This document contains clarifications to an amendment for a solicitation seeking comprehensive construction management services. The Department of Veterans Affairs Office of Construction and Facilities Management will award an indefinite delivery indefinite quantity contract with a one year base period and four one year option periods for construction management tasks orders to be issued nationwide. This requirement is set aside for 100% Service-Disabled Veteran-Owned Small Businesses. The solicitation involves responses to questions on personnel qualifications, past performance submissions, pricing worksheets, and project experience requirements. Clarification is provided on licensure needs, relevant experience evaluations, and proposal assembly instructions.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C10F19R0065 0002 CM Sev.pdf | ||
| 36C10F19R0065 0001-Amendment.pdf | ||
| Attachment C - Pricing Worksheet (Spreadsheet) 6012020.xls | XLS spreadsheet | |
| 36C10F19R0065 Solicitation CMServsIDIQ.docx | DOCX document | |
| ATTACHMENT A PROFESSIONAL DISCIPLINES-Qualifications Capabilities-.pdf | ||
| ATTACHMENT B Past Perfermance Questionnair-.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 4
0003 08-14-2020
None
003C4
Department of Veterans Affairs Office of Construction and Facilities Management (003C4C) 425 I Street NW Washington DC 20001
101F
Department of Veterans Affairs Office of Construction and Facilities Management 425 I Street NW Washington DC 20001
To all Offerors/Bidders
36C10F19R0065
07-09-2020
X
31 August 2020 2:00 PM EST
Purpose: Revised date for receipt of offers from 8/25/2020 to 8/31/2020 2:00 PM EST.
Clarifications of Government's response(s) to RFI's. in Amendment 0002.
Incorporate changes as outlined on Continuation Pages.
Clarifications of Request for information Questions and VA Responses
34. Question: The distinguishing difference between the Senior and Staff Architect is that the Senior Architect be a licensed profession, but both only require a minimum of 6 years' experience. Request that VA consider removing the minimum requirement for a license and instead state it as a preference and increase the Senior Architect's minimum experience to 10 years. Maintaining this requirement would result in many current incumbent staff not meeting this requirement and being ineligible for consideration.
Response: The Licensure for the Senior Architect/Engineer remains a requirement. The licensure for staff architects/engineers will be considered preferable, but not required.
52. Question: Will award of this IDIQ preclude the contractor from bidding or conducting work under other AE, Due Diligence, and/or Broker contracts, if the contractor is not conducting VA CMS services and non-CMS services at the same location?
Response: No.
41. Question: Requirement states that CM-SCH shall possess a current professional credentialing; however, VA does not define which credentialing meets this requirement.
As this requirement may be overly restrictive in some geographic areas, request that VA consider an additional experience substitution for the professional credentialing as this is not as common within the scheduling discipline.
Response: This has been considered and determined to be a needed requirement for this selection/evaluation process.
87. Question: In the solicitation para 4.3.2, it states that "The Non- Architectural/Engineering Positions including the Construction Administrators, Estimators, Schedulers and Safety/Environmental professionals may substitute extensive construction experience and other credentials for consideration. Expertise in the requested discipline must be evidenced by extensive experience and qualifications."
However, in Appendix A Para 8 & 11, it states that the Estimator and Scheduler must hold respective professional credentialing. Is this to be understood that significant experience can be used in place of the professional credentialing for the Estimator and Scheduler?
Response: Experience may substitute extensive construction experience and other credentials for consideration.
106. Question: Given this is an ID/IQ contract and there may be multiple tasks orders at one time, would you like us to submit multiple resumes for each Key Personnel?
Response: Yes, provided page limitations are not exceeded.
124. Question: Past Performance, a. Submission Requirements. Can a PPQ from a prior proposal outreach be utilized?
Response: Yes.
144. Question: Attachment A, Professional Qualifications. All the engineering positions require professional licensing. If a group of FTEs’ are needed for an on-site project effort, will a single licensed professional suffice?
Response: The Licensure for the Senior Architect/Engineer remains a requirement. The licensure for staff architects/engineers will be considered preferable, but not required.
145. Question: Attachment B, Past Performance Questionnaire. The provided PPQ is a standard form used in many solicitations. Rather than continually requesting the completion of this same form by our clients, may we submit a previous PPQ completed by our client for a different solicitation?
Response: No. The owner’s representative most knowledgeable of the project completed shall submit the Past Performance Questionnaires directly to the POC identified on the form no later than the proposal due date.
