This document is a detailed specification (Section 09875) from the Eastern Municipal Water District for repainting exterior surfaces of an existing welded steel tank. The specification covers three potential surface preparation methods: 100% removal, spot removal, or high-pressure water cleaning of existing paint, followed by replacement with a new paint system. The project involves comprehensive surface preparation, paint application, and handling of potential hazardous materials, with specific requirements for cleaning, coating, and quality control.

The specification provides extensive technical details on surface preparation techniques, including abrasive blasting, power tool cleaning, and water jet cleaning, with particular attention to managing potential lead or heavy metal contamination. The painting process requires precise environmental and temperature conditions, multiple coating layers, and rigorous inspection protocols. Contractors must use specific paint materials that comply with air pollution regulations, and the final coating system must achieve a minimum dry film thickness of 10.0 mils on bare metal surfaces or 6.0 mils over existing paint. The document also outlines strict safety requirements, waste disposal protocols, and post-application warranty inspection procedures.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS - DETAILED

PROVISIONS

Section 09875 Rev 13 - Repainting of Exterior Surfaces of an Existing Welded Steel Tank Based on

100%, Spot Removal, or High-Pressure Water Cleaning of Existing Paint and Replacement with a

New Paint System

C O N T E N T S

PART 1 - GENERAL

1.01 PURPOSE

1.02 SCOPE OF WORK

1.03 REFERENCE SPECIFICATIONS AND STANDARDS

1.04 COMPLETION OF WORK

1.05 CONTRACTOR

1.06 DEFINITIONS

1.07 HOURS OF WORK

1.08 PRE-BID CONFERENCE

1.09 PRE-CONSTRUCTION CONFERENCE

1.10 QUALITY ASSURANCE

1.11 SAFETY AND HEALTH REQUIREMENTS

1.12 COMPLIANCE WITH ENVIRONMENTAL REGULATORY REQUIREMENTS

PART 2 - PAINT MATERIALS

2.01 GENERAL

2.02 EXTERIOR PAINT MATERIALS

PART 3 - EXECUTION

3.01 GENERAL

3.02 TREATMENT OF HAZARDOUS MATERIALS (WHEN PRESENT AT ANY

CONCENTRATION)

3.03 SURFACE PREPARATION, GENERAL

3.04 SURFACE PREPARATION, EXTERIOR

3.05 APPLICATION, GENERAL

3.06 APPLICATION, EXTERIOR PAINT SYSTEMS

3.07 QUALITY CONTROL

3.08 CLEANUP

3.09 OMISSIONS

Rev: 11/17/2021

Section 09875 – 2

SECTION 09875

REPAINTING OF EXTERIOR SURFACES OF AN EXISTING

WELDED STEEL TANK BASED ON 100%, SPOT REMOVAL,

OR HIGH-PRESSURE WATER CLEANING OF EXISTING

PAINT SYSTEM AND REPLACEMENT WITH A NEW PAINT

SYSTEM

PART 1 - GENERAL

1.01 PURPOSE

A. The purpose of this specification is to establish methods and procedures for painting and handling of hazardous and non-hazardous materials/wastes.

1.02 SCOPE OF WORK

A. Work to be accomplished includes field application of protective paints to exterior surfaces, including surface preparation, handling of hazardous and non-hazardous materials/wastes, and other work necessary to accomplish the approved end result of a totally protected and usable structure, including attachments, accessories and appurtenances. Existing paints shall either be removed entirely, or spot repaired, as specified in the Special Conditions, generally as follows:

100% Removal

1. Remove all exterior paint by abrasive blast cleaning. Removal shall be by conventional methods if no hazardous materials are present, or by conventional method with containment, vacuum blasting, or other method approved by District if hazardous materials are present.

2. Apply prime, intermediate, and finish coats to all blast cleaned exterior surfaces in accordance with paragraph 3.06.

3. Test, handle and dispose of any hazardous or non-hazardous wastes generated from exterior painting operations in conformance to all regulations.

Spot Removal

1. Remove all oxidation, dirt, and other contaminants from exterior surfaces by washing; SSPC-WJ4, Low Pressure Water Cleaning at < 5,000 psig.

2. Remove all existing defective paint and active rust sites on exterior by abrasive blast cleaning. Removal shall be by conventional methods if no hazardous materials are present, or by conventional method with

Section 09875 – 3 containment, vacuum blasting, or other method approved by District if hazardous materials are present.

3. Apply specified primer to all abrasively blast cleaned areas.

4. Apply intermediate and finish coats of paints to complete exterior surfaces in accordance with paragraph 3.06.

5. Test, handle and dispose of any hazardous or non-hazardous wastes generated from exterior painting operations in conformance to all

High Pressure Water Cleaning

1. Remove all existing loosely bonded paint by water jetting. Cleaning shall be in conformance with SSPC WJ-4, high pressure water cleaning (HP WC) utilizing equipment producing 10,000 psig. The intent of this method of preparation is to remove any poor or marginally adhered existing paint with the anticipation that intact, well adhered film will largely remain in all areas.

2. Spot power tool clean (SSPC SP-15) active rust sites and feather all abrupt edges of sound, intact coating a minimum of 3 inches in each direction so that no edges can be lifted or probed with a dull putty knife.

