The transcript is from a pre-bid meeting held on February 8, 2024 regarding solicitation number 36C10F24R0007 for the construction of a 131,724 square foot outpatient clinic (PACT ACT) in Sarasota, Florida. Key details include:
- The Department of Veterans Affairs Office of Construction and Facilities Management is the contracting agency seeking a general contractor to build the new outpatient clinic with completion required by December 2026. Bids are due by March 15, 2024 with award notice projected for April 2024. The estimated price range for construction is between $50-75 million. The solicitation is unrestricted with no set-aside designations. Subcontracting opportunities were discussed for various trades such as mechanical, electrical and structural engineering work. The incumbent contractor was also in attendance to answer questions about ongoing operations that will be relocated due to the new construction.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
· · · · · · ·U.S. DEPARTMENT OF VETERANS AFFAIRS
· · · · · · · · · · ·PRE-BID CONFERENCE
· · · · · · · · · ·OUTPATIENT CLINIC (OPC)
· · · · · · · · · · · SARASOTA, FLORIDA
· · · · · · · · · · · RLP# 36C10F24R0007
· · ·DATE TAKEN:· · · · ·Thursday, February 8, 2024
· · ·PLACE TAKEN:· · · · Hyatt House
· · · · · · · · · · · · ·5308 Avion Park Drive
· · · · · · · · · · · · ·Tampa, Florida 33607
· · ·TIME:· · · · · · · ·10:00 a.m. - 10:47 a.m
· · ·BEFORE:· · · · · · ·LAURA DWYER PIERLE, RPR
· · · · · · · · · · · · ·STENOGRAPHIC COURT REPORTER
· · · · · · · · · · · · ·AND NOTARY PUBLIC - STATE
· · · · · · · · · · · · ·OF FLORIDA AT LARGE
· · · · · · · · BAY AREA COURT REPORTING, INC.
· · · · 601 SOUTH HARBOUR ISLAND BOULEVARD, SUITE 109
· · · · · · · · · · TAMPA, FLORIDA· 33602
· · · · · · · · · · · · 813-251-4538 http://www.bar-tampa.com/
·1
·2· ·APPEARANCES:
·3· ·VA PROJECT TEAM:
·4· · · · KENT WALKER, PROJECT MANAGER
· · · · · ERNEST JACKSON, JR. LEASE CONTRACTING OFFICER
·5· · · · JOSE BAERGA, RESIDENT ENGINEER
· · · · · TOM CHAMP, SENIOR RESIDENT ENGINEER
·6
· · ·LOCAL VA TEAM
·7
· · · · · JUSTINA WELLS, ASSISTANT DIRECTOR, BAY PINES
·8· · · · VA HEALTHCARE SYSTEM
· · · · · ALYSSA MAILLY, ACTIVATION COORDINATOR,
·9· · · · FACILITIES MANAGEMENT BP
· · · · · RYAN BOERGERS, ENGINEERING TECH, FACILITIES
10· · · · MANAGEMENT SERVICES
· · ·CONTRACTOR REPRESENTATIVES:
· · · · · PATRICIA RESTREPO, CHARTWELL ENTERPRISES, VA'S
13· · · · ADVISOR
15· · · · · · · · · · · · ·-· - -
·1· · · · · · · · · · ·- - -
·2· · · · MS. RESTREPRO:· We are here for the VA's
·3· ·requirement for Sarasota, it's an Outpatient
·4· ·Clinic.· I'll go ahead and get started and
·5· ·introduce myself and go around the room.
·6· · · · I'm Patty Restrepo.· I'm with Chartwell
·7· ·Enterprises working with Veteran's Affairs as their
·8· ·broker.
·9· · · · Kent.
10· · · · MR. WALKER:· Good afternoon.· Kent Walker, the
11· ·Project Manager of VA Central Office of D.C.· So
12· ·I've got several projects here in Florida and
13· ·appreciate Patty.· Thanks for you all showing up.
14· ·I appreciate you.
15· · · · MR. JACKSON:· Earnest Jackson.· Everyone calls
16· ·me EJ.· Lease Contracting Officer CFM.· Nice to see
17· ·everybody.
18· · · · MR. CHAMP:· Thom Champ, CFM also.· I'm the
19· ·team lead for Southeast SRE.
20· · · · MR. BAERGA:· Good morning.· I'm Jose Baerga
21· ·Resident Engineer with the office of CFM as well.
22· · · · MR. ROSE:· Zach Rose, Cullinan Properties.
23· · · · MR. OWENS:· Mike Owens, with Cullinan
24· ·Properties.
25· · · · MR. BUMGARNER:· My name is Luke Bumgarner, I'm
·1· ·with C2 Construction and Rise Developments.
·2· · · · MR. ALVERSON:· Sam Alverson with U.S. Federal
·3· ·Properties.· We're a developer.
·4· · · · MS. MAILLY:· Alyssa Mailly, Activation
·5· ·Coordinator at Bay Pines.
·6· · · · MR. WALKER:· Channing Walker Allure Management
·7· ·Solutions.
·8· · · · MR. TINGLEY:· I'm John Tingley, Blue Cord
·9· ·Design and Construction out of Orlando, Florida.
10· · · · MR. HOKANSON:· Steve Hokanson, PHV, LLC.
11· · · · MR. CONNOLLY:· Matt Connolly with Molasky
12· ·Development.
13· · · · MS. RESTREPRO:· Thank you all.· And I know
14· ·many of you have worked on VA projects, which is
15· ·wonderful.
16· · · · Kent or EJ, before I start, is there anything
17· ·that you wanted to mention or --
18· · · · MR. JACKSON:· No, I didn't have anything
19· ·specific.
20· · · · MS. RESTREPRO:· Justina, we were just
21· ·getting -- we were just introducing ourselves.
22· · · · MS. WELLS:· Right.
23· · · · MS. RESTREPRO:· You're sitting right here.
24· · · · MS. WELLS:· I just came in from Cape Coral
25· ·this morning.
·1· · · · MS. RESTREPRO:· So we're just mentioning
·2· ·everyone introduced themselves.· And so Justina
·3· ·Wells is the assistant director.· And so I think I
·4· ·mentioned earlier we, of course, have been working
·5· ·with Alyssa and Ryan and Justina and Jose and Tom
·6· ·and Kent and EJ and others in getting this package
·7· ·together and getting it out.· So obviously the
·8· ·formal solicitation has gone out and we are
·9· ·starting the process.
