About this file

This project schedule outlines the construction activities for a new VA outpatient clinic in New Port Richey, Florida from March 2020 through August 2021. Work begins with site preparation and installation of foundations, followed by erection of tilt wall panels and structural steel for the building shell. Interior buildout then commences with installation of interior walls and ceilings, mechanical, electrical and plumbing rough-ins, application of finishes including flooring, casework and medical equipment installation through early 2021. Specialized construction of radiology areas including MRI and CT suites is scheduled from late March through early June 2021. Project closeout activities including commissioning, inspections, contractor punchlist work and acceptance by the VA are scheduled to conclude by August 9, 2021. The critical path shows an overall planned duration of approximately 17 months for the project.

The related federal contract opportunity is a solicitation by the VA for information technology and architectural services for the New Port Richey CBOC project. The solicitation number is 36A77620Q0143 with a response due date that has been extended. The description indicates this is a placeholder with no existing modification to the pre-solicitation notice. Offerors are advised to check for any amendments containing questions and answers related to the solicitation.

36A77620Q0143 0002 NPR - Construction Schedule.pdf

View the file

Other files

File Type Posted
36A77620Q0143-0003000.docx DOCX document
36A77620Q0143-0002009.docx DOCX document
36A77620Q0143-0002008.docx DOCX document
36A77620Q0143-0001011.docx DOCX document
36A77620Q0143-0001009.docx DOCX document
36A77620Q0143-0001010.docx DOCX document
36A77620Q0143-214.pdf PDF
36A77620Q0143-208.pdf PDF
36A77620Q0143-210.pdf PDF
36A77620Q0143-218.pdf PDF
36A77620Q0143-216.xlsx XLSX spreadsheet
36A77620Q0143-212.pdf PDF
36A77620Q0143-206.pdf PDF
36A77620Q0143-217.pdf PDF
36A77620Q0143-207.pdf PDF
36A77620Q0143-204.pdf PDF
36A77620Q0143-219.pdf PDF
36A77620Q0143-203.docx DOCX document
36A77620Q0143-213.pdf PDF
36A77620Q0143-215.pdf PDF
36A77620Q0143-209.pdf PDF
36A77620Q0143-220.xlsx XLSX spreadsheet
36A77620Q0143-211.pdf PDF
36A77620Q0143-205.pdf PDF
36A77620Q0143-004.docx DOCX document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Activity ID Activity Name Original Duration

Remaining Duration

Duration % Complete

Start Finish Total Float

BL01-17 NewBL01-17 New Port Richey VA_Feb UpdateBL01-17 New Port Richey VA_Feb UpdateBL01-17 New Port Richey VA_Feb UpdateBL01-17 New Port Richey VA_Feb UpdateBL01-17 New Port Richey VA_Feb UpdateBL01-17 New Port Richey VA_Feb UpdateBL01-17 New Port Richey VA_Feb Update CONSTRUCCONSTRUCTIONCONSTRUCTIONCONSTRUCTIONCONSTRUCTIONCONSTRUCTIONCONSTRUCTIONCONSTRUCTION

Exterior EncExterior EnclosureExterior EnclosureExterior EnclosureExterior EnclosureExterior EnclosureExterior EnclosureExterior Enclosure Building ShBuilding Shell ConstructionBuilding Shell ConstructionBuilding Shell ConstructionBuilding Shell ConstructionBuilding Shell ConstructionBuilding Shell ConstructionBuilding Shell Construction

B3360 Install Floor Boxes @ Area 1 3 3 0% 02-Mar-20 04-Mar-20 -32 B3370 Fine Grade/Remove Spoils @ Area 1 2 2 0% 05-Mar-20 06-Mar-20 -32 B3380 Spray Pre-treat @ Area 1 1 1 0% 09-Mar-20 09-Mar-20 -32 B3390 Install Stego Wrap @ Area 1 3 3 0% 10-Mar-20 12-Mar-20 -32 B3400 Seal Stego Wrap @ Area 1 2 2 0% 13-Mar-20 16-Mar-20 -32 B3410 Install Slab Reinforcing @ Area 1 5 5 0% 17-Mar-20 23-Mar-20 -32 B3430 Cut Conduits & Boxes to FF @ Area 1 1 1 0% 24-Mar-20 24-Mar-20 -32 B3440 Adjust Floor Drains/Sinks to FF @ Area 1 1 1 0% 24-Mar-20 24-Mar-20 -32 B3450 Place Slab on Grade @ Area 1 2 2 0% 25-Mar-20 26-Mar-20 -32 B3470 Cure SOG @ Area 1 5 5 0% 27-Mar-20 02-Apr-20 -32 B3480 Layout Tilt Panels @ Area 1 3 3 0% 27-Mar-20 31-Mar-20 -32 B3490 Layout Tilt Panel Embeds/Pick Points @ Area 1 2 2 0% 27-Mar-20 30-Mar-20 -32 B3500 Form Tilt Panels @ Area 1 5 5 0% 31-Mar-20 06-Apr-20 -32 B3520 Install Reveals @ Area 1 3 3 0% 07-Apr-20 09-Apr-20 -32 B3540 Apply Bond Breaker @ Area 1 2 2 0% 10-Apr-20 13-Apr-20 -32 B3550 Install Tilt Rebar @ Area 1 5 5 0% 14-Apr-20 20-Apr-20 -32 B3570 Tilt Panel Inspections @ Area 1 1 1 0% 21-Apr-20 21-Apr-20 -32 B3580 Place Tilt Concrete @ Area 1 3 3 0% 22-Apr-20 24-Apr-20 -32 B3590 Cure Tilt Concrete @ Area 1 5 5 0% 27-Apr-20 01-May-20 -32 B3600 Strip Tilt Forms @ Area 1 2 2 0% 04-May-20 05-May-20 -32 B3620 Prepare Tilt Bracing @ Area 1 2 2 0% 06-May-20 07-May-20 -32 B3630 Prepare Tilt Footing (clean debris, etc.) @ Area 1 2 2 0% 06-May-20 07-May-20 -32 B3640 Erect Tilt Panels @ Area 1 5 5 0% 08-May-20 14-May-20 -32 B3650 P&L Tilt Panels @ Area 1 3 3 0% 15-May-20 19-May-20 -32 B3660 Weld Tilt Connections @ Area 1 5 5 0% 15-May-20 21-May-20 -32 B3670 Grout Tilt Panels @ Area 1 5 5 0% 15-May-20 21-May-20 -32 B3810 Install Columns @ Area 1 3 3 0% 22-May-20 27-May-20 -32 B3820 Install Beams @ Area 1 3 3 0% 28-May-20 01-Jun-20 -32 B3830 Bolt up Moment Frames @ Area 1 2 2 0% 02-Jun-20 03-Jun-20 -32 B3840 Weld Moment Frames Full Pen @ Area 1 5 5 0% 04-Jun-20 10-Jun-20 -32 B3850 Inspect Full Pen (interim inspection) @ Area 1 5 5 0% 04-Jun-20 10-Jun-20 -32 B3860 Install Ledgers & Bent Plate @ Area 1 5 5 0% 04-Jun-20 10-Jun-20 -32 B3870 Plumb & Line @ Area 1 3 3 0% 11-Jun-20 15-Jun-20 -32 B3880 Final Bolt Up @ Area 1 3 3 0% 11-Jun-20 15-Jun-20 -32 B3890 Install Girder Bar Joists @ Area 1 2 2 0% 16-Jun-20 17-Jun-20 -32 B3900 Install Bar Joist @ Area 1 3 3 0% 16-Jun-20 18-Jun-20 -32 B3910 Install Bridging @ Area 1 3 3 0% 19-Jun-20 23-Jun-20 -32 B3920 Load Decking @ Area 1 1 1 0% 24-Jun-20 24-Jun-20 -32 B3930 Spread Decking @ Area 1 1 1 0% 25-Jun-20 25-Jun-20 -32 B3940 Weld Decking @ Area 1 3 3 0% 26-Jun-20 30-Jun-20 -32 B3950 Install Neilson Studs @ Area 1 3 3 0% 01-Jul-20 06-Jul-20 -32 B3960 Deck Forms and Edging @ Area 1 3 3 0% 07-Jul-20 09-Jul-20 -32

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep ct 2020 2021

09-Aug-21, BL

18-Jun-21, CONSTRUCTIO

24-Jul-20, Exterior Enclosure 24-Jul-20, Building Shell Construction

Install Floor Boxes @ Area 1 Fine Grade/Remove Spoils @ Area 1 Spray Pre-treat @ Area 1 Install Stego Wrap @ Area 1 Seal Stego Wrap @ Area 1

Install Slab Reinforcing @ Area 1 Cut Conduits & Boxes to FF @ Area 1 Adjust Floor Drains/Sinks to FF @ Area 1 Place Slab on Grade @ Area 1

Cure SOG @ Area 1 Layout Tilt Panels @ Area 1 Layout Tilt Panel Embeds/Pick Points @ Area 1

Form Tilt Panels @ Area 1 Install Reveals @ Area 1 Apply Bond Breaker @ Area 1

Install Tilt Rebar @ Area 1 Tilt Panel Inspections @ Area 1 Place Tilt Concrete @ Area 1

Cure Tilt Concrete @ Area 1 Strip Tilt Forms @ Area 1 Prepare Tilt Bracing @ Area 1 Prepare Tilt Footing (clean debris, etc.) @ Area 1

Erect Tilt Panels @ Area 1 P&L Tilt Panels @ Area 1 Weld Tilt Connections @ Area 1 Grout Tilt Panels @ Area 1

Install Columns @ Area 1 Install Beams @ Area 1 Bolt up Moment Frames @ Area 1

Weld Moment Frames Full Pen @ Area 1 Inspect Full Pen (interim inspection) @ Area 1 Install Ledgers & Bent Plate @ Area 1 Plumb & Line @ Area 1 Final Bolt Up @ Area 1 Install Girder Bar Joists @ Area 1 Install Bar Joist @ Area 1

Install Bridging @ Area 1 Load Decking @ Area 1 Spread Decking @ Area 1 Weld Decking @ Area 1

Install Neilson Studs @ Area 1 Deck Forms and Edging @ Area 1

BL01-17 New Port Richey VA_Feb Update NPR Critical Path 03-Mar-20 14:17

Actual Work Remaining Work

Critical Remaining Work Milestone

Summary Page 1 of 3 TASK filter: Longest Path.

© Oracle Corporation

Remaining Duration

Duration % Complete

Start Finish Total Float

B3970 Form Special Block Outs @ Area 1 3 3 0% 07-Jul-20 09-Jul-20 -32 B3980 Slab on Deck Preparation @ Area 1 2 2 0% 10-Jul-20 13-Jul-20 -32 B3990 Reinforcing Slab on Deck @ Area 1 3 3 0% 14-Jul-20 16-Jul-20 -32 B4000 Misc Forms Slab on Deck @ Area 1 3 3 0% 14-Jul-20 16-Jul-20 -32 B4010 Place Slab on Deck @ Area 1 3 3 0% 17-Jul-20 21-Jul-20 -32 B4020 Strip forms Slab on Deck @ Area 1 3 3 0% 22-Jul-20 24-Jul-20 -32

Building InterBuilding InteriorBuilding InteriorBuilding InteriorBuilding InteriorBuilding InteriorBuilding InteriorBuilding Interior Level 1Level 1Level 1Level 1Level 1Level 1Level 1Level 1