157. Question: Typically, a CM firm does not have licensed Architects and Engineers in house. Is the expectation that the CM firm team with A/E firms for licensed design professionals?
Response: The Licensure for the Senior Architect/Engineer remains a requirement. The licensure for staff architects/engineers will be considered preferable, but not required.
163. Question: Section 4.3.1 states each Architectural or Engineering professional shall hold a four (4) year Bachelor of Science Degree and a minimum of six (6) years’ experience practicing as an Architect, Engineer, or Construction Manager. Does this meet the minimum requirements or do these individuals need to be licensed?
Response: The Licensure for the Senior Architect/Engineer remains a requirement. The licensure for staff architects/engineers will be considered preferable, but not required.
170. Question: Can this requirement be changed to "The CM-MP shall be a licensed professional with a degree in Mechanical Engineering from an accredited institution of higher learning and 5 years of experience and/or specialization in plumbing."
Response: The Licensure for the Senior Architect/Engineer remains a requirement.
The licensure for staff architects/engineers will be considered preferable, but not required.
179. Question: With the page restrictions, can you please clarify who is considered Key Personnel for the resumes? Are these the people who will manage the contract, or do you want to see personnel from the 14 positions listed?
Response: Those listed in Appendix A.
180. Question: What is expected for the letter of commitment for the Key Personnel? Will one letter of commitment signed by all Key Personnel be acceptable?
Response: No, Letters of Commitment are no longer required.
181. Question: Based on our experience in providing in providing program management to the VA on an IDIQ, will the VA consider adding a rate for a contract liaison position or task order manager to seamlessly manage task orders in multiple locations through a single point of contact for this contract.
Response: This has been considered and determined not to be a needed requirement for this selection/evaluation process.
182. Question: Does the VA require that relevant projects presented are from the Prime Contractor?
Response: Project Prime Contractor and Subcontractors as stated in the solicitation.
183. Question: VA consider overall Construction IDIQ contracts with projects completed in the project value range of this solicitation for relevant experience?
Response: Projects do not have to be immediately within this IDIQ-level range, but should be of similar magnitude.
184. Question: The project value range listed in the RFP for relevant projects is “$4-15M” for the projects. Our understanding is that CFM executes projects with total project budgets of greater than $20M. Can you confirm the term project value means the fee or contract value range is between $4-15M?
Response: Values are for Construction Management contracts.
185. Question: If the responder is a Joint Venture, does the JV need to be CVE verif ied as an SDVOSB before submission?
Response: Yes, certified SDVOSB.
186. Question: Are the title page, cover letter, and table of contents excluded from the page count?
Response: Please see the response to question # 19.
187. Question: The title of Volume III is Factor 3 Price Proposal and Offeror’s Certificate of Corporate Authority, Amendments, and Certification & Representations. On page 28/29, the required items indicate an intro page, Tab 1 requirements identified in: FAR 52.215-1, Instruction to Offerors-Competitive Acquisition, and Tab 2 Printed copy of “Representations and Certif ications.” Page 23, section3.4 indicates; The offeror shall complete the Pricing Worksheet (Attachment C). the information form the Pricing Working shall be incorporated into the labor rate pricing schedule in Section B.2 as well as one data file shall be submitted as an .XLS format as well as PDF files.
Response: Confirmed.
188. Question: Where should the labor pricing schedule in Section B.2 be submitted? As Tab 3, as a separate file or another option?
Response: Along with Attachment C and supporting rationale.
189. Question: Where should the PDF of Attachment C be submitted? As Tab 3, as a separate file or another option?
Response: Submit with pricing proposal.
190. Question: In Attachment C Pricing Worksheet – the pre-entered formulas in Column F “Fully Burdened Hourly Rate” seems to indicate that the proper entry in Colum E “Overhead” is a multiple instead of a dollar value of Overhead Costs. Please clarify which is the expected in Column E, Overhead Cost or a Multiple?
Response: Overhead cost.
191. Question: Since the PPQ’s should be sent directly to the COR, can you please let us know if anything else is expected for Volume II?
Response: No other information is expected.
192. Question: With reference to Attachment A, Item #12 – Independent Environmental Monitor
– The Regulatory experience required is quite extensive and varied for a CM-IEH with a minimum experience level of 3 years of environmental compliance/protection experience/education. Typically, environmental professionals specialize in one area of expertise like Waterway and Wetland Regulations for example. In order to satisfy the requirements listed, would you consider multiple resumes to environmental professionals to meet all the Regulatory requirements listed?
Response: This has been considered and determined to be a needed requirement for this selection/evaluation process.