Statement of Work Summary

This is a Construction Services Statement of Work (SOW) for bollard replacement and modernization at the Lloyd D. George Courthouse (Building NV0304ZZ), located at 333 S Las Vegas Boulevard. The project involves replacing the facility's existing legacy retractable vehicle bollard system with a modern, four-unit, M50-rated, 240V single-phase automatic retractable electric bollard system. The contractor must furnish all labor, materials, and supervision to install new electro-mechanical drive components, PLC-based controls, control cabinets, wiring, battery backup/uninterruptible power supply components, magnetic vehicle sensing loops, and integrations with existing facility access-control and traffic signal systems. The scope includes site preparation, electrical isolation, pavement cutting, excavation, concrete placement, drainage connections, and surface restoration. Testing and commissioning must verify proper bollard operation, vehicle detection, access-control integration, and overall system functionality prior to acceptance.

The contract is firm-fixed-price for Design-Bid-Build delivery with a 120-calendar-day performance period from Notice to Proceed (NTP) to project closeout: 90 calendar days to substantial completion, 7 days to submit HSPD-12 clearance applications, and 30 days for project closeout. The contractor must maintain building operations throughout construction without disruption to tenants, work during normal building hours (6:00 AM–6:00 PM, Monday–Friday) with coordination required for significant noise work, and comply with extensive GSA standards including PBS Interim Core Building Standards, fire protection and life safety requirements (NFPA 13, 72, 101), safety and occupational health regulations (OSHA), hazardous materials handling, energy and water efficiency requirements, and building automation system integration. Key administrative requirements include Quality Control Plan, site-specific Safety and Health Plan, Construction Indoor Air Quality Management Plan, daily progress reporting through Kahua PMIS, shop drawings and product data submissions, comprehensive testing and inspections, and detailed project closeout documentation including as-built drawings, O&M manuals, warranties, and COBie-compliant facility management data.

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Construction Services Statement of Work, V8.0 Bollard Replacement, Lloyd D. George Courthouse, Bldg# NV0304ZZ

June 30, 2026 1 of 36

Back to Top

U.S. General Services Administration

National Capital Region

Public Buildings Service www.gsa.gov

Statement of Work for

Construction Services

PROJECT IDENTIFICATION

Project Title: LDG Bollard Replacement

Building: Lloyd George Courthouse

Building ID #: NV0304ZZ

Building Location: 333 S Las Vegas Blvd

SOW Author / Project Manager: Eric Schuetz http://www.gsa.gov/

June 30, 2026 2 of 36

TABLE OF CONTENTS

1. PROJECT INFORMATION 4

1.1. PROJECT SUMMARY 4

1.2. PROJECT BACKGROUND 4

1.3. CONTRACT TYPE 4

1.4. DELIVERY TYPE 4

1.5. PROJECT OBJECTIVES 5

1.6. PROJECT SCHEDULE 5

2. SCOPE OF WORK 6

2.1. PROJECT REQUIREMENTS 6

2.2. PROJECT SITE REQUIREMENTS 7

2.3. STANDARDS AND CRITERIA DOCUMENTS 8

2.4. CUTTING & PATCHING REQUIREMENTS 11

2.5. NATIONAL HISTORIC PRESERVATION ACT (NHPA) REQUIREMENTS 12

2.6. NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) REQUIREMENTS 12

2.7. NATIONAL CAPITAL PLANNING COMMISSION (NCPC) REQUIREMENTS 12

2.8. U.S. COMMISSION OF FINE ARTS (CFA) REQUIREMENTS 12

2.9. FINE ARTS REQUIREMENTS 12

2.10. ACCESSIBILITY REQUIREMENTS 12

2.11. SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS 12

2.12. FIRE PROTECTION AND LIFE SAFETY REQUIREMENTS 14

2.13. HAZARDOUS MATERIAL REQUIREMENTS 17

2.14. ENERGY AND WATER EFFICIENCY REQUIREMENTS 19

2.15. BUILDING CONTROL SYSTEMS, INCLUDING BUILDING AUTOMATION SYSTEMS (BAS)

AND BUILDING MONITORING AND CONTROL (BMC) SYSTEMS 20

2.16. CONNECTIONS TO FEDERAL GOVERNMENT BUILDING SYSTEMS NETWORKS (BSN) 20

2.17. COMMISSIONING 20

2.18. SITEWORK AND STORMWATER REQUIREMENTS 21

2.19. PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS): KAHUA 23

2.20. MANUFACTURER REQUIREMENTS 23

2.21. BUILDING INFORMATION MODELING (BIM) 23

2.22. ENERGY MODELING AND PERFORMANCE 23

2.23. COBie 23

2.24. METERS & SUBMETERS 23

3. DESIGN STAGE 23

4. CONSTRUCTION STAGE 24

4.1. GENERAL 24

4.2. PERMITTING 24

4.3. CONSTRUCTION SCHEDULE 25

June 30, 2026 3 of 36

4.4. CONSTRUCTION PROGRESS REPORTS 25

4.5. SHOP DRAWINGS / PRODUCT DATA SUBMISSIONS 26

4.6. SCHEDULE OF INSPECTIONS AND TESTS 27

4.7. CONSTRUCTION INSPECTIONS 27

4.8. SPECIAL INSPECTIONS 28

4.9. COMMISSIONING 28

4.10. QUALITY CONTROL PLAN 28

4.11. CONSTRUCTION INDOOR AIR QUALITY (IAQ) MANAGEMENT 30

4.12. SITE SPECIFIC SAFETY AND HEALTH PLAN 32

4.13. COORDINATION OF WORK 32

4.14. REQUESTS FOR INFORMATION 32

4.15. MODIFICATIONS / CHANGE ORDERS 32

5. CONTRACT ADMINISTRATION 33

5.1. CONTRACTOR’S STAFF 33

5.2. MEETINGS 33

5.3. COMMUNICATION 34

5.4. PROJECT CLOSEOUT 34

5.5. SCHEDULE OF VALUES 36

5.6. FEE & PAYMENT 36

5.7. GOVERNMENT FURNISHED PROPERTY 36

6. ATTACHMENTS 37

June 30, 2026 4 of 36

1. PROJECT INFORMATION

This section provides an overview of the project.

