25BA017_Techcpec.pdf

PDF 2 MB Posted

Attached to
Yakima Delta 1135 Causeway Removal Federal contract opportunity
Solicitation number
W912EF25BA017
Issued by
Department of the Army Corps of Engineers Engineering District Walla Walla

About this file

This document is a technical specifications file for the Bateman Island Causeway Removal project (Contract No. W912EF25BA017) for the U.S. Army Corps of Engineers Walla Walla District. The project involves removing the causeway connecting Bateman Island to the mainland in the Yakima River, with the primary objectives of restoring natural river flows and improving passage for ESA-listed fish species. The work includes clearing and grubbing, excavation and disposal of causeway material, riprap placement, willow planting, water quality monitoring, and comprehensive environmental protection measures.

Key technical requirements include excavating approximately one foot below design elevation, handling and placing riprap with specific gradation requirements, planting live willow stakes, and implementing strict water quality monitoring protocols. The project has specific in-water work windows between December 2025 and February 2026, with rigorous turbidity control measures mandated to protect water quality. The contract is divided into multiple Contract Line Item Numbers (CLINs) covering different aspects of the work, such as clearing and grubbing, excavation, riprap placement, willow planting, and water quality monitoring, with the U.S. Army Corps of Engineers serving as the contracting agency.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bateman Island Causeway Removal W912EF25BA017

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00.00 28 GENERAL REQUIREMENTS

01 11 01.00 28 SUPPLEMENTARY REQUIREMENTS

01 14 00.10 28 PROJECT SITE RESTRICTIONS

01 14 00.90 28 INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY

(OPSEC)

01 22 00.00 28 MEASUREMENT AND PAYMENT

01 32 16.00 28 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES

01 33 00 SUBMITTAL PROCEDURES

01 35 29.10 28 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 04.00 28 CONTRACTOR QUALITY CONTROL

01 51 00.00 28 TEMPORARY UTILITIES

01 55 10.00 28 CONTRACTOR WORK, ACCESS AND STORAGE AREAS

01 57 20.00 28 ENVIRONMENTAL PROTECTION

01 71 23.01 28 CONTRACTOR SURVEYS AND REMOTE SENSING DATA COLLECTION

DIVISION 02 - EXISTING CONDITIONS

02 24 20.00 28 WATER QUALITY MONITORING

DIVISION 31 - EARTHWORK

31 00 00.00 28 EARTHWORK

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

THIS PAGE INTENTIONALLY LEFT BLANK

PROJECT TABLE OF CONTENTS Page 2

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00.00 28

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section Table of Contents --

SECTION 01 00 00.00 28 Page 1

SECTION 01 00 00.00 28 Page 2

SECTION 01 00 00.00 28

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS

In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS

222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:

Federal Veteran Employment Information https://www.opm.gov/fedshirevets/

Department of Labor Veterans Employment Assistance https://www.dol.gov/agencies/vets

Department of Veterans Affairs-VOW to Hire Heroes Act https://benefits.va.gov/vow/

Army Recovery Care Program https://myarmybenefits.us.army.mil/Benefit-Library/Federal-Benefits/Army-Recovery-Care- Program-(ARCP)-(formerly-known-as-Warrior-Care-and-Transition-Program)

U.S. Chamber of Commerce Foundation-Hiring Our Heroes https://www.hiringourheroes.org/

Guide to Hiring Veterans - Reference Material https://www.dol.gov/sites/dolgov/files/VETS/files/Employer-Guide-to-Hiring- Veterans2025-07.pdf

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section --

SECTION 01 00 00.00 28 Page 3

SECTION 01 00 00.00 28 Page 4

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 01.00 28

SUPPLEMENTARY REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 DEFINITIONS

1.4 DOCUMENT SUBMITTALS

1.5 FIELD VERIFICATION OF SITE CONDITIONS

1.6 PRE-CONSTRUCTION ON-SITE INSPECTION

1.7 REGULAR CLEANUP AND DEBRIS DISPOSAL

1.8 EQUIPMENT LIST

1.9 TESTING OF EQUIPMENT

1.10 DISPOSITION OF REMOVED MATERIALS AND EQUIPMENT

1.11 PROTECTION AND RESTORATION OF EXISTING FACILITIES

1.12 PROJECT SUPERINTENDENT

1.13 KEY PERSONNEL SUBSTITUTION

1.14 POST AWARD MEETINGS

1.14.1 Post-Award Conference

1.14.2 Pre-Construction Meeting

1.14.2.1 Minutes

1.14.3 RMS Orientation Meeting

1.15 WEEKLY PRODUCTION MEETINGS

1.15.1 Production Briefings

1.15.2 Minutes

1.16 ADDITIONAL MEETINGS

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

ATTACHMENTS:

Weekly Meeting Agenda

SECTION 01 11 01.00 28 Page 1

SECTION 01 11 01.00 28 Page 2

SECTION 01 11 01.00 28

SUPPLEMENTARY REQUIREMENTS

PART 1 GENERAL

The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS.

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 Safety and Occupational Health Requirements

Comply with the current edition and all changes posted on the web as of the effective date of this solicitation.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals having an "I" designation are for information only.

Designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Equipment List ; I, C

Pre-Construction On-Site Inspection report ; I, C

Project Superintendent ; I, C

SD-07 Certificates

Key Personnel Substitution ; G, C

1.3 DEFINITIONS

a. Qualified Person.

As defined in EM 385-1-1 ; "DEFINITIONS", unless otherwise specified.

1.4 DOCUMENT SUBMITTALS

In addition to other specified submittal requirements, a copy of all documents submitted as part of work on this contract, shall be e-mailed to the Contracting Officer and submitted in Resident Management System Contractor Mode (RMS CM). Include project contract number, title, and e-mail topic in all e-mail subject lines, per SECTION 01 33 00 1.7.1

SECTION 01 11 01.00 28 Page 3

Digital Copies.

1.5 FIELD VERIFICATION OF SITE CONDITIONS

Field verify all elevations, dimensions, and coordinates of existing features indicated on the contract drawings that affect new construction.

1.6 PRE-CONSTRUCTION ON-SITE INSPECTION

Prepare a Pre-Construction On-Site Inspection report of existing conditions, prior to start of on-site work, with the Contracting Officer.

Document existing site conditions and existing conditions of haul route if using public roads, prior to Construction by digital photographs, and/or videos along with descriptive narrative report to the Contracting Officer within five (5) days after completion.

1.7 REGULAR CLEANUP AND DEBRIS DISPOSAL

With the exception of materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all wastes and demolished materials becomes the property of the Contractor and must be removed from the job site daily in accordance with Federal, State, and local regulations. The Contractor shall furnish waste containers. All small waste containers provided by the contractor must be emptied daily, large bin containers must be emptied when full or once a week.

1.8 EQUIPMENT LIST

Furnish a complete list of all equipment to be used on the worksite 30 days prior to commencement of on-site work. Submit a revised list in the event of change of equipment. Lists shall include rented equipment as well as lease-purchase or sale-leaseback equipment. The initial list and the revised lists shall indicate dates equipment is assigned to or removed from the worksite and adequate identification or description of each item of equipment including manufacturer's name (abbreviated), model number, manufacturer's serial number, year of manufacture, and Contractor's assigned serial or record number.

1.9 TESTING OF EQUIPMENT

Before any machinery or mechanized equipment is put to use on the job, it must be inspected and tested by a qualified person and determined to be in safe operating condition. Cranes or derricks must be tested by the Contractor or a qualified testing agency in accordance with EM 385-1-1 .

Equipment must be large enough to safely handle proposed picks or tasks without exceeding the crane rating established by these tests.

1.10 DISPOSITION OF REMOVED MATERIALS AND EQUIPMENT

Unless otherwise specified in other sections of the specifications, all existing equipment removed and not reinstalled becomes the property of the Contractor, removed from the worksite, and disposed of in a legal manner.

Materials that cannot be removed daily may be temporarily stored on-site at an approved area. Salvaged materials shall not be sold on the worksite.

1.11 PROTECTION AND RESTORATION OF EXISTING FACILITIES

Reference FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984).

SECTION 01 11 01.00 28 Page 4

1.12 PROJECT SUPERINTENDENT

The Contractor's Project Superintendent must be on the worksite during performance of work on this contract. The Project Superintendent is required on the worksite, at all times work is being performed, until work on this contract is completed and accepted. Assign a competent superintendent as per FAR Clause 52.236-6 "Superintendence by the Contractor". Submit Superintendent name and contact information prior to start of on-site construction.

1.13 KEY PERSONNEL SUBSTITUTION

If the Contractor plans on replacing any Key personnel (Project Superintendent, CQC System Manager, or CQC staff Members) they must have the approval of the Contracting Officer. Personnel shall possess the qualifications that meet or exceed those stated in this contract for the position of the individual they are replacing. Submit qualifications of new personnel at least 15 calendar days in advance of date of replacement.

1.14 POST AWARD MEETINGS

1.14.1 Post-Award Conference

Within thirty (30) calendar days after receipt of Notice to Proceed, attend a Post-Award Conference. Senior Level members of the Contractor's staff involved with this contract shall participate in this meeting to discuss the overall contract requirements. The Government will lead this meeting and take the meeting minutes.

1.14.2 Pre-Construction Meeting

Coordinate with the Contracting Officer and establish the date of the Pre-Construction Meeting. The meeting will be held at the worksite at least one (1) week prior to mobilizing to the job site. The Contractor shall lead the Pre-Construction Meeting discussing the Contractor's plan on executing the work at the worksite, schedule, and plan for implementing safety and quality control. The Government will have key members in attendance to discuss environmental and other construction issues. Key members of the contractor staff shall attend this meeting including the Quality Control (QC) System Manager, Site Safety and Health Officer (SSHO) and any other members determined by the Government to be required.

1.14.2.1 Minutes

Contractor is responsible for taking the meeting minutes and shall send them electronically within 48 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer. Include project name and meeting topic in e-mail subject line.

