26-598-IFB_Risk_Assessment_Form_Complete_03192026.xlsx
XLSX spreadsheet 26 KB Posted
- Attached to
- Passenger Boarding Ramps
- Solicitation number
- 26-598-IFB
- Issued by
- Orange County, Orlando City, Florida
About this file
This is a Risk Assessment Form for Insurance Requirements completed by the Greater Orlando Aviation Authority (GOAA) Purchasing Section for a passenger boarding ramps procurement. The solicitation number is 26-598-IFB, classified as a one-time purchase with a standard purchase order. The brief scope involves procuring passenger boarding ramps for the Orlando International Airport (MCO). The estimated award amount is $550,000, with an estimated publication date of March 22, 2022. The contractor work will be performed on airside property. A pre-bid meeting was scheduled for July 19, 2017, with the solicitation package released on the street for a 30-day period from July 17 to August 16, 2017. The Notice of Intent to Award was issued on November 11, 2017, followed by contract award finalization spanning from December 5, 2017 to January 11, 2018. The Notice to Proceed was issued on January 3, 2018. The RFP procurement plan indicates this is a recurring contract with no specific expiration date provided in the assessment form.
Risk Management assessed and established comprehensive insurance requirements for the contract, including Commercial General Liability coverage of $1,000,000 per occurrence for non-AOA access areas and $5,000,000 per occurrence for AOA access at OIA; Other Auto Liability at the same coverage limits; Workers Compensation at Florida Statutory Limits with Employers Liability of $100,000/$100,000/$500,000; and Professional Liability of $1,000,000 per claim. The risk assessment was completed by Jill Overstreet on March 18, 2022, with the form returned to Purchasing for data upload into the COI tracking system. The assessment confirmed that the agreement matched the insurance requirements in Phase 1, and Additional Insured status was required. A Certificate of Insurance was to be received and reviewed prior to contract execution.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Risk Assessment Form RISK ASSESSMENT FOR INSURANCE REQUIREMENTS - Purchasing
Section I: To Be Completed by Purchasing
| Dorie Yepez | 3/10/22 | Date Submitted |
| Purchasing Agent (Requestor) |
| Passenger Boarding Ramps (one-time purchase; Standard PO) | 26-598-IFB |
| Brief Description of Services | Solicitation # |
N Will Contractor or its sub, agent, or rep occupy, rent, or maintain GOAA property? $550,000 Estimated Award Amount
Where will contractor perform work? 3/22/22 Estimated Publish Date
____ Landside or __X__ Airside or ____ Both
| N | Contract includes current insurance template from Risk Mgmt. | Detailed Scope of Services must be attached | |
| If no, attach proposed language. | Previous Risk Assessment (if applicable) must be attached |
| Section II: To Be Completed by Risk Management | |
| Risk Only: | |
| Phase 1: Risk Assessment & Insurance Requirements | Phase 2: Review of Insurance Language in Solicitation |
3/10/22 Date Received Date Final Solicitation Reviewed
| Commercial General Liability | Y / N | Agreement matches Ins. Reqmts in Phase 1 | ||
| X | $1,000,000 each occurrence - Non-AOA access/OEA | Y / N | Template Insurance Language being used |
| $5,000,000 each occurrence - AOA access @ OIA | Risk Type Based on Final Review |
| (specify reason for change) | |
| - Other |
| Auto Liability | ||||
| X | $1,000,000 each occurrence - Non-AOA access/OEA | |||
| Assessment performed by | Date | |||
| $5,000,000 each occurrence - AOA access @ OIA | ||||
| Comments/Notes: | ||||
| - Other |
| Workers Compensation & Employers Liability | ||
| X | WC: Florida Statutory Limits |
X EL: $100k/$100k/$500k
- Other
| Professional Liability | Phase 3: Review of Certificate of Insurance | ||
| X | $1,000,000 - each claim |
Cyber/Privacy Liability Date COI Received