1.1. PROJECT SUMMARY

This project involves the replacement and modernization of the facility’s existing retractable vehicle bollard system. The existing system includes legacy relay-based controls, control cabinets, wiring, vehicle detection hardware, access-control interfaces, traffic signal interfaces, photo-eye sensors, and electro-mechanical bollard operating components.

The intent of the project is to replace the legacy controls and related bollard operating infrastructure with a modern, four-unit, M50-rated, 240V single-phase automatic retractable electric bollard system.

The completed system shall provide reliable bollard operation through a modern programmable logic controller (PLC), updated electrical infrastructure, new vehicle detection capability, and integration with existing facility access-control and safety systems.

The new system shall be capable of processing required operational inputs, including card readers, traffic signal lights, photo-eye sensors, magnetic vehicle sensing loops, bollard command signals, safety interlocks, and related system status inputs.

See Section 2.1 for detailed project requirements.

The Contractor shall coordinate work and gain approvals required in this Statement of Work (SOW) with the Contracting Officer (CO) and Contracting Officer’s Representative/Project Manager

(COR/PM) as required.

1.2. PROJECT BACKGROUND

The existing bollard system at the Lloyd D. George building consists of electro-mechanical bollards at the garage entrance and exit. This system was retrofitted from a hydraulic system roughly 10 years ago. The bollard controls are most likely original to the building. The bollards and controls system has experienced intermittent operation issues for the past few years. This project seeks to replace the existing controls and existing bollards.

1.3. CONTRACT TYPE

This contract is a firm-fixed price contract. The services required shall include, but shall not be limited to, the following:

● Contract Management

● Construction Services including Materials, Labor, and Supervision

● Professional Inspection and Testing Services

1.4. DELIVERY TYPE

The project is Construction Services for Design-Bid-Build delivery type.

June 30, 2026 5 of 36

1.5. PROJECT OBJECTIVES

The current bollards were retrofitted from a hydraulic system to an electro-mechanical system roughly 10 years ago. The manufacturer of the electro-mechanical is K12 Defense (SAU Electromechanical conversion unit). GSA intends to maintain the current electro-mechanical system. This scope of work shall include the refurbishment or replacement of current electro-mechanical units. New units can match existing or contractors may use compatible units from a different manufacturer.

Existing bollards appear to be in good condition. Contractor shall inspect bollards, test function, and repair as needed.

Controls

It is assumed that the current relay controls are original to the building and most likely over 20 years old. The scope of this project includes the replacement of these controls with a programmable logic controller (PLC). This includes complete replacement of cabinets, wiring, battery backups, and any associated infrastructure. Scope also includes the replacement of the existing in-ground magnetic vehicle sensing loop. New

PLC shall incorporate all existing inputs such as card readers, traffic light, eye sensor, and magnetic loop. Specifications for the PLC are included as an addendum to this scope of work.

1.6. PROJECT SCHEDULE

The overall Period of Performance shall be 120 calendar days from Notice To Proceed (NTP) to

Project Closeout, based on the following:

● NTP to Substantial Completion 90 calendar days after NTP

● Submit All HSPD-12 Clearance Applications 7 calendar days after NTP

● Project Closeout (as defined in Section 5.4.) 30 calendar days after Substantial Completion

All actions by the Government counted in calendar day shall begin the first calendar day after the submission, unless the submission is made before 9:00 AM.

https://docs.google.com/document/d/1N4K7ExhjUsWSpSIbwbN8UGLkmXtHbIUgV2ylYBSzpA4/edit#heading=h.xluvf9gayp22

June 30, 2026 6 of 36

2. SCOPE OF WORK

This section details the technical requirements and constraints for which the Contractor is responsible. The

Contractor shall perform all services described in this Statement of Work (including work required under exercised options, if any). The Contracting Officer and the COR/PM must approve all proposed changes to the Scope of Work.

2.1. PROJECT REQUIREMENTS

2.1.1. Base Bid

The Contractor shall furnish all labor and materials to install a complete four-unit, M50-rated, 240V single-phase automatic retractable electric bollard system to replace the existing legacy bollard system. The work shall include removal of existing relay-based controls, obsolete control cabinets, wiring, bollard operating hardware, and related components necessary to complete the replacement.

The Contractor shall provide and install new electro-mechanical drive components, structural bollard components, PLC-based controls, control cabinets, internal and external wiring, battery backup or uninterruptible power supply components, magnetic vehicle sensing loop, traffic signal integration, photo-eye sensor integration, and access-control system integration.

The Contractor shall perform required site preparation, including electrical isolation, removal of existing components, pavement saw-cutting, excavation, conduit clearing, drainage verification, installation of structural casings, concrete placement, rebar installation, drainage connections, and surface restoration necessary to support the new bollard system.

The new PLC-based control system shall manage bollard operation and safety functions and shall integrate all required operational inputs and outputs, including card readers, traffic signal lights, photo-eye sensors, magnetic loop detection, bollard raise and lower commands, bollard status signals, safety interlocks, and fail-safe functions where applicable.

The Contractor shall test and commission the completed system to verify proper bollard operation, vehicle detection, access-control integration, traffic signal coordination, safety interlock performance, and overall system functionality and integration to existing systems prior to acceptance.

The Contractor shall not install alternate electro-mechanical units or materially change the operating configuration without prior GSA approval. The Contractor shall identify all assumptions, exclusions, and required Government decisions in its proposal. Any proposed alternative equipment shall include documentation demonstrating technical compatibility with the existing bollard system and required operational performance.

The Contractor shall perform all services described in all solicitation documents and Request for

Proposal documents including this Statement of Work.

2.1.2. Permits and Responsibilities

Per FAR 52.236-7 Permits and Responsibilities, the Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered, and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.