3. Apply specified primer to all power tool cleaned areas.

4. Apply intermediate and finish coats of paints to complete exterior surfaces in accordance with paragraph 3.06.

5. Test, handle and dispose of any hazardous or non-hazardous wastes generated from exterior painting operations in conformance with all

B. Surfaces not to be painted include all interior surfaces, fencing, concrete surfaces, liquid level indicator accessories, glass, plastic, nameplates, and other surfaces on which paints would not adhere or would interfere with operation or purpose of specific item.

C. If severely corroded or damaged areas are discovered during the course of abrasive blast cleaning operations, the Contractor shall notify the District or authorized representative. Welding and repair of severely corroded areas of tank and other mechanical repairs may be required during project.

1. The Contractor shall allow the District access to make tank repairs while the existing paints are being removed. The District reserves the option to repair the tank structure with:

a) Change order to the contract.

Section 09875 – 4

b) District employees.

c) A separate Contractor.

d) Any combination of the above.

2. A no cost time extension will be issued should structural repairs delay abrasive blast cleaning and/or paint application. Preparation work shall continue while tank repairs are being made. The time extension will assume the Contractor will be able to re-mobilize and begin painting within two weeks of notification. No additional time will be granted to permit the Contractor to complete other projects prior to this project.

3. Contractor is responsible for the cost of all testing and analyses unless specifically stated otherwise.

1.03 REFERENCE SPECIFICATIONS AND STANDARDS

A. Without limiting the general aspects or other requirements of this specification, work and equipment shall conform to applicable requirements of municipal, state and federal codes, laws and ordinances governing the work, the Eastern Municipal Water District, SSPC: The Society for Protective Coatings, and manufacturer's printed instructions, subject to District's approval.

B. The Contractor shall meet all the terms of the District's General Conditions for

Major Construction and Maintenance. The terms of the General Conditions shall be referenced for contractual procedures.

C. The District's decision shall be final as to interpretation and/or conflict between any of the referenced codes, laws, ordinances, specifications and standards contained herein.

D. American Society for Testing and Materials (ASTM)

1. ASTM E337, Standard Test Method for Measuring Humidity with a

Psychrometer

2. ASTM D1186, Standard Test Method for Nondestructive Measurement of

Dry Film Thickness of Nonmagnetic Coatings Applied to a Ferrous Base

3. ASTM D3359, Standard Test Method for Measuring Adhesion by Tape.

4. ASTM D4138, Standard Test Method for Measurement of Dry Paint

Thickness of Protective Coating Systems by Destructive Means

5. ASTM D4285, Standard Test Method for Indicating Oil or Water in

Compressed Air

Section 09875 – 5

6. ASTM D4414, Standard Practice for Measurement of Wet Film Thickness by Notch Gages

7. ASTM D4417, Standard Test Methods for Field Measurement of Surface

Profile of Blast Cleaned Steel

8. ASTM D5402, Standard Test Methods for Assessing the Solvent Resistance of Organic Coatings Using Solvent Rubs

E. American Water Works Association (AWWA)

1. AWWA D102, AWWA Standard for Coating Steel Water Storage Tanks

2. AWWA C652, AWWA Standard for Disinfection of Water Storage Facilities

3. AWWA M42, AWWA Manual of Water Supply Practices, Steel Water Storage

Tanks

F. SSPC: Society for Protective Coatings (SSPC)

1. SSPC-SP 1, Solvent Cleaning

2. SSPC-SP 2/3, Hand/Power Tool Cleaning

3. SSPC-SP 6, Commercial Blast Cleaning

4. SSPC-SP 7, Brush-off Blast Cleaning

5. SSPC-SP 10, Near-White Blast Cleaning

6. SSPC-SP 11, Power Tool Cleaning to Bare Metal

7. SSPC-SP 15, Power Tool Cleaning to Commercial Grade Cleanliness

8 SPC-PA1, latest revision, for "Shop, Field and Maintenance Painting

9. SSPC-PA 2, Measurement of Dry Film Thickness with Magnetic Gages

10. SSPC-VIS 1, Visual Standard for Abrasive Blast Cleaned Steel

11. SSPC-VIS 3, Visual Standard for Hand and Power Tool Cleaned Steel

12. SSPC Publication No. 91-12, Coating and Lining Inspection Manual

13. SSPC-Visual Comparison Manual

14. SSPC Guide 12 - Guide for Illumination of Industrial Painting

15. SSPC's Publication 91-12 "Testing Recirculated Abrasives

Section 09875 – 6

G. NACE International (NACE)

1. NACE SP 0188-06, Standard Recommended Practice for Discontinuity

(Holiday) Testing of Protective Coatings

2. NACE SP 0178-89, Standard Recommended Practice for fabrication Details, Surface Finish Requirements, and Proper Design Considerations for Tanks and Vessels to be Lined for Immersion Service.

1.04 COMPLETION OF WORK

A. All surface preparation, paint application, and handling/disposing of hazardous and non- hazardous materials/wastes shall be completed within the number of calendar days consistent with the Contract Completion Schedule. If work is not completed within the number of calendar days specified, Contractor shall bear all additional expenses incurred after contract completion schedule.

1.05 CONTRACTOR

A. The contractor shall be a licensed Painting and Decorating Contractor in the

State of California (C-33 Classification). He shall have a minimum of five (5) years practical experience and successful history in the application of specified products to surfaces of steel water storage tanks. Upon request, he shall substantiate this requirement by furnishing a written list of references.

1.06 DEFINITIONS

A. "Engineer" refers to the person authorized by the District to oversee the execution of the contract, acting either directly or through his properly authorized agents, each agent acting only within the scope of authority delegated to him.