1.14.3 RMS Orientation Meeting

a. Upon the Contractor's request, an RMS (Resident Management System) Orientation Meeting will be held within fifteen (15) calendar days after receipt of Notice to Proceed. See SECTION 01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM) for additional information. The Orientation Meeting will be held at NWW District Headquarters, and may occur in conjunction with, but not at the same time as, the Post-Award Conference. The Orientation Meeting can also

SECTION 01 11 01.00 28 Page 5 occur via video conference. Coordinate meeting date and time with the Contracting Officer a minimum of 7 calendar days prior to the meeting.

b. At a minimum, the Contractor's RMS-CM Administrator and QC system manager shall attend the RMS Orientation meeting. A Government Representative will lead the orientation. Anticipate the following at the meeting:

1. Allow for a maximum 4 hour duration.

2. Cover the following topics, at a minimum, in RMS Contractor Mode (CM):

i. Contractor use of RMS (CM) system.

ii. Contractor Data.

iii. Quality Control Reports.

iv. Submittals.

v. RFIs.

vi. Payment.

3. Receive a follow-up handout/guide for reference on the above items.

c. Contractor employees shall bring a computer with Wi-Fi capability (to gain access to the Internet), with RMS pre-loaded.

d. The RMS Orientation Meeting is required for Contractors with no prior RMS experience. The RMS Orientation Meeting, is optional, but may be requested, for all other Contractors.

e. The purpose of the RMS Orientation Meeting is to facilitate Contractor's use of RMS (CM). It does not relieve the Contractor of the requirement to use RMS (CM) in accordance with the Contract. See

SECTION 01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE

(RMS CM), paragraph RMS SOFTWARE for information related to required download and installation deadlines.

1.15 WEEKLY PRODUCTION MEETINGS

1.15.1 Production Briefings

During all onsite construction work, hold a weekly production meeting to brief the Government on the status of the project.

a. Use the attached "Weekly Meeting Agenda" and discuss all elements of this agenda.

b. Provide a three (3) week 'look ahead'.

1. Describe all planned construction activities, on-site and off-site over the next three (3) weeks.

2. ENSURE these activities align to the overall Construction Schedule submitted under SECTION 01 32 16.00 28 SMALL PROJECT

SECTION 01 11 01.00 28 Page 6

CONSTRUCTION PROGRESS SCHEDULES.

3. RECORD any changes to the Project Schedule AND INCLUDE IN the next scheduled update.

c. Key members of the Contractor's staff including the Quality Control System Manager and the SITE SAFETY AND HEALTH OFFICER shall attend.

d. The Quality Control System Manager shall discuss all QC aspects outlined in SECTION 01 45 04.00 28 CONTRACTOR QUALITY CONTROL.

e. The Government reserves the right to require any person from the Contractor's staff such as the Project Manager, Engineer, Scheduler or Key Subcontractor Personnel to attend the meeting.

1.15.2 Minutes

The Contractor is responsible for taking the meeting minutes and shall send them electronically within 24 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer. Include project name and meeting topic in e-mail subject line.

1.16 ADDITIONAL MEETINGS

Record the minutes of all meetings, including all conference calls, that occur between the Contractor and Government. Send minutes electronically within 24 hours of the meeting to the Contracting Officer for concurrence.

E-mail subject line shall include project name and meeting topic.

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

SECTION 01 11 01.00 28 Page 7

SECTION 01 11 01.00 28 Page 8

Weekly Meeting agenda template

Schedule - Work scheduled over the next week Three week look ahead Overall Schedule Review

Submittals Review- Submittal Register Submittals approved by QC Outstanding Submittals RFI’s Letters

Coordination - Clearances required over the next week, include the following:

A description of the work to be performed under the Clearance.

Determine the correct energy isolation points needed to perform the work safely.

Physical barriers, protective grounds, piping blanks, or bulkheads that shall be used, including locations.

Determine the procedure and method of testing for stored energy if applicable.

The date and time the Clearance shall be required.

The estimated length of time the system or equipment shall be out of service and the time to return the system or equipment to service in an emergency.

Coordination issues

Safety- Review of AHA’s for ongoing work Pending AHA’s

Required for new work Status of Gov’t approval

Safety issues

QC -

Preparatory meetings Held over last week- status of meeting minutes

Required over the next week Initial meetings over the next week Follow up over the next week Rework list Review Deficiency tracking log

SECTION 01 11 01.00 28 Page 9

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 14 00.10 28

PROJECT SITE RESTRICTIONS

PART 1 GENERAL

1.1 SITE CONDITIONS AND OPERATIONAL RESTRICTIONS

1.2 DELIVERY OF EQUIPMENT

1.3 WORK SCHEDULES

1.3.1 Contractor's Work Schedule

1.3.2 Government's Work Schedule

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

SECTION 01 14 00.10 28 Page 1

SECTION 01 14 00.10 28 Page 2

SECTION 01 14 00.10 28

PROJECT SITE RESTRICTIONS

PART 1 GENERAL

1.1 SITE CONDITIONS AND OPERATIONAL RESTRICTIONS

a. In-water work will be limited to the window established in Clause 52.211-10 Commencement, Prosecution, and Completion of Work.

b. Maintain pedestrian access to Wye Park.

1.2 DELIVERY OF EQUIPMENT

The contractor is responsible for delivery and receipt of all materials and equipment. Government personnel will not be available to assist the Contractor in these activities.

