VAMC-WRJ Building 31 Drawing 31-AS-106-DA-5.pdf
PDF 1 MB Posted
- Attached to
- Y1DA--Inpatient Ware Renovation 405-13-104
- Solicitation number
- 36C24120R0142
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
D
DC
C
4 4
4.74.7
DN
UP
UP
STAIR 2
STAIR 1
STAIR 4
E.C.
PIPE
SHAFT
DUCT SHAFT
NEW WINDOW OPENING
IN EXISTING EXTERIOR WALL
4 44 4
2 2 2 2 2
6 6 6 6
7 7 7 7 7 7 7 7 7 7 7 7
SAWCUT AND REMOVE EXISTING EXTERIOR
WALL PER THE REQUIRED DIMENSIONS OF
THE NEW WINDOW OPENING
EXISTING WALL CONSTRUCTION CONSISTS OF
8" CMU, 2" RIGID INSULATION, AIRSPACE AND
FACEBRICK
53 53 53
3 8
8 8
8 8
77777
8 8 8
8 888
535353
2 5
53 53
4 4 4
777777777777777777
7 7 7 7
53 535353
53 53 53 53
53 53 53 53
5353 53 53
2 2
2 22
8 8 8 8
8 1
4 4
8 8
4 4
4 4 4 4 4 4 4
53 53 53 53 53 53
53 2
8 8
2 2 4 4
4 4
1 1
1 1
6 6 6 6 6 6 6 6
8 8 8 8
8 8 888
4 4
4 4 4
2 2 2
53 53 53 53
8 8
4 8
53 4
4 8
53 53
4 88
NEW DOOR OPENING
IN EXISTING EXTERIOR WALL
SAWCUT AND REMOVE EXISTING EXTERIOR
WALL PER THE REQUIRED DIMENSIONS OF THE
NEW DOOR OPENING
EXISTING WALL CONSTRUCTION CONSISTS OF
8" CMU, 2" RIGID INSULATION, AIRSPACE AND
FACEBRICK
8 8
3 25
ELEC
CLO
ELEC
CLO
ELEC
CLO
COMM
REMOVE HORIZONTAL DUCT THROUGHOUT
CORRIDOR AND INFILL PENETRATION AT
SECOND FLOOR LEVEL WITH 2 HOUR FIRE
RATED ENCLOSURE DETAIL. SEE DETAIL 5/AS-31-201
DO NOT REMOVE GYPSUM
WALL BOARD - MAINTAIN
2 HOUR RATING
AT EXISTING INTERIOR COLUMN
DO NOT REMOVE GYPSUM
WALL BOARD - MAINTAIN
2 HOUR RATING
AT EXISTING INTERIOR COLUMN
DO NOT REMOVE GYPSUM
WALL BOARD - MAINTAIN
2 HOUR RATING
AT EXISTING INTERIOR COLUMN
DO NOT REMOVE GYPSUM
WALL BOARD - MAINTAIN
2 HOUR RATING
AT EXISTING INTERIOR COLUMN
DN
UP
DN
UP
DN
UP
EXISTING TO REMAIN
REMOVE EXISTING CASEWORK, LOCKERS, SHELVES, EQUIPMENT, TACK BOARDS, HAND RAILS, AND OTHER FIT-OUT ACCESSORIES. DISCARD
AS DIRECTED BY OWNER.
REMOVE PLUMBING FIXTURES, TOILETS, GRAB BARS, SINKS, SHOWER, AND ALL RELATED ACCESSORIES. DISCARD AS DIRECTED BY OWNER.
REMOVE EXISTING FLOOR COVERING AND ADHESIVES, (VCT, CARPET, NON-SLIP FLOOR) AND BASE MATERIALS, TO A CLEAN EXISTING FLOOR
SLAB.
REMOVE EXISTING DOOR, DOOR FRAME AND HARDWARE, WINDOW FRAME AND GLASS. DISCARD AS DIRECTED BY OWNER.