B. “Lining” refers to protective materials used or applied to interior surfaces. "Paint" refers to protective materials used or applied on exterior surfaces. "Coating" refers to protective materials used or applied on interior or exterior surfaces, or any protective material in general.

C. "District" refers to the Eastern Municipal Water District.

1.07 HOURS OF WORK

A. The Contractor's activities shall be confined to an eight-hour shift between the hours of 7:00 a.m. and 5:00 p.m. Monday through Friday, excluding District-designated holidays. Deviation from these hours will not be permitted without the prior consent of the District, except in emergencies involving immediate hazard to persons or property.

B. In the event of either a Contractor requested deviation or Contractor caused emergency deviation, inspection service fees for District personnel and any third-

Section 09875 – 7 party inspector will be charged against the Contractor at the discretion of the District. The service fees will be calculated at overtime rates including benefits, overhead, and travel time. The service fees will be deducted from any amounts due the Contractor. Charges will be made for any change to extraordinary work hours, including standby time due to late crew arrival or "no-show" by crew.

C. Inspection hours made necessary as a result of the Contractor’s crew working over forty hours per week must be scheduled and approved by District and overtime paid for by Contractor at the prevailing rate for overtime. Inspections requested by or made necessary as a result of actions by the Contractor on Saturdays, Sundays or holidays must be scheduled and approved by Engineer and paid for by Contractor at the prevailing rate for overtime or holiday work.

1.08 PRE-BID CONFERENCE

A. Pre-Bid Conference for the project will be conducted by the Engineer as noted in the Notice Inviting Bids. The object of the Pre-Bid Conference is to acquaint bidders with existing facility and site. The conditions and requirements of the plans and specifications shall govern over any information presented at the Pre- Bid Conference, unless amended in writing by the Engineer. All bidders must attend the Pre-Bid Conference to have their bid accepted by the District.

1.09 PRE-CONSTRUCTION CONFERENCE

A. A Pre-Construction Conference shall be scheduled prior to start of project. The

District, Contractor and Engineer shall be present. The sequence of work will be discussed and will be mutually agreed upon to ensure that the work is accomplished and completed as stated in the Contract, and to allow for inspection and operations flexibility by District. A schedule of work to be accomplished and a list of labor, material and equipment rates for additional work will be established and maintained throughout the project. Contractor shall furnish resumes of all personnel assigned to project, and a complete set of approved submittal data for use by inspection personnel. Contractor shall have a designated representative for all projects.

1.10 QUALITY ASSURANCE

A. General: Quality assurance procedures and practices shall be utilized to monitor all phases of surface preparation, application, and inspection throughout the duration of the project. Procedures or practices not specifically defined herein may be utilized provided they meet recognized and acceptable professional standards and are approved by the District.

B. The Contractor shall submit manufacturers' literature and material Safety Data Sheets (SDS) on all materials to be used in coating operations, including, but not limited to coatings, thinners, solvents, and cleaning fluids. No materials will be allowed which have been stored over 60 days, or manufacturer's recommended shelf life, whichever is less. Contractor shall maintain copies of SDS's at jobsite at all times. Copies of all invoices showing purchased dates and delivery for all

Section 09875 – 8 material mentioned above will be required.

C. All materials furnished and all work accomplished under the Contract shall be subject to inspection by the District. The Contractor shall be held strictly to the true intent of the Specifications in regard to quality of materials, workmanship, and diligent execution of the Contract.

D. Work accomplished in the absence of prescribed inspection may be required to be removed and replaced under the proper inspection, and the entire cost of removal and replacement, including the cost of all materials which may be furnished by the District and used in the work thus removed, shall be borne by the Contractor, regardless of whether the work removed is found to be defective or not. Work covered up without the authority of the Engineer, shall, upon order of the Engineer, be uncovered to the extent required, and the Contractor shall similarly bear the entire cost of accomplishing all the work and furnishing all the materials necessary for the removal of the covering and its subsequent replacement, as directed and approved by the District.

E. The District will make, or have made, such tests as it deems necessary to assure the work is being accomplished in accordance with the requirements of the Contract. Unless otherwise specified in the Special Conditions, the cost of such testing will be borne by the District. In the event such tests reveal non-compliance with the requirements of the Contract, the Contractor shall bear the cost of such corrective measures deemed necessary by the District, as well as the cost of subsequent retesting and re-inspection. It is understood and agreed the making of tests shall not constitute an acceptance of any portion of the work, nor relieve the Contractor from compliance with the terms of the Contract.

F. Warranty Inspection: Warranty inspection shall be conducted between the eleventh- and eighteenth-months following completion of all work and filing of the Notice of Acceptance. All personnel present at the Pre-Construction Conference should be present at this inspection. All defective work shall be repaired in strict accordance with this specification and to the satisfaction of the District.

1. Notification: The District shall establish the date for the inspection and shall notify the Contractor at least 30 days in advance.

2. Exterior Inspection: The entire exterior paint systems shall be visually inspected. All defective paint as well as damaged or rusting spots of the tank shall be satisfactorily repaired by and at the sole expense of the Contractor.

Defective coating shall be any of those defined by the SSPC's Visual Comparison Manual.

3. Inspection Report: The District shall prepare and deliver to the Contractor an inspection report covering the first anniversary inspection, setting forth the number and type of failures observed, the percentage of the surface area where failure has occurred, and the names of the persons making the inspection.

Section 09875 – 9

4. Schedule: Upon completion of inspection and receipt of Inspection Report as noted herein, District shall establish a date for Contractor to proceed with remedial work. Any delay on part of Contractor to meet schedule Contract and District may proceed to have defects remedied as outlined under General Provisions.

5. Remedial Work: Any location where paint has peeled, bubbled, or cracked and any location where rusting is evident shall be considered to be a failure of the system. The Contractor shall make repairs at all points where failures are observed by removing the deteriorated paint, cleaning the surface, and reapplying the same system. If the area of failure exceeds 25 percent of a specific coated surface, the entire applied system may be required to be removed and reapplied based on the District's sole judgment in accordance with the original specification.

a) Specific painted surfaces are defined as follows:

(i) Roof

(ii) Shell

(iii) Attachments, accessories, and appurtenances

6. Upon completion of warranty remedial repairs, Contractor shall clean site as originally specified.

7. Costs: All noted costs for Contractor's inspection and all costs for repair shall be borne by the Contractor and in figuring his bid, the Contractor shall include an appropriate amount for testing and repair as no additional allowance will be paid by the District for said inspection and repair.

1.11 SAFETY AND HEALTH REQUIREMENTS

A. Contractor shall fully comply with California Code of Regulations pertaining to the work including, but not limited to, the following Construction Safety Orders (CSO) or General Industry Safety Orders (GISO):

1. Illness Injury Prevention Program CSO/GISO 1508/3203

2. Confined Space Plan GISO 5156/5159

3. Respiratory Protection CSO/GISO 1531/5144

4. Hazard Communication GISO 5194

5. Lead-Based Paint Compliance Plan CSO 1532.1

6. Rolling Scaffolds CSO 1646

7. Employee Safety Instruction CSO 1510

Section 09875 – 10

8. Emergency Medical Service CSO 1512

9. Dusts, Fumes, Mists, Vapors & Gases CSO 1528

10. Fall Protection CSO

11. Hearing Conservation Program GISO

B. General: Contractor assumes the responsibility to accomplish all work in a safe and prudent manner, and to conform to all applicable safety requirements, regulations and guidelines of federal, state and local regulatory agencies, as well as applicable manufacturer's printed instructions and appropriate technical bulletins and manuals. Without in any way limiting that responsibility or assuming responsibility for safety, District is particularly concerned that the following are strictly observed:

1. Life Saving Equipment: Contractor shall provide and require use of personal protective life saving equipment for all its personnel working in or about the project site.

2. Access Facilities: All ladders, scaffolding and rigging shall be designed for their intended uses. Ladders and scaffolding shall be erected where requested by Engineer to facilitate inspection and be moved by the Contractor to locations requested by the District.

3. Ventilation: Contractor shall ensure there is proper ventilation, air eduction and exhausting of work space to reduce the concentration of lead-laden air contaminants to a level which poses no hazard to personnel at or near the job site. Air circulation and exhausting of solvent vapors shall be continued until paints have fully cured. If conventional blast cleaning is accomplished, total containment during blast cleaning and paint application operations is mandatory. The exhaust blower capacity shall be sufficient to maintain air changes within containment interior in accordance with Cal-OSHA, paint manufacturer's recommendations and local air quality management district

4. Head and Face Protection and Respiratory Devices: Equipment shall include protective helmets which shall be worn by all persons while in the vicinity of the work. During abrasive blasting operations, nozzlemen shall wear U.S. Bureau of Mines approved positive pressure air-supplied helmets and all other persons who are exposed to blasting dust shall wear respiratory protection determined necessary by the exposure assessment of the Certified Industrial Hygienist.

Positive pressure air-fed hoods and/or masks shall be supplied by an air source currently certified to produce "Class D Breathing Air". Contractor shall at all times during the work maintain onsite current documentation to substantiate the quality of the breathing air.

Section 09875 – 11

Barrier creams shall be used on any exposed areas of skin.

5. Grounding: All hoses shall be grounded to prevent accumulation of charges of static electricity.

6. Illumination: Spark proof artificial lighting shall be provided for all work in confined spaces. Light bulbs shall be guarded to prevent breakage. Lighting fixtures and flexible cords shall comply with the requirements of NFPA 70 "National Electric Code" for the atmosphere in which they will be used.

Whenever required by the Engineer, the Contractor shall provide additional illumination and necessary supports to cover all areas to be inspected. The level of illumination for inspection purposes shall be determined by the Engineer.

7. Toxicity and Explosiveness: The maximum allowable concentration of vapor shall be kept below the maximum safe concentration for eight-hour exposure, plus Lower Explosive Limit (L.E.L.) must be strictly maintained. All regulations related to safety of personnel and handling of such materials shall be strictly followed.

a) When exterior coatings have been determined to contain lead or other hazardous materials at any concentration, Contractor's responsibility for meeting all regulations relating to toxic and hazardous materials includes, but is not limited to, obtaining all permits and EPA numbers, having a Certified Industrial Hygienist onsite the first day of blasting to sample the air, processing paperwork, blood testing of personnel at start and finish of project, sampling and testing of wastes, paying fees, handling and packaging of wastes at site, and delivering materials to the selected Class I dumpsite using licensed hazardous materials transporters. All regulations relating to working with heavy metals or confined spaces shall be strictly enforced.

8. Protective Clothing: When handling and mixing paints, workmen shall wear gloves and eye shields. If working with lead or other heavy metals, regulations regarding handling of exposed clothing shall be strictly enforced.

9. Fire: Contractor shall provide appropriate fire abatement devices and prohibit any flames, welding and smoking during mixing and application of materials.

