ROOM
N362
142 SF
EXAM
W366
38 SF
BATH
N386A
31 SF
TLT
N387A28 SF
STOR.
N386B
103 SF
FEMALE
W370
11 SF
TEL CL
N359A
125 SF
SPD STOR
N359
151 SF
STORAGE
N358
ELEVATOR NO.1
ELEVATOR NO.2
SERVICE
ELEVATOR NO.3
46 SF
DUMBWAITER
CLOSET
N361
53 SF
TOILET
N360
G
E
VA Project Number:
Building:
Drawing Number:
Project Title:
Project Location:
Issue Date:
Checked By: Drawn By:
Drawing Title:
FULLY
SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
A
Submission:
ARCHITECT / ENGINEER OF RECORD:
Revisions: Date:
CONSULTANTS:
/8
/4
/8
/2
/4
-1
/2
CONSULTANT:
CFR ENGINEERING
20251 CENTURY BLVD.
SUITE 120
GERMANTOWN, MD 20874
877-871-4229
CONSULTANT:
IMEG CORP.
101 NORTH SEVENTH STREET
SUITE 404
LOUISVILLE, KY 40202
440-262-3063
ARCHITECT:
CB DESIGN GROUP
421 KING ST.
SUITE 301
ALEXANDRIA, VA 22314
703-772-4213
PROFESSIONAL SEAL:
2345678910111213141516
B
C
D
E
F
G
H
J
K
12345678910111213141516
608-23-133
AuthorChecker
3RD FLOOR LABORATORY
CONSTRUCTION
100% CD SUBMISSION
-2
-1
G C
/2
/2
.p d f
Manchester VAMC 718 Smyth Road Manchester, NH 03104
1/8" = 1'-0"A15
PLAN - 3RD FLOOR
SHEET ADDED IN RESPONSE TO BID RFI 9.12.2024
INFECTION CONTROL
ICRA BARRIER (ZIP
WALL OR EQUAL)
FROM FLOOR TO
DECK ABOVE
ICRA BARRIER (ZIP
WALL OR EQUAL).
4. When the work involves or impacts potable water systems including stagnation due to reduced usage, the piping shall be flushed twice a week or isolated from the main system.
5. Seal doors to prevent dust migration.
6. Contain all trash and debris in the work area. Perform daily cleaning and disposal of trash (covered) from work area using an identified exit route.
7. Any equipment, tools, or materials removed from the work area must be in sealed containers and/or cleaned of dust and debris prior to removal from the area.
8. Nonporous/smooth and cleanable containers (with a hard lid) must be used to transport trash and debris from the construction areas. These containers must be damp-wiped cleaned and free of visible dust/debris before leaving the contained work area.
9. Install a sticky (dust collection) mat at entrance of contained work area based on facility policy. Sticky mats must be changed routinely and when visibly soiled.
10. Maintain clean surroundings when area is not contained by damp mopping or HEPA vacuuming surfaces at least daily.vacuuming surfaces at least daily.
Level III All control measures in Levels I and II and the following:
1. Ensure availability of equipment for cleaning hands.
2. Construct and complete critical barriers meeting NFPA 241 requirements. Barriers must extend to the ceiling or if ceiling tile is removed, to the deck above.
3. All (plastic or hard) barrier construction activities must be completed in a manner that prevents dust release. Plastic barriers must be effectively affixed to floor and ceiling (or floor/roof deck above) and secure from movement or damage.
4. Seal all penetrations in containment barriers, including floors and ceiling, using approved materials (UL schedule firestop if applicable for barrier type).
5. Maintain .01 inches /water gauge negative pressurization of the entire workspace by use of HEPA exhaust air systems directed outdoors (unless a work specific waiver is approved by VHA’s Office of Healthcare Engineering); this must be maintained continuously 24/7 for the duration of the project. Exhaust discharged directly to the outdoors that is 25 feet or greater from entrances, air intakes and windows is not required to be HEPA-filtered. Exhausting discharged air into shared or recirculating HVAC systems, or other shared exhaust systems (e.g., bathroom exhaust) is prohibited.
