This is a Statement of Work (SOW) for concrete spalling repair and protective coating application at multiple Bachelor Enlisted Quarters (BEQ) facilities. The project, titled "Multiple Location BEQ Exterior Spalling Repairs" (Project Number 26M069CN), was issued on March 10, 2026, and is designated for Department of Defense (DoW) community distribution only.
The contractor must provide comprehensive concrete spalling repairs and apply a protective coating system to exterior walkways, stems, balconies, and related structures across six buildings (HP195, M430, M435, BB260, BB265, and BB270). Work includes surface preparation and demolition of unsound concrete; treatment of exposed reinforcing steel with anti-corrosion coating; repair of spalls at walkway undersides, cantilever stems, railing mount points, and balcony edges; and application of a complete protective coating system to all surfaces (top, front, and bottom). The concrete repair product must be epoxy-based with minimum compressive strength of 13,000 PSI, flexural strength of 5,500 PSI, and non-shrinking properties (2,700 PSI). The protective coating system must be epoxy, acrylic, or urethane-based, formulated for exterior balcony and walkway applications, elastomeric, UV stable, water resistant, and vapor permeable, with a grey color, anti-skid additive on walking surfaces, and minimum 13 dry MILS applied thickness. Approximate quantities across all buildings total 360 cubic feet of spalling repair (under walkways, stems, and rail mounts), 1,240 linear feet of balcony edge repair, and 108,000 square feet of protective coating application. The contractor must coordinate with designated points of contact for each building, manage all permits and utility clearances, sequence operations to minimize disruption to occupied facilities, repair any incidentally damaged surfaces at no additional cost, and be solely responsible for legal removal and disposal of all construction debris.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DISTRIBUTION: DoW COMMUNITY ONLY
STATEMENT OF WORK
1.0 Project Identification
Project Title: Multiple Location BEQ Exterior Spalling Repairs
Project Number: 26M069CN
Date Issued: March 10, 2026
2.0 General Scope of Work
The Contractor shall provide all labor, material, equipment, and supervision necessary to perform comprehensive concrete spalling repairs and apply a new protective coating system to exterior walkways, stems, and balconies for the Bachelor Enlisted Quarters (BEQ) facilities listed herein.
3.0 Detailed Requirements
The Contractor shall perform the following work for all buildings identified in Section 5.0:
3.1 Surface Preparation & Demolition
• Remove all unsound, loose, or cracked concrete from cantilevered walkways and decks.
3.2 Concrete Repair
• Treat all exposed reinforcing steel with an appropriate anti-corrosion coating prior to patching.
• Repair spalls to a sound and uniform surface at the following locations:
• Underneath walkways
• Cantilever stems
• Railing mount points
• Balcony and walkway edges
3.3 Protective Coating System
• Apply a complete protective coating system to the entire surface area (top, front, and bottom) of all walkways, cantilever stems, and stairwell balconies. The intent is to coat all surfaces, not just patched areas.
• Incorporate a non-slip additive into the coating on all walking surfaces.
3.4 Submittals
• The Contractor shall submit manufacturer product data and specifications for all proposed repair and coating materials for Government approval prior to procurement or use.
4.0 Technical Specifications
4.1 Concrete Repair Product: Minimum Performance Criteria
• Product Type: Epoxy-Based
• Compressive Strength: 13,000 PSI
• Flexural Strength: 5,500 PSI
• Shrinkage Properties: Non-Shrinking (2,700 PSI)
4.2 Protective Coating System: Minimum Performance Criteria
• Product Type: Epoxy, Acrylic, or Urethane based
• Suitability: Formulated for exterior balcony and walkway applications
• Performance: Elastomeric, UV Stable, Water Resistant, and Vapor Permeable
• Finish:
• Color: Grey
• Texture: Anti-skid additive on all walking surfaces
• Applied Thickness: Minimum of 13 Dry MILS
5.0 Schedule of Work: Locations and Approximate Quantities
The Contractor is responsible for field-verifying all quantities prior to bidding. The quantities listed below are for estimating purposes only.
Building Task Description Approx. Quantity
HP195 Spalling Repair: Under Walkways, Stems & Rail Mounts 60 CF (Total)
Spalling Repair: Balcony Edge 100 LF
Apply Protective Coating System 18,000 SF¹
M430 Spalling Repair: Under Walkways, Stems & Rail Mounts 60 CF (Total)
Spalling Repair: Balcony Edge 420 LF
M435 Spalling Repair: Under Walkways, Stems & Rail Mounts 60 CF (Total)
Spalling Repair: Balcony Edge 420 LF
BB260 Spalling Repair: Under Walkways, Stems & Rail Mounts 60 CF (Total)
BB265 Spalling Repair: Under Walkways, Stems & Rail Mounts 60 CF (Total)
BB270 Spalling Repair: Under Walkways, Stems & Rail Mounts 60 CF (Total)
6.0 Site Conditions and Administration
6.1 Points of Contact for Site Access & Coordination
The Contractor shall coordinate all site access and work schedules with the following personnel:
• HP195, BB265: Chuck Callahan | 910-451-8070 | charles.p.callahan@usmc.mil
• M430, M435: Aaron Green | 910-450-0839 | aaron.green@usmc.mil
• BB260: Casey Barnes | 910-440-0713 | casey.m.barnes.civ@socom.mil
• BB270: Daniel Tritt | 910-376-0784 | daniel.a.tritt@uscg.mil
6.2 Special Conditions
• All buildings will remain occupied throughout the construction period. The Contractor must sequence operations to minimize disruption to facility occupants and coordinate activities with the designated POC for each building.
6.3 General Notes
• Permits: The Contractor shall be responsible for securing all required permits and utility clearances.
• Incidental Damage: Any surfaces damaged by the Contractor during the execution of this work shall be repaired or refinished to a condition matching the adjacent, undisturbed surfaces, at no additional cost to the Government.
• Debris Management: The Contractor shall be solely responsible for the legal removal, transport, and disposal of all construction debris. Use of Government-provided dumpsters is strictly prohibited.