10. Sound Levels: Whenever the occupational noise exposure exceeds the maximum allowable sound levels, the Contractor shall provide and require the use of approved ear protective devices.

a) Noise suppression shall be practiced at all times to minimize disturbance to persons living or working nearby, and to the general public. Measures to be used in effecting noise suppression shall include (but not limited to) equipping all internal combustion engines

Section 09875 – 12 with critical residential silencers (mufflers), shielding noise-producing equipment from nearest areas of human occupancy by location in such positions as to direct the greatest noise emissions away from such areas, and conducting operations in the most effective manner to minimize noise generation consistent with the prosecution of the Contract in a timely and economic manner. Whenever levels are objectionable, they shall be adjusted as directed by the District.

1.12 COMPLIANCE WITH ENVIRONMENTAL REGULATORY REQUIREMENTS

A. Contractor shall comply with all current federal, state, and local environmental laws and regulations, including, but not limited to the laws and regulations of the U.S. Environmental Protection Agency (USEPA), the California Air Resources Board (CARB), and the South Coast Air Quality Management District (SCAQMD).

PART 2 - PAINT MATERIALS

2.01 GENERAL

A. Standard products of manufacturers other than those specified on the Approved Material List provided, will be accepted when it is proved to the satisfaction of the District, they are equal in composition, durability, usefulness and convenience for the purpose intended. Substitutions will be considered provided the following minimum conditions are met:

1. The proposed paint system shall have a dry film thickness equal to or greater than that of the specified system.

2. The proposed paint system shall employ an equal or greater number of separate coats.

3. The proposed paint system shall employ paints of the same generic type.

4. All requests for substitution shall carry full descriptive literature and directions for application, along with complete information on generic type, non-volatile content by volume and a list of 10 similar projects, all at least three years old, where the products have been applied to similar exposure.

5. Substitutions required as a result of new VOC regulations shall be endorsed in writing from the materials manufacturer that these substituted materials will provide equivalent performance as those specified.

6. The District requires that the Contractor provide certified laboratory data sheets showing the results of complete spectrographic and durability tests accomplished on the proposed substitute. Tests shall be accomplished by an independent testing laboratory satisfactory to the District and all costs incurred in the testing program shall be borne by the Contractor. In any case, the District shall be sole and final judge of the acceptability of any

Section 09875 – 13 proposed substitution. Requests for substitution must be approved in writing prior to date of bid.

B. All materials shall be brought to the jobsite in the original sealed containers. They shall not be opened or used until District's representative has physically inspected contents and obtained necessary data from information printed on containers or label. Materials exceeding storage life recommended by the manufacturer shall be rejected. Copy of invoice showing purchase and delivery dates will be required.

C. Flammability, toxicity, allergenic properties, and any other characteristic requiring field precautions shall be identified and specific safety practices shall be stipulated as required by federal, state, local manufacturer or SDS.

D. All paint materials shall be stored in enclosed structures to protect them from weather and excessive heat or cold. Flammable materials must be stored to conform with District, County, State and Federal safety codes for flammable materials. Paints shall be protected from freezing at all times.

E. Contractor shall use products of same manufacturer for all coats.

2.02 EXTERIOR PAINT MATERIALS

1. Paint materials shall conform to the regulations and applicable requirements of applicable local, State and Federal air pollution regulatory agencies.

Products containing perchloroethylene (PCE), trichloroethylene (TCE), lead or chromium will not be permitted. The Contractor shall provide, prior to painting any surfaces of the tank, written certifications from the coating manufacturers stating that the paint materials, thinners, solvents, and equipment cleaning fluids provided by the manufacturers do not contain PCE or TCE. The Contractor shall also certify, in writing, that no material containing PCE, TCE, lead or chromium in any form will be used for the exterior paints of the tank. This shall include all solvents, thinners, and cleaning fluids at the job site, regardless of where the materials were obtained.

2. The District may require all solvents, thinners and cleaning fluids be tested for TCE and PCE prior to being used at the job site. The Contractor shall provide the Engineer with samples of each material at no cost to the District.

Unacceptable materials shall be removed from the job site.

B. All paint materials shall comply with air pollution regulations, specifically the local air quality management district or air pollution control district rules, and rules for the District. Please refer to www.aqmd.gov/rules/reg/reg11/r1113.pdf.

C. All paint materials shall also conform to regulations and applicable requirements of local, State and Federal health regulatory agencies.

D. Paints materials shall be in accordance with the systems specified in Part 3.06.

http://www.aqmd.gov/rules/reg/reg11/r1113.pdf

Section 09875 – 14

PART 3 - EXECUTION

3.01 GENERAL

A. All surface preparation, paint application shall conform to applicable standards of the Society for Protective Coatings, the Eastern Municipal Water District, and the manufacturer's printed instructions. Material applied prior to approval of the surface preparation by the District shall be removed and reapplied to the satisfaction of the District at the expense of the Contractor.

B. All work shall be accomplished by skilled craftsmen qualified to accomplish the required work in a manner comparable with the best standards of practice.

Resumes of personnel to be used on the project shall be submitted upon Notice of Award. Continuity of personnel shall be maintained, and transfers of key personnel shall be coordinated with the District.

C. The Contractor shall provide a supervisor to be at the work site during cleaning and application operations. The supervisor shall have the authority to sign and change orders, coordinate work and make other decisions pertaining to the fulfillment of the contract.