June 30, 2026 7 of 36

2.2. PROJECT SITE REQUIREMENTS

2.2.1. Work Restrictions

The Contractor shall survey the entire worksite and review existing documentation to be familiar with the existing conditions. This includes all areas of the building, structure, and site affected by the removal and demolition work, alterations and new construction work prior to initiation of construction.

The Contractor shall limit the use of the premises to the work areas indicated, to allow for

Government occupancy and public use. The Government reserves the right to perform work, or retain other contractors to perform work, on portions of the project.

The building is to remain fully operational throughout the entirety of the project, with no disruption to tenant operations. All work areas must be cleaned at the end of every work day.

The work shall be sequenced to minimize disruption to building occupants, visitors, and maintenance activities. To the greatest extent feasible, demolition work should not take place until supplies are on hand to perform new work.

The Contractor shall coordinate all work activities with the GSA Building Manager and the COR/PM to ensure that proper security and access arrangements are made without impact on the construction schedule.

Where applicable, the contractor must employ adequate dust control measures.

2.2.2. Working Hours

2.2.2.1. Government Occupied Hours

Government personnel are scheduled to occupy the building during the following hours on weekdays, Monday through Friday, except for established Government Holidays, [6:00] AM to [6:00] PM.

2.2.2.2. Contractor's Working Hours

All work to be performed during the normal building hours of 6:00 am - 6:00 pm, M-F. Any work creating significant noise and or disruption to building activities shall not be completed during normal building hours. Additionally, all work shall be specifically coordinated through the Building Manager.

2.2.2.3. Loading Dock

Use of the existing loading dock facilities will be shared with Government activities on a first-come-first-served, wait-your-turn basis. The loading dock is available for the delivery of materials, tools, and supplies between the hours of [8:00] AM to [4:00] PM. Loading dock activities shall be coordinated with the GSA Building Manager a minimum of [72] hours in advance.

2.2.3. Parking

Limited parking is available on site. [One] parking spot will be made available for the Contractor’s use.

June 30, 2026 8 of 36

2.2.4. Staging and Storage

The Contractor may be provided a staging area within the building, contingent upon GSA approval, and provided that its use will not interfere with operations of the Government. No GSA employees will assist with unloading/loading of vehicles(s). The contractor shall provide all personnel and equipment needed for unloading, moving, and assembling the materials.

2.2.5. Dumpster

No space is available for the dumpster on site. Material is expected to be hauled off at the end of each work shift. Use of existing building dumpsters and trash bins is strictly prohibited.

2.2.6. Restrooms

Restrooms are available for use. Restrooms must be designated by the GSA Building Manager.

2.2.7. Freight Elevator

A freight elevator is not available for use at the project site.

2.2.8. Existing Conditions

All Government property or systems displaced, altered, or damaged during the performance of this contract other than stated in this SOW shall be restored to its original condition at no cost to the

Government. These repairs, if needed, shall be executed immediately when the Contractor is notified by the Contracting Officer that such repairs are required due to actions by the contractor or his/her subcontractors.

Maintenance of Existing equipment - Contractor shall collect information as needed from the Building manager or O&M staff for work to be done on any existing equipment / building systems for awareness and knowledge.

Assessment - All due diligence must be performed to assess the existing conditions of the site, building, perimeter security and roadway access for the proposed project.

Survey - A thorough survey must be done in order to understand the existing conditions and how the proposed project will impact the use , occupancy and surrounding areas.

2.3. STANDARDS AND CRITERIA DOCUMENTS

The Contractor shall ensure that all work performed, and materials used, under this scope of work are in accordance with the guidelines, codes and specifications of the following associations and agencies. Any conflicts or ambiguities within, or among, the referenced Standards and Criteria

Documents, or any deviations from requirements contained in the Standards and Criteria Documents, shall be reported to the COR/PM in writing, for determination as to applicability. The Contractor shall use the most recent versions of these documents issued at the time the RFP for the project is issued. In the event that there are conflicting requirements, the more stringent of the two shall be used.

2.3.1. GSA Requirements

June 30, 2026 9 of 36

● PBS Interim Core Building Standards, including all applicable Standards, Criteria and Guides listed therein

● PBS P-120, Public Buildings Service Cost and Schedule Management Policy Requirements

● Architectural Barriers Act Accessibility Standard (ABAAS)

● PBS Order 3490.3 CHGE 1, “Security for Sensitive Building Information Related to Federal

Buildings, Grounds, or Property”, March 22, 2021

● IAQ Guidelines for Occupied Buildings under Construction by SMACNA

● Occupational Safety and Health Administration (OSHA) regulations for Construction and

General Industry; 29 CFR Parts 1926 and 1910

● Section 01546 – Safety and Health Specification (see attachments)

● International Code Council Codes (ICC)

● National Fire Protection Association (NFPA) National Fire Codes and Standards

● ANSI NETA Standards

● PBS EASi/EDMS File Naming Requirements (see attachments)

[https://insite.gsa.gov/cdnstatic/PIB_18-02_Attach_6_File_Naming_2018_04_19.pdf]

● Section 889

● PBS Building Commissioning Guide (September 2020)

● Federal Metering Guidance (October 2022)

● The Guiding Principles for Sustainable Federal Buildings [ONLY for New Construction and

Major Renovations, for compliance with EISA 2007 § 433(a)]

● 40 CFR 61 National Emission Standards for Hazardous Air Pollutants

● 40 CFR 763 Asbestos

● 49 CFR 107 Hazardous Materials Program Procedures

● 49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials

Communications, Emergency Response Information, and Training Requirements

● EPA Mold Remediation Guidelines, September 2008

● District of Columbia Green Construction Code 2017 (construction and demolition debris recycling)

● Polycyclic Aromatic Hydrocarbons (PAHs)/Coal Tar Sealants: D.C. Code § 8–153.01; Maryland

Safer Sealant Act of 2022; Code of Virginia § 62.1-196.1 https://insite.gsa.gov/locations/region-11/public-buildings-service/office-of-planning-and-design-quality/project-submission/opdq-sow-templates]

● S ection 02085 - Asbestos Abatement Procedures (see attachments)