6. Install a differential pressure sensing device (e.g., magnehelic, manometer, or digital monitoring) on exterior of work containment to continually monitor and document negative pressurization. The “ball in the wall” or similar apparatus are not acceptable.
Level IV All control measures in Levels I, II and III and the following:
1. Barriers must be hard barriers unless temporary to install final barrier.
2. Containment must include an anteroom to ensure pressure control. Anteroom must be large enough for equipment staging, cart cleaning, workers’ PPE and cleaning.
3. Worker clothing and/or PPE must be removed or clean and free of visible dust before leaving the work area anteroom. HEPA vacuuming of clothing or use of cover suits is acceptable.
4. Workers must wear shoe covers or have a method to clean shoes in anteroom.
Shoe covers must be removed prior to exiting the anteroom to the occupied space (non-work area). Damaged shoe covers must be changed immediately.
INFECTION CONTROL PLAN
AD102
INFECTION CONTROL MATRIX - RISK CATEGORY IIIGENERAL INFECTION CONTROL NOTES
1. CONTRACTOR SHALL PROVIDE EVERYTHING NEEDED FOR INFECTION
CONTAINMENT/CONTROL SYSTEM. SOME ITEMS MAY INCLUDE, BUT ARE NOT LIMITED TO;
CONSTRUCTION ZONE SIGNS, HEPA FILTERS, AIR SCRUBBERS, ETC. CONTACT RESIDENT
ENGINEER, FACILITY INFECTION CONTROL RISKS ASSESSMENT TEAM (ICRA) FOR FULL
PROCEDURE REQUIREMENTS.
2. IT IS RECOMMENDED THAT THE CONTRACTOR UTILIZES MOVEABLE CONTAINMENT SYSTEM,
CONSTRUCTED OF A MINIMUM 6ML POLY OR PREFABRICATED ZIP WALL THAT CAN BE
SEALED TO WORK AREAS. THE INTEGRITY OF THE BARRIER WALLS MUST ASSURE A
COMPLETE SEAL OF THE CONSTRUCTION AREA FROM ADJACENT AREAS.
3. PRIOR TO CONSTRUCTION, THE CONTRACTOR SHALL SUBMIT CONTAINMENT/CONTROL
SYSTEM PLAN TO COR FOR APPROVAL, INCLUDING PERIODIC STATUS REPORTS, AND
SUBMIT TO THE VA RESIDENT ENGINEER AND FACILITY ICRA TEAM FOR REVIEW FOR
COMPLIANCE WITH CONTRACT REQUIREMENTS. ALL PERSONNEL INVOLVED IN THE
CONSTRUCTION SHALL BE EDUCATED AND TRAINED IN INFECTION PREVENTION MEASURES
ESTABLISHED BY THE MEDICAL CENTER AND SHALL FOLLOW INFECTION CONTROL
PROCEDURES.
4. IN EACH CONSTRUCTION AREA, THE CONTRACTOR SHALL UTILIZE A 120V HEPA FILTER
EQUIPPED AIR SCRUBBER MACHINE.
5. DO NOT REMOVE CONSTRUCTION BARRIERS FROM WORK AREA UNTIL COMPLETED
PROJECT IS SIGNED OFF BY COR AND VA'S INFECTION CONTROL DEPARTMENT.
6. PROVIDE DUST “STICKY” MAT AT EACH ENTRANCE/EXIT OF CONSTRUCTION AREA AND
REPLACE OR CLEAN WHEN NO LONGER EFFECTIVE.
7. ALL FURNITURE AND EQUIPMENT (IF APPLICABLE) SHALL BE PROTECTED DURING
DEMOLITION AND CONSTRUCTION.
09-12-2024
(ADDED IN RESPONSE TO BID RFI #22)#133)