10· · · · So we hold these pre-bids primarily to provide
11· ·information and provide a form of where questions
12· ·can we asked and, of course, they can be submitted
13· ·afterwards until February 15th.· But then also
14· ·there is a lot -- what we are seeing a lot of is
15· ·experienced developers, you know, coming, which is
16· ·great, which the VA likes.· But then also if there
17· ·is new people who are working with the government, 18· ·maybe haven't worked with the government, but
19· ·worked on the private sector, commercial side, it's
20· ·good for them to come to these meetings because we
21· ·do give a general overview of the solicitation
22· ·package and, you know, hit upon certain points that
23· ·are extremely important for the government which
24· ·might not always be, you know, the same kind of
25· ·emphasis in the commercial side.
·1· · · · So with that, Justina, I didn't know if you
·2· ·wanted to --
·3· · · · MS. WELLS:· Yeah.· Well, good morning.· Thank
·4· ·you all for coming.· I know for us with the VA
·5· ·we're really, really excited about the opportunity
·6· ·for a new replacement clinic for our Sarasota
·7· ·Clinic.· Our clinic now it does well for us, but we
·8· ·are struggling to continue to have enough space in
·9· ·order to expand services for Veterans and that's
10· ·something that we're really looking forward to do
11· ·increasing the access that we have at our sites but
12· ·also the quality of care and being able to do that
13· ·within a site that meets all of those different
14· ·requirements is extremely important to us.
15· · · · So I thank you for your time.· I thank you for
16· ·attending and I look forward to what we learn
17· ·today.
18· · · · MS. RESTREPRO:· Thanks, Justina.
19· · · · Would you prefer that I stand?· No.
20· · · · Okay.· So we've gone through the
21· ·introductions.· This is the agenda in terms of the
22· ·pre-bid purpose, project overview, design overview.
23· ·Jose is going to be giving a design overview.
24· · · · You know, we had the great benefit of having
25· ·Jose and Tom involved and they are always involved, ·1· ·but even more so in terms of this project because
·2· ·they were the leads in terms as it relates to
·3· ·getting the design package together which is unique
·4· ·to this project.· And then the review of request
·5· ·for lease proposal package, and then question and
·6· ·answer period.
·7· · · · We do have Laura, who is a court reporter, who
·8· ·is transcribing the questions and going to provide
·9· ·the whole transcript for the presentation.
10· · · · So we've already gone through the team.· Since
11· ·we know EJ is the lease contracting officer.· Kent
12· ·is the project manager.· We have Jose and Tom very
13· ·experienced with VA.· And then the local VA team as
14· ·Justina just spoke.· Alyssa is the activation
15· ·coordinator and then also Ryan.
16· · · · It's great.· What we have been really focused
17· ·on too is getting the activation coordinator
18· ·involved really early on because as we know as soon
19· ·as it gets awarded we get into design, 20· ·construction, and then activating the clinic.· And
21· ·then myself.
22· · · · So these are just protocols that we ask that
23· ·you hold until questions to the end.· When you do
24· ·have a question at the end please state your name
25· ·and the firm that you are with that will assist
·1· ·Laura in getting that question.· We do ask though
·2· ·that you do submit the question even if you ask it
·3· ·here for the benefit of anybody who might be
·4· ·interested in responding to this RLP.· Obviously
·5· ·speak clearly and slowly.· If you can reference the
·6· ·RLP paragraph and section that's always very
·7· ·helpful.· And then as I mentioned they all have to
·8· ·be submitted in writing.· But we can have a
·9· ·discussion here if there is a specific question.
10· ·And we'll post everything into Sam.gov.
11· · · · Hopefully if anybody has been responding to
12· ·other RLP's that have gone out you will see that
13· ·amendment that comes soon after, comes a couple of
14· ·weeks after the pre-bid where we do have the
15· ·questions, we have the attendance list, and then
16· ·the transcript and then this presentations as
17· ·posted.
18· · · · And the last thing is very important in terms
19· ·of respecting procurement integrity and
20· ·sensitivity.· That's something that's spoken about
21· ·by the LCO at any meeting that we come to as we go
22· ·through that solicitation process.
23· · · · Okay.· So the purpose, I've already mentioned
24· ·this is to provide a general overview of the
25· ·requirements for this RLP.· It is -- what I will
·1· ·mention is if you have been responding they are
·2· ·very similar, but it is extremely important to
·3· ·treat each one individually and separately.· I'll
·4· ·mentioned something too later on just as a
·5· ·reminder.· Again, I always say it helps you, it
·6· ·also helps the government in terms, and you'll
·7· ·understand when I mention it later down the road.
·8· · · · We want to make sure that it's complete your
·9· ·packages and that you do have an understanding of
10· ·the requirements and that it is fully responsive
11· ·and technically acceptable.· Because that allows us
12· ·to evaluate the proposals effectively.· And then, 13· ·of course, answer any questions that anybody has.
14· · · · Again, also to the one reason why we do this
15· ·is because we do want to promote competition, you
16· ·know, amongst very experienced developers and then
17· ·also developers that want to start working with the
18· ·government.· You might have very good experience, 19· ·as I mentioned, with the commercial side, but want
20· ·to get involved with the government.
21· · · · We will provide this transcript and the power
22· ·point as well on Sam.gov.
23· · · · So the project overview.· It is an outpatient
24· ·clinic.· It is an SDVOSB set-aside.· I think many
25· ·of you are already aware of that.· For those who
·1· ·are not, you do have to be certified as service
·2· ·disabled veteran and a small business to submit.
·3· ·You can have a joint venture.· You can be partnered
·4· ·with an SDVOSB.· But there is obviously certain
·5· ·regulations that one has to followed to be SDVOSB.
·6· · · · The maximum space -- it's a fully serviced
·7· ·lease.· So it does include the utilities and the
·8· ·janitorial.
·9· · · · The maximum space is 131,724 ABOA square feet.
10· ·So you cannot be above that.
11· · · · And then rentable square feet it is in there.
12· ·Make sure that you aren't over that rentable square
13· ·feet when you are submitting, because that is
14· ·something with the GSA delegation that, you know, 15· ·cannot be over, cannot accept the project like
16· ·that.
17· · · · And then there is 750 on-site surface parking
18· ·spaces.· That is the general requirements for this
19· ·project.