D. Contractor shall provide approved sanitary facilities for all Contractor personnel, as no existing facilities will be available to the Contractor. Facilities shall be maintained during the project to complete standards established by District and shall be removed prior to Contractor's departure from the site at completion of the project.

E. Dust, dirt, oil, grease or any foreign matter which will affect the adhesion or durability of the finish must be removed by washing with clean rags dipped in an approved commercial cleaning solution, rinsed with clean water and wiped dry with clean rags.

F. The Contractor's equipment shall be designed for application of materials specified and shall be maintained in first class working condition. Compressors shall have suitable traps and filters to remove water and oils from the air. Blotter test shall be accomplished at each start-up period and as deemed necessary by the District. Contractor's equipment shall be subject to approval of the District.

This approval does not relieve the Contractor's responsibility for the safe operation of the equipment or its performance.

1. Cleanliness of compressed air supply shall be verified daily, and as deemed necessary by District, by directing a stream of air, without abrasive, from the blast nozzle onto a white blotter or cloth for twenty seconds. If oil or water appears on the blotter or cloth, all traps and separators shall be blown down until two subsequent twenty-second tests show no further oil or water.

G. Application of the first coat shall follow immediately after surface preparation and

Section 09875 – 15 cleaning within an eight-hour working day. Any cleaned areas not receiving first coat within an eight-hour period shall be recleaned prior to application of first coat.

H. Because of presence of moisture and possible contaminants in atmosphere, care shall be taken to ensure previously coated or painted surfaces are protected or recleaned prior to application of subsequent coat(s). Methods of protection and recleaning shall be approved by the District.

1. Project is subject to intermittent shutdown if, in the opinion of the District, cleaning and application operations are creating a localized condition detrimental to ongoing facility activities, personnel or adjacent property.

2. In the event of emergency shutdown by the District, Contractor shall immediately correct deficiencies. All additional costs created by shutdown shall be borne by Contractor.

I. The Contractor shall provide, at his own expense, all necessary power required for his operations under the contract.

J. Contractor shall tightly seal any tank vents, pumps, motors, and other open areas to prevent intrusion of paint or other contaminants. The sealing system shall be designed to allow continuous operation of facilities or equipment, with no detrimental effects. If necessary, sealing system shall be removed daily at termination of work, or as directed by the District.

K. Overspray Control: The Contractor shall conduct all operations so as to confine abrasive blasting debris, water jetting debris, and coating overspray to within the bounds of the site. The Contractor shall take all precautions necessary to prevent adverse off-site consequences of application operations. Any complaints received by the District relating to any such potential off-site problems will be immediately delivered to the Contractor-assigned jobsite representative. The Contractor shall immediately halt blast cleaning or application work and shall take whatever corrective action is required to mitigate any such problems. All costs associated with protection of off-site properties and/or correction of damage to property as a result of blast cleaning or application operations shall be borne directly by the Contractor at no additional expense to the District.

1. District approval of Contractor's overspray prevention procedures and

District's presence on project does not free Contractor from responsibility for overspray. Daily approval of procedures will be required prior to start of spray operations.

3.02 TREATMENT OF HAZARDOUS MATERIALS (WHEN PRESENT AT ANY

CONCENTRATION)

A. All regulations related to safety, worker protection and handling of such materials shall be strictly followed. When exterior surfaces have been determined, by laboratory analyses, to contain varying levels of lead and other heavy metals, Section 09875 – 16 submittal of a written plan of action for the project shall be accomplished by Contractor prior to start of project.

B. When heavy metals are present, Contractor shall comply with requirements of the

Codes and Regulations listed in Section 3.02.F. below for handling and disposing of hazardous wastes resulting from surface contamination and removed coating particles. Submittal of a written plan of action for the project shall be accomplished by Contractor prior to start of project.

C. When heavy metals are present, District will remove four representative samples of soil from jobsite prior to start of work. Samples will be tested under requirements listed below for determination of lead and other heavy metals to ensure soil does not contain excessive levels of lead and other heavy metals. If soils contain excessive levels of lead or other heavy metals, site remediation will be the responsibility of the District. Copies of laboratory analyses reports shall be forwarded to Contractor immediately upon receipt from laboratory, prior to start of any work. Any required remediation schedule will be determined by the District.

D. When exterior coatings have been determined to contain lead, all work must be accomplished in compliance with 29 CFR Part 1926, Lead Exposure in Construction, and Title 8, Section 1532.1. In addition, when lead is present at any concentration, Contractor shall perform the following:

1. On first day of any heavy metals-based coating removal, Contractor shall have work environment tested by a Certified Industrial Hygienist (CIH) to determine levels of protection required to protect workers and the environment from lead and other heavy metal contamination. All costs related to testing by the CIH shall be borne by the Contractor.

2. Testing shall include air sampling and testing by use of personal air monitors to determine the level of lead exposure. Upon completion of testing, the CIH shall file a written report on the results of the testing. Level of exposure will then determine the type of respiratory protection, clothing, housekeeping, hygiene facilities, medical surveillance, medical removal protection, employee information and training, signs, record keeping, and observation of monitoring required for the project.

No work shall re-commence until the report from the CIH is filed and worker and environmental protection required is in place. Costs for the time delay shall be included in the Contractor's original bid.

E. When exterior surfaces of tank contain hazardous materials, all dust emissions, abrasive deflection and removed coating particles shall be confined to interior of containment structure where abrasive blasting is being accomplished, unless vacuum blasting or other means of cleaning are approved by the District.