● S ection 02085R - Asbestos Abatement Roofing Removal Procedures (see attachments)

● S ection 02087 - Removal of Bird and Bat Droppings (see attachments)

● S ection 02089 - Control of Polychlorinated Biphenyl Specification (see attachments)

● S ection 02090 - Control of Lead Based Paint Specification (see attachments) https://www.gsa.gov/real-estate/design-and-construction/facilities-standards-for-the-public-buildings-service https://www.gsa.gov/directives/files?file=2023-06%2FFinal%20Directive_PBS%20Cost%20and%20Schedul%20Management.pdf https://www.access-board.gov/aba/ https://www.gsa.gov/directives/files?file=2023-08%2FPBS_34903_CHGE_1_Secur_for_Sen_Build_Inform_Related_to_Fed_Build%2C_Grounds%2C_or_Property_%28Final_Word_3-22-21%29_CC044070_RV_3-30-21.pdf https://www.gsa.gov/directives/files?file=2023-08%2FPBS_34903_CHGE_1_Secur_for_Sen_Build_Inform_Related_to_Fed_Build%2C_Grounds%2C_or_Property_%28Final_Word_3-22-21%29_CC044070_RV_3-30-21.pdf https://www.wbdg.org/FFC/GSA/gsa_commissioning_guide_2020.pdf https://www.wbdg.org/FFC/GSA/gsa_commissioning_guide_2020.pdf https://www.wbdg.org/FFC/GSA/gsa_commissioning_guide_2020.pdf https://www.energy.gov/sites/default/files/2022-10/federal-metering-guidance-2022.pdf https://www.sustainability.gov/pdfs/guiding_principles_for_sustainable_federal_buildings.pdf https://www.sustainability.gov/pdfs/guiding_principles_for_sustainable_federal_buildings.pdf https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title40/40cfr61_main_02.tpl https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title40/40cfr763_main_02.tpl https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title49/49cfr107_main_02.tpl https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title49/49cfr172_main_02.tpl https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title49/49cfr172_main_02.tpl https://www.epa.gov/sites/production/files/2014-08/documents/moldremediation.pdf https://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title49/49cfr172_main_02.tpl https://dob.dc.gov/sites/default/files/dc/sites/dob/publication/attachments/2017%20DC%20Green%20Construction%20Code.pdf https://code.dccouncil.gov/us/dc/council/code/sections/8-153.01 https://mde.maryland.gov/programs/land/SolidWaste/SiteAssets/Pages/index/Driveway%20Sealant%20PAH%20Ban.pdf https://mde.maryland.gov/programs/land/SolidWaste/SiteAssets/Pages/index/Driveway%20Sealant%20PAH%20Ban.pdf http://law.lis.virginia.gov/vacode/62.1-196.1

June 30, 2026 10 of 36

● S ection 02090 - Control Of LBP

2.3.2. Tenant Agency Requirements

Not Applicable

2.3.3. Building Management and Controls (BMC) and Federal Government Building

Systems Network (BSN) Connection Requirements

● 7002.1 ADM GSA Smart Buildings (December 2021)

● Smart Buildings Implementation Guide Requirements

● Smart Buildings Program Guide

● GSA Data Normalization for Building Automation Systems

● GSA National Capital Region Advanced Metering Systems (AMS) Guide, v1.1 (see attachments)

● Niagara NiCS Statement (see attachments)

● Security and Privacy Controls for Federal Information Systems and Organizations, NIST 800-53

Rev 5

● Guide to Industrial Control Systems (ICS) Security, NIST 800-82 rev 2

● GSA IT Building Technology Technical Reference Guide (BTTRG) v2.0

● Telecommunications Distribution Design Guide, Telecommunications and Infrastructure

Standards, v8

● GSA Order 2100.1M GSA Information Technology (IT) Security Policy

● IT Security Procedural Guide: Key Management CIO-IT Security-09-43, rev4

● IT Security Procedural Guide: Building Monitoring and Control (BMC) Systems Security

Assessment Process CIO-IT Security-16-76, rev2, October 13, 2020

● IT Security Procedural Guide: Managing Enterprise Cybersecurity Risk CIO-IT Security-06-30, rev19, April 15, 2021

● 2180.2 CIO GSA Rules of Behavior for Handling Personally Identifiable Information (PII), October 8, 2019

● 2181.1 ADM Homeland Security Presidential Directive-12, Personal Identity Verification and

Credentialing, and Background Investigations for Contractors, March 18, 2020

● 2100.2C CIO P GSA Wireless Local Area Network (LAN) Security guide

● GSA IT Policy Requirements Guide 12-2018

● GSA IT Security Procedural Guide: Security and Privacy Requirements for IT Acquisition

Efforts CIO-IT Security-09-48, Rev6, April 15, 2021

● GSA IT Security Procedural Guide: SSL TLS Implementation Guide - CIO-IT Security 14-69, Rev3, April 6, 2021

● PBS Technology Policy

2.4. CUTTING & PATCHING REQUIREMENTS

The Contractor shall replace, patch, and repair material and surfaces cut or damaged by methods and with materials in such a manner as not to void any existing warranties.

All substrates must be inspected and defects repaired prior to installing new material or finish. All replacement and new materials shall match the existing in material, dimensions, color and finish. All https://www.gsa.gov/directives/files?file=2024-03%2FCC044916_%20directive_ADM%207002.1%2C%20GSA%20Smart%20Buildings.pdf https://nvlpubs.nist.gov/nistpubs/SpecialPublications/NIST.SP.800-53r5.pdf https://nvlpubs.nist.gov/nistpubs/SpecialPublications/NIST.SP.800-53r5.pdf https://nvlpubs.nist.gov/nistpubs/SpecialPublications/NIST.SP.800-82r2.pdf

June 30, 2026 11 of 36 material selections and/or mock-ups need to be reviewed and accepted by the COR/PM and Tenant

Agency prior to ordering.