REMOVE EXISTING CEILING SYSTEM, GRID AND CUBICLE CURTAIN TRACK INCLUDING ALL SUPPORTS. SOME STOCK MAY BE SALVAGED FOR
OWNERS REPLACEMENT INVENTORY. DISCARD BALANCE OF MATERIAL.
REMOVE EXISTING METAL LATH AND PLASTER AT EXTERIOR WALLS, WINDOW SILLS, JAMBS AND HEADS - EXPOSE EXISTING CMU WALL (TYPICAL
ALL EXTERIOR WALLS)
REMOVE EXISTING EXTERIOR WINDOW, ASSOCIATED BLOCKING AND TRIM
REMOVE EXISTING WALL/PARTITION TO STRUCTURE ABOVE.
REMOVE EXISTING TUB AND RELATED ACCESSORIES. HOLD ONE APPROVED TUB FOR REUSE AND REINSTALLATION IN NEW TUB ROOM
142. DELIVER TO STORAGE OR DISCARD REMAINING TUBS AS DIRECTED BY OWNER.
EXISTING WALLS TO REMAIN THESE WALLS. REMOVE EXISTING BASE. PATCH AND PAINT EXISTING WALL AND INSTALL NEW BASE AS
SCHEDULED
DEMOLITION NOTES
PRIOR TO DEMOLITION ACTIVITIES THE OWNER SHALL
DISASSEMBLE AND REMOVE FROM THE PROJECT AREA ALL
EQUIPMENT AND MATERIALS THE OWNER WISHES TO RETAIN.
ALL EQUIPMENT AND MATERIALS REMAINING UPON
COMMENCEMENT OF THE DEMOLITION ACTIVITIES SHALL BE
REMOVED AND DISPOSED BY THE CONTRACTOR, WITH THE
EXCEPTION OF ANY EQUIPMENT AND MATERIALS
SPECIFICALLY NOTED OTHERWISE.
THE OWNER SHALL ARRANGE AND PAY FOR THE CEILING-MOUNTED
PATIENT LIFT SYSTEM THROUGH THEIR LIFT SYSTEM VENDOR. THIS
WORK SHALL INCLUDE BUT IS NOT NECESSARILY LIMITED TO REMOVAL
OF THE EXISTING SYSTEM, INCLUDING ALL RELATED TRACK, CARRIERS,
ACCESSORIES AND STRUCTURAL COMPONENTS, AND MODIFICATION
AND RE-INSTALLATION OF THE SAME AT THE APPROPRIATE TIME IN THE
PROGRESSION OF THE WORK. THE CONTRACTOR SHALL PROVIDE
ADEQUATE TIME WITHIN THE DEMOLITION AND RE-CONSTRUCTION
SCHEDULES FOR THIS ACTIVITY TO OCCUR. THE CONTRACTOR SHALL
BE RESPONSIBLE FOR REMOVING AND INSTALLING ELECTRICAL
SERVICES AS NECESSARY TO DEACTIVATE THE SYSTEM AND MAKE THE
SYSTEM OPERATIONAL.
A. – Coordinate with mechanical and electrical contractors for the removal work of these respective trades.
B. –General contractor shall provide all core drilling and structural openings to accommodate all work under this contract.
C. – Throughout the project selectively saw-cut and remove existing concrete floor slab and hand-excavate to accommodate installation of plumbing waste services. Provide structural backfill, vapor retarder and concrete as necessary. Coordinate with plumbing drawings.
D. –All wall, floor, and roof openings, whether new or abandoned by the removal of existing elements, shall be fire stopped in a manner deemed acceptable by the authority having jurisdiction.
E. –Where partitions, floor covering, ceiling systems, mechanical systems, millwork, and the like are removed or altered in whole or in part, the resulting surface shall be repaired, patched and otherwise made suitable to receive the specified finish materials and to allow the progression of work.