F. Wastewater from water jetting operations shall be collected and shall not be allowed to enter storm drains. Wastewater that contains soap, detergent, cleaning products, hazardous waste, or large amounts of any other pollutant, Section 09875 – 17 must be tested, handled, filtered, and neutralized as required for proper disposal within regulatory requirements.

G. All lead coating removal work shall be governed by, but not necessarily limited to, the following:

1. Health and Safety Code, Division 20, Chapters 5 and 6 (California Hazardous Waste Control Act)

2. Title 22 California Administrative Code (Minimum Standard for Management of Hazardous and Extremely Hazardous Materials)

3. Title 8, California Administrative Code

4. Code of Federal Regulations (29 CFR 1910 and 1926, applicable sections)

H. When existing coatings have been determined by laboratory analysis to be toxic or hazardous, coating and coating/abrasive residue mixture shall be tested to assure conformance with hazardous material tolerances have been met.

It shall be the responsibility of the Contractor to provide adequate containers on the jobsite to retain spent media and removed coating until tests have been completed or approval for disposal from a landfill has been obtained. Disposal of hazardous or toxic waste at other than government regulated landfills will not be permitted. Documentation of all hazardous or toxic waste disposal will be required.

I. When heavy metals are present, then upon completion and acceptance of all recoating operations, site soil will be retested by District, in same locations tested prior to start of work, for presence of lead or other heavy metals. Testing will be accomplished by the same laboratory as the original testing. If soils contain excessive levels of lead or other heavy metals above those levels determined by testing at start of work, Contractor shall be responsible for removal and disposal of contaminated soil and returning the site to its original condition. Copies of laboratory analyses reports shall be forwarded to Contractor immediately upon receipt from laboratory, prior to start of any work. Any required remediation schedule will be determined by the District. Handling, storing, transporting and disposal of any hazardous wastes shall be in complete compliance with all regulatory requirements.

3.03 SURFACE PREPARATION, GENERAL

A. The latest revision of the following surface preparation specifications of the

Society for Protective Coatings shall form a part of this specification. (Note: An element of surface area is defined as any given square inch of surface).

1. Solvent Cleaning (SSPC-SP1): Removal of oil, grease, soil and other contaminants by use of solvents, emulsions, cleaning compounds, steam cleaning or similar materials and methods, which involve a solvent or

Section 09875 – 18 cleaning action.

2. Hand Tool Cleaning (SSPC-SP2): Removal of loose rust, loose mill scale and other detrimental foreign matter present to degree specified by hand chipping, scraping, sanding and wire brushing.

3. Power Tool Cleaning (SSPC-SP3): Removal of loose rust, loose mill scale and other detrimental foreign matter present to degree specified by power wire brushing, power impact tools or power sanders.

4. Commercial Blast Cleaning (SSPC-SP6): Blast cleaning until at least two-thirds of each element of surface area is free of all visible residues.

5. Brush-off Blast Cleaning (SSPC-SP7): Blast cleaning to remove loose rust, loose mill scale, and other detrimental foreign matter present to the degree specified.

6. Near-White Blast Cleaning (SSPC-SP10): Blast cleaning to near-white metal cleanliness, until at least ninety-five percent of each element of surface area is free of all visible residues.

7. Power Tool Cleaning to Bare Metal (SSPC-SP11): Power tool cleaning to produce a bare metal surface and to retain or produce a surface profile of at least 1.0 mil.

8. Waterjet Cleaning of Metals: (SSPC-SPWJ-4) Low-pressure water cleaning

(LP WC): Water cleaning performed at pressures less than 5,000 psig, or High-pressure water cleaning (HP WC): performed at a maximum pressure of 10,000 psi to remove loose paint, and other detrimental foreign matter present.

9. Commercial Grade Power tool Cleaning (SSPC-SP15): Power tool cleaning until at least two-thirds of each element of surface area is free of all visible residue.

B. Any burrs, weld spatter, sharp edges, corners, or rough welds which would cause difficulty in achieving a defect-free paint system shall be chipped or ground smooth in conformance to NACE Standard RP0178, latest. It is not the intent to have the welds or "scars" ground "flush". The object of the grinding is to eliminate sharp edges, corners, and overlaps to provide a surface for the application of a uniform thickness of coating or paint without voids or other defects.

C. Abrasive blasting nozzles shall be equipped with "deadman" emergency shut-off nozzles. Blast nozzle pressure shall be a minimum of 95 P.S.I. and shall be verified by using an approved nozzle pressure gage at each start-up period or as directed by the District. Number of nozzles used during all blast cleaning operations must be sufficient to ensure timely completion of project, subject to designation and approval by District.

Section 09875 – 19

D. All blast hose connections shall be tethered and secured to prevent separation during blast cleaning operations and shall be taped with duct tape prior to pressurizing. All taped connections shall be visually inspected for leaks within five minutes after start of blast cleaning operations and at the end of blast cleaning operations. Leaking connections shall be immediately repaired to prevent further damage.

E. Field blast cleaning for all surfaces shall be by dry method unless otherwise directed. Contractor is responsible for maintaining dust emissions within the legal level and that level which would not create a nuisance.

F. Particle size of abrasives used in blast cleaning shall be that which will produce a

2.0 mil surface profile or in accordance with recommendations of the manufacturer of the specified paint system to be applied, subject to approval of District.

G. Abrasive used in blast cleaning operations shall be new, washed, graded and free of contaminants which would interfere with adhesion of paints and shall not be reused unless specifically approved by the District. Abrasives shall be certified for unconfined dry blasting pursuant to the California Administrative Code, Section 92520 of Subchapter 6, Title 17, and shall appear on the current listing of approved abrasives. Invoices or load sheets confirming above shall be required.