20· · · · So what I was going to do was I was going to
21· ·go through the RLP.· And I know this is usually
22· ·more beneficial of those that have never seen an
23· ·RLP, but what I will try to do is maybe emphasis
24· ·certain items that we've been seeing and saying be
25· ·mindful of this or make sure that you are
·1· ·addressing this.
·2· · · · So let's start with the statement of
·3· ·requirements.· Some of it I've already mentioned in
·4· ·terms of the square footage and whatnot.· But we'll
·5· ·go into others.
·6· · · · We are looking for a 15-year firm term and
·7· ·also a 20-year firm term.· The reason why we look
·8· ·at both of them is because we have -- we are
·9· ·looking at scoring, you know, both.· Obviously not
10· ·always, but generally if it's shorter term lease
11· ·as, you know, you kept everything the same, it's
12· ·going to be better at scoring than at a 20-year.
13· ·So but we do ask for both and you do have to submit
14· ·both.
15· · · · Another important point is when you are
16· ·submitting this, submitting it in your 1364, it is
17· ·important to -- you are required to submit the
18· ·Attachment 1 which is the Excel file.· So you
19· ·should submit both.· Be sure to submit both.
20· · · · This is what you hear me talking about score.
21· ·The lease has to score as an operating lease.· It
22· ·cannot score as a capital lease.· And so as soon as
23· ·we get your documents, your 1364 we are submitting
24· ·that information.· We are reviewing it.· So make
25· ·sure that it's consistent the information in your
·1· ·1364 with your Attachment 1 and with your 1217.
·2· ·Those are the financials offer or information that
·3· ·goes into the financial offer for the price
·4· ·proposal.· But that information is taken and the
·5· ·government scores the offers.· And so it has to
·6· ·score as an operating lease rather than a capital
·7· ·lease.· We cannot -- the government cannot award if
·8· ·it scores as a capital lease.· So this is very
·9· ·important.
10· · · · With operating costs, this does require a
11· ·fully serviced lease.· And so, you know, your
12· ·operating cost is part of the rental consideration
13· ·and it is part of the evaluation in terms of the
14· ·present value analysis as well as the scoring.
15· · · · What we do and many of you were part of the
16· ·market survey, we do have a delineated area so your
17· ·property has to fall within the delineated area.
18· ·Here are the boundaries of the delineated area.
19· ·And then here is a map of it.· Healthy delineated
20· ·area.
21· · · · If you are new, which I know many of you are
22· ·not, but even if you are doing this, you know, if
23· ·you have done this many times I always find it very
24· ·helpful to, you know, start with Section 1.06.· It
25· ·lists all the documents that are included with the
·1· ·RLP.· You'll notice with this one there are some
·2· ·that you typically don't see.· It is more specific
·3· ·to here.· For example, this Appendix A.2.1, which
·4· ·is Bay Finish Standards, as well the Appendix
·5· ·A.2.2, which is the fixture guide.· And so that's
·6· ·something really pay attention to.· I can see where
·7· ·you might not hone in on it and see it, but it is
·8· ·important to see, to look at.· You have your
·9· ·typical appendices, but they are specific to this
10· ·project like the lease design narrative and Jose is
11· ·going to speak a little bit more about that.
12· · · · Your project content list.· Your room data
13· ·matrix.· Your FSL, facility security requirement, 14· ·is FSL-II.· And then there is conceptual floor plan
15· ·that speaks to the adjacency.· And then there is
16· ·the janitorial services, which this is a fully
17· ·serviced lease.· So this does have janitorial
18· ·services in it.
19· · · · And then you have your forms that are
20· ·generally typical to most projects.
21· · · · So moving onto Section II, this is with the
22· ·eligibility and preferences for award.· This is
23· ·something that we -- that the evaluation team has
24· ·been looking at closely is the efficiency of the
25· ·space.· So in order to be acceptable for award, the
·1· ·offered space must provide for an efficient layout
·2· ·as determined by the LCO.· So make sure when you
·3· ·are doing your plans that it is efficient within
·4· ·the ABOA square footage, but it's efficient space.
·5· ·This is very -- even when we go out to the market
·6· ·survey we are looking at this that it cannot be
·7· ·within the one-percent annual chance floodplain
·8· ·unless the government has determined that there is
·9· ·no practical alternative.· Or what we sometimes you
10· ·might have a large property and you build and none
11· ·of your ingress or egress goes into where there is
12· ·a floodplain.· But a lot of times what you will
13· ·read in the RLP is that you have to demark or, you
14· ·know, make your parcel not within the floodplain.
15· ·So that is a very basic requirement.
16· · · · It must meet the accessibility and the fire
17· ·protection and life-safety requirements.
18· · · · Many of you are very well aware of this.· This
19· ·is Phase I ESA environmental site assessment.
20· ·Those are required.· I have seen offers get
21· ·excluded or not accepted because they did not have
22· ·their Phase I that was completed within 180 days.
23· ·They might have submitted one, you know, that was a
24· ·couple of years older.· This is extremely
25· ·important.· So make sure that if you are
·1· ·submitting, you are submitting Phase I ESA with
·2· ·your project.
·3· · · · And then also what it mentions here is that
·4· ·the offeror is responsible for doing the
·5· ·environmental due diligence studies.· But the
·6· ·government is responsible for the compliance of
·7· ·NEPA.· But the government VA will look to the
·8· ·Offeror to assist with that process in terms of
·9· ·getting studies done and providing information.
10· · · · It goes on here to say that the government
11· ·does reserve the right to reject any offers where
12· ·the studies or documentations supporting the NEPA
13· ·process provided by the offeror for the offered
14· ·property are inadequate, it entails adverse impacts
15· ·on the human environment, the identified adverse
16· ·impacts cannot be readily mitigated, or the level
17· ·of NEPA analysis is more extension than is
18· ·acceptable to the government.· And I'm pretty
19· ·certain that this project will requires NEPA.· So
20· ·this will pertain.
21· · · · And then, of course, Section 106 the cultural
22· ·resource study that is required as well with your
23· ·initial offers.
24· · · · And there is in Section 2.1.3 it does -- it
25· ·does clearly outline what is required in that study
·1· ·in terms of area for potential effect and what they
·2· ·are looking for in the study.
·3· · · · So moving onto Section 3.· This also too is
·4· ·very important.· I would say probably one way to
·5· ·look at this Section 106 and then early on look at
·6· ·Section 3.02 because that tells you how it needs to
·7· ·be submitted.· Questions are due by February 15th.
