VAMC-WRJ Building 31 Drawing 31-AS-106-DA-5.pdf

PDF 1 MB Posted

Attached to
Y1DA--Inpatient Ware Renovation 405-13-104
Solicitation number
36C24120R0142
Issued by

View the file

Other files

File Type Posted
36C24120R0142 0005.docx DOCX document
Nurse Call RFI Responses.docx DOCX document
408.08115.31.A104.pdf PDF
408.08115.31.A103.pdf PDF
S06 RFIs Responses from COR and AE.docx DOCX document
VA Hospital 7-16-2020.pdf.COPY.pdf PDF
36C24120R0142 0004.docx DOCX document
20200803-182827-VA_Hospital_Electric_Run_Checklist.pdf PDF
VAMC-WRJ Building 31 Drawing 31-AS-110-DA5-SKA-01.pdf PDF
VAMC-WRJ Building 31 Structural Drawings.pdf PDF
36C24120R0142 0003.docx DOCX document
Headwall Service Panels.pdf PDF
028211 Asbestos Abatement Rev-1.pdf PDF
IMG 6306 Above Patient Rm 192.pdf PDF
VAMC Project 405-13-109 DA-5 Drawings 04162018.pdf PDF
VAMC-WRJ Building 31 Nursing Unit 31-M-505-DA-5.pdf PDF
31-AS-105B ABATEMENT DIAGRAM LEVEL-1 Revision 1.pdf PDF
36C24120R0142 0002.docx DOCX document
Building 31 Nursing Unit Patient Lift System Turn-Key Design-Build 08192020.pdf PDF
31-AS-110-DA4.pdf PDF
P07 Wages.pdf PDF
S04 Site Vist 2.pdf PDF
36C24120R0142 0001.docx DOCX document
Inpatient Ward Renovation RFIs as of 8-25-2020.docx DOCX document
S04 Site Vist 1.pdf PDF
S02 Drawings 05012019 1.pdf PDF
S02 SPEC Vol 1 May1 2019.pdf PDF
S02 SPEC Vol 2 May1 2019.pdf PDF
36C24120R0142 Solicitation.docx DOCX document
S02 Wage Determination.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

D

DC

C

4 4

4.74.7

DN

UP

UP

STAIR 2

STAIR 1

STAIR 4

E.C.

PIPE

SHAFT

DUCT SHAFT

NEW WINDOW OPENING

IN EXISTING EXTERIOR WALL

4 44 4

2 2 2 2 2

6 6 6 6

7 7 7 7 7 7 7 7 7 7 7 7

SAWCUT AND REMOVE EXISTING EXTERIOR

WALL PER THE REQUIRED DIMENSIONS OF

THE NEW WINDOW OPENING

EXISTING WALL CONSTRUCTION CONSISTS OF

8" CMU, 2" RIGID INSULATION, AIRSPACE AND

FACEBRICK

53 53 53

3 8

8 8

8 8

77777

8 8 8

8 888

535353

2 5

53 53

4 4 4

777777777777777777

7 7 7 7

53 535353

53 53 53 53

53 53 53 53

5353 53 53

2 2

2 22

8 8 8 8

8 1

4 4

8 8

4 4

4 4 4 4 4 4 4

53 53 53 53 53 53

53 2

8 8

2 2 4 4

4 4

1 1

1 1

6 6 6 6 6 6 6 6

8 8 8 8

8 8 888

4 4

4 4 4

2 2 2

53 53 53 53

8 8

4 8

53 4

4 8

53 53

4 88

NEW DOOR OPENING

IN EXISTING EXTERIOR WALL

SAWCUT AND REMOVE EXISTING EXTERIOR

WALL PER THE REQUIRED DIMENSIONS OF THE

NEW DOOR OPENING

EXISTING WALL CONSTRUCTION CONSISTS OF

8" CMU, 2" RIGID INSULATION, AIRSPACE AND

FACEBRICK

8 8

3 25

ELEC

CLO

ELEC

CLO

ELEC

CLO

COMM

REMOVE HORIZONTAL DUCT THROUGHOUT

CORRIDOR AND INFILL PENETRATION AT

SECOND FLOOR LEVEL WITH 2 HOUR FIRE

RATED ENCLOSURE DETAIL. SEE DETAIL 5/AS-31-201

DO NOT REMOVE GYPSUM

WALL BOARD - MAINTAIN

2 HOUR RATING

AT EXISTING INTERIOR COLUMN

DO NOT REMOVE GYPSUM

WALL BOARD - MAINTAIN

2 HOUR RATING

AT EXISTING INTERIOR COLUMN

DO NOT REMOVE GYPSUM

WALL BOARD - MAINTAIN

2 HOUR RATING

AT EXISTING INTERIOR COLUMN

DO NOT REMOVE GYPSUM

WALL BOARD - MAINTAIN

2 HOUR RATING

AT EXISTING INTERIOR COLUMN

DN

UP

DN

UP

DN

UP

EXISTING TO REMAIN

REMOVE EXISTING CASEWORK, LOCKERS, SHELVES, EQUIPMENT, TACK BOARDS, HAND RAILS, AND OTHER FIT-OUT ACCESSORIES. DISCARD

AS DIRECTED BY OWNER.

REMOVE PLUMBING FIXTURES, TOILETS, GRAB BARS, SINKS, SHOWER, AND ALL RELATED ACCESSORIES. DISCARD AS DIRECTED BY OWNER.

REMOVE EXISTING FLOOR COVERING AND ADHESIVES, (VCT, CARPET, NON-SLIP FLOOR) AND BASE MATERIALS, TO A CLEAN EXISTING FLOOR

SLAB.

REMOVE EXISTING DOOR, DOOR FRAME AND HARDWARE, WINDOW FRAME AND GLASS. DISCARD AS DIRECTED BY OWNER.

REMOVE EXISTING CEILING SYSTEM, GRID AND CUBICLE CURTAIN TRACK INCLUDING ALL SUPPORTS. SOME STOCK MAY BE SALVAGED FOR

OWNERS REPLACEMENT INVENTORY. DISCARD BALANCE OF MATERIAL.

REMOVE EXISTING METAL LATH AND PLASTER AT EXTERIOR WALLS, WINDOW SILLS, JAMBS AND HEADS - EXPOSE EXISTING CMU WALL (TYPICAL

ALL EXTERIOR WALLS)

REMOVE EXISTING EXTERIOR WINDOW, ASSOCIATED BLOCKING AND TRIM

REMOVE EXISTING WALL/PARTITION TO STRUCTURE ABOVE.

REMOVE EXISTING TUB AND RELATED ACCESSORIES. HOLD ONE APPROVED TUB FOR REUSE AND REINSTALLATION IN NEW TUB ROOM

142. DELIVER TO STORAGE OR DISCARD REMAINING TUBS AS DIRECTED BY OWNER.

EXISTING WALLS TO REMAIN THESE WALLS. REMOVE EXISTING BASE. PATCH AND PAINT EXISTING WALL AND INSTALL NEW BASE AS

SCHEDULED

DEMOLITION NOTES

PRIOR TO DEMOLITION ACTIVITIES THE OWNER SHALL

DISASSEMBLE AND REMOVE FROM THE PROJECT AREA ALL

EQUIPMENT AND MATERIALS THE OWNER WISHES TO RETAIN.

ALL EQUIPMENT AND MATERIALS REMAINING UPON

COMMENCEMENT OF THE DEMOLITION ACTIVITIES SHALL BE

REMOVED AND DISPOSED BY THE CONTRACTOR, WITH THE

EXCEPTION OF ANY EQUIPMENT AND MATERIALS

SPECIFICALLY NOTED OTHERWISE.

THE OWNER SHALL ARRANGE AND PAY FOR THE CEILING-MOUNTED

PATIENT LIFT SYSTEM THROUGH THEIR LIFT SYSTEM VENDOR. THIS

WORK SHALL INCLUDE BUT IS NOT NECESSARILY LIMITED TO REMOVAL

OF THE EXISTING SYSTEM, INCLUDING ALL RELATED TRACK, CARRIERS,

ACCESSORIES AND STRUCTURAL COMPONENTS, AND MODIFICATION

AND RE-INSTALLATION OF THE SAME AT THE APPROPRIATE TIME IN THE

PROGRESSION OF THE WORK. THE CONTRACTOR SHALL PROVIDE

ADEQUATE TIME WITHIN THE DEMOLITION AND RE-CONSTRUCTION

SCHEDULES FOR THIS ACTIVITY TO OCCUR. THE CONTRACTOR SHALL

BE RESPONSIBLE FOR REMOVING AND INSTALLING ELECTRICAL

SERVICES AS NECESSARY TO DEACTIVATE THE SYSTEM AND MAKE THE

SYSTEM OPERATIONAL.

A. – Coordinate with mechanical and electrical contractors for the removal work of these respective trades.

B. –General contractor shall provide all core drilling and structural openings to accommodate all work under this contract.