2.4.1. Structural Systems

Do not cut structural beams or major structural elements without the written review and approval of a

Licensed Structural Engineer. Additionally, the COR/PM shall obtain review and acceptance from

GSA’s OPDQ’s structural engineer and A/E’s structural engineer. Prior to cutting and/or drilling through any structural member, the Contractor shall conduct ground penetrating radar, or similar type of investigative measure to prevent cutting concealed material. Submit structural calculations sealed by a Licensed Structural Engineer to the COR/PM concurrently for acceptance.

Do not cut and patch structural elements in a manner that would change their load-carrying capacity or load-deflection ratio.

2.4.2. Operational Systems

The Contractor shall not cut and patch operating elements, safety related systems, or related components in a manner that would result in reducing their capacity to perform as intended, or that would result in increased maintenance, or decreased operational life or safety.

2.4.3. Visual / Finishes

The Contractor shall not cut and patch construction exposed on the exterior, or in occupied spaces, in a manner that would, in GSA's opinion, reduce the building's aesthetic qualities, or that would result in visual evidence of cutting and patching. The Contractor shall remove and replace construction that is cut and patched in a visually unsatisfactory manner.

Patched areas shall be neatly trimmed prior to patching. Feather all patches to provide a complete and finished surface. Paint all exposed work provided under the contract including all patched areas, and exposed areas uncovered during demolition, to provide a complete and finished project. Paint patched areas and surrounding areas to the nearest break in wall surface, or other building line to provide a neat and finished appearance. All paint shall match adjacent painted surfaces. Protect all surrounding areas including fixtures, furniture, floors and accessories from paint splatter and droppings. Clean and restore all areas splashed with paint.

Any work related to removing equipment, brackets, supports, etc. that leaves holes or damaged surfaces on the floor, walls, and ceilings, shall be patched with the same adjacent material and finish.

2.5. NATIONAL HISTORIC PRESERVATION ACT (NHPA) REQUIREMENTS

Intentionally Omitted

2.6. NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) REQUIREMENTS

Pursuant to paragraph 5.3 of the PBS NEPA Desk Guide (October 1999), this project is an automatic

CATEX and requires no checklist.

2.7. NATIONAL CAPITAL PLANNING COMMISSION (NCPC) REQUIREMENTS

The design has been approved by NCPC. Modifications to the design of the exterior of the building or site work will require a review by OPDQ, and could result in a resubmission to NCPC.

June 30, 2026 12 of 36

2.8. U.S. COMMISSION OF FINE ARTS (CFA) REQUIREMENTS

The design has been approved by CFA. Modifications to the design of the exterior of the building or site work will require a review by OPDQ, and could result in a resubmission to CFA.

2.9. FINE ARTS REQUIREMENTS

It is not anticipated that Fine Arts will be disturbed during construction activities. The Contractor shall protect Fine Arts per the Fine Art Protection Work Plan and coordinate with SME in OPDQ

(Office of Planning and Design Quality).

2.10. ACCESSIBILITY REQUIREMENTS

The Architectural Barriers Act Accessibility Standard (ABAAS) is mandatory for all GSA projects, and shall be maintained at all times.

2.11. SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS

The Contractor(s) shall comply with the safety standards and guidelines referenced in Section 2.3.1 as well as the following requirements:

GSA NCR Safety and Health are the authority having jurisdiction (AHJ) for all safety and health concerns at all GSA owned facilities.

The Contractor shall provide a site-specific Safety and Health Plan that includes job hazard analysis, bloodborne pathogens, emergency response, personal protective equipment (PPE) requirements, hazard mitigation, hazardous energy control (lock out/tag out), arc flash requirements, hazardous noise, confined space, crane plans, fall protection, chemicals being used onsite, trainings/ certification, and when safety toolbox meetings will occur.

The Contractor shall provide Safety Data Sheets (SDSs) for all substances/ materials to be used in the performance of this contract to the onsite O&M shop. The Contractor will ensure all personnel wear the appropriate personal protective equipment required by the SDSs.

The Contractor shall ensure that all hazards at the end of the workday/ project end are mitigated to ensure that the site is not left in an unsafe condition (e.g., fall, confined space, excavation, chemicals, walkways).

The Contractor shall ensure a first aid kit is available at the site and that all employee injuries and incidents are reported to the COR immediately for reporting to GSA Safety and Health.

The Contractor shall ensure that all hazardous energy sources are locked and tagged out, arc flash procedures are followed to include all PPE, lock out/ tag out (LOTO), labeling, demarcation of zones, and all 1-line drawings are updated. All new electrical must be updated on the inside electrical panel door, all wires are run correctly, and wires are labeled.

All equipment and material that is owned by the contractor must be labeled with the contractor's contact name and cell number for rapid identification during inspections or emergency situations.

The Contractor shall only use extension cords with three (3) prongs (ground) and only use them for temporary power on a daily basis. All extension cords will be inspected before use for damage, frayed electrical, exposed wires, and must dispose of all damaged extension cords. Damaged extension cords cannot be repaired with electrical tape and must be replaced with new to prevent electrical shock hazards and fire. Extension cords cannot be plugged into outlets that have appliances or essential

June 30, 2026 13 of 36 equipment plugged into them. The GFCI extension cord adaptors can be used to prevent tripping of electrical services.

The Contractor shall not store chemicals, equipment, debris, or trash in or around electrical rooms/ panels, in hallways, stairwells, on stairs, or in authorized spaces at any time.

The Contractor shall not permit any contractors/ employees from entering a confined space, accessing the roof top areas without the proper clearance, fall protection, RF Radiation hazard areas, or any other area deemed unsafe by the COR or GSA NCR Safety and Occupational Health.

The Contractor will ensure compliance with all confined spaces with attention to the entry of permit required confined spaces. The contractor is responsible for working with the O&M contractor and building manager for compliance with the site confined space program.

The Contractor shall at any time be able to submit inspection documentation and training documentation for its employees to the COR and GSA NCR Safety and Occupational Health personnel.

