This is a Submittal Register form template used in federal construction contracts to track and manage contractor submittals throughout project execution. The document serves as a comprehensive log for all required submissions, including preconstruction documents, test reports, certificates, product data, and closeout materials.

The register tracks submissions across multiple categories referenced by specification sections and paragraph numbers. Preconstruction submittals (SD-01) include the Accident Prevention Plan, Quality Control Plan, Activity Hazard Analysis, Construction Schedule, Equipment Delivery Schedule, and crane-related documentation such as Critical Lift Plans and Work Plans. Environmental submittals include Environmental Protection Plans, Preconstruction Surveys, and Storm Water Discharge Permits. The form also documents Test Reports (SD-06) for backflow preventers and certificates (SD-07) including confined space entry permits and third-party certifications for barge-mounted mobile cranes. Product Data (SD-03) submissions cover items such as backflow preventers. Closeout submittals (SD-11) include the Submittal Register, Complete Submittal Package, Quality Control Plan, and interim DD Form 1354 for transfer and acceptance. The form provides columns for tracking action codes, submission dates, approval needed dates, material needed dates, transmission dates to and from approving authorities and other reviewers, and remarks. This template enables systematic management of contractor compliance with federal construction contract requirements throughout all project phases.

View the file

Other files

File Type Posted
Amend 0005.pdf PDF
Amend 0004.pdf PDF
Amend 0003.pdf PDF
Amend 0002.pdf PDF
Amend 0001.pdf PDF
Contractor Environmental Guide Updated Format_20231009 with ESOP.pdf PDF
26M069CN Mutiple Location BEQ Exterior Spalling Repairs SOW.pdf PDF
Combined DIV 01 DBB SPECS.pdf PDF
RFP 260417.pdf PDF
Typical Spalling Repairs Details.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT NO.

CONTRACTOR

SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

01 20 00

1.3

01 30 00

1.4.1

01 31 50

1.2

01 32 16

1.2

1.3

01 33 00

1.4.1

1.6.1

01 35 29

1.9

1.10

1.9.1

1.9.1

1.7.1.4

1.14

1.14.1

1.14.3

1.14.4

1.14.5

1.11

1.14.6

1.14.7

01 45 10

1.6

01 50 00

1.6.2.1

2.1

3.1

SD-03 PRODUCT DATA

Backflow Preventers (If Applicable)

SD-06 TEST REPORTS

SD-07 CERTIFICATES

SD-01 PRECONSTRUCTION SUBMITTALS

Traffic Control Plan (If Applicable)

Crane Critical Lift Plan (If Applicable)

Crane Operators (If Applicable)

Reports

Accident Reports

Monthly Exposure Reports

Regulatory Citations and Violations

Crane Reports

(Enter Contract No. Here)

SD-01 PRECONSTRUCTION SUBMITTALS

Accident Prevention Plan (APP)

SD-01 PRECONSTRUCTION SUBMITTALS

Equipment Delivery Schedule

SD-01 PRECONSTRUCTION SUBMITTALS

SUBMITTAL REGISTER

P A R A G R A P H

N O

S P E C

S E C T

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W R

(Enter Contractor Name Here)

Qaulity Control Plan (QC Plan)

Crane Work Plan (If Applicable)

Activity Hazard Analysis (AHA)

SD-06 TEST REPORTS

Certificate of Compliance

SD-01 PRECONSTRUCTION SUBMITTALS

TITLE AND LOCATION

(Enter Contract Title and Locaiton Here)

Schedule of Prices

List of Contact Personnel

Construction Schedule of Military Real Property (If Applicable)

A C T I V I T Y

N O

T R A N S M I T T A L

N O

(d)

DESCRIPTION ITEM SUBMITTED

SD-11 CLOSEOUT SUBMITTALS

SD-11 CLOSEOUT SUBMITTALS

Interim DD1354, Transfer & Acceptance

SD-11 CLOSEOUT SUBMITTALS

Submittal Register

Complete Submittal Package

Backflow Preventer Tests (If Applicable)

SD-07 CERTIFICATES

Third Party Certification of Barge-

Mounted Movile Cranes

Confined Space Entry Permit

Approving AuthorityContractor Schedule Dates

Contractor Action

1.3

01 57 19

1.6.1

1.6.4

1.7.2

1.7

1.7

PAGE 1 OF _

Backflow Preventers Certificate (If Applicable)

SUBMITTAL FORM, JAN 96 PREVIOUS EDITION OBSOLETE

MSDS for Class I ODS Waivered Product

SD-01 PRECONSTRUCTION SUBMITTALS

Permit for Storm Water Discharge (If applicable)

Environmental Protection Plan

Preconstruction Survey

Notice of Intent (If applicable)

Backflow Tester Certification (If Applicable)