1.3 WORK SCHEDULES

1.3.1 Contractor's Work Schedule

At the Post-Award Conference, furnish a schedule of number of working days per week, shifts per day, and hours per shift for contract work. Furnish notification of any change of schedule of regular work hours, overtime work hours, and shifts of work crews and personnel at the site. This notification shall be provided a minimum of 48 hours prior to any schedule change to allow suitable scheduling of Government personnel and inspection. Exception to this requirement may be allowed in case of schedule change due to emergency conditions.

1.3.2 Government's Work Schedule

a. Government personnel typically work from 8:00 a.m. to 5:00 p.m., Monday through Friday. Government personnel do not work on weekends and Federal holidays.

b. If the Contractor requires Government support or assistance outside of normal work hours, the Contractor must make a formal written request to the Contracting Officer at least one week prior to the date that support/assistance is needed. The Government will review this request, but there is no guarantee that Government support or assistance can be provided.

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

SECTION 01 14 00.10 28 Page 3

SECTION 01 14 00.10 28 Page 4

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 14 00.90 28

INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 RESOURCES

1.4 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

SECTION 01 14 00.90 28 Page 1

SECTION 01 14 00.90 28 Page 2

SECTION 01 14 00.90 28

INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)

PART 1 GENERAL

The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS. This contract does not require access to or handling of classified material.

This contract does not require access to secured and restricted areas, sensitive information, or equipment. Secured area is considered any location where on-site work is performed by contractor personnel.

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

FEDERAL ACQUISITION REGULATIONS (FAR)

FAR 52.222-54 Employment Eligibility Verification

FAR 22.18 Employment Eligibility Verification

Website for Federal Acquisition Regulation Supplement:

https://www.acquisition.gov/browse/index/far

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals having an "I" designation are for information only. The designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Pre-Screen Candidates Using E-Verify Program ; G, C

1.3 RESOURCES

The following resources are accessible from the Walla Walla District (NWW) Public Website:

https://www.nww.usace.army.mil/Business-With-Us/Contracting/AT-OPSEC-for-Contractors/

a. E-Verify Program.

1.4 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM

a. Contractors shall comply with the requirements set forth in FAR 52.222-54 Employment Eligibility Verification and FAR 22.18 in using the E-Verify Program to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration

SECTION 01 14 00.90 28 Page 3 laws in accordance with FAR 22.102-1(i). See paragraph RESOURCES for link to the E-Verify website.

b. An initial list of verified/eligible candidates shall be provided to the KO no later than three business days after receipt of Notice to Proceed. Submit pre-screening results to the KO via email as a password protected pdf file.

c. Submit updates to list of verified/eligible candidates within three business days of new verifications. The Contractor shall maintain a current list of verified/eligible employees as part of their contract files and provide copies to the KO upon request.

d. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

SECTION 01 14 00.90 28 Page 4

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 28

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 RETAINAGE OF PAYMENT

1.2 CLIN 0001 CLEARING AND GRUBBING

1.3 CLIN 0002 EXCAVATION AND DISPOSAL OF CAUSEWAY MATERIAL

1.4 CLIN 0003 RIPRAP

1.5 CLIN 0004 PLANTING WILLOWS

1.6 CLIN 0005 WATER QUALITY MONITORING

1.7 CLIN 0006 CONTRACTOR SURVEYS

1.8 CLIN 0007 CITY OF KENNEWICK WATER INTAKE SILT CURTAIN

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 22 00.00 28 Page 1

SECTION 01 22 00.00 28 Page 2

SECTION 01 22 00.00 28

MEASUREMENT AND PAYMENT

PART 1 GENERAL

In each instance, the contract price for an item shall constitute full compensation for furnishing all plant, labor, equipment, and materials, and for performing all operations required to complete the work included in the item as herein specified, or as otherwise approved.

1.1 RETAINAGE OF PAYMENT

Retainage in the amount of 10 percent of original contract award amount will be withheld until the final submittals, listed below, have been approved by the Government. The 10 percent retainage for final submittals will start once the Contractor has earned 90 percent of the original contract value. See SECTION 01 71 23.01 28 CONTRACTOR SURVEYS AND REMOTE SENSING DATA COLLECTION for additional information.

FINAL SUBMITTALS

a. Geospatial Data.

b. As-Built Surveys.

1.2 CLIN 0001 CLEARING AND GRUBBING

Clearing and grubbing is measured for payment as a complete pay item (JOB). Payment is made at the lump sum price for CLIN 0001, "CLEARING AND GRUBBING," which price and payment is full compensation for all work required for clearing and grubbing, complete, as specified and approved.

1.3 CLIN 0002 EXCAVATION AND DISPOSAL OF CAUSEWAY MATERIAL

Excavation and disposal of causeway material is measured for payment as the number of cubic yards (CY) of in-situ material excavated, hauled and disposed of. Payment is made at the unit price for CLIN 0002, "EXCAVATION AND DISPOSAL OF CAUSEWAY MATERIAL," which price and payment is full compensation for all work required for excavation, hauling and disposal of causeway material, complete, as specified and approved. Volume is to be calculated using the Contractor's preliminary survey and the as-built survey.

1.4 CLIN 0003 RIPRAP

Riprap is measured for payment as a complete pay item (JOB). Payment is made at the lump sum price for CLIN 0003, "RIPRAP," which price and payment is full compensation for all work required for riprap placement, complete, as specified and approved.

