36C24124B0032 0003.docx

DOCX document 28 KB Posted

Attached to
Z1DA-- 523A5-22-010 Enhanced Kitchen Equipment Site Prep
Solicitation number
36C24124B0032
Issued by

About this file

This solicitation is for an invitation for bid for project 523A5-22-010 Enhanced Kitchen Equipment Site Prep at the VAMC Brockton located at 940 Belmont Street, Brockton, MA 02301. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1 is seeking bids for site preparation work to install new kitchen equipment. Bids are due by the date specified in the solicitation document. The project involves preparing the site at the Brockton VAMC for new kitchen equipment, including any necessary construction, demolition, utility work and other preparations. The awarded contractor will be expected to complete the site prep work to ready the kitchen for the new equipment on the schedule outlined in the solicitation.

View the file

Other files

File Type Posted
2018 B20 Electrical As-Built Drawings.pdf PDF
CRP 20 Conduit run towards door.jpeg JPEG file
Hood Vent Pictures above ceiling tiles 5.jpeg JPEG file
Scope Ph1 14 Drain connection below floor.jpeg JPEG file
Mechanical Original Drawings.pdf PDF
2010 B20 Roof Warranty Letter.pdf PDF
Electrical Original Drawings.pdf PDF
Rm.116E looking towards Rm.102.jpeg JPEG file
Scope 1.1 Pipes.jpeg JPEG file
Panel CRP 20.jpeg JPEG file
Rm.116E at near door opening 2.jpeg JPEG file
Plumbing Original Drawings.pdf PDF
Hood Vent Pictures above ceiling tiles 2.jpeg JPEG file
Rm.116C looking towards E.jpeg JPEG file
2009 B20 HVAC Drawings 523A5-08-101.pdf PDF
Rm.118 Panel CRP20.jpeg JPEG file
Scope Clarifications.pdf PDF
S06 523A5-22-010 Site Visit Sign In-Sheet.pdf PDF
Hood Vent Pictures above ceiling tiles 7.jpeg JPEG file
Hood Vent Pictures above ceiling tiles 8.jpeg JPEG file
Hood Vent Pictures above ceiling tiles 3.jpeg JPEG file
Rm.118 Panel CRP20 from door.jpeg JPEG file
CRP 20 conduit in direction of LSP 20.jpeg JPEG file
CRP 20 Conduit from door to wall.jpeg JPEG file
1983 B.20 Upgrade Freezer Area MEP plans.pdf PDF
Hood Vent Pictures above ceiling tiles 6.jpeg JPEG file
2021 B20 Fire Protection As-Built Drawings.pdf PDF
WD MA202400112 03012024.pdf PDF
Hood Vent Pictures above ceiling tiles 4.jpeg JPEG file
RFIs.pdf PDF
Rm.116E at near door opening.jpeg JPEG file
PDR Wall counter pipes above freezer 110A.jpeg JPEG file
Architectural Original Drawings.pdf PDF
PDR Wall counter pipes above freezer 110A to demo.jpeg JPEG file
Hood Vent Pictures above ceiling tiles 1.jpeg JPEG file
Structural Original Drawings.pdf PDF
Floor Plans with Room Numbers.pdf PDF
CRP 20 Interior.jpeg JPEG file
2005 Roof Specifications.pdf PDF
Rm.118 next to stairs.jpeg JPEG file
Scope 1.1 Water Pipe.jpeg JPEG file
2005 Roofing Details.pdf PDF
36C24124B0032 0002.docx DOCX document
36C24124B0032 0001.docx DOCX document
Spec Sheet RTV7-05UV-ST Retherm Ovens.pdf PDF
Design Drawings DMA Brock 091823 FS.pdf PDF
B-22 Roof Warranty Letter.pdf PDF
ICRA Kitchen Site Prep.pdf PDF
Spec List Final 091323.pdf PDF
36C24124B0032 Pre-SOL.docx DOCX document
Show 40 more

Latest 50 of 59 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7.

ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF

PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE

OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERE

D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED

STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF

CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF

SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 3/1/2024 523A5-22-010 36C241 Department of Veterans Affairs Network Contracting Office 1 VA Central Western Massachusetts HCS 421 North Main Street Leeds MA 01053-9764 36C241 Department of Veterans Affairs Network Contracting Office 1 VAMC Bedford 200 Springs Road Bedford MA 01730 To all Offerors/Bidders

36C24124B0032 01-29-2024

X X X 2:00PM EST on 3/19/2024 See CONTINUATION Page The purpose of Amendment 3 is to provide the following:

1. RFI questions and answers.

2. Scope clarification and attachments.

3. Site visit attendance sheet.

4. Updated wage determination.

5. Bid opening conference line.

6. The bid opening is extended to 2:00PM EST on 3/19/2024.

All other terms and conditions remain unchanged.

Heather Libiszewski-Gallien Contracting Officer 523A5-22-010 Enhanced Kitchen Equipment Site Prep Bid Opening Line

Microsoft Teams meeting Join on your computer, mobile app or room device Click here to join the meeting Meeting ID: 276 450 729 809 Passcode: iShM5N Download Teams | Join on the web Or call in (audio only) +1 205-235-3524,,860781229# United States, Birmingham Phone Conference ID: 860 781 229# Find a local number | Reset PIN Learn More | Meeting options

See attached document: Scope Clarifications.

See attached document: RFIs.

See attached document: 2005 Roof Specifications.

See attached document: 2005 Roofing Details.

See attached document: 2010 B20 Roof Warranty Letter.

See attached document: CRP 20 Conduit from door to wall.

See attached document: CRP 20 conduit in direction of LSP 20.

See attached document: CRP 20 Conduit run towards door.

See attached document: CRP 20 Interior.

See attached document: Panel CRP 20.

See attached document: Hood Vent Pictures above ceiling tiles 1.

See attached document: Hood Vent Pictures above ceiling tiles 2.

See attached document: Hood Vent Pictures above ceiling tiles 3.

See attached document: Hood Vent Pictures above ceiling tiles 4.

See attached document: Hood Vent Pictures above ceiling tiles 5.

See attached document: Hood Vent Pictures above ceiling tiles 6.

See attached document: Hood Vent Pictures above ceiling tiles 7.

See attached document: Hood Vent Pictures above ceiling tiles 8.

See attached document: PDR Wall counter pipes above freezer 110A to demo.

See attached document: PDR Wall counter pipes above freezer 110A.

See attached document: Rm.116C looking towards E.

See attached document: Rm.116E at near door opening.

See attached document: Rm.116E at near door opening 2.

See attached document: Rm.116E looking towards Rm.102.

See attached document: Rm.118 next to stairs.

See attached document: Rm.118 Panel CRP20 from door.

See attached document: Rm.118 Panel CRP20.

See attached document: Scope 1.1 Pipes.

See attached document: Scope 1.1 Water Pipe.

See attached document: Scope Ph1 14 Drain connection below floor.

See attached document: 1983 B.20 Upgrade Freezer Area MEP plans.

See attached document: 2009 B20 HVAC Drawings 523A5-08-101.

See attached document: 2018 B20 Electrical As-Built Drawings.

See attached document: 2021 B20 Fire Protection As-Built Drawings.

See attached document: Architectural Original Drawings.

See attached document: Electrical Original Drawings.

See attached document: Floor Plans with Room Numbers.

See attached document: Mechanical Original Drawings.

See attached document: Plumbing Original Drawings.

See attached document: Structural Original Drawings.

See attached document: S06 523A5-22-010 Site Visit Sign In-Sheet.

See attached document: WD MA202400112 03012024.

File details come from the government source that posted it. Updated .