About this file

This document is a plan for infection control procedures for a construction project related to the renovation of a third-floor laboratory at the Manchester, VAMC. The plan outlines a multi-level approach to infection control based on the risk category of the work, including requirements for physical containment barriers, negative air pressure, HEPA filtration, worker PPE, and cleaning protocols. Key details include:

The project involves construction on the third floor of a building at the Manchester, VAMC. The work is designated as a Risk Category III project, requiring enhanced infection control measures. Requirements include constructing physical containment barriers, maintaining negative air pressure with HEPA-filtered exhaust, controlling worker access and PPE, and following stringent cleaning protocols. The contractor is responsible for providing all necessary containment and control equipment and submitting a detailed plan for approval prior to commencing work. Failure to comply with the infection control plan could result in work stoppages or other remedial actions.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--608-23-133, Third Floor Lab Construction, newest first.
File Type Posted
603-23-133 Third Floor Lab Construction RFIs and Answers 9-20-2024.pdf PDF
Revised SOW - 608-23-133 Third Floor Lab Construction 8-7-2024.pdf PDF
VA MHT Lab Reno - Addendum 1 MEP Sheets.pdf PDF
Warranty_Roofs_23_19_15_14.pdf PDF
01 45 29 Testing Laboratory Services - Bid RFI 81.pdf PDF
36C24124B0052 0004.pdf PDF
ACM Inspection Report 2020-10 Building 1.pdf PDF
AC-4000_ALUMINUM-INSULATED-1-INCH-INFILL-PANEL-SYSTEM-SPECIFICATIONS.pdf PDF
07 81 00 Applied Fireproofing -Bid RFI 83.pdf PDF
36C24124B0052 0003.pdf PDF
608-23-133 Lab project existing conditions photos.pdf PDF
36C24124B0052 0002.pdf PDF
Attachment 1 Site Visit Sign-In Lab Project.pdf PDF
VA.MHT Lab Reno -100% Bid Set at full size.pdf PDF
Attachment 2 Manchester Lab Specs Vol. 2.pdf PDF
Attachment 3 of 5 VA MHT 100 Percent Design.pdf PDF
Attachment 1 of 5 VA MHT 100 Percent Design.pdf PDF
Attachment 4 of 5 VA MHT 100 Percent Design.pdf PDF
36C24124B0052 0001.pdf PDF
Attachment 2 of 5 VA MHT 100 Percent Design.pdf PDF
Attachment 6 Manchester Lab 100 Percent Bid Set Specs.pdf PDF
Attachment 5 of 5 VA MHT 100 Percent Design 02.pdf PDF
Davis-Bacon Act WD NH20240021.docx DOCX document
S02 PRE-AWARD CONTRACTOR EVALUATION FORM.docx DOCX document
SOW - 608-23-133 Third Floor Lab Construction 8-7-2024.pdf PDF
608-23-133 3rd Floor Lab JandA Brand Name Products v1.pdf PDF
Instructions to Bidders.docx DOCX document
23031.00 VA.MHT Lab Reno 95 CD VA Submission compressed.pdf PDF
36C24124B0052_1.docx DOCX document
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

382 SF

CALL CENTER

W347 303 SF

OFFICE

W348

185 SF

STAIR NO.3

W349

CH

AS

E

31 SF

UTILITY RM

W352

182 SF

MALE TLT

W353

152 SF

STORAGE

W354

159 SF

EXAM ROOM

W355

83 SF

LACTATION RM

W357

61 SF

BIOHAZARD

W356 22 SF

ELEC.

W357A

FIRE CL

382 SF

BIOMED

W346

297 SF

OFFICE

W345

146 SF

OFFICE

W341

289 SF

OFFICE

W342

286 SF

OFFICE

W343

283 SF

STORAGE

W344

34 SF

TOILET

W340

384 SF

OFFICE

W339

LC

CORRIDOR

CORRIDOR

AREA NOT IN SCOPE

A B C D F

H I K LJ

NOT IN SCOPE

NOT IN SCOPE

285 SF

EXAM ROOM

N363

269 SF

EXAM ROOM

N362

142 SF

EXAM

W366

38 SF

BATH

N386A

31 SF

TLT

N387A28 SF

STOR.