1.5 CLIN 0004 PLANTING WILLOWS

Planting willows is measured for payment as a complete pay item (JOB).

Payment is made at the lump sum price for CLIN 0004, "PLANTING WILLOWS," which price and payment is full compensation for all work required for planting willows, complete, as specified and approved.

SECTION 01 22 00.00 28 Page 3

1.6 CLIN 0005 WATER QUALITY MONITORING

Water Quality Monitoring is measured for payment as a complete pay item (JOB). Payment is made at the lump sum price for CLIN 0005, "WATER QUALITY MONITORING," which price and payment is full compensation for all work required for water quality monitoring during in-water work, complete, as specified and approved.

1.7 CLIN 0006 CONTRACTOR SURVEYS

Contractor surveys is measured for payment as a complete pay item (JOB).

Payment is made at the lump sum price for CLIN 0006, "CONTRACTOR SURVEYS," which price and payment is full compensation for all work required for preliminary survey and as-built survey, complete, as specified and approved.

1.8 CLIN 0007 CITY OF KENNEWICK WATER INTAKE SILT CURTAIN

City of Kennewick water intake silt curtain is measured for payment as a complete pay item (JOB). Payment is made at the lump sum price for CLIN 0007, "CITY OF KENNEWICK WATER INTAKE SILT CURTAIN," which price and payment is full compensation for all work required to visually inspect the silt curtain at the city of Kennewick water intake at least once every three months for a duration of 12 months, all maintenance of the silt curtain, and removal of the silt curtain (1) year after completion of in-water work, complete, as specified and approved.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 22 00.00 28 Page 4

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 32 16.00 28

SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES

PART 1 GENERAL

1.1 SUBMITTALS

1.2 ACCEPTANCE

1.3 SCHEDULE FORMAT

1.3.1 Network Analysis Schedule (NAS)

1.3.1.1 Primavera P6 Settings and Parameters

1.3.1.2 Microsoft Project 2016 Settings and Parameters

1.3.1.3 Cost Loading Microsoft Project 2016 Schedules

1.3.2 Schedule Submittals and Procedures

1.4 SCHEDULE MONTHLY UPDATES

1.5 CONTRACT MODIFICATION

1.6 3-WEEK LOOK AHEAD SCHEDULE

1.7 CORRESPONDENCE AND TEST REPORTS:

1.8 ADDITIONAL SCHEDULING REQUIREMENTS

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

SECTION 01 32 16.00 28 Page 1

SECTION 01 32 16.00 28 Page 2

SECTION 01 32 16.00 28

SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals having an "I" designation are for information only.

Designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Construction Schedule ; G, C

SD-07 Certificates

Monthly Updates ; G, C

1.2 ACCEPTANCE

a. Prior to the start of work, prepare and submit a Baseline construction schedule for acceptance. Schedule shall be in the form of a Network Analysis Schedule (NAS) in accordance with the terms in Contract Clause "FAR 52.236-15, Schedules for Construction Contracts," except as modified in this contract.

b. The Baseline Construction Schedule must be accepted prior to any of the following:

1. The Contractor starting work on the demolition or construction stage(s) of the contract.

2. Processing Contractor's invoice(s) for construction activities/items of work.

3. Review of any schedule updates.

c. Submittal of the Baseline Schedule, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).

d. All Construction Schedules must be cost loaded. Cost load material, labor and equipment costs to their respective Construction Activities. Evenly disperse overhead and profit to each activity over the duration of the project. Cost loading must total to 100 percent of the value of the contract, and is required to process Contractor's invoice(s).

SECTION 01 32 16.00 28 Page 3

1.3 SCHEDULE FORMAT

1.3.1 Network Analysis Schedule (NAS)

Use the critical path method (CPM) to schedule and control project activities. Prepare and maintain project schedules using Primavera P6 or Microsoft Project 2016 . Importing data into the scheduling program using data conversion techniques or third party software is cause for rejection of the submitted schedule. Build the schedule as follows:

a. Show pre-construction submittals, Government review periods, material/equipment delivery, utility outages, all on-site construction, inspection, testing, and closeout activities. Government and Contractor on-site work activities must be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-work days.

b. With the exception of the Contract Award and End Contract milestone activities, no activities shall be open-ended. Each activity shall have predecessor and successor ties. No activity is to have open start, or open finish (dangling) logic. Minimize redundant logic ties. Once an activity exists on the schedule it is not to be deleted, or renamed to change the scope of the activity, and must not be removed from the schedule logic without approval from the Contracting Officer. While an activity cannot be deleted, where said activity is no longer applicable to the schedule but must remain within the logic stream for historical record, it can be changed to a milestone. Document any such change in the milestone's "Notebook", including a date and explanation for the change. The ID number for a deleted activity must not be re-used for another activity.

c. Each activity is to be assigned an appropriate Responsibility Code indicating responsibility to accomplish the work indicated by the activity, Phase Code and Work Location Code.

d. Date/time constraint(s) and/or lags, other than those required by the contract, are not allowed unless accepted by the Contracting Officer.

Include as the last activity in the contract schedule, a milestone activity named "Contract Completion Date".

1.3.1.1 Primavera P6 Settings and Parameters

Use the following Primavera P6 settings and parameters in preparing the Baseline Schedule. Deviation from these settings and parameters, without prior consent of the Contracting Officer, is cause for rejection of schedule submission.

a. General: Define or establish Calendars and Activity Codes at the "Project" level, not the "Global" level.

b. Admin Drop-Down Menu, Admin Preferences, Time Periods Tab:

(1) Set time periods for P6 to 8.0 Hours/Day, 40.0 Hours/Week, 172.0 Hours/Month and 2000.0 Hours/Year.

(2) Use assigned calendar to specify the number of work hours for each time period: Must be checked.

c. Project Level, Dates Tab:

SECTION 01 32 16.00 28 Page 4

(1) Set "Must Finish By" date to "Contract Completion Date".

d. Project Level, Defaults Tab:

(1) Duration Type: Set to "Fixed Duration & Units".

(2) Percent Complete Type: Set to "Physical".

(3) Activity Type: Set to "Task Dependent".

(4) Calendar: Set to "Standard 5 Day Workweek". Calendar must reflect Saturday, Sunday and all Federal holidays as non-work days.

Alternative calendars may be used with Contracting Officer approval.

e. Project Level, Calculations Tab:

(1) Activity percent complete based on activity steps: Must be Checked.

(2) Reset Remaining Duration and Units to Original: Must be Checked.

(3) Subtract Actual from At Completion: Must be Checked.

(4) Recalculate Actual units and Cost when duration percent(%) complete changes: Must be Checked.

(5) Link Actual to Date and Actual This Period Units and Cost: Must be Checked.

f. Project Level, Settings Tab:

(1) Define Critical Activities: Check "Total Float is less than or equal to" and add "0d".

g. No on-site construction activity may have durations in excess of 10 working days.

1.3.1.2 Microsoft Project 2016 Settings and Parameters

The Network must have a minimum of 30 construction activities. No on-site construction activity may have durations in excess of 10 working days.

1.3.1.3 Cost Loading Microsoft Project 2016 Schedules

Assign material, labor and equipment costs to their respective Construction Activities. Material and equipment costs for which payment will be requested in advance of installation must be assigned to their respective procurement activity (i.e. the material/equipment on-site activity). See paragraph ACCEPTANCE in this SECTION for additional Cost Loading requirements.

a. Submit an Earned Value Report with each schedule update showing activity budget, cost percent complete, earned amount and cost to complete as directed by the Contracting Officer.

b. With each schedule submission, provide a Schedule Variance control (SVC) diagram showing:

SECTION 01 32 16.00 28 Page 5

(1) Cash Flow S-Curves indicating planned project cost based on projected early and late activity finish dates.

(2) Earned Value to-date. Revise Cash Flow S-Curves when the contract is modified, or as directed by the Contracting Officer.

1.3.2 Schedule Submittals and Procedures

Submit Network Analysis Schedules (NAS) and updates in hard copy and on electronic media that is acceptable to the Contracting Officer. Submit an electronic back-up of the project schedule in an import format compatible with the Government's scheduling program.

1.4 SCHEDULE MONTHLY UPDATES

Update the Construction Schedule at monthly intervals, and when the schedule has been revised. The updated schedule must be kept current, reflecting actual activity progress and plan for completing the remaining work. Submit copies of purchase orders and confirmation of delivery dates as directed by the Contracting Officer.

a. Narrative Report: Provide with schedule updates. Identify and justify;

(1) Progress made in each area of the project

(2) Critical Path

(3) Date/time constraint(s), other than those required by the contract

(4) Changes in the following; added or deleted activities, original and remaining durations for activities that have not started, logic, milestones, planned sequence of operations, and critical path

(5) Status of Contract Completion Date and interim milestones;

(6) Current and anticipated delays (describe cause of delay and corrective actions(s) and mitigation measures to minimize);

(7) Description of current and future schedule problem areas.

Each entry in the narrative report must cite the respective Activity ID and Activity Description, the date and reason for the change, and description of the change.

1.5 CONTRACT MODIFICATION

Submit a Time Impact Analysis (TIA) with each cost and time proposal for a proposed change. TIA must illustrate the influence of each change or delay on the Contract Completion Date or milestones. No time extensions will be granted nor delay damages paid unless a delay occurs which consumes all available Project Float, and extends the Projected Finish beyond the Contract Completion Date.

a. Each TIA must be in both narrative and schedule form. The narrative must define the scope and conditions of the change; provide start and finish dates of impact, successor and predecessor activity to impact period, responsible party, describe how it originated, and how it impacts the schedule. The schedule submission must consist of three

SECTION 01 32 16.00 28 Page 6 native files:

(1) Fragnet used to define the scope of the changed condition

(2) Most recent accepted schedule update as of the time of the proposal or claim submission that has been updated to show all activity progress as of the time of the impact start date.

(3) The impacted schedule that has the fragnet inserted in the updated schedule and the schedule "run" so that the new completion date is determined.

b. For claimed as-built project delay, the inserted fragnet TIA method must be modified to account for as-built events known to occur after the data date of schedule update used.

c. All TIAs must include any mitigation, and must determine the apportionment of the overall delay assignable to each individual delay. The associated narrative must clearly describe the findings in a chronological listing beginning with the earliest delay event.