All accidents must be reported to the COR immediately and any injuries to personnel must be reported to the COR and NCR Safety and Health immediately with updates hourly until the situation is addressed. A written report shall be submitted within 24 hours of the injury to the COR and NCR

Safety and Health. Incidents without injury must submit a written report to the COR within 24 hours.

2.12. FIRE PROTECTION AND LIFE SAFETY REQUIREMENTS

GSA’s Fire Protection Engineers are the authority having jurisdiction (AHJ) for all GSA owned facilities.

2.12.1. Egress/Life Safety

● The existing means of egress for the remainder of the occupied building shall be maintained in an

NFPA 101 compliant manner at all times unless specifically approved by the GSA regional fire protection engineer.

● Demonstrate compliance with the safeguarding construction and alteration operations requirements of NFPA 241. Construction activities for tenant alterations or building modernizations shall be separated from the remainder of an occupied building with walls having a minimum 1-hr fire resistant rating with 45-min opening protectives, or shall be provided with an active sprinkler system and continuous smoke partitions throughout the duration of construction.

Construction phasing and/or separation walls shall be located in such a manner to maintain an

NFPA 101 compliant egress arrangement for the remainder of the occupied building (dead-ends, common paths of travel, travel distances, etc.).

2.12.2. Fire Protection Systems

● Modify existing sprinkler systems in accordance with the latest requirements of NFPA 13, Standard for the Installation of Sprinkler Systems.

● Working plans sprinkler system layout shall be performed by a minimum NICET Level III or IV

Water Based Systems Layout technician, or a licensed Fire Protection Engineer.

● Provide detailed shop drawings, in accordance with NFPA 13, "Working Plans”. Drawings shall be drawn to an indicated scale on sheets of uniform size and be submitted to the COR for review

June 30, 2026 14 of 36 and approval by the GSA regional fire protection engineer. Information shall include but not be limited to the following:

○ Layout indicating details, plan view, elevations and sections of the system piping.

Indicate the location of sprinkler heads and piping in relation to the ceiling layout, showing pipe lengths and sizes.

○ Detailed riser diagram showing schematic of systems supply, supply connection, devices, valves, pipe and fittings.

○ Hydraulic calculations

○ Annotated manufacturer’s data sheets showing the specific model, type and size of each item.

○ The signature and seal of a licenced Professional Fire Protection Engineer, or a NICET

Level III or IV Technician.

● Perform hydrostatic testing of sprinkler piping in accordance with the requirements of NFPA 13.

● Final Inspection and Testing: Advise the COR/PM when hydrostatic and alarm tests have been completed and all necessary corrections made, so as to permit final inspection and testing.

Submit requests for testing at least 15 calendar days prior to the test date.

○ The final test shall be witnessed by the GSA regional fire protection engineer and/or the third-party fire protection engineer responsible for inspections and acceptance testing.

The Contractor and an authorized representative from each supplier of equipment shall be in attendance at the final test.

○ Final testing shall include, but is not limited to, testing of all waterflow and tamper switches.

○ Provide all equipment, services and labor to properly perform all required tests.

2.12.3. Fire Alarm Systems

● Modify existing fire alarm system in accordance with the requirements of NFPA 72, National

Fire Alarm and Signalling Code. Provide new UL-listed fire alarm equipment. All new equipment shall be compatible with the existing fire alarm equipment manufacturer.

● Fire alarm initiating device and notification appliance shop drawing layout shall be performed by

NICET Level III or IV fire alarm systems technician, or licensed fire protection engineer.

Installation shall be accomplished by an electrical contractor with a minimum of five years experience in the installation of fire alarm systems.

● All circuits and pathways shall match existing in class and survivability designations. Conductors must match existing gauge, type, and color coding. All conductors which are terminated, spliced, or otherwise interrupted in any enclosure, cabinet, mounting or junction box shall be connected to terminal blocks in a workman like manner.

● Provide detailed installation shop drawings, in accordance with NFPA 72 documentation and shop drawing requirements. Drawings shall be drawn to an indicated scale on sheets of uniform size, and submitted to the COR/PM for review and approval by the GSA regional fire protection engineer. Submittal information shall include but not be limited to the following:

○ A complete description of the system operation.

○ A complete list of device addresses and corresponding messages.

○ Point to point wiring diagrams showing the points of connection and terminals used for all electrical field connections in the system, including all interconnections between the equipment or systems which are supervised or controlled by the system.

June 30, 2026 15 of 36

○ Annotated manufacturer’s data sheets showing the specific model, type and size of each item.

○ Notification appliance circuit calculations including voltage drop, circuit capacity, amplifier capacity, and power supply capacity.

○ Battery calculations for both the alarm and supervisory power requirements. Ampere-

¬hour requirements for each system component shall be submitted with the calculations.

○ Provide a color code schedule for the wiring and floor plans showing the location of all devices and equipment.

○ The signature and seal of a licensed Professional Fire Protection Engineer, or a NICET

Level III or IV Technician.

● Prior to installation the contractor shall coordinate and schedule a fire alarm outage with the GSA project manager or GSA facilities management office. When work is being performed on an active fire alarm circuit(s), the fire alarm system must be taken out of service by the O&M vendor or their designated representative. The fire alarm system shall be returned to “normal” operating condition before the contractor and subcontractor(s) leave for the work shift.

● Fire alarm programming changes are permitted only when confirmed acceptance testing is scheduled with the AHJ or their designated representative. A fire alarm program change must be acceptance tested within 24 hours of the change. The AHJ is the GSA regional fire protection engineer.

● Perform preliminary tests to ensure that all devices and circuits are functioning properly. After preliminary testing is complete, provide a letter certifying that the installation is complete and fully operable.

● Perform final acceptance testing in accordance with the requirements of NFPA in the presence of the GSA regional fire protection engineer or third-party fire protection engineer.

2.12.4. Fire and Life Safety System Testing and Acceptance

● The Contractor shall provide a subcontracting Fire Protection Engineering firm, other than the

Design Team Fire Protection Engineer (FPE subcontractor), acceptable to the GSA Fire

Protection Engineering Section, to witness system acceptance testing and inspections.

