SOW Flooring 4 Units Sturgeon Bay FYCOM 2025.docx
DOCX document 797 KB Posted
- Attached to
- 31050PR250000138 Carpet Replacement Sturgeon Bay
- Solicitation number
- 31050PR250000138
About this file
This is a Statement of Work (SOW) for carpet and flooring replacement at four United States Coast Guard housing units in Sturgeon Bay, Wisconsin. The project involves removing existing carpets and flooring, preparing subfloors, and installing new Dreamweaver broadloom carpet on second floors and stairs, and MSI click luxury vinyl plank flooring on ground floors across four residential addresses. The solicitation (31050PR250000138) is set aside for small businesses, with a firm fixed-price purchase order contract type, using NAICS code 314110 and a small business size standard of 500 employees. Contractors must provide a detailed quote on business letterhead including material estimates, labor costs, man-hours, and worker requirements. A mandatory site visit is scheduled for March 24th at 1000 Central time, and quotes should be emailed to SKC Jordan Drew. Contractors must be registered in the System for Award Management (SAM.gov) and will submit invoices through the Invoice Processing Platform (IPP).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Request for Information Q-A.pdf | ||
| SF 30 - AMENDMENT OF SOLICITATION.MODIFICATION OF CONTRACT 00001.pdf | ||
| Amendment 00001 Answers to RFI.docx | DOCX document | |
| WAGE DETERMINATION.pdf | ||
| RFQ for Services_Carpet Replacment Sturgeon Bay.docx | DOCX document | |
| FAR MATRIX SERVICE.pdf | ||
| SOW_CARPET.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of Homeland Security United States Coast Guard Base Cleveland Housing Division
Scope of Work (SOW) Housing Site Sturgeon Bay WI, 54235 For Carpet replacement
Point of Contact (POC) DC2 Michael Curtis (920)-510-3602 or DCC Carter
(216) 902-6290
Site Addresses
110 N 16th Drive Sturgeon Bay, WI 54235 231 N 16th Place Sturgeon Bay, WI, 54235 337 N 16th Place Sturgeon Bay, WI, 54235 323 N 16th Drive Sturgeon Bay, WI, 54235
Scope of Work
Carpet Area -
1.1 The contractor is to remove all carpet on stairs and on the second floor along with the padding to be replaced and dispose of all materials off the USCG property at the contractor expense to an approved disposal site.
1.2 The contractor will repair or replace any damaged or loose tack strips as needed; inspect and repair the subfloor for any loose staples, screws, nails, etc.; identify and report any water, pet staining or odors, or any other abnormal damages that may cause further damage or odors to the USCG POC before continuing work.
1.3 All flooring will need to be cleaned of all loose debris, swept and/or vacuumed, before installing any new materials.
1.4 Install any needed rubber shims to level the carpet with any other flooring in use and install transitions to areas connecting to different flooring materials.
1.5 Install stain resistant padding and carpet following the manufacturer’s recommendations.
1.6 Carpet installation on stairs is to be tucked.
1.7 Baseboards will be removed in a way so as not to cause damage baseboard or wall and will be reinstalled at the conclusion of work. If damage does occur, contractor will supply new baseboard that closely matches existing and install.
Laminate Flooring Install –
1.1 Contractor to remove all installed carpet and padding in the downstairs area of the home.
1.2 Contractor to remove all tack strips from old, removed carpet.
1.3 Contractor will remove all tile flooring to include any old flooring that previously was installed on top of, if applicable, (possibly two to three layers) in the dining area. Contractor to take all lower-level flooring down to subfloor level in areas to have laminate flooring installed.
1.4 Contractor will flush cut all flooring along back and side of kitchen floor cabinetry in dining room to remove any tile or flooring in dining room without disturbing the kitchen cabinetry, flooring in kitchen area will remain along transition of kitchen entry in a clean-cut manner with a transition strip to match flooring being installed.
1.5 Contractor is to fill any cracks found in subfloor work area and if necessary, level sub- floor in preparation of new laminate flooring installation.