1F1000 Layout Interior Walls @ Lvl 1/Area 1 2 2 0% 22-Jul-20 23-Jul-20 -32 1F1005 Layout Duct / Dampers @ Lvl 1/Area 1 2 2 0% 22-Jul-20 23-Jul-20 -32 1F1010 Heavy Misc Steel Ceiling Support Frames @ Lvl 5 5 0% 24-Jul-20 30-Jul-20 -32 1F1015 1 Hour Wall Framing @ Lvl 1/Area 1 5 5 0% 31-Jul-20 06-Aug-20 -32 1F1020 Full Height Sound Wall Framing @ Lvl 1/Area 1 5 5 0% 07-Aug-20 13-Aug-20 -32 1F1025 Acoustical Insulation at Upper Full Height Walls @ 3 3 0% 11-Aug-20 13-Aug-20 -32 1F1030 1 Hour Gyp & Fire Tape Above Ceiling @ Lvl 1/A 5 5 0% 14-Aug-20 20-Aug-20 -32 1F1035 Full Height Sound Walls Gyp & Fire Tape Above C 3 3 0% 21-Aug-20 25-Aug-20 -32 1F1040 Mechanical Overhead & Chases @ Lvl 1/Area 1 12 12 0% 26-Aug-20 11-Sep-20 -32 1F1045 Electrical Overhead @ Lvl 1/Area 1 12 12 0% 26-Aug-20 11-Sep-20 -32 1F1065 Re-Snap Out Walls @ Lvl 1/Area 1 1 1 0% 14-Sep-20 14-Sep-20 -32 1F1070 Set HM Frames @ Lvl 1/Area 1 2 2 0% 15-Sep-20 16-Sep-20 -32 1F1075 Interior Full Height Framing @ Lvl 1/Area 1 3 3 0% 17-Sep-20 21-Sep-20 -32 1F1080 Interior Remaining Framing @ Lvl 1/Area 1 5 5 0% 22-Sep-20 28-Sep-20 -32 1F1085 Soffit Framing @ Lvl 1/Area 1 3 3 0% 29-Sep-20 01-Oct-20 -32 1F1090 Plumbing Wall Rough In @ Lvl 1/Area 1 10 10 0% 02-Oct-20 16-Oct-20 -32 1F1095 Electrical Wall Rough In @ Lvl 1/Area 1 10 10 0% 02-Oct-20 16-Oct-20 -32 1F1100 Low Voltage Wall Rough-in @ Lvl 1/Area 1 10 10 0% 02-Oct-20 16-Oct-20 -32 1F1120 Thermal Insulation Walls @ Lvl 1/Area 1 5 5 0% 19-Oct-20 23-Oct-20 -32 1F1140 Drywall - Top Out @ Lvl 1/Area 1 5 5 0% 20-Oct-20 26-Oct-20 -32 1F1145 Fire Tape Above Hard Ceilings @ Lvl 1/Area 1 3 3 0% 27-Oct-20 29-Oct-20 -32 1F1165 Hard Ceiling Drywall H/T/F @ Lvl 1/Area 1 8 8 0% 04-Nov-20 16-Nov-20 -32 1F1170 Drywall Spray Texture @ Lvl 1/Area 1 3 3 0% 17-Nov-20 19-Nov-20 -32 1F1175 Swing HM Doors for Paint @ Lvl 1/Area 1 2 2 0% 20-Nov-20 23-Nov-20 -32 1F1185 Fire Stop Above Ceilings @ Lvl 1/Area 1 3 3 0% 30-Oct-20 03-Nov-20 -32 1F1190 Drywall - H/T/F @ Lvl 1/Area 1 5 5 0% 17-Nov-20 23-Nov-20 -32 1F1200 Interior Paint - Primer-1st Coat @ Lvl 1/Area 1 5 5 0% 24-Nov-20 01-Dec-20 -32 1F1240 Ceiling Grid @ Lvl 1/Area 1 8 8 0% 24-Nov-20 04-Dec-20 -32 1F1255 Electrical Ceiling Boxes @ Lvl 1/Area 1 3 3 0% 07-Dec-20 09-Dec-20 -32 1F1260 Low Voltage Ceiling Boxes @ Lvl 1/Area 1 3 3 0% 07-Dec-20 09-Dec-20 -32 1F1265 Fine Tune Ceiling Backing/boxes @ Lvl 1/Area 1 3 3 0% 07-Dec-20 09-Dec-20 -32 1F1290 Lighting Fixtures @ Lvl 1/Area 1 3 3 0% 10-Dec-20 14-Dec-20 -32 1F1295 Special Cuts and Perimeter Ceiling Tile @ Lvl 1/A 5 5 0% 15-Dec-20 21-Dec-20 -32 1F1305 Ceiling Field Tile @ Lvl 1/Area 1 5 5 0% 22-Dec-20 29-Dec-20 -32 1F1335 Ceiling Mounted Med Equipment @ Lvl 1/Area 1 8 8 0% 30-Dec-20 11-Jan-21 -32 1F1340 Wall Mounted Med Equipment @ Lvl 1/Area 1 8 8 0% 30-Dec-20 11-Jan-21 -32 1F1350 Moisture Test Floors @ Lvl 1/Area 1 5 5 0% 12-Jan-21 19-Jan-21 -32 1F1355 Prep Slab for Flooring @ Lvl 1/Area 1 3 3 0% 20-Jan-21 22-Jan-21 -32 1F1360 Terrazzo / Ceramic Tile Flooring & Base @ Lvl 1/ 5 5 0% 25-Jan-21 29-Jan-21 -32