·8· ·So a week from today by 4:00 p.m. and once you
·9· ·submit them we are going to have an internal
10· ·meeting and respond to those questions in a Q&A
11· ·matrix and that will be part of Amendment 1.
12· · · · Initial offers are due March 26th.· I will not
13· ·try to guess what day it is.· But March 26th, 2024
14· ·by 4:00 p.m.
15· · · · And they're to be submitted to Chartwell
16· ·Enterprises.· We ask you to submit ten.· You are
17· ·required to submit ten CDs.· Volume one is the
18· ·technical proposal and volume two is the price
19· ·proposal.· No hard copies will be accepted.
20· · · · It is really important to review Section 3.02
21· ·of the RLP.· And it is very important that it gets
22· ·submitted by this date and time that is posted on
23· ·the RLP.· Or there is an amendment that extends it
24· ·by that extension date.
25· · · · Another document that is part of the package
·1· ·is the proposal compliance matrix and this -- this
·2· ·really outlines nicely, I think, in terms of what
·3· ·we're asking the private sector to respond and to
·4· ·organize the offer.· What you will see is it's
·5· ·broken up in the evaluation factors.· And the
·6· ·government is very firm about they let you know
·7· ·what we are going to evaluate you on and that's
·8· ·what we're going to evaluate you on.· And so that
·9· ·obviously I'm sure you're all very well aware it's
10· ·found in Section 4 of the RLP.· So it's very
11· ·important to read that.· And you will see it aligns
12· ·with these different evaluation factors.
13· · · · So the first one is technical quality, which
14· ·is the most important evaluation factor.· It goes
15· ·in descending order of importance.· So these are
16· ·items it in.· So it's important to go through the
17· ·proposal compliance matrix.· Make sure that you are
18· ·providing that information so we can evaluate it.
19· · · · And also too I'll mention what I've been
20· ·seeing is if you put -- I know it says number of
21· ·pages.· But if can you put the page numbers, the
22· ·actual page numbers.· So don't say -- I am just
23· ·making this up.· In your project management plan
24· ·you did ten pages of a PMP, don't put ten.· But the
25· ·actual page numbers of what they are, you know, in
·1· ·your proposal, if it's 950 to 960, that's what we
·2· ·are interested in seeing.
·3· · · · So moving along.· The next technical
·4· ·quality -- excuse me -- evaluation factor past
·5· ·performance.· And this is a compliance matrix.· So
·6· ·it's broken out.· It's letting you understand what
·7· ·we're, you know, what we're expecting in terms of
·8· ·the initial offer.· So we have past performance.
·9· ·PPQs, you know, I know many of you are sending them
10· ·out as you should because as it states in Section 4
11· ·is that you have up to five that you can submit.
12· ·And they need to be corroborated with the PPQs.
13· ·There is a mechanism, though, that they don't get
14· ·submitted, you know, it's not detrimental if it's
15· ·not submitted.· But it is important that you do get
16· ·those PPQs and, you know, they get submitted.
17· · · · Also with the A/E and the GC there is, you
18· ·know, it states the different standard form 330, 19· ·527 for the general contractor.· Make sure that the
20· ·licenses are, you know, up to date, they are not
21· ·expired.· Just very basic stuff.
22· · · · And then also to I'll mention this, make sure
23· ·that -- I know there is a lot of proposals that are
24· ·being done that you treat each one individually and
25· ·that there is technical qualify control of it.· And
·1· ·I only say that because it really does help you
·2· ·because it's a shame when you are going through it
·3· ·and you see something that's carried over from
·4· ·another project.· Because as much as you can go --
·5· ·people do go over it, they see it, but it just
·6· ·makes your package much better, much nicer if you
·7· ·have that technical quality control.
·8· · · · So then moving onto we have financial
·9· ·information that's important.· And then also the
10· ·project management plan.
11· · · · So it's broken down as I have been saying in
12· ·terms of evaluation factors and then the offering
13· ·entity submittals, the building site submittals.
14· ·They do have to show evidence of control of the
15· ·property.· You know, whether it's an option, a
16· ·purchase option.· Sometimes ground lease and then
17· ·there is additional RLP submittals.· For anybody
18· ·who is new you do have to resubmit those documents
19· ·that we sent out with the RLP.· Because we want to
20· ·know that you read them and that you initialed them
21· ·and understand the documents that we sent out.· So
22· ·those do need to be sent out.· And what it does, 23· ·ultimately too if you are awarded the one we have
24· ·those documents already as part of the lease
25· ·package.
·1· · · · And then the price proposal.· I've already
·2· ·mentioned this Attachment 1 is required.· So submit
·3· ·Attachment 1 with your 1364.
·4· · · · I have already hit upon this in terms of
·5· ·evidence of ownership or control of the building.
·6· ·Again, if we do not receive that and we do not know
·7· ·that you control that property whether through an
·8· ·option to purchase or whatnot, it's clearly
·9· ·outlined in Section 3.06, I've seen it where the
10· ·LCO has not accepted it because there is no reason
11· ·to spend time with a group that doesn't even
12· ·control the property.· So it is important that we
13· ·do see that you do control the property.· So it
14· ·outlines it.· So the option to purchase, the sales
15· ·contract, the deed showing fee simple owner or an
16· ·option to lease the site for longer than the lease
17· ·term plus the post award design and construction
18· ·phase and any renewal options.
19· · · · This is something that we just have been
20· ·making sure that -- a lot of it actually I think it
21· ·came from one of the activation sites.· What we've
22· ·been -- what we've heard from the field is it's
23· ·really important that we have these documents, the
24· ·design documents or whatnot in Revit format.· And
25· ·so we want the private sector to understand this
·1· ·because as soon as it is awarded and you are the
·2· ·awardee the government is going to be looking for
·3· ·the Revit files because it really helps with
·4· ·transition into design, construction and
·5· ·application.
·6· · · · Section 3.06 is also an important section
·7· ·because it talks about additional submittals and
·8· ·provides more insight into certain items that the
·9· ·government does require.· One of the items is that
10· ·we are looking for green globes for new
11· ·construction.· So it is for two green globes.· Also
12· ·I've mentioned this that the government requires a
13· ·fully serviced lease and then that you should be
14· ·submitting a building operating plan.
15· · · · Tenant improvements, what it has been as of
16· ·late is that we do provide the tenant improvement
17· ·allowance amount.· So you understand what that TI
18· ·is going to be.· We have -- the government has the
19· ·right to amortize it.· But we have every
20· ·expectation it's going to be paid lump sum.
21· ·Obviously as the private entity you will be funding
22· ·it until the space is accepted and that's when they
23· ·will pay the lump sum.
24· · · · Method of award.· So Section 4 I've referenced
25· ·this is where it indicates that this is the best
·1· ·value trade off.· And so in accordance with FAR
·2· ·Part 15.101, the competitively negotiated best
·3· ·value trade off source selection procedures will be
·4· ·used to evaluate the proposals and the award will
·5· ·be made to the responsible offeror offering the
·6· ·best value to the government after evaluation of
·7· ·both the total evaluated contract, price and
·8· ·non-price technical factors.· So those are your
·9· ·evaluation factors that are outlined in Section 4
10· ·of the RLP.
11· · · · This is important for everybody to understand
12· ·that the government intends to evaluate proposals
13· ·and award a contract without discussion with the
14· ·offeror.· So the LCO can make a determination that
15· ·he is going to award off the initial offers.· So
16· ·your initial offer does need to be the most
17· ·competitive.· They obviously have the right to set
18· ·a competitive range and go into a second TEB or
19· ·asked for revised proposals and do a second TEB.
20· ·But I do want to emphasize that they can award off
21· ·the initial offer.· So it is important that you
22· ·submit a competitive offer.
23· · · · These are the evaluation factors.· Factor one
24· ·is technical quality.· That includes architectural
25· ·concept and building design, quality of site
·1· ·characteristics and sustainable design and energy
·2· ·efficiency.
·3· · · · As I mentioned there are four evaluation
·4· ·factors.· The fourth one is your socio-economic.
·5· ·This is set-aside SDVOSB and we are just confirming
·6· ·that you would factor SDVOSB.· So three other ones
·7· ·the technical quality being the most important.· It
·8· ·does provide a good outline of what we are
·9· ·evaluating.· So I am sure many of you have already
10· ·read through evaluation factor -- Section 4, 11· ·evaluation factor one because that's what we do
12· ·evaluate you on.
13· · · · The second evaluation factor offeror's
14· ·qualifications and past performance.· So we are
15· ·looking at your past performance, your design team, 16· ·your general contractor, your financial resources
17· ·in terms of your funding plan and then also the
18· ·conditional commitment letters and then your
19· ·project management plan.· And that plan, what we
20· ·are looking at is the schedule, how you are going
21· ·to deliver the project on time and within budget
22· ·and mitigated risk.
23· · · · And in Factor 3 is the operations and
24· ·maintenance plan.· How are you going to operate the
25· ·facility for the next, you know, most likely 20
·1· ·years, potentially 15 years.
·2· · · · And we then talked about the socio-economic
·3· ·status.
·4· · · · So there are some additional terms within the
·5· ·RLP.· Cost of off-site improvements will be borne
·6· ·by the lessor.· You are -- the lessor is
·7· ·responsible for determining the cost of off-site
·8· ·improvements prior to lease award and including the
·9· ·cost of off-site improvements in the proposed rent.
10· · · · And then you are to acknowledge that it's your
11· ·duty to conduct reasonable site inspections for the
12· ·proposed site.
13· · · · And then also it's mentioned in the evaluation
14· ·factors, but you are to submit evidence of teaming
15· ·arrangements within your bid.
16· · · · So this is just an overview of what the RLP
17· ·is, the five sections.· We went through those five
18· ·sections.
19· · · · The lease -- I am not going to get into
20· ·everything.· But I just want to lay out this is the
21· ·document that you're going to live with for the
22· ·next 20 years.· You do get -- it starts as a
23· ·template, VA template that's used by GSA but it is
24· ·tailored for the specific project.· So there are
25· ·specific items for the specific price are being
·1· ·included in the lease and L100.· But once it's
·2· ·awarded that will get -- there are certain items
·3· ·that haven't been filled in obviously the rent, ·4· ·other items like if there are certain improvements
·5· ·that are going to be required before they accept
·6· ·this space, that's outside of maybe it might be off
·7· ·campus, you know, signal light or something that
·8· ·would get included in there so it's very clear as
·9· ·to what the government is requiring.
10· · · · But so this is the lease.· These are the
11· ·sections in it which you will notice is Section 3
12· ·with the shell costs.· Something that comes up a
13· ·lot.· HVAC is included in Section 3.· And then you
14· ·have the design, construction and post award
15· ·activity.
16· · · · I will mention Section 4 because when you are
17· ·doing your schedule you'll see this in evaluation
18· ·factor.· What we are asking you to do is when you
19· ·do your schedule look at Section 4.· Because what
20· ·we've done is we've put dates of what the
21· ·government their timing as the amount of days they
22· ·have to review the design concept drawings or the
23· ·construction drawings or the CDs.· We said, you
24· ·know, it said it indicates how many days the
25· ·government requires.· But we're looking to the
·1· ·private sector to fill in those dates of how long
·2· ·they are going to take.· It's important that you
·3· ·meet the timeline.· But we're going to be
·4· ·evaluating it because potentially you will be able
·5· ·to do it much quicker or hopefully not much longer, ·6· ·but it's part of the evaluation.· So you will see
·7· ·some of the items not -- they will have X's that
·8· ·intends for you-all to include that in your
·9· ·schedule.
10· · · · So this is probably the more important aspect
11· ·of it is the design.· And so I am going to hand it
12· ·over to Jose who is going to discuss the design
13· ·overview.· It's the crux of the project.· Sit here.
14· · · · MR. BAERGA:· Good morning everyone.· Actually
15· ·thank you-all for coming in and joining us.
16· · · · This package is actually a compilation of a
17· ·lot of work that has taken place from the medical
18· ·center side and the services to give you the best
19· ·approach to what's actually development of this new
20· ·Sarasota Outpatient Clinic.· Again, the design
21· ·concept the submission should be -- shall include a
22· ·technical narrative of the facility design
23· ·approach.
24· · · · The design concept submitted by the offeror
25· ·will be used to evaluate technical proposals and
·1· ·develop design development drawings after award.
·2· · · · That Section 4 that we discussed actually maps
·3· ·the delivery of the project.· So just want to make
·4· ·sure that you are actually paying attention to
·5· ·that.