○ The contracting firm shall be a firm whose prime enterprise is in the field of fire protection engineering. The contracting firm should have a fully operational and fully staffed office within a 50 mile radius of Washington, DC. The contracting firm must provide a program manager who possesses a BS or MS in Fire Protection Engineering, and meets the experience requirements for fire protection engineers listed below.

Complete documentation to support fire alarm systems testing experiences must be resubmitted as a part of the submittal package.

○ Qualified fire protection engineer(s) shall witness acceptance testing. The FPE subcontractor must employ a full-time team of at least two qualified fire protection engineers, available for the Testing required by this contract. The engineers shall possess a BS or MS in fire protection or fire safety engineering with at least four consecutive years of experience in fire protection engineering work, within the past six (6) years, or professional engineering licensure in fire protection. Proposed personnel shall demonstrate that they have been involved in fire protection and life safety systems inspection and testing similar in complexity relevant to the scope.

June 30, 2026 16 of 36

○ The fire protection engineer(s) shall have experience in submittal review, construction inspection, acceptance testing and commissioning systems.

○ The fire protection engineer(s) shall demonstrate a thorough working knowledge and formal training in fire protection codes and standards, especially the latest edition of

NFPA 101, NFPA 13, NFPA 72, NFPA 90A and the International Building Code. The proposed personnel shall demonstrate that they have acted in charge of fire protection engineering designs including fire protection and extinguishment systems, fire alarm systems, life safety systems, and smoke control systems.

● Testing and inspections for the fire alarm shall include the following minimum criteria:

○ Testing and commissioning in accordance with NFPA 72

○ All new equipment shall be 100% fully tested

○ Confidence (re-acceptance) testing to include 10% of the building field devices

○ Test each fire alarm initiating and indicating device and circuit for proper operation and response

○ Test the system for all specified functions in accordance with the contract specifications, and the approved sprinkler and fire alarm submittals

○ Determine that the system is operable under trouble conditions

○ Test the adequacy of the notification appliances (visible and audible characteristics)

○ Program changes to the building fire alarm control panel will require re-acceptance testing within 24 hours of the change

○ As applicable, perform a battery test for all new control panels and extender panels

● Testing and inspections for the fire protection system shall include the following minimum criteria:

○ Verify compliance with NFPA 13

○ Visual inspection of the sprinkler system adequacy, coverage, piping, hangars, sprinkler locations, hydraulic nameplates, and sprinkler types.

● Inspections for fire compartment integrity shall include the following minimum criteria:

○ Visually inspect fire rated partition/wall and floor assemblies, partition stenciling, fire door, and fire/smoke damper operation.

● Inspections for life safety and egress shall include the following minimum criteria:

○ Verify compliance with the NFPA 101 egress requirements

○ Visually inspect emergency lighting, exit signage, and egress arrangement (pathways, exits, special locking, etc)

The Contractor shall provide a written Discrepancies and Omissions (D&O) list within 48 hours of completion of each test or inspection. The D & O list shall include a description of the work that was completed, a description on the system equipment and operation, and describe conditions which do not comply with the above criteria. Provide corrective action recommendations for all discrepancies and omissions. Note that the task includes follow up inspections and testing necessary to verify corrections of items. If no items are necessary for correction, the D&O list shall indicate all items have been corrected and the space is acceptable for issuance of an occupancy certificate.

2.13. HAZARDOUS MATERIAL REQUIREMENTS

All work, including contact with and handling of hazardous materials, the disturbance or dismantling of structures containing hazardous materials, and/or the transport and disposal of hazardous materials shall comply with the applicable requirements of 29 CFR 1910/1926, and 40 CFR 761/260-271.

June 30, 2026 17 of 36

2.13.1. Hazardous Materials Survey

Not Applicable Intentionally Omitted.

2.13.2. Asbestos Containing Material

Not Applicable Intentionally Omitted.

2.13.3. Lead Based Paint

Not Applicable Intentionally Omitted.

2.13.4. Polychlorinated Biphenyl

For all caulking and/or waterproofing removal projects in buildings constructed prior to 1979, assume

PCB contamination above 50 ppm. Testing of waste materials is not mandatory, but if no testing is conducted the waste must be classified per EPA as "PCB Bulk Waste". The Contractor’s Industrial

Hygiene Consultant has the option to test caulking, waterproofing materials, and waste generated for

PCB content in accordance with 40 CFR 761. If the materials yield PCB levels below 50 ppm they can be disposed of as standard construction debris.

Work involving the disturbance, dismantling or demolition of PCBs shall comply with GSA

Specification 02089 Small PCB Items and Mercury Lamps. The Contractor shall survey the project area for PCBs per section 2.13.1. of this SOW.

Fluorescent and high intensity discharge lamps shall be managed as Universal Waste and sent to a recycler, or as Hazardous Waste, if materials are not sent to a recycler. In addition, lamps that are broken or crushed must be managed as hazardous waste unless otherwise stated in local regulations.

2.13.5. Radon

Not Applicable Intentionally Omitted.

2.13.6. Mercury

Not Applicable Intentionally Omitted.

2.13.7. Universal / Hazardous Waste

Not Applicable Intentionally Omitted.

2.13.8. Exit Signs Requiring Special Disposal

Not Applicable Intentionally Omitted.

2.13.9. Hazardous Materials Cost Tracking

The Contractor shall propose and invoice costs for all effort related to asbestos separately from costs for all efforts related to all other hazardous materials, both of which shall be separate from all other costs for GSA’s accounting purposes.

2.13.10. Construction and Demolition (C&D) Debris

Not Applicable Intentionally Omitted.

June 30, 2026 18 of 36

2.13.11. Protection of Stratospheric Ozone

The Contractor shall not allow the venting of refrigerants to the atmosphere in compliance with section 608 of the Clean Air Act (40 CFR Part 82).

2.13.12. Refrigerant Recovery and Significant New Alternatives Policy (SNAP) Requirements

The Contractor shall identify the type(s)/amount(s) of refrigerant(s) to be recovered as part of the project and their viability for reuse as recovered or after reclamation. GSA will determine and inform the Contractor of the disposition plan (reuse by GSA, reuse by the DOD, sale to a certified technician or reclaimer or disposal per RCRA regulations).