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep ct 2020 2021

Form Special Block Outs @ Area 1 Slab on Deck Preparation @ Area 1 Reinforcing Slab on Deck @ Area 1 Misc Forms Slab on Deck @ Area 1

Place Slab on Deck @ Area 1 Strip forms Slab on Deck @ Area 1

18-Jun-21, Building Interior 25-Mar-21, Level 1

Layout Interior Walls @ Lvl 1/Area 1 Layout Duct / Dampers @ Lvl 1/Area 1

Heavy Misc Steel Ceiling Support Frames @ Lvl 1/Area 1 1 Hour Wall Framing @ Lvl 1/Area 1

Full Height Sound Wall Framing @ Lvl 1/Area 1 Acoustical Insulation at Upper Full Height Walls @ Lvl 1/Area 1

1 Hour Gyp & Fire Tape Above Ceiling @ Lvl 1/Area 1 Full Height Sound Walls Gyp & Fire Tape Above Ceiling @ Lvl 1/Area 1

Mechanical Overhead & Chases @ Lvl 1/Area 1 Electrical Overhead @ Lvl 1/Area 1 Re-Snap Out Walls @ Lvl 1/Area 1 Set HM Frames @ Lvl 1/Area 1 Interior Full Height Framing @ Lvl 1/Area 1

Interior Remaining Framing @ Lvl 1/Area 1 Soffit Framing @ Lvl 1/Area 1

Plumbing Wall Rough In @ Lvl 1/Area 1 Electrical Wall Rough In @ Lvl 1/Area 1 Low Voltage Wall Rough-in @ Lvl 1/Area 1

Thermal Insulation Walls @ Lvl 1/Area 1 Drywall - Top Out @ Lvl 1/Area 1 Fire Tape Above Hard Ceilings @ Lvl 1/Area 1

Hard Ceiling Drywall H/T/F @ Lvl 1/Area 1 Drywall Spray Texture @ Lvl 1/Area 1 Swing HM Doors for Paint @ Lvl 1/Area 1

Fire Stop Above Ceilings @ Lvl 1/Area 1 Drywall - H/T/F @ Lvl 1/Area 1

Interior Paint - Primer-1st Coat @ Lvl 1/Area 1 Ceiling Grid @ Lvl 1/Area 1

Electrical Ceiling Boxes @ Lvl 1/Area 1 Low Voltage Ceiling Boxes @ Lvl 1/Area 1 Fine Tune Ceiling Backing/boxes @ Lvl 1/Area 1 Lighting Fixtures @ Lvl 1/Area 1

Special Cuts and Perimeter Ceiling Tile @ Lvl 1/Area 1 Ceiling Field Tile @ Lvl 1/Area 1

Ceiling Mounted Med Equipment @ Lvl 1/Area 1 Wall Mounted Med Equipment @ Lvl 1/Area 1

Moisture Test Floors @ Lvl 1/Area 1 Prep Slab for Flooring @ Lvl 1/Area 1

Terrazzo / Ceramic Tile Flooring & Base @ Lvl 1/Area 1

BL01-17 New Port Richey VA_Feb Update NPR Critical Path 03-Mar-20 14:17

Actual Work Remaining Work

Critical Remaining Work Milestone

Summary Page 2 of 3 TASK filter: Longest Path.

