250402 CHILLER REPLACEMENT SOW.pdf

PDF 3 MB Posted

Attached to
Chiller Replacement 19, 321, AS255, FC300, HP513
Solicitation number
N4008525R2548
Issued by

About this file

This document is a Statement of Work (SOW) for a federal contract opportunity to replace chillers at several buildings on a military installation. The key details are:

The contractor shall replace the chillers at the following buildings: HP513 (110 nominal ton), AS255 (128 nominal ton), FC300 (80 nominal ton), BLDG 321 (80 nominal ton), and BLDG 19 (125 nominal ton). The contractor is responsible for verifying the existing pump sizes and replacing them if needed to properly operate the new chillers. The new chillers shall have brazed plate heat exchangers with a 10-year warranty, factory-installed water strainers, and GFCI convenience outlets. The contractor shall also replace the chiller disconnects, flexible conduits, and add heat trace to protect against freezing. The contract requires the use of TEFC PSC style condenser fan motors with VFDs for optimal efficiency. The condenser coils shall have a cationic epoxy polymer e-coat for corrosion resistance.

The related federal contract opportunity is Solicitation N4008525R2548 issued by the Department of the Navy Naval Facilities Engineering Command for the Chiller Replacement 19, 321, AS255, FC300, HP513 project. Only Mechanical MACC Contractors listed on the General Requirements cover page may submit a proposal.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT # 25M005CN

MACC # 25-0402

TITLE: CHILLER REPLACEMENT 19, 321, AS255, FC300, HP513

ATTACHMENTS:

Loop Cleaning Procedures Spec Sheets for pumps and chiller.

General Description:

Replace chillers at the following buildings.

1. HP513 is a 110 nominal ton chiller.

2. AS255 is a 128 nominal ton chiller.

3. FC300 is a 80 nominal ton chiller.

4. BLDG 321is a 80 nominal ton chiller.

5. BLDG 19 is a 125 nominal ton chiller.

*Chiller and disconnect sizes should be verified by the contractor.

*** It is the responsibility of the contractor to assure that the existing pump on site of each new chiller install will properly operate the new chiller with the proper GMP. If pump does not meet the new chiller requirements it is the responsibility of the contractor to replace the pump with the proper style and GPM for the chiller. All pump voltages are the responsibility of the contractor.

SCOPE OF WORK:

The contractor shall provide all material, labor, equipment, and supervision required to accomplish the following:

Detailed Requirements and Specifications: The contractor shall make site visits coordinated with PWD, Clifton Smith at Clifton.smith@usmc.mil or call 910-389-8872.

Chiller Specifications and Basis of Design.

1. All chilled water piping and strainers shall be cleaned prior to installation of new chiller. See attachment for hydronic pipe cleaning and flushing procedures.

2. Replace chilled water pumps and drives (if Needed) on all chiller installs. Pump must meet the manufacturer specifications for each chiller.

3. Chiller can have brazed plate heat exchangers if manufacture can provide a 10-year parts, labor, and refrigerant warranty the entire chiller. In addition to adding a bypass line that allows the chiller to be isolated from the rest of the chilled water piping loop for post-installation/pre-startup system flushing. A factory installed water strainer shall also be included for each chiller.

4. Chiller shall be equipped with a 20amp GFCI convenience outlet for maintenance to be performed. Chiller disconnects shall be replaced along with the flexible liquid tight conduit and connectors between disconnect and the chiller. New disconnect shall meet the manufacturers recommendations. Heat Trace shall protect the evaporator and all piping that is subject to freezing. The 20amp heat trace circuit shall be on a separate circuit. It is the responsibility of the contractor to verify circuit is active. If not, a new circuit shall be run. Location of circuits and existing disconnects listed above.

5. Chiller shall include single point power connection to a non-fused disconnect switch with through-the-door handle and compressor circuit breakers.

6. Chiller condenser fan motors shall include VFD’s to optimize chiller efficiency and maintain proper head pressure. The condenser fan motors shall be TEFC PSC style motors.

7. Condenser coils shall have a flexible cationic epoxy polymer e-coat uniformly applied to all metallic surfaces with no material bridging between fins. The electro-coat shall ensure complete HX encapsulation of all conductive surfaces with uniform dry film thickness from 0.6-1.2 mils (15-30um). E-coating shall meet 5B rating for cross- hatch adhesion per ASTM B3359. Corrosion durability will be confirmed through testing no less than10000 hours salt spray resistance per ASTM B117 using scribed aluminum test coupons.

After e-coat cure, HX shall receive a spray applied, 2K polyurethane black topcoat to prevent UV degradations of epoxy e-coat film. Topcoat shall have a 60-degree gloss (<90%) and dry film thickness of 50-60um.

8. All condenser coils shall be Microchannel coils constructed of aluminum alloy 9150 (Long Life Alloy), to help prevent inter-granular corrosion and increase mechanical strength before and after brazing. Aluminum alloy 3102 coils will not be accepted due to mechanical failure rates. Copper tube and aluminum fin condenser coils will be accepted as an alternate if they can include the factory coating with published 10000-hour salt spray rating listed above.

9. Condenser coils shall be protected by louvered coil guards and compressor housing shall have equivalent protection.

10. Chiller shall sit on Seismic Feet. And rubber pads installed on bottom of rails to elevate side rails to allow wash down of debris from under chiller.

11. Chiller must include thermal dispersion type flow switches. Paddle type will not be accepted. The flow shall be factory installed at the evaporator outlet.

12. Chillers must include phase loss with under/over voltage protection with LED indication of the type of fault to guard against compressor motor burn out.

13. All piping shall be a minimum of schedule 40 mild steel, welded to pipe fitting standards.

14. Emergency chiller connections: a set of emergency tees shall be installed before entering the chiller on supply and return lines. The tees shall match the diameter of the pipe. A butterfly valve and a bolted cover plate shall be installed.

15. Control panel shall have access to microprocessor (controller) for viewing and set up, without interrupting machine operation. Chiller shall include a centrally located weatherproof control panel including DDC microprocessor controller. Control box shall be designed in accordance with NEMA 3R rating. Controllers and screens must be located within the panel and not exposed to sunlight. All wiring within control panel shall be ran through slotted wiring duct with covers. Loose wires with zip ties will not be accepted.

16. Units 75 nominal tons and up shall include reduction mode to allow for reduced sound operation. VFD’s are to limit the condenser fan speeds to reduce sound. User shall be able to specify times chiller will operate in sound reduction mode. Chiller shall be set to override the reduced sound mode when the additional capacity is needed. This will make sure the chiller is optimized between required capacity and the lowest sound level possible.

17. Each refrigerant circuit must include a minimum of 2 scroll compressor. Multiple scroll compressors shall be utilized to prevent large capacity loss due to compressor failures. Compressor modules must have isolation valves and controls to lock out individual compressor stages. If low load levels are required, then the chiller is to include hot gas bypass to allow unit operation to 10% of full load to prevent compressors from staging on and off.

18. Each condenser circuit shall have isolation valves, service valves and replaceable core filter driers.

19. Chillers must meet the sound data listed in the below at specified frequencies.

Nominal Tonnage

Octave Band at Center Frequency, 30 ft. from unit. Overall A-Weighted

63 125 250 500 1000 2000 4000 8000 100% Load

75% Load

50% Load

25% Load

30 65 64 61 60 56 51 46 41 61 60 58 57

35 65 64 62 60 56 51 46 41 61 60 58 57

40 65 64 63 61 57 52 47 42 62 61 59 58

45 66 65 64 62 58 52 47 42 63 62 60 59

50 66 66 64 62 58 52 47 42 63 62 60 59

55 66 66 66 62 59 54 49 44 64 63 61 60

60 67 66 67 62 59 54 49 44 64 63 61 60

65 68 67 67 62 60 54 49 44 65 64 62 61

70 68 68 67 62 60 54 49 44 65 64 63 62

75 68 68 68 62 60 54 49 44 65 64 62 61

80 66 63 63 63 62 56 53 53 66 65 63 62

90 67 67 67 64 62 56 54 54 67 66 64 63

100 66 65 65 65 62 56 57 55 67 66 64 63

110 66 67 67 65 61 55 55 55 67 66 64 63

120 68 67 67 65 61 59 60 57 68 67 65 64

130 67 68 68 64 61 60 60 55 68 67 65 64

140 68 69 69 65 61 60 61 56 69 68 66 66

150 69 70 70 65 62 62 62 56 70 69 67 66

160 69 70 70 65 62 63 62 56 70 69 67 66

170 69 71 69 67 64 61 60 58 70 69 67 66

180 69 71 69 67 64 61 61 58 70 69 67 66

190 69 71 69 67 64 61 61 58 70 69 67 66

Sound data must be published to meet or be lower than the above numbers for respective tonnage. Any chiller that do not conform to these published sound targets must provide attenuation to meet at the installing contractor’s expense. Sound attenuation should not affect or degrade the chillers performance. The chiller manufacturers catalog data should support all listed sound data.

20. Factory supplied strainer shall be field installed on the evaporator inlet side. There are to be no welds downstream of the strainer prior to the heat exchanger.

Chiller manufacture must provide “Y” type strainer with the following CV values listed below.

Pipe Size CV 2” 120

2.5” 165 3: 227 4” 457 5” 641 6” 976 8” 1,607 10” 2,574 12” 3,576

21. Sight glasses shall be installed.

22. Controls shall be BACnet/MSTP, the controller shall be in English, and must monitor phase loss, over and under voltage, line, and load monitoring. Manual latch on critical faults and delayed restart on non-latched errors. Chiller shall enable on 45 Degree F and above.

Any control interface presently installed and operable on the chiller shall be reinstalled and made to operate. This includes hardwire start-stop, alarm, trouble, or integration to a BACnet/MSTP communication bus.

23. Chiller manufacture must have a service organization with at least one service technician within 35 miles from Camp Lejeune, NC.

24. New Chiller must comply with the buy America Act/Free Trade Agreement with the United States of America.

25. Piping diagrams shall be developed by the contractor based on chiller selection.

1.1 All piping shall be approved by PWD/OPS prior to installation.

1.2 All piping shall be minimum of schedule 40 welded steel pipe. All welds shall be primed and painted with a minimum of two (2) coats of alkyd enamel. All external piping shall have heat trace to prevent freezing. All pipes shall be insulated with minimum of 2” of polyisocyanurate insulation. All insulation shall be covered with aluminum UV cover. All piping shall be supported with pipe stands and or welded supports.

26. Electrical feed

1.1 All electrical feeds and controls shall conform to the “NEC”. Contractor shall replace electrical disconnects and liquid tight conduit and connectors. Existing wiring can be reused if it meets manufactures recommendations.

1.2 All electrical wiring sizes, voltage and amp draws of equipment is the responsibility of the contractor.

1.3 All information provided in this scope of work is for reference only.

1.4 Site visits shall be required by all bidding contractors.

DETAILED REQUIREMENTS AND SPECIFICATIONS

1. Provide spec sheets for material and equipment being used prior to start of work for government approval.

Provide a copy of Maximo Equipment Inventory Sheet for each piece of equipment removed and installed.

SPECIAL SCHEDULING AND ACCESS:

1. Scheduled outages are to be scheduled thru PWD. Outages shall be scheduled fourteen (14) days prior to equipment shut down. Contact Clifton Smith 910-389—8872.

SPECIAL CONDITIONS: Contract shall be completed whit in 300 days after award.

Contractor shall ensure all employees and subcontractors have access and fully vetted.

The contractor shall give Public Works the right to all HVAC equipment, including but not limited to chillers, AHUs, DOAS units, and any DDC controllers that are involved with the sequence of operation for the buildings HVAC system.

The contractor shall give Public Works the right to reclaim all refrigerant from any HVAC system before any equipment is to leave the work area. Any controls that are on existing chiller that need to be installed on new chiller can be removed and installed by the contractor. After Public Works remove any parts as listed above, the chiller will be the property of the contractor to dispose of offsite.

Submittals:

All equipment shall /must be approved. Summit all proposals to the ROICC and PWD for consideration. The contractor shall be required to submit work schedules to POC for approval. The contractor shall submit to the Contracting Officer, the manufacturer’s product specifications, complete with technical product data. The product specifications shall, as a minimum, provide technical details on the following items:

a. Manufacturer’s name and product line.

b. Manufacturer’s Warranty

HAZARDOUS MATERIALS: None

ENVIRONMENTAL: None

25-0402 CHILLER REPLACEMENT 19, 321, AS255, FC300, HP513 - SOW.pdf
BLDG19-DRawings
19-Location Map
BLDG321-Drawings
321-Location Map
AS255-Drawings
AS225-Location
HP513-Drawings
HP519-Location Map
FC300-Drawings
FC300-Location Map

File details come from the government source that posted it. Updated .