26-0402- PROJECT DESCRIPTION.pdf

PDF 46 KB Posted

Attached to
Building 2600 and Building 11 New Wall/Door
Solicitation number
N4008526R9025
Issued by

About this file

This document is a Project Description for a Department of Defense construction project at Camp Lejeune, North Carolina. The scope of work involves the installation of new doors and walls at two buildings: Building 2600 located on Charles Street and Building 11 located on Post Lane, both at Camp Lejeune. The work is intended to accommodate the tenants occupying these facilities.

The project requires that the facility remain operational throughout the entire construction period, with the contractor obligated to minimize disruption to normal operations. The contractor's supervision structure permits a single individual to serve concurrently as the Superintendent, Quality Control Manager, and Safety & Health Officer, provided that person meets all qualifications as defined in the project specification. This document is distributed for DoD community use only and establishes the foundational parameters for contractor performance on this facility improvement project.

View the file

Other files

File Type Posted
RFP 260402.pdf PDF
Contractor Environmental Guide.pdf PDF
Combined DIV 01 specs small projects.pdf PDF
MAXIMO.pdf PDF
26-0402- SUBMITTAL REGISTRY.pdf PDF
26-0402- SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DISTRIBUTION: DoD COMMUNITY ONLY

PROJECT DESCRIPTION

This scope of work is to be accomplished at Building 2600 located on Charles St. aboard, Camp Lejeune, North Carolina & Building 11 located on Post Ln. aboard, Camp Lejeune, North Carolina. The work includes installation of new door and wall for the tenants of both bldgs 2600 & 11.

SPECIAL SCHEDULING

The facility/activity will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the facility/activity.

SUPERVISION

One person may fill the roles of Superintendent, Quality Control Manager, and Safety & Health Officer, if duly qualified for all three positions as defined in the project specification.