H. During blast cleaning operations for "Spot Removal", caution shall be exercised to ensure existing adjacent paint systems are not exposed to over blast from blast cleaning.

I. Blast cleaning from rolling scaffolds shall only be accomplished within confines of interior perimeter of scaffold. Reaching beyond limits of perimeter will be allowed only if blast nozzle is maintained in a position which will produce a profile acceptable to the District.

J. The Contractor shall keep the area of his work in a clean condition and shall not permit blasting materials to accumulate as to constitute a nuisance or hazard to the prosecution of the work or the operation of the existing facilities. Spent abrasives and other debris shall be removed at the Contractor's expense as directed by the District. When existing paints have been determined by laboratory analysis to be toxic or hazardous, handling shall be in accordance with Paragraph 3.02.G herein.

K. Blast cleaned and painted surfaces shall be cleaned prior to application of specified paints via a combination of blowing with clean dry air, brushing/brooming and/or vacuuming as directed by the District. Air hose for blowing shall be at least ½” in diameter and shall be equipped with a shut-off device.

L. All welds, when required, shall be neutralized with a suitable chemical compatible with the specified paint materials.

Section 09875 – 20

M. Brush-Off Water Jet Blast Cleaning (SSPC-SP12) shall be used only when and as directed by District. Pressures shall be those determined by District to effectively accomplish removal of loose, peeling/flaking coating or other detrimental surface contaminants.

3.04 SURFACE PREPARATION,

EXTERIOR

100% Removal

A. With the exception of the underside of the tank bottom, all exterior surfaces of tank shall be abrasively blast cleaned to "Commercial Blast Cleaning" In conformance to SSPC's Surface Preparation Specification No. 6 (SSPC-SP6) and a surface profile or anchor pattern of 2 to 3 mils (.002" - .003").

1. When heavy metals are present, existing paints shall be removed by vacuum blasting, or by methods other than vacuum blasting, after approval by District, which accomplish the specified results while containing all paint, abrasive, etc. during cleaning operations. These include conventional blast cleaning with containment, SABAR method with containment, chemical stripping, and Cavi-Tech method with containment.

B. All sandblast sand, removed coating, and any other residual debris shall be collected, removed from the site, and disposed of at an approved legal disposal site in accordance with the approved disposal plan. Said material shall be collected and directly moved from site. When existing paints have been determined by laboratory analysis to be toxic or hazardous, handling shall be in accordance with Paragraph 3.02.G herein.

Spot Removal

A. All surfaces shall be inspected jointly by the Contractor and the District to determine the condition of existing paint. During said inspection, Contractor shall perform adhesion tests in accordance with ASTM-D-3359 (Adhesion Tape Test) and ASTM-D-6677 (Adhesion Knife Test). The District shall then designate the surface condition by marking deficient areas, and cleaning shall be accomplished as noted below. Any areas overlooked during the joint inspection shall not relieve the Contractor from completely preparing surfaces:

1. Step One: All oily or greasy surface contaminants shall be removed by wiping the contaminated area with a clean rag wetted with solvent or degreasing solution in accordance with Society for Protective Coatings Specification SSPC-SP1 (Solvent Cleaning), then rinsed with clean water, wiped clean and dried.

2. Step Two: All chalking paint or other surface contaminants shall be removed by low pressure water cleaning (LP WC) or scrubbing the complete surface

Section 09875 – 21 with a suitable broom or brush as approved by the District, wetted with a solution of trisodium phosphate, detergent and water, or other approved cleaning solution. Cleaned surfaces shall then be rinsed with clean water, wiped clean and dried. When exterior paints have been determined by laboratory analyses to contain excessive levels of lead and other heavy metals, all cleaning operations shall be conducted to ensure removed paint particles or water are contained and not allowed to fall onto the site.

3. Step Three: All rusting, scaling, damaged areas and low adhesion areas shall be blast cleaned in conformance with Society for Protective Coatings Specification SSPC-SP6 (Commercial Blast Cleaning). Remaining paint shall be firmly bonded to the substrate with blast cleaned edges feathered.

Extreme care should be exercised to ensure remaining paint is not damaged by cleaning operations.

a) Cleaning methods other than blast cleaning may be used after approval by District, which accomplish the specified results. These include power tool cleaning to bare metal or chemical stripping. When heavy metals are present, cleaning methods other than vacuum blasting may be used, after approval by District, which accomplish the specified results while containing all paint, abrasive, etc. during cleaning operations. These include conventional blast cleaning with containment, SABAR method with containment, chemical stripping, and Cavi-Tech method with containment.

B. All sandblast sand, removed coating, and any other residual debris shall be collected, removed from the site, and disposed of at an approved legal disposal site in accordance with the approved disposal plan. Said material shall be collected and directly moved from site. When existing paints have been determined by laboratory analysis to be toxic or hazardous, handling shall be in accordance with Paragraph 3.02.G herein.

High Pressure Water (10,000 psig) Cleaning

A. All exterior surfaces and appurtenances to be painted shall be pressure water cleaned in accordance with SSPC-WJ-4, HPWC, (10,000 psi minimum). This work will include the scrubbing of all surfaces with a stiff bristle brush using a solution of trisodium phosphate (TSP). All scrubbed surfaces shall then be fresh water rinsed.

1. All existing exterior paint to be overcoated…