F. –All plumbing, mechanical, and electrical work to be removed shall be done in its entirety or where noted or acceptable to the owner, shall be capped behind the finished plan (inclusive of walls, ceilings and floors) and shall be so noted on the “as-built” construction documents.
G. –Contractor shall furnish and maintain exterior rubbish containers. The contractor shall transport materials to these containers by manual covered carts.
H. –Deliver to storage, on-site, all removed materials deemed by the owner to be worthy of salvage. Hold and protect for reuse, all materials so noted.
I. –Contractor to make provisions for ceiling removal and replacement to accommodate mechanical and electrical work above ceilings in areas not designated to receive a new ceiling system whether or not the full scope of this work is indicated on the documents.
J. –Prepare existing surfaces for new finishes. Refer to product manufacturer for recommended surface preparation prior to installation of new materials/finishes. See room finish schedule.
K. –Coordinate demolition work with project phasing.
L. –Dispose of removed material at the least costly legal disposal site.
M. –Removal work shall include, but shall not be limited to, all general construction within the project areas as follows:
-Wall construction -Wallboard on partitions that remain as may be necessary to install new services or remove existing services -Doors, frames, hardware, & borrowed lights -Floor covering and wall bases -Wall protection -Casework -Ceiling systems -Electrical systems & fixtures -Plumbing fixtures & piping -Sprinkler heads -Medical gases -Miscellaneous accessories
GENERAL NOTES:
DA
TE
TI
M E
PR
IN
T E D:
th re e in ch es o ne fo ot 6"
A on e an d on e ha lf in ch es o ne fo ot 6"
B on e in ch o ne fo ot
C
6" th re e qu ar te rs in ch o ne fo ot
D
6" on e ha lf in ch o ne fo ot
E th re e ei gh th s in ch o ne fo ot
F on e qu ar te r i nc h on e fo ot on e ei gh th in ch o ne fo ot
1 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
VA FORM 08-6231
Number Date Revision
D e p a r tm e n t o f
V e te r a n s A ff a ir s
Of fic e of F ac ili ti es
Date
VA Project No.
Drawing No.ScaleBuilding #
Location
Project Title
Approved By:
Approved By:
Approved By:
Drawing Title
N
KEY PLAN
ARCHITECT
Hazardous Materials ATC Associates 171 Commerce Street Williston, VT 05495 802-862-1980
185 Talcott Road Williston, VT 05495
T: 802.878.8841 www.e4harchitecture.com
405-13-104
Mechanical, Plumbing & Electrical Engineering L.N. Consulting 69 Union St Winooski, VT 05404 802-655-1753
Structural Engineering Engineering Ventures 208 Flynn Avenue, Suite 2A Burlington, VT 05401 802-863-6225
Commissioning Services Cx Associates 110 Main Street Burlington, VT 05401 802-861-2715
Life Safety Consultant Jensen-Hughes 1661 Worcester Road Suite 501 Framingham, MA
Construction Cost Estimating & Scheduling VIS Construction Consultants 595 Dorset Street, Suite #5 South Burlington, VT 05403 802-658-6100
Historic Preservation Suzanne Jamele 1 High Street Plainfield, VT 05667 802-454-7825
Interior Signage Design Creative Signage 9101 51st Place College Park, MD 20740
301-345-3700 VAMC - WHITE RIVER JUNCTION
Issued for Bidding & Construction
As indicated
C:
\U se rs
\s ra m se y\ Do cu m en ts
\s te ve
IN
PA
TI
EN
T
W
AR
D
RE
NO
VA
TI
ON
_B
LD
G3 1_ ce nt ra l m od el _S
Ra m se y.
rv t
4/
/2
:0 9:
A
M
Approver
DEDUCT ALTERNATE DA-5
31-AS-106
DA-5
INPATIENT WARD
RENOVATION
04/16/2018
Approver
Approver
Southwest Corner Scope Removal (AKA: Desk-80) - Demolition Plan
1/8" = 1'-0"1 FIRST FLOOR DEMOLITON PLAN
File details come from the government source that posted it. Updated .