·6· · · · Failure to submit plans and design criteria in
·7· ·accordance with the government's requirements may
·8· ·cause offers to be deemed unacceptable and
·9· ·non-responsive.
10· · · · The next screen is the lessor shall design and
11· ·construct the building and site in accordance with
12· ·the RLP, all the requirements, and appendices that
13· ·are included, the federal regulations, building
14· ·codes and ordinances in case of conflict, most
15· ·stringent standard applies.· Green globes for new
16· ·construction, two green globes level for this
17· ·particular facility.
18· · · · Accessibility standards are actually to be
19· ·taken into account.· In addition, with compliance
20· ·with local codes, and ordinances, design, 21· ·construction and alterations must comply with ADA, 22· ·VA program guides and UFAS, also Davis Bacon wages.
23· · · · As you can see actually you will see on the
24· ·actual package you have a list of different items
25· ·that we have included in the program for design, ·1· ·the room content list, the lease design narrative, ·2· ·actually where you are spending quite a bit of
·3· ·time.· This compliments what you actually have in
·4· ·Sections 3 and Sections 5 of your L100.
·5· · · · Particularly to this project and we're very
·6· ·thankful for the medical center to have provided
·7· ·this to us their finish standards.· So we don't
·8· ·actually have to guess what finishes and what type
·9· ·of values we're going to have.· They give us a
10· ·guide so can use it as part of our design.· You
11· ·also have the room data matrix.· The VA CBOC
12· ·information Transport System Specs.
13· · · · You also have the OIT Data Center and you may
14· ·have seen this same package in other proposals too.
15· ·But it's actually particular to outpatient clinic.
16· · · · Facility -- the FSL II description.· The
17· ·Conception Plan and drawings actually.· And the
18· ·janitorial and site management services.
19· · · · We have the agency specific requirements and
20· ·this one particularly refers to the items that we
21· ·have discussed before.
22· · · · Program for Design is actually included.· And
23· ·this is the source document for the diagram that
24· ·you are about to see.· You have also the project
25· ·room content list.· Actually we have tailored it to
·1· ·this project and actually make sure that you pay
·2· ·attention to all the components that go into every
·3· ·room.
·4· · · · Leased Design Narrative actually is provided
·5· ·to you as well with all the different sections
·6· ·included.· The purpose of Appendix A.2, the leased
·7· ·design narrative is to consolidate the governing
·8· ·codes, standards, references, and guidelines in a
·9· ·document that provides performance-based standards
10· ·for a VA leased facility.
11· · · · The governing codes, standards and references
12· ·are based on the VA affiliated facility.
13· · · · The design of the VA leased clinic is based on
14· ·the prototype for standardized design and
15· ·construction of community based outpatient clinics, 16· ·which is described in Part 3 of planning and design
17· ·criteria.
18· · · · We also have, as we discussed before, the
19· ·finish standards for Bay Pines network and also the
20· ·finishes and fixtures standards included.
21· · · · You will have the room data matrix that's
22· ·included in your package to be taken into account
23· ·as well at the OIT specs that we actually provide.
24· ·You will have both.· They actually complement each
25· ·other.· You will have drawings as well as the
·1· ·description of the OIT requirements.
·2· · · · FSL Level II standard that's actually included
·3· ·should be part of your proposal as well.
·4· · · · The diagram Conceptual layout provided is
·5· ·actually a layout that provides you with proximity
·6· ·of the different services using a two-story set up
·7· ·for this size facility and actually you will see
·8· ·the different services on the first floor and
·9· ·second floor.
10· · · · Again, note actually that for particular
11· ·accurate count of rooms is referencing in the
12· ·program for design.· That note on the bottom left
13· ·corner.· Just make sure that if you have a question
14· ·as to how many of what always go back to PFD.
15· · · · There is a second floor as well actually that
16· ·you will have the PAC and mental health and other
17· ·services on the second floor.· Again, also on the
18· ·lower left-hand side making a reference to the
19· ·program for design.
20· · · · We also have included appendix janitorial and
21· ·site management services.· It's very detailed.
22· ·Please make sure you actually include that in your
23· ·description and how you are to achieve the
24· ·janitorial requirements for this new facility.
25· · · · For any questions please make sure that you
·1· ·send them to us and we will answer them expediently
·2· ·going on with the process.· Thank you.
·3· · · · MS. RESTREPRO:· And we will have some time at
·4· ·the end to ask questions.· I am just quickly going
·5· ·to go over some of the -- review some of the
·6· ·standard forms and clauses some of which have been
·7· ·updated.· I mean, they are self-explanatory in
·8· ·terms of the update.
·9· · · · We've already gone through the proposal
10· ·compliance matrix.· With the GSA Form 1364 one of
11· ·the items I've already mentioned was just making
12· ·sure it's consistent with the information that you
13· ·have in your Attachment 1 is consistent with what's
14· ·in your 1364.
15· · · · And there is information -- it doesn't show it
16· ·here, but you are to put, you know, in terms of
17· ·what the acreage is, what the land cost is, all of
18· ·this information gets submitted for scoring
19· ·purposes so that's important.· So make sure it's
20· ·completed.
21· · · · GSA Form 1217, you know, must ensure all
22· ·operational costs and any maintenance required for
23· ·the lease are included in your submissions.· Line
24· ·27 is an important line.· It's the total of the
25· ·operating costs.· And then lines 28 through 32 are
·1· ·costs -- annual costs of ownership.· So it is
·2· ·included in the shell rent those costs.
·3· · · · And it's been good.· I've been seeing this a
·4· ·lot.· It's what we asked you to do.· I am happy to
·5· ·see that.· In line 26 we do ask for the breakdown.
·6· ·So continue to provide the breakdown of line 26.
·7· ·Line 26 is more of other.· So we do want to
·8· ·understand of that other cost is if you do have a
·9· ·number in that line item.
10· · · · So contract requirements we've already
11· ·addressed this in terms of fire protection, life
12· ·safety, accessibility and sustainability standards.
13· ·Offered space must be zone for VA's intended use.
14· ·Letter from the authority having jurisdiction
15· ·substantiating compatible zoning is required.· If
16· ·it's not currently zoned, you do have -- it states
17· ·in the RLP what you need to do to provide to the
18· ·LCO saying how it's going to get zoned, and it will
19· ·be zoned by performance of construction.· So that's
20· ·important to include if it's not already zoned
21· ·which it's required to include.
22· · · · Codes in accordance with the LDN and local
23· ·codes.
24· · · · And the Davis Bacon wages.· With that we do go
25· ·out with initial RLP with the latest Davis Bacon
·1· ·Wages, but we are -- you know, you need to be
·2· ·looking on -- you can look it up on Sam.gov what's
·3· ·the latest one.· We will use the latest one.· So if
·4· ·you are in the competitive range and we send out a
·5· ·request for revised proposal, our expectation is
·6· ·that you are confirming that you are using the
·7· ·latest one as you are doing the pricing or putting
·8· ·your proposal together.
·9· · · · So just some parting notes.· To read all parts
10· ·of the RLP and respond accordingly.· So please
11· ·treat each one of them as an individual project.
12· ·It's important.· I know there is a lot of
13· ·similarities in the projects that are going out.
14· ·But they are very discrete or distinct details for
15· ·each project.
16· · · · Audit/ensure compliance with Section 3.02.
17· ·Fully complete and include offeror proposal
18· ·compliance matrix with the proposal.· As I
19· ·mentioned, when you are doing the page numbers if
20· ·you can put the actual pages numbers that's
21· ·helpful.
22· · · · Initial every page of the entire offer.· So
23· ·electronic signatures are acceptable.· When you are
24· ·resubmitting the document initial all of them.
25· · · · Again, I will emphasize ensure completeness
·1· ·and consistency throughout the proposal.· Ensure
·2· ·all forms have been completed in their entirety.
·3· ·And do not recycle from past proposals.
·4· · · · It's very little -- it's very easy to fix.
·5· ·So, again, I think it helps one's proposal be
·6· ·mindful of that.· And no one is immune to that. I
·7· ·mean, even when we are doing proposals I'm always
·8· ·weary of it and make sure.· But it does help, you
·9· ·know, overall proposal.
10· · · · Make certain all documents that require
11· ·signature has been signed by the authorized
12· ·signatory for the offering entity.
13· · · · You must be -- the offering entity must be
14· ·registered in Sam and must be registered under
15· ·531120.· Must be consistent with the operating
16· ·agreement.· Also to make sure you are submitting
17· ·Offering Entity Acknowledgment Form.· Even though
18· ·we -- SVDOSB we do use that form.
19· · · · Then as we mentioned 1364.
20· · · · A few things also just to reiterate Phase 1
21· ·ESA and Cultural Resource Study is required that
22· ·you submit that during initial offers.
23· · · · Submit your authority having jurisdiction
24· ·letter for life/safety services, utilities, and
25· ·zoning.
·1· · · · Structure and formatting follow the RLP.
·2· · · · Also too with the narrative's substantiations.
·3· ·So it is important that you provide adequate detail
·4· ·for RLP requirements.· Also to make sure that
·5· ·they're consistent with your drawings.· If you are
·6· ·saying something in your narrative that it is
·7· ·consistent with the drawing that you are providing.
·8· ·I know sometimes across proposals it does pertain
·9· ·to one but just make sure that the drawing matches
10· ·up, that it is consistent.
11· · · · Eliminate discrepancies.· So offering entity
12· ·consistency.· ABOA, rental square foot, parking, 13· ·the price/cost, forms.· Make sure it is all
14· ·consistent.
15· · · · The VA will not accept conditional offers.· No
16· ·contingencies nor changes to the RLP may be
17· ·submitted.
18· · · · We talked about evidence of ownership and site
19· ·control.
20· · · · The occupancy, the project management plan.
21· ·It's important that you have a comprehensive
22· ·solution to deliver and mitigate risks.· Providing
23· ·methodology and actual techniques.
24· · · · Financial resources.· You must submit the
25· ·required information.· And it is stated in there
·1· ·Section 4 as well of the RLP.
·2· · · · So right now are going to open up to the
·3· ·question and answer period.· As I mentioned if you
·4· ·could state your name and your firm that helps
·5· ·Laura.· We will get the information.
·6· · · · And then what we do ask you to submit it --
·7· ·submit it to myself by February 15th and then when
·8· ·you do submit it if you could submit it in this
·9· ·format that is always helpful.· In terms of
10· ·referencing the document and the section and the
11· ·question.· And we will work as a team to respond to
12· ·those questions.
13· · · · So with that I will open it up to questions.
14· · · · MR. BUMGARNER:· I guess -- Luke Bumgarner with
15· ·C2 Construction.· I have been working on a couple
16· ·of different RLPs lately and when I follow through, 17· ·you know, without a matrix typically will follow
18· ·the RLP how to offer Section 3.· So it's easy to
19· ·follow along with that.· When you add in a matrix
20· ·sometimes, though, Section 3, you are almost
21· ·jumping back and forth.· Does the VA prefer that we
22· ·follow the matrix and package that package product
23· ·together step by step how the matrix reads or maybe
24· ·follow how we typically done them with how to offer
25· ·and then like you said referencing page numbers?
·1· ·You know, so we could follow 303 price, you put
·2· ·that, that's technically volume one or volume two, ·3· ·I guess.· You could do that and then the put page
·4· ·number on the matrix or you can follow along with
·5· ·the matrix.· Does that make sense what I'm asking?
·6· · · · MS. RESTREPRO:· Somewhat.· I think what we are
·7· ·interested in today, we're not going to prescribe
·8· ·exactly how you should.· But it's the easy -- one, ·9· ·I think the most important is that you are
10· ·providing all the information that we've requested.
11· ·That's the basic, you know, make sure that all that
12· ·information gets in there.· That's number one.
13· · · · Number two in terms of construction we've seen
14· ·it different ways.· You know, with the bookmarks
15· ·those that are required.· So that's always very
16· ·helpful with the bookmarks.· We've seen it where
17· ·people do go with the proposal compliance matrix or
18· ·they might group it with evaluation factor.· And
19· ·just in general speaking, I mean, with that.· But
20· ·it's really up to you.· What you feel is the best
21· ·way to provide the information that we have
22· ·requested of you.· The most basic is that you do
23· ·provide, you know.
24· · · · MR. BUMGARNER:· Everything requested.
25· · · · MS. RESTREPRO:· So that's why I say Section
·1· ·1.06 is really important.· Section 3.06 RLP and
·2· ·then looking at Section 4 those evaluation factors.
·3· · · · MR. BUMGARNER:· Okay.