1.6 Contractor will use an underlayment to the specifications listed below for an extra noise and moisture barrier between the subfloor and the laminate floor to be installed. This will be provided by the contractor.
1.7 The specific flooring to be installed is indicated below under materials, this will be provided by the contractor.
1.8 All transition strips required through the unit will be matched with the flooring installed. Minimal use of transitional strips is required per contract, if flooring can be floated through multiple rooms, then install will be completed in this manner.
1.9 Install area is to include all alcoves, closets and other flooring areas in accordance with the POC guidance upon contractor’s walkthrough for accurate worksite measurements.
1.10 This flooring will not be installed in any rooms where Toilet or Shower facilities are present. Flooring in such spaces is to be properly separated with a transition strip to match the installed floor coverings being placed by this contract.
1.11 Baseboards will be removed in a way so as not to cause damage to baseboard or wall and will be reinstalled at the conclusion of work. If damage does occur, contractor will supply new baseboard that closely matches existing and install.
\Material/ Part Information
2.1. All materials will be supplied by the contractor.
2.2. 3/8” Spill guard padding is to be used.
2.3. Dreamweaver broadloom carpet. (Color to be determined.)
2.4. All rubber shims used will be Johnsonite LS-40-E (D or E according to thickness required).
2.5. All transitions and other exposed materials planned for use will have to be approved by the POC listed for quality and color.
2.6. All hard flooring to be installed will be MSI click luxury vinyl plank, Style- Cyrus, Color- To be determined, Size- 7" x 48" with 5mm. Any deviation from this must meet the same specifications of the above flooring, especially for thickness, durability and function. All deviations outside the flooring listed above must be previously approved by the Coast Guard listed POC.
2.7: All materials will be color checked to verify close representation of previous materials installed in unit.
| Carpeted Estimate |
| Hard Floor Estimate |
| Rolled Vinyl |
110 N 16th Drive- Sturgeon Bay WI 54235
| 610 Sq. Yards |
| 0 Sq. Feet |
| 0 Sq. Yards |
231 N 16th Place- Sturgeon Bay WI 54235
570 Sq. Yards
| 0 Sq. Feet |
| 0 Sq. Yards |
337 N 16th place- Sturgeon Bay WI 54235
| 582 Sq Yards |
| 0Sq. Feet |
| 0 Sq. Yards |
| 323 N 16th Drive- Sturgeon Bay WI 54235 |
| 582 Sq. Yards |
| 0 Sq. Feet |
| 0 Sq. Yards |
References
3.1 All work is to be completed shall comply with Federal, State and Local Laws, Codes and Regulations.
Liabilities
4.1 The contractor will be financially responsible for any and all damages incurred while working on Government property.
Coordination
5.1 All communications will go through the POC listed. No work can be modified or changed without their permission.
5.2 A site visit is highly encouraged to provide valuable insight into homes. Allowing the assessment of needs and condition of each unit to ensure quality and precise work. To schedule a site visit prior to commencing work and to accurately quote work needed, please contact the POC listed.
| 5.3 | Work to be completed should have minimal impact on the unit’s operation. In the event any of the utilities need to be secured, these items should be well planned out. |
| 5.4 | Normal work hours for the unit are 8:00 AM to 4:00 PM, Monday-Friday, excluding all Federal Holidays. Any work outside these times needs to be worked out ahead of time. |
| 5.5 | All required License, Certificates, Accreditation Card, etc. will be submitted with the quote or bid. |
Project Completion
| 6.1 | All work completed is up to the POC’s approval. The site is to be at a minimum as clean of a condition it was found in. All trash, debris, materials removed, etc. should be properly disposed of by the contractor. There will be no on-site storage available for the duration of this project. |
| 6.2 | This contract will be awarded for multiple addresses, all with different start schedules; these will not run consecutively but as available units become vacant. The contractor will be given a one-week window to schedule and complete each job. The Coast Guard POC will attempt to provide a 30-day notice prior to the availability timeline as they can do so. |
133 N 16th drive carpet stairs
133 N 16th drive carpet
353 N 16th place carpet (example)
353 N 16th place carpet (example) image3.png image4.png image1.png image2.png