(1) Identify types of delays as follows:

(a) Excusable Delay: Force-Majeure (e.g. weather) - Contractor may receive time extension, but time will not be compensable.

(b) Inexcusable Delay: Contractor Responsibility - Contractor will not receive time extension.

(c) Compensable Delay: Government Responsibility - Contractor may receive compensable time extension.

(2) If a combination of any of the delay types outlined above occurs, it is considered a Concurrent Delay, which will require an analysis of the facts to determine compensability and entitlement to any time extension under the applicable contract clauses.

d. Submit Data disks containing the narrative and native schedule files.

e. Unless the Contracting Officer requests otherwise, only add conformed contract modifications into the Project NAS.

1.6 3-WEEK LOOK AHEAD SCHEDULE

Prepare and issue a 3-Week Look Ahead schedule to provide a more detailed day-to-day plan of upcoming work identified on the Construction Schedule.

Key the work plans to activity numbers when a NAS is required and update each week to show the planned work for the current and following two-week period. Additionally, include upcoming outages, closures, preparatory meetings, and initial meetings. Identify critical path activities on the Three-Week Look Ahead Schedule. The detail work plans are to be bar chart type schedules, maintained separately from the Construction Schedule on an electronic spreadsheet program and printed on 8-1/2 by 11 inch sheets as directed by the Contracting Officer. Activities must not exceed 5 working days in duration and have sufficient level of detail to assign crews, tools and equipment required to complete the work. Deliver three hard copies and one electronic file of the 3-Week Look Ahead Schedule to the Contracting Officer no later than 8 a.m. each Monday, and review during the weekly CQC Coordination or Production Meeting.

SECTION 01 32 16.00 28 Page 7

1.7 CORRESPONDENCE AND TEST REPORTS:

All correspondence (e.g., letters, Requests for Information (RFIs), e-mails, meeting minute items, Production and QC Daily Reports, material delivery tickets, photographs) must reference Schedule Activities that are being addressed. All test reports (e.g., concrete, soil compaction, weld, pressure) must reference Schedule Activities that are being addressed.

1.8 ADDITIONAL SCHEDULING REQUIREMENTS

Any references to additional scheduling requirements, including systems to be inspected, tested and commissioned, that are located throughout the remainder of the Contract Documents, are subject to all requirements of this section.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

SECTION 01 32 16.00 28 Page 8

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 REFERENCES

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

1.2.2 Reviewing Authority

1.2.2.1 Action Elements for Submittal Review

1.2.3 Work

1.3 SUBMITTAL CLASSIFICATION

1.3.1 Government Approved (G)

1.3.2 Information Only (I)

1.4 CAD FILE REQUIREMENTS

1.4.1 USACE CAD/BIM Technology Center

1.5 PREPARATION

1.5.1 Transmittal Form

1.5.2 Identifying Submittals

1.5.3 Format For Digital Submittals

1.5.4 Format for SD-02 Shop Drawings

1.5.4.1 Shop Drawing Submittals

1.5.5 Format of SD-03 Product Data and SD-08 Manufacturer's

Instructions

1.5.6 Format of SD-04 Samples

1.5.7 Format of SD-05 Design Data and SD-07 Certificates

1.5.8 Format of SD-06 Test Reports and SD-09 Manufacturer's Field

Reports

1.5.9 Format of SD-01 Preconstruction Submittals and SD-11 Closeout

Submittals

1.6 QUANTITY OF SUBMITTALS

1.6.1 Digital Copies

1.6.2 Hard Copies (HC)

1.6.2.1 Hard Copy Submittals

1.6.3 Official Receipt of Transmittals

1.6.4 Number of Samples SD-04 Samples

1.7 INFORMATION ONLY SUBMITTALS

1.8 VARIATIONS REQUESTS

1.8.1 Considering Variations

1.8.2 Proposing Variations

1.8.3 Warranting That Variations Are Compatible

1.8.4 Review Schedule Is Modified

1.9 SUBMITTAL REGISTER

1.9.1 Use Of Submittal Register

1.9.2 Contractor Use of Submittal Register

1.9.3 Approving Authority Use of Submittal Register

1.9.4 Contractor Action Codes

1.9.5 Contractor Action Code and Action Code

1.9.6 Copies Delivered to the Government

SECTION 01 33 00 Page 1

1.10 SCHEDULING

1.11 GOVERNMENT APPROVING AUTHORITY

1.11.1 Review Notations

1.12 DISAPPROVED OR REJECTED SUBMITTALS

1.13 APPROVED/ACCEPTED SUBMITTALS

1.14 APPROVED SAMPLES

1.15 WITHHOLDING OF PAYMENT

1.16 STAMPS

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

ATTACHMENTS:

ENG Form 4025

Submittal Register

SECTION 01 33 00 Page 2

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Make certain that each submittal is complete and in sufficient detail to easily determine contract compliance.

a. Use the same units of weights and measures as the contract drawings.

b. Contractor's Quality Control (CQC) System Manager shall check and approve all items prior to submittal and stamp, sign, and date indicating action taken.

c. Clearly identify any proposed variations from the contract requirements.

d. Include drawings; literature (catalog cuts, diagrams, operating charts or curves); test reports; samples; O&M manuals (including parts list); certifications; warranties; and other necessary information.

e. Obtain submittal approval prior to acquiring the covered material or equipment.