C. – Throughout the project selectively saw-cut and remove existing concrete floor slab and hand-excavate to accommodate installation of plumbing waste services. Provide structural backfill, vapor retarder and concrete as necessary. Coordinate with plumbing drawings.

D. –All wall, floor, and roof openings, whether new or abandoned by the removal of existing elements, shall be fire stopped in a manner deemed acceptable by the authority having jurisdiction.

E. –Where partitions, floor covering, ceiling systems, mechanical systems, millwork, and the like are removed or altered in whole or in part, the resulting surface shall be repaired, patched and otherwise made suitable to receive the specified finish materials and to allow the progression of work.

F. –All plumbing, mechanical, and electrical work to be removed shall be done in its entirety or where noted or acceptable to the owner, shall be capped behind the finished plan (inclusive of walls, ceilings and floors) and shall be so noted on the “as-built” construction documents.

G. –Contractor shall furnish and maintain exterior rubbish containers. The contractor shall transport materials to these containers by manual covered carts.

H. –Deliver to storage, on-site, all removed materials deemed by the owner to be worthy of salvage. Hold and protect for reuse, all materials so noted.

I. –Contractor to make provisions for ceiling removal and replacement to accommodate mechanical and electrical work above ceilings in areas not designated to receive a new ceiling system whether or not the full scope of this work is indicated on the documents.

J. –Prepare existing surfaces for new finishes. Refer to product manufacturer for recommended surface preparation prior to installation of new materials/finishes. See room finish schedule.

K. –Coordinate demolition work with project phasing.

L. –Dispose of removed material at the least costly legal disposal site.

M. –Removal work shall include, but shall not be limited to, all general construction within the project areas as follows:

-Wall construction -Wallboard on partitions that remain as may be necessary to install new services or remove existing services -Doors, frames, hardware, & borrowed lights -Floor covering and wall bases -Wall protection -Casework -Ceiling systems -Electrical systems & fixtures -Plumbing fixtures & piping -Sprinkler heads -Medical gases -Miscellaneous accessories

GENERAL NOTES:

DA

TE

TI

M E

PR

IN

T E D:

th re e in ch es o ne fo ot 6"

A on e an d on e ha lf in ch es o ne fo ot 6"

B on e in ch o ne fo ot

C

6" th re e qu ar te rs in ch o ne fo ot

D

6" on e ha lf in ch o ne fo ot

E th re e ei gh th s in ch o ne fo ot

F on e qu ar te r i nc h on e fo ot on e ei gh th in ch o ne fo ot

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

VA FORM 08-6231

Number Date Revision

D e p a r tm e n t o f

V e te r a n s A ff a ir s

Of fic e of F ac ili ti es

Date

VA Project No.

Drawing No.ScaleBuilding #

Location

Project Title

Approved By:

Approved By:

Approved By:

Drawing Title

N

KEY PLAN

ARCHITECT

Hazardous Materials ATC Associates 171 Commerce Street Williston, VT 05495 802-862-1980

185 Talcott Road Williston, VT 05495

T: 802.878.8841 www.e4harchitecture.com

405-13-104

Mechanical, Plumbing & Electrical Engineering L.N. Consulting 69 Union St Winooski, VT 05404 802-655-1753

Structural Engineering Engineering Ventures 208 Flynn Avenue, Suite 2A Burlington, VT 05401 802-863-6225

Commissioning Services Cx Associates 110 Main Street Burlington, VT 05401 802-861-2715

Life Safety Consultant Jensen-Hughes 1661 Worcester Road Suite 501 Framingham, MA

Construction Cost Estimating & Scheduling VIS Construction Consultants 595 Dorset Street, Suite #5 South Burlington, VT 05403 802-658-6100

Historic Preservation Suzanne Jamele 1 High Street Plainfield, VT 05667 802-454-7825

Interior Signage Design Creative Signage 9101 51st Place College Park, MD 20740

301-345-3700 VAMC - WHITE RIVER JUNCTION

Issued for Bidding & Construction

As indicated

C:

\U se rs

\s ra m se y\ Do cu m en ts

\s te ve

IN

PA

TI

EN

T

W

AR

D

RE

NO

VA

TI

ON

_B

LD

G3 1_ ce nt ra l m od el _S

Ra m se y.

rv t

4/

/2

:0 9:

A

M

Approver

DEDUCT ALTERNATE DA-5

31-AS-106

DA-5

INPATIENT WARD

RENOVATION

04/16/2018

Approver

Approver

Southwest Corner Scope Removal (AKA: Desk-80) - Demolition Plan

1/8" = 1'-0"1 FIRST FLOOR DEMOLITON PLAN