·4· · · · MS. RESTREPRO:· Because it helps us really get
·5· ·a great understanding of what you're offering and
·6· ·then being able to really evaluate it against the
·7· ·evaluation factors.
·8· · · · MR. BUMGARNER:· Okay.
·9· · · · MS. RESTREPRO:· That's what we're doing.
10· · · · MR. BUMGARNER:· Again, I just wanted to make
11· ·sure there was maybe a way you guys preferred.
12· ·We've done it different ways on RLPs in the past
13· ·and haven't really got much feedback one way or the
14· ·other.· So I thought I would take my chance to ask
15· ·it here.
16· · · · MS. RESTREPRO:· Right.· Okay.
17· · · · MR. BAERGA:· Jose Baerga with CFM.· There is
18· ·something to be said about proofing, please.
19· ·Actually we want to rate you superior.· But when we
20· ·talk about actually asking for 750 parking spaces
21· ·and the next paragraph you refer to 450 parking
22· ·spaces then it makes it very difficult for us to
23· ·actually give you that.· So please actually make
24· ·sure proofing, if you take anything the last path
25· ·is to make sure it reads accurately and it will
·1· ·help us tremendously as we try to evaluate all of
·2· ·the proposals.
·3· · · · MS. RESTREPRO:· Thanks, Jose.
·4· · · · Any other questions?· Other comments.· Zach.
·5· · · · MR. ROSE:· Zach, Cullinan Properties.· Just
·6· ·real quick question is I know you guys have an MRI
·7· ·in the concept plan and you reference it in LDN.
·8· ·The concept also shows a technology pad which in
·9· ·history serves as the mobile MRI.· Are you guys
10· ·anticipating a mobile MRI as well to in the
11· ·facility MRI?
12· · · · UNIDENTIFIED VOICE:· So the intent would be if
13· ·we needed to replace an MRI we would bring one in, 14· ·use the pad for that or there is also a CT we would
15· ·bring in a mobile CT.· Or we find that we got a lot
16· ·more demand for MRIs.· The one in-house is not
17· ·substantial enough we would bring in an additional
18· ·one and use that mobile technology pad for that.
19· · · · MR. ROSE:· Got it.· I just wanted to make
20· ·sure.
21· · · · MR. BAERGA:· Just as the template refers a
22· ·technology pad it may be for something else.· It
23· ·doesn't necessarily have to be for that particular
24· ·purpose.· Down the road we actually will be in this
25· ·facility for 20 years there may be other treatments
·1· ·that are required to bring a separate type of
·2· ·vehicle, there is a place for it.
·3· · · · MR. ROSE:· Got it.
·4· · · · MR. BAERGA:· So that's one of the reasons for
·5· ·it.
·6· · · · MR. ROSE:· I just wanted to confirm.· Thank
·7· ·you.
·8· · · · MS. RESTREPRO:· Any other questions or
·9· ·comments?· No.
10· · · · Any comments or comments from the VA?
11· · · · UNIDENTIFIED VOICE:· No, I don't have
12· ·anything.
13· · · · MR. WALKER:· No, I'd just like to thank --
14· ·Kent Walker, CFM, I'd just like to thank Jose and
15· ·Patty for putting this together.· The main thing I
16· ·would like to say to keep these proposal too just
17· ·answer what you they are asking, don't put a bunch
18· ·of fluff in there, because we see a lot with a
19· ·bunch of junk that has nothing to do with the
20· ·things itself.· Keep it simple, to the point.
21· ·Appreciate it.
22· · · · MS. RESTREPRO:· Thank you very much everyone.
23· ·We appreciate you coming out.· We look forward to
24· ·receiving your offers -- questions and offers.
25· · · · MR. BAERGA:· Thank you all.
·1· · · ·(Thereupon, at 10:47 a.m. the meeting was
·2· ·concluded.)
·3
·4
·5
·6
·7
·8
·9
·1· · · · · · · · · C E R T I F I C A T E
·2
·3· ·The State of Florida· · ·)
· · ·County of St. Johns· · · ) ·4
·5
· · · · · I, Laura Dwyer Pierle, Court Reporter, do ·6· ·hereby certify that I was authorized to and did
· · ·report the above meeting in stenotype; and that the ·7· ·foregoing pages numbered from 1 to 41, inclusive,
· · ·are a true and correct transcription of my stenotype ·8· ·notes taken during said meeting.
·9
· · · · · I further certify that I am not attorney or 10· ·counsel of any of the parties, nor am I a relative
· · ·or employee of any attorney or counsel of party 11· ·connected with the action, nor am I financially
· · ·interested in the action.
13· · · · The foregoing certification of this transcript
· · ·does not apply to any reproduction of the same by 14· ·any means unless under the direct control and/or
· · ·direction of the certifying reporter.
16· · · · IN WITNESS WHEREOF, I have hereunto set my hand
· · ·this 25th day of February, 2024.
· · · · · · · · · · · · · · · · ·Laura Dwyer Pierle, Notary 22· · · · · · · · · · · · · · · ·Public, in and for the State
· · · · · · · · · · · · · · · · ·of Florida at large.
23· · · · · · · · · · · · · · · ·My Commission Expires
· · · · · · · · · · · · · · · · ·10/26/24 24· · · · · · · · · · · · · · · ·My Commission #HH 053319
| Transcript |
| Caption |
| Page 2 |
| Page 3 |
| Page 4 |
| Page 5 |
| Page 6 |
| Page 7 |
| Page 8 |
| Page 9 |
| Page 10 |
| Page 11 |
| Page 12 |
| Page 13 |
| Page 14 |
| Page 15 |
| Page 16 |
| Page 17 |
| Page 18 |
| Page 19 |
| Page 20 |
| Page 21 |
| Page 22 |
| Page 23 |
| Page 24 |
| Page 25 |
| Page 26 |
| Page 27 |
| Page 28 |
| Page 29 |
| Page 30 |
| Page 31 |
| Page 32 |
| Page 33 |
| Page 34 |
| Page 35 |
| Page 36 |
| Page 37 |
| Page 38 |
| Page 39 |
| Page 40 |
| Page 41 |
| Page 42 |
| Word Index |
| Index: 1..already |
| 1 (7) |
| 1.06 (2) |
| 106 (2) |
| 10:47 (1) |
| 1217 (2) |
| 131,724 (1) |
| 1364 (7) |
| 15 (1) |
| 15-year (1) |
| 15.101 (1) |
| 15th (3) |
| 180 (1) |