26QB154 SOW Termite Remediation_Rev 1 27Aug26.docx

DOCX document 32 KB Posted

Attached to
Termite Fumigation
Solicitation number
FA252126QB154
Issued by

About this file

This is a Statement of Work (SOW) for corrective drywood termite fumigation services at Building 708, Patrick Space Force Base (PSFB), Florida, issued by the Department of the Air Force Space Command. The contractor must provide complete whole-building tenting and structural fumigation services to achieve 100% termite eradication, with measurable objectives including zero fumigant gas residue (less than 1 ppm for safe re-entry), all work completion within a strict 3 to 4-day continuous operational window, and a 2-year service warranty for drywood termites. The scope encompasses pre-fumigation inspection, structural tenting installation, perimeter security, fumigant gas introduction (Sulfuryl Fluoride or equivalent EPA-approved chemical), continuous monitoring and aeration, and clearance testing with certification documentation.

All work must comply with FIFRA, EPA guidelines, Florida Department of Agriculture and Consumer Services regulations (Chapter 482, Florida Statutes), OSHA standards, DoD pest management regulations, and PSFB environmental and safety standards. Key contractor deliverables include state fumigation documents and work/safety plan (due 10 days prior), metal roof release form (3 days prior), pre-fumigation inspection report (1 day prior), fumigation execution (days 1-4), clearance certificate (day 4), and warranty documentation (5 days after clearance). Performance must commence within 10 days of contract award and be completed within 20 days of initial work start. All contractor personnel require Defense Biometric Identification System (DBIDS) passes or equivalent base access credentials, background checks, and potential military escort requirements in restricted areas. No photography or recording of military assets is permitted. PSFB is responsible for mandatory facility preparation including removal of all non-factory sealed food items, medicines, animal feed, and aircraft equipment, plus HVAC system deactivation and unobstructed building access provision.

View the file

Other files

File Type Posted
FA252126QB154 Q and A.docx DOCX document
26QB154 SOW Termite Remediation_Rev 4 15 Sep26.docx DOCX document
FA252126QB154 Q and A.pdf PDF
Outlet Pictures.pdf PDF
B708 Fumigation Project East Side Facing North.jpg JPG image
B708 Fumigation Project North Side Facing East.jpg JPG image
B708 Fumigation Project West Side Facing North.jpg JPG image
B708 Fumigation Project North Side Facing West.jpg JPG image
26QB154 SOW Termite Remediation_Rev 3 10Sep26.docx DOCX document
FA252126QB154 Q and A.docx DOCX document
26QB154 RFQ Termite Fumigation.docx DOCX document
26QB154 RFQ Termite Fumigation.docx DOCX document
26QB154 RFQ Termite Fumigation.docx DOCX document
26QB154 RFQ Termite Fumigation.docx DOCX document
26QB154 RFQ Termite Fumigation.docx DOCX document
Site Visit Participation Confirmation.xlsx XLSX spreadsheet
Addendum to PWS.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

Project Title: Corrective Termite Fumigation Location: Patrick Space Force Base (PSFB), Florida Bldg708 Date: August 27, 2026 Rev: 1

1. Introduction and Background This Statement of Work (SOW) defines the requirements for corrective drywood termite fumigation services at building 708 located at Patrick Space Force Base (PSFB), Florida. A pre-fumigation inspection will confirm the scope of active infestation. Due to the destructive nature of drywood termites, a complete whole-building tenting and structural fumigation is required to eradicate the pests and safeguard the structural integrity of the facility.

2. Measurable Objectives The primary objective of this project is the complete eradication of the Drywood Termite infestation within the designated structure.

· Metric 1 (Eradication): Achieve 100% mortality rate of live termites within the treated building.

· Metric 2 (Safety): Achieve 0 parts per million (ppm) or the legally mandated safe clearance level of fumigant gas (less than 1 ppm for Sulfuryl Fluoride) before re-entry is authorized.

· Metric 3 (Schedule): Complete all physical stages of the fumigation process—including tenting, gas introduction, exposure, aeration, and final clearance—within a strict 3 to 4-day continuous operational window to minimize facility and mission downtime.

3. Scope of Work The Contractor shall provide all personnel, equipment, tools, materials, supervision, and non-personal services necessary to perform whole-building tenting and corrective fumigation. The scope includes:

· Pre-Fumigation Inspection: Conducting a comprehensive walkthrough of the structure prior to treatment to verify building preparation, identify structural hazards, and map optimal gas introduction points.

· Structural Tenting: Erecting high-durability fumigation tents/tarpaulins to completely seal the entire building.

· Securing the Perimeter: Placing warning signs, secondary locks (clamshells), and securing all exterior access points to prevent unauthorized entry.

· Fumigant Introduction: Introducing the approved fumigant gas (e.g., Sulfuryl Fluoride or equivalent approved chemical) at dosage rates calculated based on target volume, temperature, and wind speed.

· Monitoring and Aeration: Monitoring gas levels during exposure and executing a controlled aeration and ventilation process.

· Clearance Testing: Conducting precision safety testing to officially certify the building as safe for human re-entry.

4. Applicable Regulations and Standards The Contractor must comply with all local, state, and federal laws, as well as military regulations, including but not limited to:

· Federal Insecticide, Fungicide, and Rodenticide Act (FIFRA).

· Environmental Protection Agency (EPA) guidelines for structural fumigation.

· Florida Department of Agriculture and Consumer Services (FDACS) rules and regulations (Chapter 482, Florida Statutes).

· Occupational Safety and Health Administration (OSHA) standards for confined space and hazardous chemical exposure.

· Department of Defense (DoD) Pest Management Program regulations.

· PSFB Base Environmental, Safety, and Fire Protection standards.

5. Roles and Responsibilities Contractor Responsibilities:

· Perform a mandatory pre-fumigation inspection prior to treatment.

· Prepare, complete, and submit all required Florida state fumigation documents and notifications to FDACS and local authorities.

· Obtain a signed Metal Roof Release form from the authorized PSFB representative prior to climbing or working on the facility's roof.

· Provide a detailed Fumigation Work Plan, including safety, security, and emergency response procedures.

· Execute the tenting and fumigation process in strict adherence to manufacturer label instructions and Florida regulations.

· Furnish 24/7 monitoring or secure guards for the tented structure during the active fumigation window.

· Issue a signed "Certificate of Safe Re-entry" once gas levels drop below 1 ppm.

PSFB Responsibilities:

· Coordinate and sign the required Metal Roof Release form to clear the Contractor for operations on the metal roof.

· Mandatory Preparation: Ensure the complete removal of all non-factory sealed food items, medicines, and animal feed from the premises.

· Mandatory Preparation: Ensure the complete removal of all aircraft items and associated sensitive equipment from the immediate treatment area or interior.

· Provide the Contractor with unobstructed access to the building and surrounding 10-foot perimeter.

· Deactivate all building HVAC systems, gas lines, and interior fire detection/alarm systems (to prevent false alarms) prior to tenting.

· Coordinate security escorts and gate access permissions for Contractor personnel.

6. Deliverables and Timelines The following deliverables must be submitted to the PSFB according to the outlined schedule:

Deliverable
Description
Deadline
Florida Fumigation Documents
Completed state-mandated regulatory filings and notifications.
10 days prior to work commencement
Deliverable
Description
Deadline
Fumigation Work & Safety Plan
Comprehensive plan detailing chemicals used, hazard controls, and contact list.
10 days prior to work commencement

Metal Roof Release Form Fully executed release form acknowledging the metal roof structural safety.

3 days prior to work commencement

Pre-Fumigation Inspection Report
Results of the pre-treatment walkthrough.

1 day prior to treatment

Fumigation Process Execution
Tenting, gas introduction, exposure, and aeration.
Days 1 to 4 of operational window
Clearance Certificate
Signed document certifying safe air quality ( < 1 ppm) for re-entry.
Day 4 of operational window
2-Year Service Warranty
Executed warranty document for Drywood Termites.
5 days after clearance is issued

7. Security Requirements Because the work is being performed on a military installation (PSFB), strict security compliance is mandatory.

· Base Access: All Contractor personnel must pass a background check to obtain Defense Biometric Identification System (DBIDS) passes or equivalent base access credentials.

· Escorts: If working in restricted, flight line, or secure areas, Contractor personnel must be escorted by authorized PSFB personnel at all times.

· Operational Security: No photography, video, or recording of military assets (especially flight line operations) is permitted. Documentation is strictly restricted to the specified building's exterior and interior for pest control validation.

8. Place and Period of Performance

· Place of Performance: Building 708 Spacelift Drive, PSFB Florida 32925.

· Period of Performance: Performance shall commence no later than 10 days after contract award and shall be completed within 20 days from the start of initial work. The physical fumigation process, from tent installation through final clearance, shall be completed within a strict 3‑ to 4‑day continuous window.

9. Warranty and Liability

· 2-Year Service Warranty: The Contractor shall provide a two (2) year service warranty for Drywood Termites starting from the date the Clearance Certificate is issued.

· Coverage Terms: If active Drywood Termite infestation is discovered within the treated structure during the 2-year warranty period, the Contractor will perform corrective spot treatments or retreatment at no additional cost to the Government.

· Exclusion of Damage Protection: This warranty is strictly a service-only warranty. No structural damage protection, structural repair coverage, or financial compensation for pest-related damage is offered, implied, or provided.