| Date of Notice of Award | |||
| Environmental/Pollution Liability | |||
| Y / N | COI matches Phase 1 Ins. Reqmts |
Other Coverages Required: Y / N Additional Insured
| Y / N | Acceptable SIR/DED | ||
| P04A | Risk Type based on Initial Assessment | ||
| Y / N | Modifications | ||
| If yes, attach completed form |
| Jill Overstreet | ||
| Risk Mgmt. Risk Assessment Performed By | Risk Management Review of COI By |
| 3/18/22 | |
| Date Returned to Purchasing | Date Returned to Purchasing for data upload into COI tracking system |
RM Form # 1130_P v.12.2020
RFP Timeline
| ID | Task | Duration | Start | Finish |
| 1 | Project Name | 304 | Tue 03/14/17 | Fri 01/12/18 |
| 2 | Spec Received from AAR | 37 | Thu 04/20/17 | Sat 05/27/17 |
| 3 | Board Notification | 0 | Tue 04/18/17 | Tue 04/18/17 |
| 4 | Pre-Document Review | 45 | Tue 05/30/17 | Fri 07/14/17 |
| 5 | Risk Assessment by Risk Manger | 5 | Thu 06/01/17 | Tue 06/06/17 |
| 6 | MWBE/LDB Review by SBO | 5 | Thu 06/01/17 | Tue 06/06/17 |
| 7 | Spec Review by SPA | 7 | Wed 06/07/17 | Wed 06/14/17 |
| 8 | Prepare Solicitation Documents | 3 | Wed 06/14/17 | Sat 06/17/17 |
| 9 | Item No. Review for Pricing Pg | 3 | Sat 06/17/17 | Tue 06/20/17 |
| 10 | Purchasing Manager Review | 5 | Sat 06/17/17 | Thu 06/22/17 |
| 11 | Legal Review | 7 | Fri 06/23/17 | Fri 06/30/17 |
| 12 | Finalize Solicitation Documents | 7 | Sat 07/01/17 | Sat 07/08/17 |
| 13 | Customer Finalization and Approval | 7 | Sat 07/08/17 | Sat 07/15/17 |
| 14 | Advertisement Period | 2 | Thu 07/13/17 | Sat 07/15/17 |
| 15 | Bid/Proposal Release Notification | 0 | Fri 07/14/17 | Fri 07/14/17 |
| 16 | Solicitation Package on Street | 30 | Mon 07/17/17 | Wed 08/16/17 |
| 17 | On Street | 30 | Mon 07/17/17 | Wed 08/16/17 |
| 18 | Pre-Bid/Proposal Meeting | 0 | Wed 07/19/17 | Wed 07/19/17 |
| 19 | Addendum | 3 | Wed 07/26/17 | Sat 07/29/17 |
| 20 | Solicitation Opening | 0 | Wed 08/16/17 | Wed 08/16/17 |
| 21 | Evaluation Period | 85 | Wed 08/16/17 | Thu 11/09/17 |
| 22 | Document Review | 5 | Thu 08/17/17 | Tue 08/22/17 |
| 23 | MWBE/LDB Review by SBO | 5 | Thu 06/01/17 | Tue 06/06/17 |
| 24 | Reference Check | 12 | Thu 08/17/17 | Tue 08/29/17 |
| 25 | Staff Review Meeting | 0 | Tue 08/29/17 | Tue 08/29/17 |
| 26 | Prepare Matrix | 7 | Wed 08/30/17 | Wed 09/06/17 |
| 27 | Staff Review Final Meeting | 0 | Wed 09/06/17 | Wed 09/06/17 |
| 28 | Prepare CPC Memo | 7 | Thu 09/07/17 | Thu 09/14/17 |
| 29 | Draft Agenda Review | 7 | Fri 09/08/17 | Fri 09/15/17 |
| 30 | CPC Committee Meeting | 0 | Tue 10/03/17 | Tue 10/03/17 |
| 31 | 5 day wait | 7 | Wed 10/04/17 | Wed 10/11/17 |
| 32 | CPC Meeting/Shortlist/Interviews | 0 | Tue 10/10/17 | Tue 10/10/17 |
| 33 | Notice of Intent to Award Issued | 0 | Sat 11/11/17 | Sat 11/11/17 |
| 34 | Await Board Meeting | 29 | Wed 10/11/17 | Thu 11/09/17 |
| 35 | GOAA Board Meeting | 0 | Thu 11/09/17 | Thu 11/09/17 |
| 36 | Contract Award Finalization | 37 | Tue 12/05/17 | Thu 01/11/18 |
| 37 | Vendor Contract Submittal Time | 14 | Sat 11/11/17 | Sat 11/25/17 |
| 38 | New Vendor Set Up | 3 | Sat 11/11/17 | Tue 11/14/17 |
| 39 | COI Review by Risk Manager | 3 | Tue 11/28/17 | Fri 12/01/17 |
| 40 | Legal Review | 7 | Fri 12/01/17 | Fri 12/08/17 |
| 41 | Chief Financial Officer Review | 7 | Fri 12/08/17 | Fri 12/15/17 |
| 42 | Contract Execution by CEO | 7 | Fri 12/15/17 | Fri 12/22/17 |
| 43 | Pre Performance Contract Meeting | 0 | Wed 01/03/18 | Wed 01/03/18 |
| 44 | Notice to Proceed Issued | 0 | Wed 01/03/18 | Wed 01/03/18 |
| 45 | Post Notification of Executed Award | 0 | Wed 01/03/18 | Wed 01/03/18 |
| 46 | Create Contract Header | 7 | Wed 01/03/18 | Wed 01/10/18 |
| 47 | Contract Filing | 1 | Thu 01/11/18 | Fri 01/12/18 |
RFP PROCUREMENT PLAN
Solicitation Number: PXX-23 MWBE: Directed/Participation/None Recurring Contract: Yes/No SPA: Department: Replace Expiring Contract: PIF Rec'd: Est. Cost.:$ Expires:
Spec Rev'd/ Due: Contract Start Date: