This is a Request for Proposals (RFP) issued by the Salt Lake City Department of Public Utilities (SLCDPU) for professional design and engineering services related to the Orange Street Sewer Trunkline Rehabilitation Phase IV project. SLCDPU seeks qualified firms to provide comprehensive engineering services including inspection and condition assessment, pre-design, permitting, design, bidding, construction administration, and public engagement for the rehabilitation of approximately 3,825 linear feet of the 42-inch diameter Orange Street Sewer Trunkline, constructed in 1963 and located between 1040 South and 1500 South in Salt Lake City, Utah. The project scope encompasses seven major tasks: updated CCTV inspection and condition assessment; pre-design services with preliminary cost estimates; comprehensive permitting for multiple local, state, and federal agencies including USACE, UDOT, and SLC entities; 60/90/100 percent design phases with specifications; bidding process support; construction-related services including submittal and RFI review; and public engagement planning and coordination. Technical proposals are due at 2:00 PM on Friday, May 29, 2026, through the Utah Public Procurement Place (U3P) website. Possible interviews are anticipated for the week of June 1, 2026, with contract award approval targeted for Thursday, June 11, 2026. Pre-design completion is scheduled for December 31, 2026, design completion for June 30, 2027, bidding for February 2029, and construction completion for June 2030.
The RFP requires separate submission of technical and cost proposals in PDF format, with technical proposals not exceeding 10 pages (11-point font minimum) and cost proposals itemized in U.S. dollars including hourly wage rates for all consultants. Proposers must provide detailed information on firm qualifications and experience with similar large-diameter pipeline projects, key personnel qualifications, project approach and schedule, references, and commitment to comply with the Sample Service Provider/Professional Services Agreement including insurance requirements. Selection will be based on consultant qualifications and experience (25 percent weight), key personnel experience and qualifications (25 percent), responsiveness and availability with local office presence (25 percent), understanding of scope of work (15 percent), and overall quality of response (10 percent). No specific funding amount or contract term is identified in the RFP, and consultants must acknowledge compliance with Salt Lake City's ethics requirements and conflict of interest ordinance provisions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-Sample Agreement Attachment A 05MAY2026.pdf | ||
| 2-Homeland Security Form 05MAY2026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSALS
FOR PROFESSIONAL DESIGN SERVICES
Orange St Sewer Trunkline Rehab Phase IV Indiana to 1500 South
525003178
May 5, 2026
1805 W 500 South Salt Lake City, UT 84104
REQUEST FOR PROPOSALS
Salt Lake City Department of Public Utilities (SLCDPU) is seeking proposals from qualified firms to provide design and professional engineering services for the Orange St Sewer Trunkline Rehab Phase IV Indiana to 1500 South (Project). The engineering services will include inspection and condition assessment, pre-design, permitting, design, bidding, construction, and public engagement services for the proposed Project. The following information is intended to provide additional instructions and information regarding this Request for Proposals (RFP) along with a schedule and other requirements for submitting a proposal.
INTRODUCTION AND BACKGROUND
The Orange Street Sewer Trunkline was constructed in 1963 of steel-reinforced concrete, and is 42” in diameter. The interior of the pipe and its manholes are seriously corroded.
Downstream segments have been rehabilitated in previous phases of this work. A condition assessment and pre-design report for the current phase (IV) was completed in 2013. SLCDPU is seeking engineering design services, bidding services, and services during construction for the rehabilitation of roughly 3,825 linear feet of the Orange Street Sewer Trunkline.
This project is included within the scope of the Surplus Canal permitting and specific levee mitigation measures will be required. Additionally, this project crosses through a cement superfund site. Project risks include contaminated groundwater within the superfund site, proximity of work to the surplus canal, and bypassing across redwood road and the surplus canal.
SCOPE OF WORK
Task 1. Inspection and Condition Assessment Updated inspection and condition assessment is included as a part of this project to inform design and bidding decisions. Inspect 42” Orange Street sewer trunkline from 1040 South to 1500 South to determine sediment buildup and pipeline condition, and develop a cross-section of the internal diameter of the pipe.
Deliverables
• CCTV submitted to SewerAI in .mdb format.
• Cross section of internal diameter of the pipe.
• Condition Assessment report following NASSCO standards.
Task 2. Pre-Design Services The pre-design report will define the final project design criteria and elements of success.
Evaluate possibility of constructing permanent bypass under surplus canal. Activities and deliverables include:
• Kick-off meeting to establish roles and responsibilities, review scope, schedule, deliverables, and project goals.
• Review of updated inspection data, cross-sections of internal pipe diameters, Condition Assessment Report, and GIS.
• Confirm rehabilitation method and describe project approach.
• Third Party Coordination - Review utility locations and potential conflicts to identify and understand any third-party requirements. Coordination with third party entities will begin in pre-design and continue throughout the duration of the project.
• Survey of existing conditions.
• Preliminary Design Report including construction constraints, project approach, preliminary cost estimate, identify key stakeholders, identify third-party coordination issues, and outline permit requirements.
• Survey and Replating
• Utility Conflict Matrix
• Permitting Matrix
• 30% cost estimate (25% contingency)
Task 3. Permitting Obtaining all necessary permits will be required as a service throughout the project. This project is included within the scope of the Surplus Canal permitting and specific levee mitigation measures will be required. Additionally, mitigating groundwater contaminants is necessary for dewatering permits. Permitting will require a significant effort for this project. Local, state, federal agencies, and others, will have interest in this work. Several permits will require action by Salt Lake City during the design process:
• Design Permitting:
o ACOE/SLCO Flood Control 408 Permit – Surplus Canal Crossing o UDOT Encroachment Permit o SLC Floodplain Permit o SLC Lowland Conservancy
• Construction Permitting:
o Utah DWQ/SLCDPU– Construction Dewatering Permit o SLC Transportation – Traffic Control Permit o SLC Engineering – Public Way Permit o SLC Public Utilities – SWPPP
Task 4. Design Services Provide design of the project using a 60/90 final design review process:
60% - This task progresses the pre-design adding detail on pre-design plans and sections and adds plans, sections, profiles, and elevations as needed. When this task is complete, design does not have to include Details, Specifications, and some minor design modifications for existing utilities. This task shall include a bypass schematic.
Input
• Surveying, design calculations, feasibility analysis and layout
• Information from outside utility companies and other outside agencies is added to the plans
• Final horizontal and vertical design
• Identify conflicts with other utilities
• Special permits and right-of-way/easements obtained
• Preliminary construction staging and traffic control plans
• Development of all appropriate plan sheets
• QC and maintenance review Deliverables
• 60% plans including bypass schematic
• 60% cost estimate/budget check (20% contingency)
• Send two sets of plans to maintenance, outside utility companies, and other outside agencies to get their utility information.
• Adjudicated responses to all pre-design review comments.
90% - When this task is complete, design is finalized such that the final project manual includes all plans and specifications.
Input
• Final vertical and design changes implemented
• Final design details implemented
• Final plans and design details produced
• QC review and maintenance approval of design Deliverables
• 90% plans and specifications (Project Manual) including bypass schematic
• 90% cost estimate/budget check (10% contingency)
• As a courtesy one plan set is sent to maintenance, outside utility companies and other outside agencies
• Adjudicated responses to all 60% design review comments.
100% - Final bid package stamped and sealed and ready for construction
• 100% plans and specifications (Project Manual) including bypass schematic, stamped and sealed by licensed engineers
• Adjudicated responses to all 90% design review comments.
Task 5. Bidding Process Bidding Services – Bidding Services should include preparation of Contract Documents, conduct pre-bid meeting, provide contract document clarification, prepare addendums as required, attend bid opening, complete bid review, prepare bid abstract, and make recommendation of lowest responsible and responsive bidder.
Task 6. Construction-Related Services Construction Services should include:
• Office engineering - submittal review, RFI review, prepare field work orders and change orders.
• Pre-construction meeting including agenda and minutes.
• Pre- and post-installation CCTV review, tracking any defects noted.
• Weekly construction progress meetings.
• Project commissioning including punch list and substantial completion documentation.
• Preparation of as-built drawings and project closeout.
Task 7. Public Engagement Develop Public Engagement Plan and messaging for the project throughout design and construction. Plan to include stakeholder identification, engagement tactics, and support for Community Council meetings. Identify high-profile issues that may delay project or become controversial.
Deliverables
• Public Engagement Plan, timeline, and schedule.
• Communications materials such as postcards, notices, hangers, and fliers.
• Deliver fliers, notices, etc. to impacted stakeholders. Develop stakeholder contact list. Identify public impacts and required mitigation measures.
• Host and monitor project phone line and email.
• Public Engagement Log documenting all interactions with the public including name, address, contact information, date, time, and resolution.
• Final Public Engagement Report.
• Prepare project related content for city website.
Available Project Information Additional project information can be provided during the procurement period upon request, with the submittal of a Homeland Security Request (HSR) Form to SLCDPUEng@slc.gov. This information includes a map of the project area and the 2013 Condition Assessment and Pre-Design Report.
SUBMISSION REQUIREMENTS
For the Proposal to be considered, submit no later than 2:00 PM on Friday, May 29, 2026, through the Utah Public Procurement Place (U3P) project site.
Instructions: Compile your cover sheet, proposal criteria responses, and any other correspondence into one single PDF file. A separate PDF file containing the cost proposal will be uploaded as a separate document. Upload your two files for this event using the Utah Public Procurement Place website. Responses must be uploaded and the electronic submission completed by the time and date specified. After uploading your response file, offerors MUST go to "Review and Submit" and click "SUBMIT RESPONSE" to complete the process. Responses submitted electronically through U3P require uploading of electronic attachments. U3P will accept a wide variety of document types as Word, Excel, and PDF attachments but not all. You MAY NOT submit documents that are mailto:SLCDPUEng@slc.gov embedded (zip files), movies, wmp and mp3 files or password protected files, etc. Such actions may cause your proposal to be deemed as "non-responsive".
The consultant shall use the list of tasks above as a reference for the initial submission.
Consultant’s submission must follow these requirements:
• Submit all required information as defined in the subsection Content of Submission in this RFP.
• Submit via U3P one (1) electronic response in PDF format. Submit a separate PDF file containing the cost proposal.
• Label the submitted file “Orange St Sewer Trunkline Rehab Phase IV Indiana to 1500 South – SLC Department of Public Utilities” and the submission deadline date. Label the cost proposal as “Orange St Sewer Trunkline Rehab Phase IV Indiana to 1500 South – Cost Proposal.”
• Submission deadline is 2:00 PM on Friday, May 29, 2026. Responses received after the 2:00 pm deadline will not be considered.
Content of Submission
The Proposal shall be submitted as an PDF document on 8.5 x 11” paper and shall not exceed 10 pages, minimum 11-point font. Résumés may be attached and are not included in the page limit. The document shall include a cover identifying it as “Orange St Sewer Trunkline Rehab Phase IV Indiana to 1500 South – Project No. 525003178, Proposal, SLC Department of Public Utilities”. The cover does not count as one of the 10 pages.
The response shall be signed by an officer or employee of the consultant authorized to bind the consultant contractually.
It is the consultant’s responsibility to assure delivery of its submittal to SLCDPU prior to or at the designated date and time. Consultants will not be entitled to withdraw or amend their proposals once submitted to SLCDPU.
SLCDPU reserves the right to request clarification of any item in a team’s response or to request additional information necessary to properly evaluate particular qualifications.
All requests for clarification and responses shall be in writing via U3P.
Please provide the following information in the sequence listed below:
• Statement of Interest signed by an official authorized to bind the firm.
• Consultant’s Experience & Qualifications o Name of firm or team.
o Describe the team’s organizational structure, the location of the office where staff will be located to manage this effort, and any other pertinent information.
o Describe the team’s experience and documentable performance of other projects similar in size and scope to the requested services for this project that may include pipeline inspection and condition assessment, CIPP design and construction, CCTV review, NASSCO certification, trenchless technology, permanent bypass design and construction, permitting with
USACE, UDOT, etc. The project descriptions should clearly demonstrate the capability of the team to perform the work required by this project.
o Key Personnel Experience and Qualifications Provide a description of individual experts or each team member’s professional experience and specializations related to the project, and a summary of each member’s qualifications, education degrees, certifications, professional licenses, etc.