N386B

103 SF

FEMALE

W370

11 SF

TEL CL

N359A

125 SF

SPD STOR

N359

151 SF

STORAGE

N358

ELEVATOR NO.1

ELEVATOR NO.2

SERVICE

ELEVATOR NO.3

46 SF

DUMBWAITER

CLOSET

N361

53 SF

TOILET

N360

G

E

VA Project Number:

Building:

Drawing Number:

Project Title:

Project Location:

Issue Date:

Checked By: Drawn By:

Drawing Title:

FULLY

SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

A

Submission:

ARCHITECT / ENGINEER OF RECORD:

Revisions: Date:

CONSULTANTS:

/8

/4

/8

/2

/4

-1

/2

CONSULTANT:

CFR ENGINEERING

20251 CENTURY BLVD.

SUITE 120

GERMANTOWN, MD 20874

877-871-4229

CONSULTANT:

IMEG CORP.

101 NORTH SEVENTH STREET

SUITE 404

LOUISVILLE, KY 40202

440-262-3063

ARCHITECT:

CB DESIGN GROUP

421 KING ST.

SUITE 301

ALEXANDRIA, VA 22314

703-772-4213

PROFESSIONAL SEAL:

2345678910111213141516

B

C

D

E

F

G

H

J

K

12345678910111213141516

608-23-133

AuthorChecker

3RD FLOOR LABORATORY

CONSTRUCTION

100% CD SUBMISSION

-2

-1

G C

/2

/2

.p d f

Manchester VAMC 718 Smyth Road Manchester, NH 03104

1/8" = 1'-0"A15

PLAN - 3RD FLOOR

SHEET ADDED IN RESPONSE TO BID RFI 9.12.2024

INFECTION CONTROL

ICRA BARRIER (ZIP

WALL OR EQUAL)

FROM FLOOR TO

DECK ABOVE

ICRA BARRIER (ZIP

WALL OR EQUAL).

4. When the work involves or impacts potable water systems including stagnation due to reduced usage, the piping shall be flushed twice a week or isolated from the main system.

5. Seal doors to prevent dust migration.

6. Contain all trash and debris in the work area. Perform daily cleaning and disposal of trash (covered) from work area using an identified exit route.

7. Any equipment, tools, or materials removed from the work area must be in sealed containers and/or cleaned of dust and debris prior to removal from the area.

8. Nonporous/smooth and cleanable containers (with a hard lid) must be used to transport trash and debris from the construction areas. These containers must be damp-wiped cleaned and free of visible dust/debris before leaving the contained work area.

9. Install a sticky (dust collection) mat at entrance of contained work area based on facility policy. Sticky mats must be changed routinely and when visibly soiled.

10. Maintain clean surroundings when area is not contained by damp mopping or HEPA vacuuming surfaces at least daily.vacuuming surfaces at least daily.

Level III All control measures in Levels I and II and the following:

1. Ensure availability of equipment for cleaning hands.

2. Construct and complete critical barriers meeting NFPA 241 requirements. Barriers must extend to the ceiling or if ceiling tile is removed, to the deck above.

3. All (plastic or hard) barrier construction activities must be completed in a manner that prevents dust release. Plastic barriers must be effectively affixed to floor and ceiling (or floor/roof deck above) and secure from movement or damage.

4. Seal all penetrations in containment barriers, including floors and ceiling, using approved materials (UL schedule firestop if applicable for barrier type).

5. Maintain .01 inches /water gauge negative pressurization of the entire workspace by use of HEPA exhaust air systems directed outdoors (unless a work specific waiver is approved by VHA’s Office of Healthcare Engineering); this must be maintained continuously 24/7 for the duration of the project. Exhaust discharged directly to the outdoors that is 25 feet or greater from entrances, air intakes and windows is not required to be HEPA-filtered. Exhausting discharged air into shared or recirculating HVAC systems, or other shared exhaust systems (e.g., bathroom exhaust) is prohibited.

6. Install a differential pressure sensing device (e.g., magnehelic, manometer, or digital monitoring) on exterior of work containment to continually monitor and document negative pressurization. The “ball in the wall” or similar apparatus are not acceptable.

Level IV All control measures in Levels I, II and III and the following:

1. Barriers must be hard barriers unless temporary to install final barrier.

2. Containment must include an anteroom to ensure pressure control. Anteroom must be large enough for equipment staging, cart cleaning, workers’ PPE and cleaning.

3. Worker clothing and/or PPE must be removed or clean and free of visible dust before leaving the work area anteroom. HEPA vacuuming of clothing or use of cover suits is acceptable.

4. Workers must wear shoe covers or have a method to clean shoes in anteroom.

Shoe covers must be removed prior to exiting the anteroom to the occupied space (non-work area). Damaged shoe covers must be changed immediately.

INFECTION CONTROL PLAN

AD102

INFECTION CONTROL MATRIX - RISK CATEGORY IIIGENERAL INFECTION CONTROL NOTES

1. CONTRACTOR SHALL PROVIDE EVERYTHING NEEDED FOR INFECTION

CONTAINMENT/CONTROL SYSTEM. SOME ITEMS MAY INCLUDE, BUT ARE NOT LIMITED TO;

CONSTRUCTION ZONE SIGNS, HEPA FILTERS, AIR SCRUBBERS, ETC. CONTACT RESIDENT

ENGINEER, FACILITY INFECTION CONTROL RISKS ASSESSMENT TEAM (ICRA) FOR FULL

PROCEDURE REQUIREMENTS.

2. IT IS RECOMMENDED THAT THE CONTRACTOR UTILIZES MOVEABLE CONTAINMENT SYSTEM,

CONSTRUCTED OF A MINIMUM 6ML POLY OR PREFABRICATED ZIP WALL THAT CAN BE

SEALED TO WORK AREAS. THE INTEGRITY OF THE BARRIER WALLS MUST ASSURE A

COMPLETE SEAL OF THE CONSTRUCTION AREA FROM ADJACENT AREAS.

3. PRIOR TO CONSTRUCTION, THE CONTRACTOR SHALL SUBMIT CONTAINMENT/CONTROL

SYSTEM PLAN TO COR FOR APPROVAL, INCLUDING PERIODIC STATUS REPORTS, AND

SUBMIT TO THE VA RESIDENT ENGINEER AND FACILITY ICRA TEAM FOR REVIEW FOR

COMPLIANCE WITH CONTRACT REQUIREMENTS. ALL PERSONNEL INVOLVED IN THE

CONSTRUCTION SHALL BE EDUCATED AND TRAINED IN INFECTION PREVENTION MEASURES

ESTABLISHED BY THE MEDICAL CENTER AND SHALL FOLLOW INFECTION CONTROL

PROCEDURES.

4. IN EACH CONSTRUCTION AREA, THE CONTRACTOR SHALL UTILIZE A 120V HEPA FILTER

EQUIPPED AIR SCRUBBER MACHINE.

5. DO NOT REMOVE CONSTRUCTION BARRIERS FROM WORK AREA UNTIL COMPLETED

PROJECT IS SIGNED OFF BY COR AND VA'S INFECTION CONTROL DEPARTMENT.

6. PROVIDE DUST “STICKY” MAT AT EACH ENTRANCE/EXIT OF CONSTRUCTION AREA AND

REPLACE OR CLEAN WHEN NO LONGER EFFECTIVE.

7. ALL FURNITURE AND EQUIPMENT (IF APPLICABLE) SHALL BE PROTECTED DURING

DEMOLITION AND CONSTRUCTION.

09-12-2024

(ADDED IN RESPONSE TO BID RFI #22)#133)

#133