This is a Submittal Register form used in federal construction contracts to track and manage contractor submissions throughout a project lifecycle. The document serves as a comprehensive checklist for monitoring preconstruction submittals, test reports, certificates, and closeout documentation required from the contractor.

The register identifies required submittals organized by contract line item numbers and specification sections, including preconstruction items such as Schedule of Prices, List of Contact Personnel, Construction Schedule, Accident Prevention Plan, Activity Hazard Analysis, Equipment Delivery Schedule, and Traffic Control Plan. Additional preconstruction submittals include crane-related documents (Critical Lift Plan, Work Plan, Operator certifications), environmental protection plans, preconstruction surveys, permits for storm water discharge, and Notices of Intent. The form tracks product data submittals for backflow preventers and requires test reports including backflow preventer tests and various safety reports (Accident Reports, Monthly Exposure Reports, Regulatory Citations and Violations, and Crane Reports). Certificates required include Confined Space Entry Permits, Backflow Tester Certifications, Third Party Certifications of Barge-Mounted Mobile Cranes, and Certificates of Compliance. Closeout submittals include interim DD1354 transfer and acceptance forms, submittal registers, and complete submittal packages with Quality Control Plans. The register provides columns for tracking approval needs, material delivery dates, contractor action dates, and approval authority sign-offs to ensure systematic documentation and timely completion of all contractual deliverables.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT NO.

CONTRACTOR

SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

01 20 00

1.3

01 30 00

1.4.1

01 31 50

1.2

01 32 16

1.2

1.3

01 33 00

1.4.1

1.6.1

01 35 29

1.9

1.10

1.9.1

1.9.1

1.7.1.4

1.14

1.14.1

1.14.3

1.14.4

1.14.5

1.11

Crane Reports

SD-07 CERTIFICATES

Confined Space Entry Permit

Approving AuthorityContractor Schedule Dates

SD-11 CLOSEOUT SUBMITTALS

Interim DD1354, Transfer & Acceptance

SD-11 CLOSEOUT SUBMITTALS

Submittal Register

Complete Submittal Package

TITLE AND LOCATION

(Enter Contract Title and Locaiton Here)

Schedule of Prices

List of Contact Personnel

Construction Schedule of Military Real Property (If Applicable)

A C T I V I T Y

N O

T R A N S M I T T A L

N O

(d)

Contractor Action

DESCRIPTION

ITEM SUBMITTED

(Enter Contractor Name Here)

Crane Work Plan (If Applicable)

Activity Hazard Analysis (AHA)

SD-06 TEST REPORTS

SD-01 PRECONSTRUCTION SUBMITTALS

(Enter Contract No. Here)

SD-01 PRECONSTRUCTION SUBMITTALS

Accident Prevention Plan (APP)

SD-01 PRECONSTRUCTION SUBMITTALS

Equipment Delivery Schedule

SD-01 PRECONSTRUCTION SUBMITTALS

SUBMITTAL REGISTER

P A R A G R A P H

N O

S P E C

S E C T

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W R

Crane Critical Lift Plan (If Applicable)

Crane Operators (If Applicable)

Reports

Accident Reports

Monthly Exposure Reports

Regulatory Citations and Violations

1.14.6

1.14.7

01 45 10

1.6

01 50 00

1.6.2.1

2.1

3.1

1.3

01 57 19

1.6.1

1.6.4

1.7.2

1.7

1.7

PAGE 1 OF _

Third Party Certification of Barge-

Mounted Movile Cranes

SD-11 CLOSEOUT SUBMITTALS

Qaulity Control Plan (QC Plan)

Certificate of Compliance

Backflow Tester Certification (If Applicable)

Backflow Preventer Tests (If Applicable)

SD-01 PRECONSTRUCTION SUBMITTALS

Traffic Control Plan (If Applicable)

SUBMITTAL FORM, JAN 96 PREVIOUS EDITION OBSOLETE

MSDS for Class I ODS Waivered Product

SD-01 PRECONSTRUCTION SUBMITTALS

Permit for Storm Water Discharge (If applicab

Environmental Protection Plan

Preconstruction Survey

Notice of Intent (If applicable)

SD-03 PRODUCT DATA

Backflow Preventers (If Applicable)

Backflow Preventers Certificate (If Applicable)

SD-06 TEST REPORTS

SD-07 CERTIFICATES

File details come from the government source that posted it. Updated .