If applicable, identify any of the work you intend to subcontract to others and identify the proposed subcontractors including names, specific assignments, and the qualifications of the subcontracting firm and its key personnel.
Provide the names and contact information of at least three (3) references for your firm’s or team’s professional capabilities in providing similar services requested in this RFP for similar clients of similar size. Also, include dates of performance.
A statement of whether your firm or any of your proposed subcontractors is currently involved in arbitration or litigation for any reason. If so, please elaborate.
A statement of whether your firm or any of your proposed subcontractors have ever filed for reorganization or bankruptcy. If so, please elaborate.
Unique and specialized expertise provided by your firm that will contribute to the project’s success should be highlighted in this section.
• Project Approach o Provide a general description of your approach to perform the project. In this section, demonstrate an understanding of the type of activities that SLCDPU has proposed, use the Scope of Work as a reference and include a general description of the information/data needs and highlight any outstanding features, including project management strategies and quality control and assurance processes. Include any recommendation to perform the Scope of Work or to support the project goals.
o Provide a project schedule outline
• Cost Proposal o Submit a Cost Proposal for all services in a separate electronic file labeled as described above.
o The Cost Proposal must be itemized in U.S. dollars and include hourly wages paid for consultants on the project.
o Proposer shall provide its best estimate of all costs associated with the performance of the services specified, including materials, supervision, labor, insurance, transportation, delivery, fuel or other surcharges, and related costs. Charges not listed in the RFP response will not be allowed.
o If there is a conflict between the written and numerical cost amounts, the written amount shall supersede.
• Include a statement indicating that the firm will comply with the terms and conditions of the Sample Service Provider/Professional Services Agreement (Attachment A), including the insurance requirements listed in this document.
• Other Required Information & Materials o Exceptions. If you have any exceptions to any of the terms, conditions, or requirements of this RFP or the attached Standard Agreement they must be identified and included in response to this RFP. Exceptions or deviations to any of the terms, conditions, or requirements must not be added to the Proposal pages but must be submitted in a separate document accompanying consultant’s response identified as “Exceptions.” Such exceptions shall be considered in the evaluation and the award processes.
SLCDPU shall be the sole determiner of the acceptability of any exception. Include a response to this item stating whether you have, or have not, included any exceptions.
o Electronic payment. The City is encouraging consultants to accept electronic payments using a process whereby vendors can receive payments and remittance advices electronically. Please provide information relating to: (1) your ability to accept electronic payments and remittance advices; (2) your policy, if any, regarding electronic payments and (3) your discount, if any, for electronic payments.
• Salt Lake City’s Ethics Requirement o Include the following two paragraphs in your response and then add your own written acknowledgement that you have read the paragraphs and agree to comply with their terms.
REPRESENTATION REGARDING ETHICAL STANDARDS FOR SALT LAKE
CITY OFFICERS AND EMPLOYEES AND FORMER CITY OFFICERS AND
EMPLOYEES
The respondent represents that it has not: (1) provided an illegal gift or payoff to a Salt Lake City officer or employee or former City officer or employee, or his or her relative or business entity; (2) retained any person to solicit or secure this contract upon an agreement or understanding for a commission, percentage, or brokerage or contingent fee, other than bona fide employees or bona fide commercial selling agencies for the purpose of securing business; (3) knowingly breached any of the ethical standards set forth in the City's conflict of interest ordinance, Chapter 2.44, Salt Lake City Code; or (4) knowingly influenced, and hereby promises that it will not knowingly influence, a City officer or employee or former City officer or employee to breach any of the ethical standards set forth in the City's conflict of interest ordinance, Chapter 2.44, Salt Lake City Code.
Pursuant to the foregoing, it is the City’s policy that City employees are prohibited from personally accepting gifts, incentives, and marketing or promotional items from suppliers and those suppliers shall not offer such items to City employees. Such offers from suppliers are inappropriate and may result in suspension or debarment of the supplier from the City’s procurement processes.
TENTATIVE SCHEDULE
The anticipated schedule for this project is shown below in the tentative project schedule.
Advertise in U3P ...................................................................... May 5 – May 29, 2026 RFP Available ................................................................................................. May 5, 2026
Technical Proposals Due.......................................................2:00pm, Friday, May 29, 2026 Possible Interviews ........................................................................... Week of June 1, 2026 Negotiation ........................................................................................ Week of June 1, 2026 Approval to Award Contract .......................................................... Thursday, June 11, 2026 Completion of Pre-Design ............................................................. December 31, 2026 Completion of Design ............................................................................ June 30, 2027 Bidding ........................................................................................................... February 2029 Completion of Construction ........................................................................ June 2030
SELECTION PROCESS
SLCDPU requests responses from consultants possessing the necessary qualifications, experience, and ability to complete the anticipated Scope of Work.
Complete submissions from interested and qualified consultants will be reviewed by an internal selection committee at SLCDPU. Based on the criteria outlined in this RFP, the committee will determine which consultant team best meets SLCDPU’s objectives. If necessary, interviews will be requested with chosen consultants during the selection process.
SLCDPU will evaluate Proposals based on completeness, qualifications and experience, and overall project value. The specific criteria used to select a firm or team are identified below (selection criteria section).
SLCDPU will be the sole judge as to which RFP submittals best meet the selection criteria.
SLCDPU reserves, at its sole discretion, the right to reject any or all responses received, to waive any submission requirements contained within this RFP, or to waive any irregularities in any submitted response.
The process for the selection of a consulting team or firm will be as follows:
1. Response to RFP: Complete Proposal submissions from interested and qualified consulting teams will be reviewed by an internal committee at SLCDPU.
2. Selection: SLCDPU may award based upon the proposals or may elect to interview any or all of those who respond to the RFP. SLCDPU reserves the right to reject all submissions and not select any consultant for the project.
3. Contract negotiation and award between the selected firm and SLCDPU.
SELECTION CRITERIA
The criteria for selection will be based on the following:
Criteria Weight (%)
1. Consultant’s qualifications and experience with other projects similar in size and scope to the requested services that may include large-diameter pipeline inspection and condition assessment, rehabilitation design and construction, CCTV review, NASSCO certification, trenchless technology, permanent bypass design and construction, permitting with USACE, UDOT, etc. Preference given to project experience with SLCDPU.
2. Experience and qualifications of key personnel to be involved in the project 25
3. Consultant’s ability to be responsive and available to SLCDPU staff such as local offices, team members, and ability to meet schedule outlined above. 25
4. Understanding of potential scope of work 15
5. Overall Quality of the RFP response 10
TOTAL 100
CONFIDENTIALITY
All responses, inquiries, and correspondence relating to this RFP and all reports, charts, displays, schedules, exhibits, and other documentation produced by the bidder that are submitted to the City, as part of the proposal or otherwise, shall become the property of the City when received by the City and may be considered public information under applicable law. The City is subject to the disclosure requirements of the Government Records Access and Management Act, Title 63G, Chapter 2, Utah Code Annotated (“GRAMA”). The City generally considers proposals and all accompanying material to be public and subject to disclosure. Any material considered by the Bidder to be proprietary must be accompanied by a written claim of business confidentiality containing a concise written statement of reasons supporting the claim. Blanket claims that the entire RFP is confidential will be denied. The City cannot guarantee that any information will be held confidential. If the bidder makes a claim of business confidentiality, the City, upon receipt of a request for disclosure, will determine whether the material should be classified as public or nonpublic, and will notify the Bidder of such determination. The bidder is entitled under GRAMA to appeal an adverse determination. The City is not obligated to notify the bidder of a request to see the bidder’s proposal, and will not consider a claim of confidentiality, unless the bidder's claim of confidentiality is made in a timely basis and in accordance with
GRAMA.
ATTACHMENT A
Sample Salt Lake City Department of Public Utilities
Agreement
| REQUEST FOR PROPOSALS |
| FOR PROFESSIONAL DESIGN SERVICES |
| 1805 W 500 South |
File details come from the government source that posted it. Updated .