Remaining Duration

Duration % Complete

Start Finish Total Float

1F1405 Plumbing Fixture @ Lvl 1/Area 1 10 10 0% 01-Feb-21 12-Feb-21 -32 1F1425 Toilet Partitions & Accessories @ Lvl 1/Area 1 5 5 0% 16-Feb-21 22-Feb-21 -32 1F1430 Install Specialties Lvl @ Lvl 1/Area 1 10 10 0% 16-Feb-21 01-Mar-21 -32 1F1435 Specialty Ceiling Finish Touch Up @ Lvl 1/Area 1 5 5 0% 02-Mar-21 08-Mar-21 -32 1F1440 Medical & Laboratory Equipment @ Lvl 1/Area 1( 10 10 0% 09-Mar-21 22-Mar-21 -32 1F1445 Medical & Laboratory Equipment @ Lvl 1/Area 1 10 10 0% 09-Mar-21 22-Mar-21 -32 1F1450 Rough Clean @ Lvl 1/Area 1 3 3 0% 23-Mar-21 25-Mar-21 -32

RadiologyRadiologyRadiologyRadiologyRadiologyRadiologyRadiologyRadiology A9410 VA Site Specific MRI-CT-Xray Shop Drawings 5 5 0% 26-Mar-21 01-Apr-21 -32 A9420 MRI-CT-Xray Detailed Layout 10 10 0% 02-Apr-21 15-Apr-21 -32 A9430 VA Vendor Site Review-Confirmation 10 10 0% 16-Apr-21 29-Apr-21 -32 A9440 RF Shielding Install 5 5 0% 30-Apr-21 06-May-21 -32 A9450 Overhead Structural Alignment 5 5 0% 07-May-21 13-May-21 -32 A9460 Mechanical Rough 5 5 0% 14-May-21 20-May-21 -32 A9470 Electrical Rough 3 3 0% 14-May-21 18-May-21 -32 A9480 Low Voltage Rough 5 5 0% 14-May-21 20-May-21 -32 A9490 Pour backs 5 5 0% 21-May-21 27-May-21 -32 A9500 RF Shielding/Testing 5 5 0% 28-May-21 04-Jun-21 -32 A9630 Testing 5 5 0% 28-May-21 04-Jun-21 -32 A9640 Commissioning 10 10 0% 07-Jun-21 18-Jun-21 -32

PROJECT CPROJECT CLOSEOUTPROJECT CLOSEOUTPROJECT CLOSEOUTPROJECT CLOSEOUTPROJECT CLOSEOUTPROJECT CLOSEOUTPROJECT CLOSEOUT A15006 Commissioning 20 20 0% 07-Jun-21 02-Jul-21 -32 A15030 Owner Punchlist Review/Issuance 10 10 0% 21-Jun-21 02-Jul-21 -32 A15040 Contractor Final Punchlist Completion 15 15 0% 06-Jul-21 26-Jul-21 -32 A15050 Final Cleaning 5 5 0% 27-Jul-21 02-Aug-21 -32 A15060 Punchlist Review with Government 5 5 0% 03-Aug-21 09-Aug-21 -32 A15080 Government Inspections - Final Acceptance 5 5 0% 03-Aug-21 09-Aug-21 -32 A15090 GOVERNMENT ACCEPTANCE - 23Jun21 0 0 0% 09-Aug-21* -32

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep ct 2020 2021

Plumbing Fixture @ Lvl 1/Area 1 Toilet Partitions & Accessories @ Lvl 1/Area 1

Install Specialties Lvl @ Lvl 1/Area 1 Specialty Ceiling Finish Touch Up @ Lvl 1/Area 1

Medical & Laboratory Equipment @ Lvl 1/Area 1(Con Medical & Laboratory Equipment @ Lvl 1/Area 1 (Ow Rough Clean @ Lvl 1/Area 1

18-Jun-21, Radiology VA Site Specific MRI-CT-Xray Shop Drawings

MRI-CT-Xray Detailed Layout VA Vendor Site Review-Confirmation

RF Shielding Install Overhead Structural Alignment

Mechanical Rough Electrical Rough Low Voltage Rough

Pour backs RF Shielding/Testing Testing

Commissioning 09-Aug-21, PR

Commissioning Owner Punchlist Review

Contractor Final P Final Cleaning

Punchlist Rev Government I

GOVERNMEN

BL01-17 New Port Richey VA_Feb Update NPR Critical Path 03-Mar-20 14:17

Actual Work Remaining Work

Critical Remaining Work Milestone

Summary Page 3 of 3 TASK filter: Longest Path.