1.1 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

ERDC/ITL SR-23-1 (Aug 2023) A/E/C Graphics Standard, Release 2.2

ERDC/ITL SR-24-3 (Jul 2024) A/E/C Computer-Aided Design (CAD) Standard - Release 6.2

1.2 DEFINITIONS

1.2.1 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections.

Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

Submittals which are required to be approved prior to commencing construction work and fabrication work. Submittals required prior to the start of the next major phase of the construction on a multi-phase contract. Schedules or tabular list of data or tabular list including location, features, or other pertinent information regarding products, SECTION 01 33 00 Page 3 materials, equipment, or components to be used in the work.

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Unless otherwise specified testing must have been completed within three (3) years of date of contract award for the project.)

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

Final acceptance test and operational test procedure.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.

Confined space entry permits.

Text of posted operating instructions.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

SECTION 01 33 00 Page 4

Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

1.2.2 Reviewing Authority

Office or designated person to review submittal.

1.2.2.1 Action Elements for Submittal Review

AE Architect/Engineer C Engineering & Construction Division, Construction Branch CS Cybersecurity, Electrical Design Lead DDC Walla Walla District Dive Coordinator, Safety Office A Engineering & Construction Division, Structural Design

"Architectural" ECC Operation's Division, Environmental Compliance Coordinator ECCS Operation's Division, Environmental Compliance Coordinator and

Safety Officer OPC Operation's Division, Pesticide Coordinator EL Engineering & Construction Division, Electrical Design GT Engineering & Construction Division, Geotechnical Design H Engineering & Construction Division, Hydraulic Design ME Engineering & Construction Division, Mechanical Design ST Engineering & Construction Division, Structural Design TL Engineering & Construction Division, Technical Lead HDC Hydroelectric Design Center GE Engineering & Construction Division, General Engineering GS Engineering & Construction Division, Geospatial PMP Project Management Division, Planning PEC Project Management Division, Planning, Environmental Compliance SO Safety Office SLE Security Law Enforcement Officer EOC Engineering Design, Project Operations and Construction CERL Construction Engineering Research Laboratory EC Engineering and Construction

1.2.3 Work

As used in this SECTION, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.3 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

G - This code is for submittals requiring government approval that were listed in the original government-generated specs.

I - This code is used for both Government-generated submittals and Contractor-generated submittals. This code is reserved for submittals that don't require approval, e.g. test reports.

SECTION 01 33 00 Page 5

NOTE: See "Contractor Action Codes" Paragraph in this SECTION for further information.

1.3.1 Government Approved (G)

Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Government approval is required for any variations from the Solicitation or Accepted Proposal and other items as designated by the Contracting Officer. Within the terms of the Contract Clause entitled "Specifications and Drawings for Construction," submittals are considered to be "shop drawings."

1.3.2 Information Only (I)

Submittals not requiring Government approval will be for information only

(FIO).

1.4 CAD FILE REQUIREMENTS

The following applies to all CAD File submittals for this Contract, unless otherwise noted:

a. Furnish CAD files in the latest version of Bentley DGN format, for all CAD Files submitted by the Contractor in performance of this contract.

b. Unless otherwise noted, all CAD Files shall meet A/E/C CAD and Graphic Standards, as follows:

1. Compliant with the A/E/C CAD Standard ERDC/ITL SR-24-3 , A/E/C Graphics Standard ERDC/ITL SR-23-1 .

c. CAD Files shall have presentation graphics which can be edited by Bentley software (with the exception of photographs). Presentation graphics typically consist of drawing elements such as lines, arcs, shapes, text, and their attributes (e.g., color, width, line style).

d. If CAD files are developed in a format other than the specified Bentley software, furnish the following:

1. The converted CAD files in Bentley DGN format, in compliance with all specified CAD file requirements.

2. The original CAD files in their native file format.

e. In addition to CAD files, submit a PDF of each CAD File. The PDFs and the CAD files shall be identical.

f. Submit files using the DoD SAFE (Secure Access File Exchange) website as directed by the Contracting Officer.

g. Request Government CAD/BIM files through the Contracting Officer, who will then request the files from the USACE CAD/BIM Managers.

1.4.1 USACE CAD/BIM Technology Center

The USACE CAD/BIM Technology Center hosts all standard content for USACE.

SECTION 01 33 00 Page 6

This content can be accessed through the CAD/BIM Technology Center website, https://cadbimcenter.erdc.dren.mil .

1.5 PREPARATION

1.5.1 Transmittal Form

The attached sample transmittal form (ENG Form 4025) is in RMS and shall be completed in RMS 3.0 Contractor Mode. Use ENG Form 4025 for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form.

Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

1.5.2 Identifying Submittals

When submittals are provided by either the Prime Contractor or subcontractor, the Prime Contractor is responsible to prepare, review and stamp with Contractor's approval all specified submittals prior to submitting for Government approval.

Identify submittals, except sample installations and sample panels, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:

a. Project title, location, and date.

b. Contract number.

c. Date of the drawings…