New chiller equipment, refrigerators, air conditioners, and heat pumps may only use refrigerants listed as “Acceptable” by the U.S. Environmental Protection Agency (EPA)’s Significant New

Alternatives Policy (SNAP) Program, even if EPA's "Unacceptable as of" date is in the future.

2.13.13. Polycyclic Aromatic Hydrocarbons (PAHs)/Coal Tar Sealants

Note that, per [District of Columbia/Maryland/Virginia] Code, high PAH sealants, including coal tar sealant, shall not be used. Sealcoat (two applications at a rate of 0.11 – 0.13 gallon/yd²) with a Coal

Tar Pitch Emulsion (CTPE) sealer that meets or exceeds RP 355e and ASTM D5727 specifications and standards may be used (strive for 30% asphalt content). Include CTPE sealer specifications.

2.14. ENERGY AND WATER EFFICIENCY REQUIREMENTS

Refer to PBS Interim Core Building Standards for applicable laws and regulations to follow.

If any pumps or motors will be purchased, they shall be NEMA Premium Efficiency rated and controlled by a Variable Frequency Drive (VFD).

If insulation will be replaced or installed, it shall be the maximum feasible insulation on tanks, pipes, fittings, valves, and other associated equipment related to the domestic hot water system in the building.

2.14.1. Cost Comparison Analysis

This project requires the Contractor to provide a basic cost comparison which demonstrates that the equipment that is being installed is the best value for the taxpayer when the annual water and energy usage is taken into account. Note that this is intended to be simple calculations, not an engineering study. Cost Comparison Table Attachment must be included with the bid sheet.

2.14.2. Lighting Fixtures

Lighting fixtures should be approved by the DesignLights Consortium® (DLC) with a DLC Premium

Certification—as the first priority—and Energy Star certified if no DLC rating is available. Lighting-inclusive projects shall use efficient light-emitting diode (LED) fixtures and automatic lighting controls (i.e. either occupancy or vacancy sensors—the preference is for vacancy sensors) that are linked to the Building Automation System, if present. When retrofitting an existing lighting fixture with new LED bulbs or tubular LEDs, ANSI & ASHRAE must be followed.

Interior lighting color temperature is recommended to be 3500 K and not to exceed 4000 K. Indoor lighting should be on motion detection controls and daylight controls if within 10 feet of a window or skylight.

Outdoor lighting should follow these guidelines to limit light pollution:

https://www.epa.gov/snap/overview-snap https://www.epa.gov/snap/overview-snap https://www.gsa.gov/real-estate/design-and-construction/facilities-standards-for-the-public-buildings-service

June 30, 2026 19 of 36

● Outdoor lighting color temperature should be limited to 3000 K with a maximum of 3500 K, (CCT < 3000 K; S/P ratio < 1.2) to minimize blue emission, use “warm-white” or filtered LEDs

● All exterior lighting should be on a timeclock or photocell control, as well as vacancy or occupancy sensors

● Provide fully shielded fixtures that emit no light upward

● Provide for dimming or turning off the lights during overnight hours

● Avoid over-lighting due to the higher luminous efficiency of LEDs

● Only light the exact space and in the amount required for particular tasks

● Outdoor lighting products that can help meet these specifications can be found on The

International Dark Sky Association’s website

2.14.3. Energy Rebates

Not Applicable Intentionally Omitted.

2.14.4. HVAC System Replacement, HVAC System Controls, Cooling Tower Replacement

Not Applicable Intentionally Omitted.

2.14.5. Roof Replacement

Not Applicable Intentionally Omitted.

2.15. BUILDING CONTROL SYSTEMS, INCLUDING BUILDING AUTOMATION

SYSTEMS (BAS) AND BUILDING MONITORING AND CONTROL (BMC)

SYSTEMS

The property does have a BAS or BMC.

The Contractor shall integrate all new equipment into the existing BAS or BMC and controllers. This includes interface compatibility, required programming, and commissioning to ensure performance meets required performance objectives per the PBS Smart Buildings Directive, Smart Building

Implementation Guide Requirements, Smart Buildings Program Guide, GSA Data Normalization for

Building Automation Systems, GSA National Capital Region AMS Guide, Technology Policy for PBS

Owned Building, Monitoring and Control Systems, and Niagara NiCS Statement. If the BAS or BMC are on a Federal Government network, or will be connected to the network by this project, then the

Contractor shall comply with Section 2.16 of this SOW.

2.16. CONNECTIONS TO FEDERAL GOVERNMENT BUILDING SYSTEMS

NETWORKS (BSN)

This project [is not] anticipated to connect to [GSA’s or the Tenant Agency’s] Network. All persons working on this task order, and interfacing with a Federal Government internet or intranet network shall be HSPD-12 cleared prior to working on the network, regardless of the number of days engaged in the project. All work shall comply with Section 2.3.3. of this SOW.

2.17. COMMISSIONING

2.17.1. Commissioning Agent

The GSA will retain the services of a Commissioning Agent (CxA) through the Construction

Manager as Advisor (CMa) to verify that the Contractor has executed the project per the design.

Commissioning services will include [building enclosure, HVAC, electrical, lighting, acoustics, and stormwater best management practices].

https://www.darksky.org/our-work/lighting/lighting-for-industry/fsa/fsa-products/#!/Search-by-Application/c/19306351/offset=0&sort=nameAsc https://www.darksky.org/our-work/lighting/lighting-for-industry/fsa/fsa-products/#!/Search-by-Application/c/19306351/offset=0&sort=nameAsc

June 30, 2026 20 of 36

2.17.2. Mechanical/HVAC Commissioning

The Contractor shall execute commissioning of the required systems identified in the project specifications. The Contractor shall complete the required commissioning checklists, and schedule commissioning of the systems with the CxA, and make adjustments to the systems until the systems pass the required tests including, but not…