250257_PP_CH_GMEDITS.pdf

PDF 189 KB Posted

Attached to
Towing and Recovery Services
Solicitation number
250257
Issued by
Orange County, California

About this file

This is a Procurement Plan memo from the Orange County Transportation Authority (OCTA) dated April 2, 2026, outlining the release, selection, and award process for RFP 250257 for Towing and Recovery Services. The procurement seeks qualified contractors to provide towing and recovery services on an as-needed basis to support OCTA's operational requirements. The contract will be awarded for an initial three-year term with a budget of $435,000. The evaluation process will utilize multiple criteria weighted as follows: Qualifications of the Firm (30%), Staffing/Project Organization (20%), Work Plan (25%), and Cost (25%). This weighting structure prioritizes demonstrated experience, proper equipment, effective response procedures, and operator capability to ensure safe and reliable service delivery while managing operational risk.

The contract will be structured as a time and expense agreement with a firm-fixed hourly rate, allowing contractors to provide services as needed by OCTA. The procurement plan includes prevailing wage requirements and designates a Disadvantaged Business Enterprise (DBE) goal. The internal evaluation team consists of Trevor Worthy (Senior Contract Administrator), Casey Gladding (Section Manager II, MRM), Kevin Levan (Section Manager II, Maintenance-Specialty Shops), and Jason Morris (Section Manager II, Facilities Maintenance-Santa Ana). An independent cost estimate of $435,000 has been received, and the requisition (R001064) has been submitted. The procurement is funded through local sources, with project management oversight by Christine Herrera, Contracts Analyst for Maintenance Resource Management.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revised: 07/20/2010

INTEROFFICE MEMO

Date: April 2, 2026

To: Christine Herrera, Contracts Analyst, Maintenance Resource

Management (MRM)

From: Trevor Worthy, Senior Contract Administrator, CAMM

Subject: Procurement Plan for Release, Selection and Award

RFP 250257 “Towing and Recovery Services”

Please review the procurement plan for the subject RFP and advise your concurrence with the evaluation criteria and contract elements. Include suggested evaluation team members and/or comments. Thanks.

Procurement Type: RFP IFB

A Request for Proposals (RFP) is issued as the nature of the procurement demands that evaluation criteria, in addition to price, be used to select a firm.

Evaluation Criteria:

PROPOSAL WEIGHT

Qualifications of the Firm 30% Staffing/Project Organization 20% Work Plan 25% Cost 25% Justification:

The criteria are structured to select a contractor that can safely and reliably support OCTA’s towing and recovery needs. Greater weight is placed on qualifications and work plan to ensure demonstrated experience, proper equipment, and effective response procedures. Staffing is weighted to evaluate coverage and operator capability. Cost is weighted at 25% in accordance with requirements; however, due to the safety-sensitive and operational nature of these services, experience and reliability are prioritized to reduce risk and service disruption.

Procurement Plan, RFP 250257

Revised: 0720/2010

Contract Type: Time & Expense CTO-Based Firm Fixed Price

Justification (Explain the rationale for using the particular contract type):

A time and expense contract is appropriate for this procurement as firms are required to provide services on an as-needed basis at a firm-fixed hourly rate.

Retention: Yes No N/A

Prevailing Wages: Yes $ No N/A

Liquidated Damages: Yes $ No N/A

Procurement Schedule: Attached

Internal Evaluators:

Trevor Worthy, Senior Contractor Administrator, Contracts Administration and Materials Management

Casey Gladding, Section Manager II, MRM

Kevin Levan, Section Manager II, Maintenance-Specialty Shops Administrator

Jason Morris, Section Manager II, Facilities Maintenance-Santa Ana

Contract Term: Three (3) year term

Funding Source: Local Measure M Federal (CMAQ)

Dollar Amount: Initial Term $438,255.00

Option Term

Independent Cost Estimate Received: Yes No

Requisition Received: Yes Req. R001064

DBE Goal: Yes No

Georgia Martinez Oval $435,000

Procurement Plan, RFP 250257

Revised: 0720/2010

Project Manager Concurrence:

Christine Herrera, Contracts Analyst, Maintenance Resource Management Date

CAMM Section/Department Manager Concurrence:

Georgia Martinez, Department Manager, Contracts and Procurement Date

4/7/2026