This is a Submittal Register form used in federal construction contracts to track and manage contractor submissions throughout a project lifecycle. The document serves as a comprehensive checklist for monitoring preconstruction submittals, test reports, certificates, and closeout documentation required from the contractor.
The register identifies required submittals organized by contract line item numbers and specification sections, including preconstruction items such as Schedule of Prices, List of Contact Personnel, Construction Schedule, Accident Prevention Plan, Activity Hazard Analysis, Equipment Delivery Schedule, and Traffic Control Plan. Additional preconstruction submittals include crane-related documents (Critical Lift Plan, Work Plan, Operator certifications), environmental protection plans, preconstruction surveys, permits for storm water discharge, and Notices of Intent. The form tracks product data submittals for backflow preventers and requires test reports including backflow preventer tests and various safety reports (Accident Reports, Monthly Exposure Reports, Regulatory Citations and Violations, and Crane Reports). Certificates required include Confined Space Entry Permits, Backflow Tester Certifications, Third Party Certifications of Barge-Mounted Mobile Cranes, and Certificates of Compliance. Closeout submittals include interim DD1354 transfer and acceptance forms, submittal registers, and complete submittal packages with Quality Control Plans. The register provides columns for tracking approval needs, material delivery dates, contractor action dates, and approval authority sign-offs to ensure systematic documentation and timely completion of all contractual deliverables.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT NO.
CONTRACTOR
SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
01 20 00
1.3
01 30 00
1.4.1
01 31 50
1.2
01 32 16
1.2
1.3
01 33 00
1.4.1
1.6.1
01 35 29
1.9
1.10
1.9.1
1.9.1
1.7.1.4
1.14
1.14.1
1.14.3
1.14.4
1.14.5
1.11
Crane Reports
SD-07 CERTIFICATES
Confined Space Entry Permit
Approving AuthorityContractor Schedule Dates
SD-11 CLOSEOUT SUBMITTALS
Interim DD1354, Transfer & Acceptance
SD-11 CLOSEOUT SUBMITTALS
Submittal Register
Complete Submittal Package
TITLE AND LOCATION
(Enter Contract Title and Locaiton Here)
Schedule of Prices
List of Contact Personnel
Construction Schedule of Military Real Property (If Applicable)
A C T I V I T Y
N O
T R A N S M I T T A L
N O
(d)
Contractor Action
DESCRIPTION
ITEM SUBMITTED
(Enter Contractor Name Here)
Crane Work Plan (If Applicable)
Activity Hazard Analysis (AHA)
SD-06 TEST REPORTS
SD-01 PRECONSTRUCTION SUBMITTALS
(Enter Contract No. Here)
SD-01 PRECONSTRUCTION SUBMITTALS
Accident Prevention Plan (APP)
SD-01 PRECONSTRUCTION SUBMITTALS
Equipment Delivery Schedule
SD-01 PRECONSTRUCTION SUBMITTALS
SUBMITTAL REGISTER
P A R A G R A P H
N O
S P E C
S E C T
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W R
Crane Critical Lift Plan (If Applicable)
Crane Operators (If Applicable)
Reports
Accident Reports
Monthly Exposure Reports
Regulatory Citations and Violations
1.14.6
1.14.7
01 45 10
1.6
01 50 00
1.6.2.1
2.1
3.1
1.3
01 57 19
1.6.1
1.6.4
1.7.2
1.7
1.7
PAGE 1 OF _
Third Party Certification of Barge-
Mounted Movile Cranes
SD-11 CLOSEOUT SUBMITTALS
Qaulity Control Plan (QC Plan)
Certificate of Compliance
Backflow Tester Certification (If Applicable)
Backflow Preventer Tests (If Applicable)
SD-01 PRECONSTRUCTION SUBMITTALS
Traffic Control Plan (If Applicable)
SUBMITTAL FORM, JAN 96 PREVIOUS EDITION OBSOLETE
MSDS for Class I ODS Waivered Product
SD-01 PRECONSTRUCTION SUBMITTALS
Permit for Storm Water Discharge (If applicab
Environmental Protection Plan
Preconstruction Survey
Notice of Intent (If applicable)
SD-03 PRODUCT DATA
Backflow Preventers (If Applicable)
Backflow Preventers Certificate (If Applicable)
SD-06 TEST REPORTS
SD-07 CERTIFICATES