This is a Submittal Register template used to track contractor submissions throughout a construction contract lifecycle. The document serves as a control mechanism for managing all required submittals from the contractor to the approving authority, documenting submission dates, approval timelines, and review status.
The register tracks submittals across multiple construction phases and disciplines, including preconstruction items (SD-01), shop drawings (SD-02), product data (SD-03), samples (SD-04), test reports (SD-06), and certificates (SD-07), as well as closeout submittals (SD-11). Preconstruction submittals include schedule of prices, contact personnel lists, construction schedules, equipment delivery schedules, accident prevention plans, activity hazard analyses, and safety-related documents such as crane work plans and confined space entry permits. Shop drawing and product data submittals cover framing components, studs, doors, accessories, and backflow preventers. The register requires tracking of approval needed dates, material needed dates, action codes, dates forwarded to approving authority and other reviewers, and dates received from contractors and reviewers. The template includes columns for remarks and provides specification section numbers and classification codes (marked with "G" designation) for cross-reference with contract specifications. This form is designed to ensure compliance with contractual submittal requirements and maintain clear documentation of the review and approval process throughout the contract execution.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MAXIMO.pdf | ||
| 26-0402- SOW.pdf | ||
| 26-0402- PROJECT DESCRIPTION.pdf | ||
| Contractor Environmental Guide.pdf | ||
| Combined DIV 01 specs small projects.pdf | ||
| RFP 260402.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT NO.
CONTRACTOR
SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
01 20 00
1.3
01 30 00
1.4.1
01 31 50
1.2
01 32 16
1.2
1.3
01 33 00
1.4.1
1.6.1
01 35 29
1.9
1.10
1.9.1
1.9.1
1.7.1.4
1.14
1.14.1
1.14.3
1.14.4
1.14.5 Crane Reports
Approving Authority Contractor
Schedule Dates
SD-11 CLOSEOUT SUBMITTALS
Interim DD1354, Transfer & Acceptance
SD-11 CLOSEOUT SUBMITTALS
Submittal Register
Complete Submittal Package
TITLE AND LOCATION
(Enter Contract Title and Locaiton Here)
Schedule of Prices
List of Contact Personnel
Construction Schedule of Military Real Property (If Applicable)
A C T I V I T Y
N O
T R A N S M I T T A L
N O
(d)
Contractor Action
DESCRIPTION
ITEM SUBMITTED
(Enter Contractor Name Here)
Crane Work Plan (If Applicable)
Activity Hazard Analysis (AHA)
SD-06 TEST REPORTS
SD-01 PRECONSTRUCTION SUBMITTALS
(Enter Contract No. Here)
SD-01 PRECONSTRUCTION SUBMITTALS
Accident Prevention Plan (APP)
SD-01 PRECONSTRUCTION SUBMITTALS
Equipment Delivery Schedule
SD-01 PRECONSTRUCTION SUBMITTALS
SUBMITTAL REGISTER
P A R A G R A P H
N O
S P E C
S E C T
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W R
Crane Critical Lift Plan (If Applicable)
Crane Operators (If Applicable)
Reports
Accident Reports
Monthly Exposure Reports
Regulatory Citations and Violations
1.11
1.14.6
1.14.7
01 45 10
1.6
01 50 00
1.6.2.1
2.1
3.1
1.3
01 57 19
1.6.1
1.6.4
1.7.2
1.7
1.7
PAGE 1 OF _
05 40 00 1.6.1
2.1
08 11 13
2.5
2.3
08 14 00
2.1 G
2.1 G
2.2
2.3.7
Frames
SD-07 CERTIFICATES
Third Party Certification of Barge-
Mounted Movile Cranes
Confined Space Entry Permit
SD-02 Shop Drawings: Framing components
SD-03 Product Data studs
SD-02 Shop Drawings
SD-11 CLOSEOUT SUBMITTALS
Qaulity Control Plan (QC Plan)
Certificate of Compliance
Backflow Tester Certification (If Applicable)
Backflow Preventer Tests (If Applicable)
SD-01 PRECONSTRUCTION SUBMITTALS
Traffic Control Plan (If Applicable)
SUBMITTAL FORM, JAN 96 PREVIOUS EDITION OBSOLETE
MSDS for Class I ODS Waivered Product
SD-01 PRECONSTRUCTION SUBMITTALS
Permit for Storm Water Discharge (If applicable)
Environmental Protection Plan
Preconstruction Survey
Notice of Intent (If applicable)
Accessories
SD-02 Shop Drawings
Doors
SD-03 Product Data
Doors
SD-03 PRODUCT DATA
Backflow Preventers (If Applicable)
Backflow Preventers Certificate (If Applicable)
SD-06 TEST REPORTS
SD-07 CERTIFICATES
Accessories
Water Resistant Sealer
1.5
2.1.3 G
2.1
2.3.6.4 G
2.4
1.3.1
1.5
Warranty
Sound Transmission Class Rating
SD-04 Samples
Doors
Door Finish Colors
SD-06 Test Reports
Cycle-Slam
SD-07 Certificates
Certificates of Grade
SD-11 Closeout Submittals
Warranty
File details come from the government source that posted it. Updated .