This is a Submittal Register form template used in federal construction contracts to track and manage contractor submittals throughout project execution. The document serves as a comprehensive log for all required submissions, including preconstruction documents, test reports, certificates, product data, and closeout materials.
The register tracks submissions across multiple categories referenced by specification sections and paragraph numbers. Preconstruction submittals (SD-01) include the Accident Prevention Plan, Quality Control Plan, Activity Hazard Analysis, Construction Schedule, Equipment Delivery Schedule, and crane-related documentation such as Critical Lift Plans and Work Plans. Environmental submittals include Environmental Protection Plans, Preconstruction Surveys, and Storm Water Discharge Permits. The form also documents Test Reports (SD-06) for backflow preventers and certificates (SD-07) including confined space entry permits and third-party certifications for barge-mounted mobile cranes. Product Data (SD-03) submissions cover items such as backflow preventers. Closeout submittals (SD-11) include the Submittal Register, Complete Submittal Package, Quality Control Plan, and interim DD Form 1354 for transfer and acceptance. The form provides columns for tracking action codes, submission dates, approval needed dates, material needed dates, transmission dates to and from approving authorities and other reviewers, and remarks. This template enables systematic management of contractor compliance with federal construction contract requirements throughout all project phases.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT NO.
CONTRACTOR
SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
01 20 00
1.3
01 30 00
1.4.1
01 31 50
1.2
01 32 16
1.2
1.3
01 33 00
1.4.1
1.6.1
01 35 29
1.9
1.10
1.9.1
1.9.1
1.7.1.4
1.14
1.14.1
1.14.3
1.14.4
1.14.5
1.11
1.14.6
1.14.7
01 45 10
1.6
01 50 00
1.6.2.1
2.1
3.1
SD-03 PRODUCT DATA
Backflow Preventers (If Applicable)
SD-06 TEST REPORTS
SD-07 CERTIFICATES
SD-01 PRECONSTRUCTION SUBMITTALS
Traffic Control Plan (If Applicable)
Crane Critical Lift Plan (If Applicable)
Crane Operators (If Applicable)
Reports
Accident Reports
Monthly Exposure Reports
Regulatory Citations and Violations
Crane Reports
(Enter Contract No. Here)
SD-01 PRECONSTRUCTION SUBMITTALS
Accident Prevention Plan (APP)
SD-01 PRECONSTRUCTION SUBMITTALS
Equipment Delivery Schedule
SD-01 PRECONSTRUCTION SUBMITTALS
SUBMITTAL REGISTER
P A R A G R A P H
N O
S P E C
S E C T
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W R
(Enter Contractor Name Here)
Qaulity Control Plan (QC Plan)
Crane Work Plan (If Applicable)
Activity Hazard Analysis (AHA)
SD-06 TEST REPORTS
Certificate of Compliance
SD-01 PRECONSTRUCTION SUBMITTALS
TITLE AND LOCATION
(Enter Contract Title and Locaiton Here)
Schedule of Prices
List of Contact Personnel
Construction Schedule of Military Real Property (If Applicable)
A C T I V I T Y
N O
T R A N S M I T T A L
N O
(d)
DESCRIPTION ITEM SUBMITTED
SD-11 CLOSEOUT SUBMITTALS
SD-11 CLOSEOUT SUBMITTALS
Interim DD1354, Transfer & Acceptance
SD-11 CLOSEOUT SUBMITTALS
Submittal Register
Complete Submittal Package
Backflow Preventer Tests (If Applicable)
SD-07 CERTIFICATES
Third Party Certification of Barge-
Mounted Movile Cranes
Confined Space Entry Permit
Approving AuthorityContractor Schedule Dates
Contractor Action
1.3
01 57 19
1.6.1
1.6.4
1.7.2
1.7
1.7
PAGE 1 OF _
Backflow Preventers Certificate (If Applicable)
SUBMITTAL FORM, JAN 96 PREVIOUS EDITION OBSOLETE
MSDS for Class I ODS Waivered Product
SD-01 PRECONSTRUCTION SUBMITTALS
Permit for Storm Water Discharge (If applicable)
Environmental Protection Plan
Preconstruction Survey
Notice of Intent (If applicable)
Backflow Tester Certification (If Applicable)