This document contains construction drawings and specifications for the Runway 18L/36R Tunnel Rehabilitation & Safety Improvements project managed by the Kenton County Airport Board at Cincinnati/Northern Kentucky International Airport in Boone County, Kentucky. The project scope encompasses comprehensive tunnel rehabilitation including concrete slab, wall, and soffit repairs totaling 8,000 square feet; expansion joint and sealant replacement; waterproofing installation; pavement and sidewalk replacement; drainage and storm sewer improvements; LED lighting system upgrades with 404 new fixtures and controls; electrical distribution and emergency power replacement; ventilation system upgrades including replacement of four 65,000 cfm axial fans with variable frequency drives and new unit heaters; and fire protection, fire alarm, security, and technology system enhancements. The tunnel spans stations 85+00 to 107+30. A mandatory pre-proposal meeting and site visit is scheduled for August 19, 2026 at 1:00 p.m. at CVG Centre in Erlanger, Kentucky. Questions must be submitted by August 24, 2026 at 11:59 p.m. ET with answers posted by August 28, 2026. Two proposal deadline options are presented: September 3, 2026 at 2:00 p.m. ET or September 17, 2026 at 2:00 p.m. ET, depending on which addendum applies. The contractor must commence work within 10 days of Notice to Proceed and achieve substantial completion within 120 days with final closeout within 30 days; an outside completion date of October 30, 2027 applies. Bids remain valid for 120 days after opening, and contract award is expected within 120 days of bid opening.

The project is federally funded through the Airport Improvement Program and subject to Buy American requirements for steel and manufactured goods under 49 USC 50101, with bidders required to submit Buy American certifications selecting one of three compliance pathways or requesting Type 3 or Type 4 waivers if unable to meet 100% compliance. Prevailing wage requirements apply under the Davis-Bacon Act with wage determination KY20260039 effective May 18, 2026, establishing rates for electricians ($38.05 base with $22.97 fringe), plumbers ($43.30 with $27.40 fringe), and equipment operators ($36.34–$45.14 with $16.41 fringe). Executive Order 13706 requires paid sick leave of one hour per 30 hours worked, and Executive Order 13658 establishes a minimum wage of $13.65 per hour through December 31, 2026. Bidders must comply with 49 CFR Part 26 regarding Disadvantaged Business Enterprise participation through good faith efforts and submit a subcontractor and DBE list. Required bonds include a proposal bond of at least 5% of the total bid amount and performance and payment bonds of 100% of the contract amount from a surety rated "A" or better by Best Insurance Reports and authorized in Kentucky. Liquidated damages apply for failure to meet project deadlines. The project was budgeted at $4.3 million for design and construction, with mobilization costs limited to 10% of total project cost. All work is guaranteed for one year from Final Acceptance. Work must comply with Kentucky Transportation Cabinet standards and FAA Advisory Circular 150/5370-2, with airfield access restricted to scheduled monthly maintenance periods when the runway is closed.

View the file

Other files

File Type Posted
Runway_18L_36R_Tunnel_Rehabilitation_&_Safety_Improvements_(Addendum_#5_Revision).pdf PDF
26-045_ITB_18L-36R_Tunnel_Rehab_&_Safety_Improvements_-_Technical_Specs_9.15.26.pdf PDF
Runway_18L_36R_Tunnel_Rehabilitation_&_Safety_Improvements.pdf PDF
26-045-ITB_Drawings_-_8.5.26.pdf PDF
26-045-ITB_Technical_Specs.pdf PDF
26-045-ITB_-_Exhibit_A_-_Proposal_Forms_(AIP).pdf PDF
Wage_Rate_Schedule_-_Boone_County_KY_Highway.pdf PDF
25-045-ITB_Tunnel_Rehab_&_Safety_Improv_-_Exhibit_B_-_Contract_&_Bonds.pdf PDF
26-16_South_Airfield_Tunnel_-_Construction.pdf PDF
Affidavit_Regarding_Worker's_Compensation.docx DOCX document
Subcontractor_List.docx DOCX document
EEO_Certification.docx DOCX document
Proposal_Form.docx DOCX document
Affirmative_Action_Certification.docx DOCX document
Non_Debarment_or_Suspension_Certification.docx DOCX document
Safety_Evaluation_and_Plans.docx DOCX document
Proposal_Bond.docx DOCX document
NonSegregated_Facilities_Certification.docx DOCX document
Bidder's_Qualifications.docx DOCX document
Certification_of_Offeror-Bidder_Regarding_Tax_Delinquency_and_Felony_Convictions.docx DOCX document
DBE_List.docx DOCX document
Disclosure_of_Lobbying_Activities_Certification.docx DOCX document
Buy_American_Certification-Equipment-Building_Projects.docx DOCX document
Buy_American_Certification-Construction_Projects.docx DOCX document
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .